CN210418967U - Connecting device for I-steel rail of crane - Google Patents

Connecting device for I-steel rail of crane Download PDF

Info

Publication number
CN210418967U
CN210418967U CN201920998907.XU CN201920998907U CN210418967U CN 210418967 U CN210418967 U CN 210418967U CN 201920998907 U CN201920998907 U CN 201920998907U CN 210418967 U CN210418967 U CN 210418967U
Authority
CN
China
Prior art keywords
clamp
steel beam
steel
front clamp
connecting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920998907.XU
Other languages
Chinese (zh)
Inventor
姚巨
刘新国
王震
冷平
付元东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201920998907.XU priority Critical patent/CN210418967U/en
Application granted granted Critical
Publication of CN210418967U publication Critical patent/CN210418967U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)

Abstract

The utility model relates to a lifting device field specifically is a orbital connecting device of hoist I-steel, characterized by: the clamp comprises a front clamp, a rear clamp and a fastening bolt; the front clamp and the rear clamp are made of steel plates through welding, the front clamp and the rear clamp are sleeved on the cantilever steel beam, the track I-shaped steel beam is clamped by the front clamp and the rear clamp to be connected to the cantilever steel beam after the upper flange is clamped, the front clamp and the rear clamp are fastened with the cantilever steel beam through bolts, and the front clamp and the rear clamp are connected and fastened through bolts arranged on rib plates of the clamps. The connecting device has reasonable and reliable structure stress, does not need welding connection during site construction, has large adjusting range, only carries out bolt tightening operation through a simple wrench, and can also be disassembled through the simple wrench after the construction is finished. So, through simple construction operation, can realize girder steel track arrangement operation on a large scale.

Description

Connecting device for I-steel rail of crane
Technical Field
The utility model relates to a lifting device field specifically is a orbital connecting device of hoist I-steel.
Background
When high-rise and super high-rise building construction, each facade of building all has the perpendicular handling, the demand of transporting on the same floor or cross-layer level from the first floor to the top layer, through arranging the I-steel track at the high-rise outdoor, installs the middle-size and small-size hoist of walking, the transportation installation that realizes the article that can be quick has higher work efficiency than the construction tower crane. However, when the traditional I-steel rail is erected, the I-steel or the steel structure which is cantilevered is welded with the I-steel rail, so that the mounting difficulty is high, the workload is high, destructive cutting is needed during disassembly, and the material cannot be reused.
Disclosure of Invention
An object of the utility model is to overcome above-mentioned defect, provide an install swift and repeatedly usable's orbital connecting device of hoist I-steel.
In order to achieve the above object, the present invention is realized as follows:
a connecting device for an I-steel rail of a crane comprises a front clamp, a rear clamp and a fastening bolt; the front clamp and the rear clamp are made of steel plates through welding, the front clamp and the rear clamp are sleeved on the cantilever steel beam, the track I-shaped steel beam is clamped by the front clamp and the rear clamp to be connected to the cantilever steel beam after the upper flange is clamped, the front clamp and the rear clamp are fastened with the cantilever steel beam through bolts, and the front clamp and the rear clamp are connected and fastened through bolts arranged on rib plates of the clamps.
The steel beam for cantilever is specifically an I-steel cantilever from indoor to outdoor.
The connecting device has reasonable and reliable structure stress, does not need welding connection during site construction, has large adjusting range, only carries out bolt tightening operation through a simple wrench, and can also be disassembled through the simple wrench after the construction is finished. So, through simple construction operation, can realize girder steel track arrangement operation on a large scale.
Drawings
Fig. 1 is a first schematic structural diagram of the connecting device.
Fig. 2 is a second schematic structural diagram of the present connecting device.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in fig. 1 and 2, a connecting device for an i-steel rail of a crane comprises a front clamp, a rear clamp and a fastening bolt; 1I-shaped steel beam for overhanging is connected with a 20I-shaped steel beam as a track construction through a front clamp and a rear clamp. In the installation process, the 16# I-shaped steel beam 3 is connected and fixed with a structural beam or a floor, the clamp 1 and the clamp 2 are sleeved at the front end of the 16# I-shaped steel beam 3, and then the upper flange of the I-shaped steel beam 4 is clamped in a gap between the clamp 1, the clamp 2 and the lower flange of the I-shaped steel beam 3. After the installation position is adjusted, the bolts 6 are respectively fastened by using a wrench.
The width of the upper flange and the lower flange of the No. 16I-shaped steel beam 3 is 88mm, the clamp 1 and the clamp 2 are made of Q235B steel with the thickness of 12mm, and the clearance size inside the clamp is 90 mm. The thickness of the ribbed slab 5 for the clamp connecting bolt is 10mm, and the two sides of the ribbed slab are symmetrically arranged. The diameter of a fastening bolt between the clamp and the I-shaped steel beam 3 is M12, and the diameter of a bolt for connecting the clamp and the clamp through a ribbed plate is M10. The reinforcing rib plates 7 are symmetrically arranged on the clamp, and the thickness of the reinforcing rib plates is 8 mm.

