CN210368654U CN201920937874.8U CN201920937874U CN210368654U CN 210368654 U CN210368654 U CN 210368654U CN 201920937874 U CN201920937874 U CN 201920937874U CN 210368654 U CN210368654 U CN 210368654U
Authority
CN
China
Prior art keywords
arch rib
steel pipe
installation
arch
buttress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920937874.8U
Other languages
Chinese (zh)
Inventor
苏涛
赵全治
刘贵锋
吴立波
张民
董淼燚
谭景昊
奚兴华
温德新
刘海泉
宋明
李义
谢刚
王权政
张天宝
赵娟
孟凡林
张喜波
张群鹏
秦志强
牛晓宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN URBAN CONSTRUCTION GROUP CO Ltd
Original Assignee
TIANJIN URBAN CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN URBAN CONSTRUCTION GROUP CO Ltd filed Critical TIANJIN URBAN CONSTRUCTION GROUP CO Ltd
Priority to CN201920937874.8U priority Critical patent/CN210368654U/en
Application granted granted Critical
Publication of CN210368654U publication Critical patent/CN210368654U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a well formula steel arch bridge construction technical field, in particular to slope arch rib supports and installation device. The structure of the bidirectional inclined pier comprises a cast-in-place pile below a concrete strip foundation, a steel pipe support is connected above the cast-in-place pile, the top end of the steel pipe support is connected with the bidirectional inclined pier through a transverse distribution beam, arch ribs are installed at the top of the bidirectional inclined pier, and working platforms are arranged on two sides of the bidirectional inclined pier on the transverse distribution beam. The utility model discloses a slope arch rib supports and installation device, it can realize arch rib installation and accurate location.

Description

Inclined arch rib supporting and mounting device
Technical Field
The utility model relates to a well formula steel arch bridge construction technical field, in particular to slope arch rib supports and installation device.
Background
The half-through bridge is used for large bridgeSpanThe rib arch bridge of (2) is generally considered when the building height of the bridge is strictly controlled. The arch rib isArch bridgeSkeleton of main arch ring. The arch rib is in the buildingArch waveIn the process, the self-weight, the transverse connection component, the arch wave and the corresponding construction load are borne.
At present, a half-through steel arch bridge is generally fabricated by a construction process of sectional fabrication and field assembly, temporary supports are erected by steel pipes, and lifting equipment is adopted for sectional lifting. The bracket design and buttress design of the inclined arch rib and the conventional arch rib hoisting have the related problems of bracket stability, buttress angle and the like.
Disclosure of Invention
In order to solve the problem of the prior art, the utility model provides a slope arch rib supports and installation device, it can realize arch rib installation and accurate location.
The utility model discloses the technical scheme who adopts as follows:
the utility model provides an incline arch rib and support and installation device, includes the bored concrete pile of concrete strip foundation below, bored concrete pile top be connected with steel pipe support, steel pipe support's top connect the two-way slope buttress through horizontal distribution beam, two-way slope buttress top installation arch rib, the two-way slope buttress's on the horizontal distribution beam both sides be provided with work platform.
An oblique support is arranged between the arch rib and the working platform.
And channel steel cross braces are arranged between the steel pipe brackets.
And a pedestrian ladder is arranged on one side of the steel pipe support.
The utility model provides a beneficial effect that technical scheme brought is:
adopt the utility model discloses a support installation device utilizes the bearing capacity of bored concrete pile, through the platform of steel pipe support as slope arch rib installation, the key technology lies in the preparation and the installation of two-way slope buttress. The technology can solve the problem of accurate installation of various arch ribs in an extending way.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a front view of the inclined arch rib supporting and mounting device of the present invention;
fig. 2 is a left side view of the structure of the oblique arch rib supporting and mounting device of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention clearer, embodiments of the present invention will be described in further detail below with reference to the accompanying drawings.
Example one
As shown in the attached drawing 1, the inclined arch rib supporting and mounting device comprises a cast-in-place pile 1 below a concrete strip foundation 2, a steel pipe support 4 is connected above the cast-in-place pile 1, the top end of the steel pipe support 4 is connected with a bidirectional inclined buttress 6 through a transverse distribution beam 5, an arch rib 10 is mounted at the top of the bidirectional inclined buttress 6, and working platforms 7 are arranged on two sides of the bidirectional inclined buttress 6 on the transverse distribution beam 5.
An oblique support 8 is arranged between the arch rib 10 and the working platform 7.
And channel steel cross braces 3 are arranged between the steel pipe brackets 4.
A pedestrian ladder 9 is arranged on one side of the steel pipe bracket 4.
The method comprises the steps of firstly, calculating the total load according to the weight of an arch rib segment to determine the pile length of a cast-in-place pile 1, facilitating steel pipe support installation for enhancing the integrity and stability of a foundation, pouring a concrete strip foundation 2, installing a steel pipe support 4 according to the height of an arch rib splicing port, and welding a pedestrian ladder 9 on the side face of one steel pipe during steel pipe support installation to facilitate the upper and lower supports of a constructor. Because the steel pipe support is high, adopt channel-section steel bridging 3 to connect between every group support, strengthen the overall stability of support body. And double-spliced 36b I-shaped steel 5 is arranged on the top surface of the steel pipe and serves as a distribution beam and a foundation of a temporary buttress and a construction operation platform. And manufacturing a bidirectional inclined buttress 6 matched with the bottom surface of the arch rib according to the three-dimensional structure of the arch rib, and installing the bidirectional inclined buttress on the transverse distribution beam according to a theoretical position, so that the installation precision of the arch rib is ensured, and the horizontal thrust during installation of the arch rib is eliminated. Meanwhile, a temporary operating platform 7 is erected on the distribution beam by adopting square timber to provide safety guarantee for installation, measurement and positioning. After the arch rib 10 is installed, the inclined support 8 is arranged at the joint position, so that the joint is prevented from displacing before welding.
The above description is only for the preferred embodiment of the present invention, and is not intended to limit the present invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included within the protection scope of the present invention.

Claims (4)

1. The utility model provides an incline arched rib and support and installation device, includes the bored concrete pile of concrete strip foundation below, its characterized in that, bored concrete pile top be connected with the steel pipe support, the top of steel pipe support connect two-way slope buttress through horizontal distribution roof beam, two-way slope buttress top installation arch rib, the two-way slope buttress both sides on the horizontal distribution roof beam be provided with work platform.
2. An inclined rib support and mounting apparatus as claimed in claim 1, wherein diagonal bracing is provided between said rib and said work platform.
3. An inclined arch rib supporting and installing apparatus as claimed in claim 1, wherein channel steel cross braces are provided between the steel pipe supports.
4. An inclined arch rib supporting and installing apparatus as claimed in claim 1, wherein a pedestrian ladder is provided at one side of the steel pipe support.
CN201920937874.8U 2019-06-21 2019-06-21 Inclined arch rib supporting and mounting device Active CN210368654U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920937874.8U CN210368654U (en) 2019-06-21 2019-06-21 Inclined arch rib supporting and mounting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920937874.8U CN210368654U (en) 2019-06-21 2019-06-21 Inclined arch rib supporting and mounting device

Publications (1)

Publication Number Publication Date
CN210368654U true CN210368654U (en) 2020-04-21

Family

ID=70265999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920937874.8U Active CN210368654U (en) 2019-06-21 2019-06-21 Inclined arch rib supporting and mounting device

Country Status (1)

Country Link
CN (1) CN210368654U (en)

Similar Documents

Publication Publication Date Title
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN106012864A (en) Method for lifting and installing whole bridge arch rib
CN107090975A (en) A kind of big across the cast-in-situ concrete beam Bailey bracket formwork construction method of superelevation
CN110344412A (en) A kind of positioning device and method in deep water torrent region Bored Pile of Bridge steel pile casting
AU2013212529B2 (en) Automated formwork climbing system
CN108755377B (en) Construction method of deepwater non-covering layer steel trestle
CN103866693A (en) Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN210368654U (en) Inclined arch rib supporting and mounting device
CN203821248U (en) Steel pipe arch main arch assembling supporting system
CN206337555U (en) Steel reinforcement cage support and steel reinforcement cage erecting device
CN209906223U (en) Beam gantry crane
CN111663451A (en) Construction method of ultrahigh tower of long-span bearing type continuous steel truss girder bridge in high mountain canyon
CN204715362U (en) A kind of deep foundation ditch embedded column base bracing frame
CN215107081U (en) Large-span silo roofing construction platform shore
CN208685457U (en) Cast-in-place box beam bracket device
CN215167934U (en) Large-span silo roofing construction platform bottom pillar
CN215104738U (en) Quick installation device of overlength steel box girder outrigger suitable for narrow place
CN111622091B (en) Stress test method for prefabricated bridge pier
CN106436593A (en) Jack supporting platform for hollow slab beam jacking construction
CN209128895U (en) A kind of support system for installing across river steel lid beam
CN210216415U (en) Positioning device for bridge pile foundation steel casing in deepwater and rapid stream area
CN212426769U (en) Temporary river channel section support for hoisting steel box girder of upper-span steel structure bridge
CN212176685U (en) Instrument formula foundation ditch hangs step ladder
CN209905088U (en) Helicopter taking-off and landing platform capable of being quickly disassembled and assembled
CN210216495U (en) Multifunctional measuring base station structure for subway construction