CN210766266U - Highway construction is with floating device - Google Patents
Highway construction is with floating device Download PDFInfo
- Publication number
- CN210766266U CN210766266U CN201921116033.7U CN201921116033U CN210766266U CN 210766266 U CN210766266 U CN 210766266U CN 201921116033 U CN201921116033 U CN 201921116033U CN 210766266 U CN210766266 U CN 210766266U
- Authority
- CN
- China
- Prior art keywords
- trowelling
- sliding frame
- support
- hydraulic
- road construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 22
- 238000007667 floating Methods 0.000 title claims abstract description 13
- 230000003028 elevating Effects 0.000 claims description 7
- 239000010720 hydraulic oil Substances 0.000 claims description 7
- 238000000034 method Methods 0.000 claims description 5
- 238000007790 scraping Methods 0.000 claims description 3
- 230000001360 synchronised Effects 0.000 claims description 3
- 238000005516 engineering process Methods 0.000 abstract description 3
- 241000893018 Armeria Species 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000000875 corresponding Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
Abstract
The utility model belongs to the technical field of road construction equipment, concretely relates to floating device is used in highway construction, including track, support, a sliding frame, No. two sliding frames, fixing device, troweling board, vibrating motor and vibrting spear, the track has two, is parallel arrangement, all is provided with running gear on every track, and the support setting is on running gear, and parallel arrangement has two crossbeams between the support on the both sides about, and a sliding frame and No. two sliding frames slidable respectively set up on two crossbeams, and the both ends of a sliding frame and No. two sliding frames all are provided with fixing device, and troweling board sets up in the below of a sliding frame, and vibrating motor sets up in the top of troweling board, and is a plurality of the vibrting spear sets up on No. two sliding frames. The utility model provides a shortcoming that current troweling device tamping and troweling technology can not go on simultaneously, through setting up vibrting spear and troweling board simultaneous working, realized that tamping and troweling technology go on simultaneously for the construction progress.
Description
Technical Field
The utility model belongs to the technical field of the road construction equipment, concretely relates to floating device is used in highway construction.
Background
Concrete floor troweling machine is a more even device that trowels the surface of cement when it is laid but not yet set completely. Trowelling machine on the existing market all needs to be earlier with the concrete again trowelling after vibrating tamper, tamp and trowelling technology can not go on simultaneously, has reduced the construction progress of engineering, and the trowelling plate on the crossbeam can not slide yet in addition, need change the length of trowelling plate according to the width that the road surface is different, has caused the inconvenience of using.
SUMMERY OF THE UTILITY MODEL
The utility model provides a floating device for highway construction to above-mentioned problem.
In order to achieve the purpose, the utility model adopts the following technical proposal:
the utility model provides a highway construction is with floating device, includes track, support, skid, No. two skids, fixing device, floating board, vibrating motor and vibrting spear, the track has two, is parallel arrangement, all is provided with running gear on every track, the support sets up on running gear, and parallel arrangement has two crossbeams between the support on the left and right sides both sides, a skid and No. two skids slidable respectively set up on two crossbeams, and the both ends of a skid and No. two skids all are provided with fixing device, floating board sets up the below at a skid, vibrating motor sets up in the top of floating board, and are a plurality of the vibrting spear sets up on No. two skids.
Furthermore, a scraping plate is fixedly arranged below the first sliding frame and is positioned between the smearing plate and the vibrating rod.
Still further, the front end of the troweling plate is arc-shaped, so that concrete is prevented from being accumulated in front of the troweling plate.
Furthermore, still include elevating gear, elevating gear sets up on running gear, elevating gear includes a plurality of hydraulic telescoping rod, tribit cross switching-over valve, hydraulic pump and hydraulic tank, the hydraulic pump is taken hydraulic oil out from the hydraulic tank, carries to a plurality of hydraulic telescoping rod after the tribit cross switching-over valve adjustment direction to control a plurality of hydraulic telescoping rod's lift, and a plurality of hydraulic telescoping rod is located between support and the running gear.
Furthermore, a guardrail is arranged on the periphery of the hydraulic telescopic rod along the action direction of the hydraulic telescopic rod so as to prevent the support from deviating in the lifting process.
Furthermore, scales are arranged on the support and used for observing the lifting height of the support.
Furthermore, the fixing device is a clamping ring, a threaded hole is formed in the clamping ring, and the friction force between the screw and the cross beam is increased by tightening the screw in the threaded hole to realize fixing.
Furthermore, the walking device comprises a roller and a driving motor, and the driving motor drives the roller to roll along the rail through synchronous belt transmission.
Furthermore, the cross beam is detachably arranged.
Furthermore, a level gauge is arranged on the support, and an illuminating lamp is arranged on the support.