Claims (2)

1. The utility model provides a connecting device of hoist I-steel track, characterized by: the clamp comprises a front clamp, a rear clamp and a fastening bolt; the front clamp and the rear clamp are made of steel plates through welding, the front clamp and the rear clamp are sleeved on the cantilever steel beam, the track I-shaped steel beam is clamped by the front clamp and the rear clamp to be connected to the cantilever steel beam after the upper flange is clamped, the front clamp and the rear clamp are fastened with the cantilever steel beam through bolts, and the front clamp and the rear clamp are connected and fastened through bolts arranged on rib plates of the clamps.
2. The connecting device of the I-steel rail of the crane according to claim 1, wherein: the steel beam for cantilever is specifically an I-steel cantilever from indoor to outdoor.
CN201920998907.XU 2019-06-29 2019-06-29 Connecting device for I-steel rail of crane Active CN210418967U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920998907.XU CN210418967U (en) 2019-06-29 2019-06-29 Connecting device for I-steel rail of crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920998907.XU CN210418967U (en) 2019-06-29 2019-06-29 Connecting device for I-steel rail of crane

Publications (1)

Publication Number Publication Date
CN210418967U true CN210418967U (en) 2020-04-28

Family

ID=70377853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920998907.XU Active CN210418967U (en) 2019-06-29 2019-06-29 Connecting device for I-steel rail of crane

Country Status (1)

Country Link
CN (1) CN210418967U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117506281A (en) * 2023-11-15 2024-02-06 中建八局第二建设有限公司 A special safety fixing device for ring rail hoisting and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117506281A (en) * 2023-11-15 2024-02-06 中建八局第二建设有限公司 A special safety fixing device for ring rail hoisting and its construction method

Similar Documents

Publication Publication Date Title
CN202139833U (en) Cantilever scaffold for building construction
CN111335610B (en) High-altitude large-span cantilever formwork operation platform and erection method thereof
CN102518300B (en) Embedded conical bearing joint type steel structure support and construction method thereof
CN203475806U (en) Tool type anchoring bolt assembly used for fixing shape steel cantilever beam in construction sites
CN110409319B (en) Bracket for large-span steel-concrete composite beam cast-in-place bridge deck and construction method
CN209780193U (en) Suspension type scaffold
CN206942109U (en) One kind is without special bracket and the protection support body of encorbelmenting of off-load industrialization security protection
CN204676914U (en) A kind of rope support that slips safely
CN210418967U (en) Connecting device for I-steel rail of crane
CN212336672U (en) I-steel overhanging bearing frame of basket pull rod for constructional engineering
CN203462586U (en) Large steel corbel combination structure with side baffles
CN203238971U (en) Combination and adjustment device of truss end portions
CN211172708U (en) Column foot structure of channel steel column
CN103225396A (en) Beam frame type construction template system
CN203188612U (en) Beam frame type building template system
CN103195235A (en) Design and calculation for detachable steel plate type steel fixture
CN208056107U (en) A kind of combined steel formwork support system
CN217997844U (en) Arch ring formwork support system
CN115341701B (en) Hanging formwork construction method for high-altitude overhanging steel bar truss floor support plate
CN207794690U (en) The assembled steel reinforced machining shed that can be had enough to meet the need
CN102383613B (en) Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device
CN217947286U (en) Construction elevator attached combined structure fixed on floor
CN211850774U (en) A new type of fast-installing welding-free cantilever steel beam fixing device
CN216516786U (en) Flexible structure of encorbelmenting of dismantling of peripheral protection circulation of superelevation layer
CN209244293U (en) Temporary fixing device for movable arched rod

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant