CN210797999U - Full glass curtain wall mounting structure - Google Patents
Full glass curtain wall mounting structure Download PDFInfo
- Publication number
- CN210797999U CN210797999U CN201921148076.3U CN201921148076U CN210797999U CN 210797999 U CN210797999 U CN 210797999U CN 201921148076 U CN201921148076 U CN 201921148076U CN 210797999 U CN210797999 U CN 210797999U
- Authority
- CN
- China
- Prior art keywords
- wall
- glass
- installation
- installation channel
- section steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000011521 glass Substances 0.000 title claims abstract description 69
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 99
- 239000010959 steel Substances 0.000 claims abstract description 99
- 238000009434 installation Methods 0.000 claims abstract description 86
- 230000001681 protective effect Effects 0.000 claims abstract description 31
- 238000007789 sealing Methods 0.000 claims description 28
- 229920001875 Ebonite Polymers 0.000 claims description 2
- 238000010276 construction Methods 0.000 claims 1
- 230000015572 biosynthetic process Effects 0.000 description 2
- 239000003292 glue Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 229910000838 Al alloy Inorganic materials 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000007496 glass forming Methods 0.000 description 1
- 230000001771 impaired effect Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 239000010410 layer Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 239000000565 sealant Substances 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The utility model discloses a full glass curtain wall mounting structure has solved among the prior art problem that the connection structure of curtain wall glass and building outer wall top exposes, connect the life-span weak point, and its technical essential is: the building beam on the outer wall of the top end of the tower outer wall is built at a plurality of horizontal intervals, an installation beam is connected between the building beams, one side, away from the tower outer wall, of the installation beam is provided with an installation channel steel, a protection cover plate is fixedly arranged above the building beam, the two sides of the protection cover plate respectively extend to the tower outer wall and the installation channel steel, the two sides of the protection cover plate are downwards turned over to form turnups and are fixedly connected with the inner side of the tower outer wall or the installation channel steel, and the bottom of the turnups outside the installation channel steel is lower than the bottom. Through the scheme, the top end of the curtain wall glass is installed inside the installation channel steel, the protective cover plate is arranged above the top end of the curtain wall glass, the protective capacity of the installation structure at the top end of the curtain wall glass is effectively enhanced, and the safety is further guaranteed.
Description
Technical Field
The utility model belongs to the technical field of architectural decoration's technique and specifically relates to a full glass curtain wall mounting structure is related to.
Background
The glass curtain wall is a building outer protective structure or decorative structure which has a certain displacement capacity relative to the main structure by a supporting structure system and does not bear the action of the main structure. The glass curtain wall body has two types of single-layer glass and double-layer glass, and when the glass curtain wall body is installed, upright columns fixedly installed on building walls such as a tower and the like, such as aluminum alloy upright columns, are often needed to be installed, so that the tower is maintained while the glass curtain wall body is installed at intervals with the wall body. The glass curtain wall has the advantages that the glass curtain wall is an all-glass curtain wall, and the curtain wall glass forming the all-glass curtain wall can be installed only at the top end and the bottom end of a building when being installed, so that an integrated all-glass structure is formed on the outer wall of the building, and the appearance of the building is more integral and attractive.
However, when the existing full-glass curtain wall is installed, the top end of the full-glass curtain wall is mostly exposed, so that the curtain wall glass is directly influenced by rain and snow weather with the connecting structure on the top end of the building outer wall, the curtain wall glass is easy to damage after a long time, the potential safety hazard of the curtain wall glass is caused, and manual and timely repair is needed.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a curtain wall glass connection structure can obtain sheltering from full glass curtain wall mounting structure of protection.
The utility model discloses a can realize through following technical scheme:
the building beam is built on outer wall of tower outer wall top including a plurality of horizontal intervals, it is connected with the installation crossbeam to build between the crossbeam, one side that the tower outer wall was kept away from to the installation crossbeam is provided with the decurrent installation channel-section steel of notch, installation channel-section steel below is provided with has installed curtain glass, curtain glass both sides with installation channel-section steel both sides inner wall fixed connection, it is fixed to be provided with protective cover plate to build the crossbeam top, protective cover plate's both sides extend to the tower outer wall respectively with outside the installation channel-section steel, protective cover plate's both sides are turned over a formation turn-ups downwards and are inboard or the installation channel-section steel fixed connection with the tower outer wall, the installation channel-section steel outside the turn-.