Compared with the prior art, the utility model has the advantages of it is following:
1. the utility model discloses install vibrating spear tamping and trowelling plate simultaneously and trowelling, realize that tamping and trowelling process go on simultaneously, improved the efficiency of construction, simultaneously the utility model discloses a skid and No. two skids can slide on the crossbeam, can carry out a lot of trowelling to the road surface of different width, need not to change the trowelling plate, have practiced thrift equipment cost;
2. the utility model discloses set up elevating gear between running gear and support, can be according to the height of the altitude mixture control trowelling plate on road surface and vibrting spear, increased application scope, set up the guardrail simultaneously around hydraulic telescoping rod, guaranteed that the support lift in-process can not produce the skew, set up the scale on the support to the guardrail can accurately observe the lift height of support as the reference.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the present invention;
fig. 3 is a schematic structural view of the fixing device of the present invention;
fig. 4 is a side view of the troweling plate of the present invention;
fig. 5 is a schematic structural view of the lifting device of the present invention;
in the figure: the device comprises a track-1, a walking device-2, a support-3, a cross beam-4, a first sliding frame-5, a second sliding frame-6, a fixing device-7, a floating plate-8, a vibrating motor-9, a vibrating rod-10, a hydraulic telescopic rod-11, a guardrail-12, a scale-13, a scraper-14, a level gauge-15, a lighting lamp-16, a three-position four-way reversing valve-17, a hydraulic pump-18, a hydraulic oil tank-19 and a lifting device-20.
Detailed Description
In order to further explain the technical solution of the present invention, the present invention is further explained with reference to the accompanying drawings and embodiments.
As shown in fig. 1 to 5, the road construction floating device comprises two rails 1, a support 3, a first skid 5, a second skid 6, a fixing device 7, a floating plate 8, a vibration motor 9, a vibration rod 10 and a lifting device 20, wherein the rails 1 are arranged in parallel, a walking device 2 is arranged on each rail 1, the support 3 is arranged on the walking device 2, a level gauge 15 is arranged on the support 3, and an illuminating lamp 16 is arranged on the support 3. Two crossbeams 4 are arranged between the supports 3 on the left side and the right side in parallel, the crossbeams 4 are detachably arranged, the length of the crossbeams can be lengthened or shortened according to the width of a road surface, the first sliding frame 5 and the second sliding frame 6 are respectively arranged on the two crossbeams 4 in a sliding mode, the two ends of the first sliding frame 5 and the second sliding frame 6 are both provided with fixing devices 7, each fixing device 7 is a clamping ring, a threaded hole is formed in each clamping ring, and the friction force between each screw and the corresponding crossbeam 4 is increased by screwing down the screw in the threaded hole to achieve fixing. The troweling plate 8 is arranged below the first sliding frame 5, and the front end of the troweling plate 8 is arc-shaped so as to prevent concrete from being accumulated in front of the troweling plate 8. The vibrating motor 9 is arranged above the trowelling plate 8, the vibrating rods 10 are arranged on the second sliding frame 6, and vibration is realized through the vibrating motor connected with the vibrating rods. A scraper blade 14 is fixedly arranged below the first sliding frame 5, the scraper blade 14 is located between the trowelling plate 8 and the vibrating rod 10, the lifting device 20 is arranged on the traveling device 2, the lifting device 20 comprises a plurality of hydraulic telescopic rods 11, a three-position four-way reversing valve 17, a hydraulic pump 18 and a hydraulic oil tank 19, the hydraulic pump 18 pumps hydraulic oil out of the hydraulic oil tank 19, and the hydraulic oil is conveyed to the plurality of hydraulic telescopic rods 11 after the direction of the hydraulic telescopic rods is adjusted through the three-position four-way reversing valve 17, so that the lifting of the plurality of hydraulic telescopic rods 11 is controlled, and the plurality of hydraulic telescopic rods 11 are located between the support 3 and the traveling device 2. A guard rail 12 is provided at the periphery of the hydraulic telescopic rod 11 in the acting direction thereof to prevent the support 3 from deviating during the lifting process. The rack 3 is provided with a scale 13, and the lifting height of the rack 3 can be observed by taking the guard rail 12 as a reference object. Running gear 2 is including gyro wheel and driving motor 21, driving motor 21 passes through synchronous belt drive and drives the gyro wheel is followed track 1 rolls.
The essential features and advantages of the invention have been shown and described above, it will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, but may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (10)
1. The utility model provides a highway construction is with floating device which characterized in that: the device comprises rails (1), supports (3), a first sliding frame (5), a second sliding frame (6), fixing devices (7), a troweling plate (8), a vibrating motor (9) and a vibrating rod (10), wherein the two rails (1) are arranged in parallel, a walking device (2) is arranged on each rail (1), the supports (3) are arranged on the walking devices (2), two cross beams (4) are arranged between the supports (3) on the left side and the right side in parallel, the first sliding frame (5) and the second sliding frame (6) are respectively arranged on the two cross beams (4) in a sliding manner, the fixing devices (7) are arranged at the two ends of the first sliding frame (5) and the second sliding frame (6), the troweling plate (8) is arranged below the first sliding frame (5), and the vibrating motor (9) is arranged above the troweling plate (8), the vibrating rods (10) are arranged on the second sliding frame (6).
2. The trowelling device for road construction according to claim 1, wherein: a scraping plate (14) is fixedly arranged below the first sliding frame (5), and the scraping plate (14) is positioned between the trowelling plate (8) and the vibrating rod (10).