Through adopting above-mentioned technical scheme, curtain glass top can realize stretching into in the installation channel-section steel and carry out fixed connection with the both sides inner wall of installation channel-section steel in the installation channel-section steel, and the protection apron that sets up simultaneously on the installation channel-section steel can be further shelters from the protection with the installation channel-section steel to finally realize leading to mounting structure impaired with the protection of curtain glass including, avoid receiving external environment influence. The turn-ups that is less than the installation channel-section steel bottom that the protective cover board both sides set up then can be in the strong wind and heavy rain weather decline rainwater etc. get into the inside possibility of installation channel-section steel, and can improve the succinct wholeness nature in the appearance after curtain glass installs after the turn-ups shelters from the protection channel-section steel completely for the integral erection curtain is more pleasing to the eye.
Further setting the following steps: the curtain glass both sides with be provided with the backing plate between the both sides inner wall of installation channel-section steel, the curtain glass the cushion with the installation bolt is worn to be equipped with by the level between the installation channel-section steel, the both ends threaded connection of installation bolt supports tightly the mounting nut of installation channel-section steel outer wall, turn-ups bottom to curtain glass one side level is turned over and is rolled over and form the closing plate, the closing plate with installation channel-section steel fixed connection.
Through adopting above-mentioned technical scheme, curtain wall glass passes through the backing plate and realizes and install the mounting means of channel-section steel inner wall butt more simple swift with the mounting means of installation channel-section steel with the size unanimity, cooperation insertion and direct butt in the installation in-process, make curtain wall glass can stretch into respectively from both sides after the installation channel-section steel and fill up the backing plate and can realize the butt, recycle mounting bolt and mounting nut and connect the realization with three fixed connection, the closing plate of turn-ups bottom can realize further improvement curtain wall glass waterproof performance when the installation.
Further setting the following steps: the sealing plate is provided with first angle steel, the two sides of the first angle steel are respectively abutted to the outer wall of the installation channel steel and the top surface of the sealing plate, the end portion of the installation bolt penetrates through one side of the first angle steel, the installation nut is far away from the first angle steel, one side of the installation channel steel is abutted to the first angle steel, and a connecting bolt which penetrates through the sealing plate and the first angle steel in the vertical direction is arranged between the first angle steel and the sealing plate.
Through adopting above-mentioned technical scheme, first angle steel utilizes mounting nut and connecting bolt to realize being connected between with installation channel-section steel and the closing plate, makes installation channel-section steel and protective cover plate form to be connected, forms integral atress system with curtain wall glass's mounting structure, and is more reliable and more stable.
Further setting the following steps: the sealing plate is characterized in that the same sealing plate is arranged between the bottom end of the turned edge on one side of the outer wall and the outer wall, second angle steel connected with the sealing plate and the outer wall is arranged above the sealing plate, two sides of the second angle steel are respectively abutted against the top surface of the sealing plate and the side wall of the outer wall, and connecting bolts driven into the sealing plate and the outer wall penetrate through two sides of the second angle steel perpendicularly.
Through adopting above-mentioned technical scheme, realize improving the waterproof performance of protective cover board at the tower outer wall inboard with the help of the closing plate to protective cover board and outer wall form fixed connection when being connected the closing plate with the outer wall with the help of the second angle steel.
Further setting the following steps: sealing pieces are arranged between the sealing plate at the bottom end of the turned edge on the two sides of the protective cover plate and the curtain wall glass and between the sealing plate and the outer wall.
Through adopting above-mentioned technical scheme, the gas tightness of reinforcing protective cover board after the installation, and then effectively place rainwater and humid air entering installation channel-section steel in corrosion curtain wall glass's fixed mounting structure, make curtain wall glass's installation life obtain effective extension.
Further setting the following steps: and the flanging bottom edges are all provided with obliquely downward flow guide eaves in a downward extending manner.
Through adopting above-mentioned technical scheme, can break away from protective cover plate with the rainwater direct diversion of this department when rainy day with the help of the water conservancy diversion eaves, avoid the rainwater to trickle in the closing plate bottom and soak the sealing member, prolong the effective sealed life-span of sealing member.
Further setting the following steps: the backing plate is a hard rubber cushion block.
Through adopting above-mentioned technical scheme, utilize the rubber cushion to make curtain wall glass's mounting means for having certain movable distance's elastic mounting, avoid rigid contact between curtain wall glass and the installation channel-section steel, have certain shock resistance, and change the installation when the installation.
Further setting the following steps: the outer wall top with horizontally connect has between the installation crossbeam and is used for the erection bracing the support beam of protective cover plate, wear to be equipped with downwards in the protective cover plate top and squeeze into connecting bolt in the support beam.
Through adopting above-mentioned technical scheme, further strengthen the stability of protective cover board after the installation, improve curtain wall glass's security.
To sum up, the utility model discloses a beneficial technological effect does:
(1) the top end of the curtain wall glass is arranged in the mounting channel steel, and the protective cover plate is arranged above the mounting channel steel, so that the protection capability of the mounting structure at the top end of the curtain wall glass is effectively enhanced, the repairing times are reduced, and the safety is further guaranteed;
(2) through the combined sealing of the sealing plate and the sealing piece, the phenomenon that moist air and rainwater enter the mounting channel steel to be rusted can be effectively reduced.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is an enlarged schematic view taken along a portion a in fig. 1.
Reference numerals: 1. building a cross beam; 2. mounting a cross beam; 3. mounting channel steel; 4. curtain wall glass; 5. a base plate; 6. installing a bolt; 7. mounting a nut; 8. flanging; 9. a sealing plate; 10. sealing glue; 11. a first angle steel; 12. a second angle steel; 13. a connecting bolt; 14. a support beam; 15. a flow guiding brim; 16. a protective cover plate.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1 and 2, the utility model discloses an all-glass curtain wall mounting structure. A plurality of building cross beams 1 are vertically built on the outer wall of the top of the outer wall of the tower at intervals, and installation cross beams 2 are connected between the end parts, far away from the outer wall of the tower, of the building cross beams 1. The mounting beam 2 is provided with a mounting channel steel 3 at one side far away from the outer wall of the tower through bolts, wherein the opening of the mounting channel steel 3 faces downwards. Curtain wall glass 4 has then been installed to installation channel-section steel 3 below, and in the vertical upwards stretching into installation channel-section steel 3 in the top of curtain wall glass 4, and be provided with the backing plate 5 of being made by the stereoplasm rubber cushion between the both sides of curtain wall glass 4 and the both sides inner wall of installation channel-section steel 3. The curtain wall glass 4, the base plate 5 and the installation channel steel 3 are finally connected through the installation bolt 6 which horizontally penetrates through the curtain wall glass, the base plate and the installation channel steel 3, and installation nuts 7 are arranged at the end parts, located at two sides of the installation channel steel 3, of the installation bolt 6.
Referring to fig. 1 and 2, for preventing that curtain wall glass 4 and installation channel-section steel 3 from exposing in the external world, fixed being provided with protective cover 16 in the top of putting up crossbeam 1, protective cover 16's both sides extend to the inboard of tower outer wall and the one side that the tower outer wall was kept away from to installation channel-section steel 3 respectively, and protective cover 16's both sides turn over a formation turn-ups 8 of turning over downwards, turn down 8's bottom is less than the bottom of installation channel-section steel 3. The turn-ups 8 of protective cover 16 both sides all are connected with horizontally closing plate 9 at its bottom, and the closing plate 9 of both sides extends to tower outer wall and installation channel-section steel 3 one side respectively, and the tip of two closing plates 9 bonds sealed glue 10 respectively with the inner wall of tower outer wall and between curtain wall glass 4.
Referring to fig. 1 and 2, in order to further reinforce the installation of the protective cover 16, a first angle steel 11 and a second angle steel 12 are provided above the sealing plates 9 on both sides, wherein, two sides of the first angle steel 11 are respectively abutted against the outer wall of the installation channel steel 3 and the top surface of the sealing plate 9, two sides of the second angle steel 12 are respectively abutted against the inner wall of the outer wall of the tower and the top surface of the sealing plate 9, besides the side of the first angle steel 11 abutting against the installation channel steel 3, connecting bolts 13 which are driven into the abutting surface are arranged on the other side of the first angle steel 11 and the two sides of the second angle steel 12 in a penetrating way, the side of the first angle steel 11 abutting against the installation channel steel 3 is connected through the installation bolts 6, the end part of each installation bolt 6 penetrates through the side of the first angle steel 11 abutting against the installation channel steel 3, and the mounting nut 7 is tightly propped against the first angle steel 11, and finally the protective cover plate 16 is connected with the outer wall of the tower and the mounting channel steel 3 through the connecting bolt 13 and the mounting bolt 6.
Referring to fig. 1, in order to further support the protective baffle, a supporting beam 14 for installing and supporting the protective baffle is horizontally connected between the top end of the outer wall of the tower and the installation beam 2, and the protective baffle is arranged above the supporting beam 14 and provided with a connecting bolt 13 driven into the supporting beam 14 in the upper direction and the lower direction.
Referring to fig. 2, in order to prevent rainwater from flowing along the flange 8 to the bottom surface of the sealing plate 9 to wet the sealant 10 for a long time, an inclined flow guiding eave 15 extends downwards along the bottom edge of the flange 8, and the flow guiding eave 15 inclines downwards towards one side far away from the sealing plate 9.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (8)
1. The utility model provides a full glass curtain wall mounting structure, includes that a plurality of horizontal intervals are built crossbeam (1) of putting up on tower outer wall top outer wall, it is connected with installation crossbeam (2), its characterized in that to put up between crossbeam (1): one side that tower outer wall was kept away from in installation crossbeam (2) is provided with notch decurrent installation channel-section steel (3), installation channel-section steel (3) below is provided with has installed curtain glass (4), curtain glass (4) both sides with installation channel-section steel (3) both sides inner wall fixed connection, it is fixed to be provided with protective cover board (16) to build crossbeam (1) top, the both sides of protective cover board (16) extend to the tower outer wall respectively with outside the installation channel-section steel (3), the both sides of protective cover board (16) are turned over downwards and are formed turn-ups (8) and with tower outer wall inboard or installation channel-section steel (3) fixed connection, the installation channel-section steel (3) outside turn-ups (8) bottom is less than the bottom of installation channel-section steel (3).
2. The all-glass curtain wall mounting structure as claimed in claim 1, wherein: curtain glass (4) both sides with be provided with backing plate (5) between the both sides inner wall of installation channel-section steel (3), curtain glass (4) backing plate (5) with installation channel-section steel (3) between the level wear to be equipped with mounting bolt (6), the both ends threaded connection of mounting bolt (6) supports tightly mounting nut (7) of installation channel-section steel (3) outer wall, turn-ups (8) bottom to curtain glass (4) one side level is turned over and is rolled over and is formed closing plate (9), closing plate (9) with installation channel-section steel (3) fixed connection.
3. The all-glass curtain wall mounting structure as claimed in claim 2, wherein: be provided with both sides on closing plate (9) respectively with installation channel-section steel (3) outer wall and closing plate (9) top surface supports tight first angle steel (11), the tip of construction bolt (6) passes one side of first angle steel (11), mounting nut (7) are kept away from in first angle steel (11) one side of installation channel-section steel (3) supports tightly first angle steel (11), first angle steel (11) with be provided with between closing plate (9) and run through in vertical direction closing plate (9) and thereby first angle steel (11) connect connecting bolt (13) between them.
4. The all-glass curtain wall mounting structure as claimed in claim 2, wherein: be located outer wall one side be provided with same closing plate (9) between turn-ups (8) bottom and the outer wall, closing plate (9) top is provided with the connection closing plate (9) with the second angle steel (12) of outer wall, the both sides of second angle steel (12) are supported tightly respectively on closing plate (9) top surface and the outer wall lateral wall, all wear to be equipped with perpendicularly on second angle steel (12) both sides and squeeze into connecting bolt (13) of closing plate (9) and outer wall.
5. The all-glass curtain wall mounting structure as claimed in claim 4, wherein: sealing elements are arranged between the sealing plate (9) at the bottom end of the turned edge (8) at the two sides of the protective cover plate (16) and the curtain wall glass (4) and between the sealing plate and the outer wall.
6. The all-glass curtain wall mounting structure as claimed in claim 5, wherein: and the bottom edges of the turned edges (8) are provided with oblique downward flow guide eaves (15) in a downward extending manner.
7. The all-glass curtain wall mounting structure as claimed in claim 2, wherein: the backing plate (5) adopts a hard rubber cushion block.
8. The all-glass curtain wall mounting structure as claimed in claim 1, wherein: the outer wall top with horizontally connect with between the installation crossbeam (2) and be used for the installation to support a supporting beam (14) of protection apron (16), downward the wearing and tearing of protection apron (16) top are equipped with and are squeezed into connecting bolt (13) in supporting beam (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921148076.3U CN210797999U (en) | 2019-07-20 | 2019-07-20 | Full glass curtain wall mounting structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921148076.3U CN210797999U (en) | 2019-07-20 | 2019-07-20 | Full glass curtain wall mounting structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210797999U true CN210797999U (en) | 2020-06-19 |
Family
ID=71243529
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921148076.3U Expired - Fee Related CN210797999U (en) | 2019-07-20 | 2019-07-20 | Full glass curtain wall mounting structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210797999U (en) |
-
2019
- 2019-07-20 CN CN201921148076.3U patent/CN210797999U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205206106U (en) | Stone material curtain system of cracking | |
CN104652670B (en) | It is a kind of can indoor location glass curtain wall system | |
CN105525712A (en) | Slotted stone curtain wall system | |
CN207427039U (en) | The stent and photovoltaic system of photovoltaic module | |
CN101498158A (en) | Combined curtain wall | |
CN103352549A (en) | Steel-structure backflow-type double-layer colorful-plate rain tent | |
CN210797999U (en) | Full glass curtain wall mounting structure | |
CN212200816U (en) | Steel construction roof curtain waterproof construction | |
CN217380213U (en) | Prefabricated integral window structure that wafts | |
CN214272685U (en) | Go out roofing air shaft mounting structure | |
CN216216656U (en) | Seamless sinking is to waterproof photovoltaic support of wire drawing locking formula building integration | |
CN206091112U (en) | Novel sunshade rainshelter | |
CN204507801U (en) | With the liquefied natural gas vertical storage tank of freeing arrangement | |
CN210797987U (en) | Horizontal aluminum plate line structure | |
CN114293718A (en) | Waterproof photovoltaic building integrated roof system replacing color steel tiles | |
CN210530089U (en) | Roof with steel frame structure | |
CN201158878Y (en) | Combined curtain wall | |
CN215054661U (en) | Stainless steel pre-dredging runner of glass ceiling | |
CN220686537U (en) | Inclined roof protection structure for color steel plate curtain wall | |
CN220620763U (en) | Novel rainwater riser in curtain wall | |
CN207998996U (en) | Parapet wall top rigid waterproofing structure | |
CN201474192U (en) | Water flanged board joint structure | |
CN2291459Y (en) | Laminated composite building lighting cover structure | |
CN206487186U (en) | A kind of novel assembled high intensity is solar vehicle-shed | |
CN204940957U (en) | A kind of novel pair of pull-type carport of stud sides |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200619 |
|
CF01 | Termination of patent right due to non-payment of annual fee |