3. The trowelling device for road construction according to claim 1, wherein: the front end of the troweling plate (8) is arc-shaped, so that concrete is prevented from being accumulated in front of the troweling plate (8).
4. The trowelling device for road construction according to claim 1, wherein: still include elevating gear (20), elevating gear (20) set up on running gear (2), elevating gear (20) include a plurality of hydraulic telescoping rod (11), tribit four-way reversing valve (17), hydraulic pump (18) and hydraulic tank (19), hydraulic pump (18) are taken hydraulic oil out from hydraulic tank (19), carry to a plurality of hydraulic telescoping rod (11) after tribit four-way reversing valve (17) direction adjustment to control the lift of a plurality of hydraulic telescoping rod (11), and a plurality of hydraulic telescoping rod (11) are located between support (3) and running gear (2).
5. The trowelling device for road construction according to claim 4, wherein: and a guardrail (12) is arranged on the periphery of the hydraulic telescopic rod (11) along the action direction of the hydraulic telescopic rod to prevent the support (3) from deviating in the lifting process.
6. The trowelling device for road construction according to claim 5, wherein: scales (13) are arranged on the support (3) and used for observing the lifting height of the support (3).
7. The trowelling device for road construction according to claim 1, wherein: the fixing device (7) is a clamping ring, a threaded hole is formed in the clamping ring, and the friction force between the screw and the cross beam (4) is increased by screwing down the screw in the threaded hole to realize fixing.
8. The trowelling device for road construction according to claim 1, wherein: the walking device (2) comprises a roller and a driving motor (21), and the driving motor (21) drives the roller to roll along the track (1) through a synchronous belt.
9. The trowelling device for road construction according to claim 1, wherein: the cross beam (4) is arranged in a detachable mode.
10. The trowelling device for road construction according to claim 9, wherein: a level gauge (15) is arranged on the support (3), and an illuminating lamp (16) is arranged on the support (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921116033.7U CN210766266U (en) | 2019-07-17 | 2019-07-17 | Highway construction is with floating device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921116033.7U CN210766266U (en) | 2019-07-17 | 2019-07-17 | Highway construction is with floating device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210766266U true CN210766266U (en) | 2020-06-16 |
Family
ID=71063145
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921116033.7U Active CN210766266U (en) | 2019-07-17 | 2019-07-17 | Highway construction is with floating device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210766266U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110924272A (en) * | 2019-12-11 | 2020-03-27 | 刘士英 | Bridge pavement vibration compaction device |
CN112160602A (en) * | 2020-09-03 | 2021-01-01 | 中建三局集团有限公司 | Integrated flat plate vibrator for concrete vibrating, surface collecting and film covering maintenance |
CN112921756A (en) * | 2021-01-25 | 2021-06-08 | 李之龙 | Pebble paving device for garden construction |
-
2019
- 2019-07-17 CN CN201921116033.7U patent/CN210766266U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110924272A (en) * | 2019-12-11 | 2020-03-27 | 刘士英 | Bridge pavement vibration compaction device |
CN112160602A (en) * | 2020-09-03 | 2021-01-01 | 中建三局集团有限公司 | Integrated flat plate vibrator for concrete vibrating, surface collecting and film covering maintenance |
CN112921756A (en) * | 2021-01-25 | 2021-06-08 | 李之龙 | Pebble paving device for garden construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210766266U (en) | Highway construction is with floating device | |
US7950874B2 (en) | Slipform paving machine with adjustable length paving kit | |
CN104533460B (en) | Support replacement formula formwork jumbo and the construction method of underpass concreting | |
CN106593469B (en) | A kind of trolley for inverted arch construction | |
CN104632251A (en) | Integrally cast type mould plate trolley and construction method of concrete pouring of underground passage | |
CN100424322C (en) | Full circle once lining segregation type nose girder module bench and its construction method | |
CN111188247B (en) | Road curb erection and laying equipment | |
CN204457802U (en) | Formed by integrally casting formula formwork jumbo | |
CN110904969A (en) | High steep slope slab corridor structure concrete placement slipform system | |
CN212612285U (en) | Concrete paving device for canal lining | |
CN206299394U (en) | A kind of tunneling subway station side wall self-propelled hydraulic lining trolley | |
CN205936645U (en) | A full liquid die plate system for culvert is pour | |
CN111764346A (en) | Canal lining system | |
CN112080994A (en) | Concrete road surface dowel bar fixing device | |
CN111648306A (en) | Concrete paving device for canal lining | |
CN211547804U (en) | Cantilever type retaining wall rapid construction device | |
CN204492846U (en) | Movable type with inverted arch lining device crosses car trestle | |
CN210217757U (en) | Overlength lining cutting platform truck | |
CN210561618U (en) | Concrete pavement pouring formwork system | |
CN208453118U (en) | Extension type brick paving machine base apparatus | |
CN207646552U (en) | A kind of running gear being applicable in tunnel curved surface and plane and rubber-tyred subway change paving machine | |
CN216786758U (en) | Integrated paving equipment | |
CN102094648A (en) | Mobile support device | |
CN210766400U (en) | Operating means suitable for construction of thin layer ultra high performance concrete | |
CN203438372U (en) | Full-automatic fabric machine of brick making system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |