Prior art keywords
foundation pit
slope
support frame
anchoring
pit slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920634324.9U
Other languages
Chinese (zh)
Inventor
汪洋
鲁旭荣
舒敏洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kaili University
Original Assignee
Kaili University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kaili University filed Critical Kaili University
Priority to CN201920634324.9U priority Critical patent/CN209989819U/en
Application granted granted Critical
Publication of CN209989819U publication Critical patent/CN209989819U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a foundation pit slope supporting construction, including the anchor pole, the anchor head, the support rack, cut the diagonal bar, water guide canal and wash port, the anchor pole is square matrix and tamps into the foundation pit slope respectively perpendicularly in, the outer end of anchor pole exposes domaticly, the bottom surface and the anchor pole outer end fixed connection of anchor head, the first inside cross passageway that all is equipped with of anchor, and the top surface of anchor head is equipped with the connector, the support rack includes horizontal support frame and perpendicular support frame, horizontal support frame level respectively runs through the passageway, erect the support frame vertical through the passageway respectively, it connects each other between the connector at the apex angle to cut the diagonal bar respectively, the water guide canal sets up on the level ground of foundation pit slope top, the wash port level respectively sets up the inside at the side slope, and the export of wash port is located the support rack. In a word, the utility model has the advantages of novel structure, the construction degree of difficulty is low, strut effectually.

Description

一种基坑边坡支护结构A kind of foundation pit slope support structure

技术领域technical field

本实用新型属于建筑工程技术领域,具体是涉及一种基坑边坡支护结构。The utility model belongs to the technical field of construction engineering, in particular to a foundation pit slope supporting structure.

背景技术Background technique

基坑支护工程是个临时工程,设计的安全储备相对可以小些,但又与地区性有关。不同区域地质条件其特点也不相同。基坑支护工程又是岩土工程、结构工程以及施工技术互相交叉的学科,是多种复杂因素交互影响的系统工程,是理论上尚待发展的综合技术学科。由于基坑支护工程造价高,开工数量多,是各施工单位争夺的重点,又由于技术复杂,涉及范围广,变化因素多,事故频繁,是建筑工程中最具有挑战性的技术上的难点,同时也是降低工程造价,确保工程质量的重点。The foundation pit support project is a temporary project, and the designed safety reserve can be relatively small, but it is related to the region. Geological conditions in different regions have different characteristics. Foundation pit support engineering is also an interdisciplinary subject of geotechnical engineering, structural engineering and construction technology. Due to the high cost of the foundation pit support project and the large number of starts, it is the focus of the construction units. Due to the complex technology, a wide range of involved, many changing factors, and frequent accidents, it is the most challenging technical difficulty in construction projects. At the same time, it is also the focus of reducing project cost and ensuring project quality.

基坑支护作为一个结构体系,应要满足稳定和变形的要求,即通常规范所说的两种极限状态的要求,即承载能力极限状态和正常使用极限状态。所谓承载能力极限状态,对基坑支护来说就是支护结构破坏、倾倒、滑动或周边环境的破坏,出现较大范围的失稳。一般的设计要求是不允许支护结构出现这种极限状态的。而正常使用极限状态则是指支护结构的变形或是由于开挖引起周边土体产生的变形过大,影响正常使用,但未造成结构的失稳。As a structural system, foundation pit support should meet the requirements of stability and deformation, that is, the requirements of the two limit states usually mentioned in the specification, namely the limit state of bearing capacity and the limit state of normal service. The so-called limit state of bearing capacity, for foundation pit support, is the failure of the support structure, dumping, sliding or damage of the surrounding environment, resulting in a large range of instability. The general design requirements do not allow the support structure to appear in this limit state. The normal service limit state refers to the deformation of the supporting structure or the excessive deformation of the surrounding soil caused by the excavation, which affects the normal use, but does not cause the instability of the structure.

实用新型内容Utility model content

针对上述存在的问题,本实用新型提供了一种基坑边坡支护结构。In view of the above existing problems, the utility model provides a foundation pit slope support structure.

本实用新型提供的技术方案是:一种基坑边坡支护结构,主要包括锚固杆、锚固头、支护网架、剪斜筋、导水渠和排水孔,所述锚固杆共有多个,呈方形矩阵分别垂直夯入基坑边坡内,锚固杆的外端露出坡面,所述锚固头共有多个,锚固头的底面与锚固杆外端固定连接,锚固头内部均设有十字型的通道,且锚固头的顶面设有连接头,所述支护网架包括横支护架和竖支护架,所述横支护架共有多条,分别水平贯穿所述通道,所述竖支护架共有多条,分别竖直贯穿通道,所述剪斜筋共有多条,分别连接在互为顶角的连接头之间,所述导水渠设置在基坑边坡上方的水平地面上,所述排水孔共有多个,分别水平设置在边坡的内部,且排水孔的出口位于支护网架内。The technical scheme provided by the utility model is: a foundation pit slope support structure, which mainly includes anchor rods, anchor heads, support grids, shear diagonal bars, aqueducts and drainage holes. They are vertically rammed into the slope of the foundation pit in a square matrix, and the outer ends of the anchoring rods are exposed to the slope surface. There are a plurality of anchoring heads. The bottom surface of the anchoring heads is fixedly connected with the outer ends of the anchoring rods. and the top surface of the anchoring head is provided with a connecting head, and the support grid includes a horizontal support frame and a vertical support frame. There are a plurality of vertical support frames, which vertically penetrate the passages, and there are a plurality of the shear diagonal bars, which are respectively connected between the joints that are at the top angles of each other, and the aqueduct is arranged on the horizontal ground above the slope of the foundation pit. Above, there are a plurality of the drainage holes, which are arranged horizontally inside the slope, and the outlet of the drainage holes is located in the support grid.

进一步地,所述基坑表面喷洒有混凝土保护层,混凝土保护层可以加固基坑边坡表面,避免边坡产生滑坡。Further, the surface of the foundation pit is sprayed with a concrete protective layer, and the concrete protective layer can strengthen the surface of the side slope of the foundation pit and avoid landslides on the side slope.

进一步地,所述横支护架、竖支护架与基坑边坡外层锚固头固定焊接,加强固定效果,避免横支护架、竖支护架从外层锚固头处脱离。Further, the horizontal support frame and the vertical support frame are fixedly welded with the outer anchoring head of the foundation pit slope to strengthen the fixing effect and prevent the horizontal support frame and the vertical support frame from being separated from the outer anchoring head.

进一步地,所述横支护架、竖支护架的直径均小于通道直径的二分之一,使横支护架、竖支护架可以同时贯穿通道。Further, the diameters of the transverse support frame and the vertical support frame are both smaller than half of the diameter of the passage, so that the transverse support frame and the vertical support frame can penetrate the passage at the same time.

进一步地,所述剪斜筋上施加有预应力,预应力可以在支护网架内部产生预应张力,加强支护结构的稳定性。Further, prestressing is applied to the diagonal shear bars, and the prestressing can generate prestressing tension inside the supporting grid, thereby enhancing the stability of the supporting structure.

进一步地,所述导水渠与基坑边坡上端边缘平行,使边坡上方的水经导水渠排走,避免雨水冲刷边坡表面使边坡滑坡。Further, the aqueduct is parallel to the upper edge of the slope of the foundation pit, so that the water above the side slope is drained away through the aqueduct, so as to prevent the rainwater from scouring the surface of the slope and causing the slope to landslide.

本实用新型的施工方法是:勘测基坑边坡地质情况,确定锚固杆位置,将锚固头与锚固杆焊接后根据位置点将锚固杆夯入边坡内部,旋转锚固头方向,使一条直线上的锚固头内十字形通道分别处于同一直线上,然后分别将横支护杆和竖支护杆贯穿入通道,并将横支护杆、竖支护杆与外层锚固头连接处焊接,用剪斜筋连接互为顶角的两个锚固头上的连接头,向剪斜筋施加预应力并固定,向边坡表面喷洒一层混凝土层,待凝固后在边坡表面挖设排水孔,在边坡上方水平地面上挖设导水渠。The construction method of the utility model is as follows: surveying the geological conditions of the slope of the foundation pit, determining the position of the anchoring rod, after welding the anchoring head and the anchoring rod, ramming the anchoring rod into the interior of the slope according to the position point, and rotating the direction of the anchoring head so that a straight line The cross-shaped channels in the anchoring head are respectively on the same straight line, and then the transverse support rod and the vertical support rod are respectively penetrated into the channel, and the connection between the transverse support rod and the vertical support rod and the outer anchoring head is welded. The shear bars connect the connectors on the two anchoring heads that are at the top angle of each other, apply prestress to the shear bars and fix them, spray a layer of concrete on the surface of the slope, and dig drainage holes on the surface of the slope after solidification. An aqueduct shall be dug on the level ground above the slope.

与现有技术相比,本实用新型的有益效果是:本实用新型提供的一种基坑边坡支护结构,在锚固杆外端固定设置锚固头,在锚固头内部设置十字形通道,使横支护架和竖支护架分别贯穿通道并与锚固头固定,通过多点固定的方式对边坡进行支护,并且在互为顶角的两个锚固头之间连接施加有预应力的剪斜筋,使支护架构内部产生预应张力,增强了支护架构的稳定性,并且在边坡表面喷洒混凝土层,可以加固基坑边坡表面,避免边坡产生滑坡。总之,本实用新型具有结构新颖、施工难度低、支护效果好等优点。Compared with the prior art, the beneficial effects of the present utility model are as follows: the utility model provides a foundation pit slope support structure, an anchoring head is fixedly arranged at the outer end of the anchoring rod, and a cross-shaped channel is arranged inside the anchoring head, so that the The transverse support frame and the vertical support frame respectively penetrate the channel and are fixed with the anchoring head, support the slope by means of multi-point fixing, and connect the two anchoring heads which are at the apex of each other with a prestressed anchorage head. Shearing the diagonal reinforcement can generate prestressed tension inside the support structure and enhance the stability of the support structure, and spraying a concrete layer on the surface of the slope can strengthen the surface of the slope of the foundation pit and avoid landslides on the slope. In a word, the utility model has the advantages of novel structure, low construction difficulty, good supporting effect and the like.

附图说明Description of drawings

图1是本实用新型的整体结构示意图;Fig. 1 is the overall structure schematic diagram of the present utility model;

图2是本实用新型的锚固头结构示意图;Fig. 2 is the structural schematic diagram of the anchoring head of the present invention;

图3是本实用新型的锚固头剖视图;3 is a sectional view of the anchoring head of the present invention;

图4是本实用新型的支护网架结构示意图。Figure 4 is a schematic diagram of the structure of the support grid of the present invention.

其中,1-锚固杆、2-锚固头、21-通道、22-连接头、3-支护网架、31-横支护架、32-竖支护架、4-剪斜筋、5-导水渠、6-排水孔。Among them, 1-anchor rod, 2-anchor head, 21-channel, 22-connector, 3-support grid, 31-horizontal support, 32-vertical support, 4-shear diagonal bar, 5- Aqueduct, 6-drainage hole.

具体实施方式Detailed ways

为便于对本实用新型技术方案的理解,下面结合附图1-4和具体实施例对本实用新型做进一步的解释说明,实施例并不构成对本实用新型保护范围的限定。In order to facilitate the understanding of the technical solutions of the present utility model, the present utility model will be further explained below with reference to the accompanying drawings 1-4 and specific embodiments, which do not constitute a limitation on the protection scope of the present utility model.

如图1所示,一种基坑边坡支护结构,主要包括锚固杆1、锚固头2、支护网架3、剪斜筋4、导水渠5和排水孔6;As shown in Figure 1, a foundation pit slope support structure mainly includes an anchor rod 1, an anchor head 2, a support grid 3, a shear diagonal bar 4, an aqueduct 5 and a drainage hole 6;

锚固杆1共有多个,呈方形矩阵分别垂直夯入基坑边坡内,锚固杆1的外端露出坡面,锚固头2共有多个,锚固头2的底面与锚固杆1外端固定连接;There are many anchor rods 1, which are vertically rammed into the slope of the foundation pit in a square matrix. The outer end of the anchor rod 1 is exposed to the slope surface, and there are many anchor heads 2. The bottom surface of the anchor head 2 is fixedly connected with the outer end of the anchor rod 1. ;

如图2-3所示,锚固头2内部均设有十字型的通道21,且锚固头2的顶面设有连接头22;As shown in Figure 2-3, the anchoring head 2 is provided with a cross-shaped channel 21 inside, and the top surface of the anchoring head 2 is provided with a connecting head 22;

如图4所示,支护网架3包括横支护架31和竖支护架32,横支护架31共有多条,分别水平贯穿通道21,竖支护架32共有多条,分别竖直贯穿通道21,横支护架31、竖支护架32的直径均为通道21直径的四分之一,横支护架31、竖支护架32与基坑边坡外层锚固头2固定焊接,加强固定效果,避免横支护架31、竖支护架32从外层锚固头处脱离,剪斜筋4共有多条,分别连接在互为顶角的连接头22之间,剪斜筋4上施加有预应力,预应力可以在支护网架3内部产生预应张力,加强支护结构的稳定性,基坑表面喷洒有混凝土保护层,混凝土保护层可以加固基坑边坡表面,避免边坡产生滑坡;As shown in FIG. 4 , the support grid 3 includes a horizontal support frame 31 and a vertical support frame 32. There are a plurality of horizontal support frames 31, which penetrate the channel 21 horizontally, and a plurality of vertical support frames 32, which are respectively vertical. Straight through the channel 21, the diameters of the transverse support frame 31 and the vertical support frame 32 are one-fourth of the diameter of the channel 21. Welding is fixed to strengthen the fixing effect and prevent the horizontal support frame 31 and the vertical support frame 32 from being separated from the outer anchoring head. Prestressing force is applied to the diagonal bars 4, which can generate prestressing tension inside the support grid 3 to strengthen the stability of the support structure. The surface of the foundation pit is sprayed with a concrete protective layer, which can strengthen the slope of the foundation pit. surface to avoid landslides on slopes;

导水渠5设置在基坑边坡上方的水平地面上,导水渠5与基坑边坡上端边缘平行,使边坡上方的水经导水渠排走,避免雨水冲刷边坡表面使边坡滑坡,排水孔6共有多个,分别水平设置在边坡的内部,且排水孔6的出口位于支护网架3内。The aqueduct 5 is arranged on the horizontal ground above the slope of the foundation pit, and the aqueduct 5 is parallel to the upper edge of the slope of the foundation pit, so that the water above the side slope is drained through the aqueduct to avoid rainwater scouring the surface of the side slope and causing the side slope to landslide. There are a plurality of drainage holes 6 , which are respectively arranged horizontally inside the side slope, and the outlet of the drainage holes 6 is located in the support grid 3 .

本实施例的施工方法为:勘测基坑边坡地质情况,确定锚固杆1位置,将锚固头2与锚固杆1焊接后根据位置点将锚固杆1夯入边坡内部,旋转锚固头2方向,使一条直线上的锚固头2内十字形通道21分别处于同一直线上,然后分别将横支护杆31和竖支护杆32贯穿入通道21,并将横支护杆31、竖支护杆32与外层锚固头连接处焊接,用剪斜筋4连接互为顶角的两个锚固头2上的连接头,向剪斜筋4施加预应力并固定,向边坡表面喷洒一层混凝土层,待凝固后在边坡表面挖设排水孔6,在边坡上方水平地面上挖设导水渠5。The construction method of this embodiment is as follows: survey the geological conditions of the foundation pit slope, determine the position of the anchor rod 1, weld the anchor head 2 and the anchor rod 1, and ram the anchor rod 1 into the slope according to the position point, rotate the direction of the anchor head 2 , so that the cross-shaped channels 21 in the anchoring head 2 on a straight line are respectively on the same straight line, and then the transverse support rod 31 and the vertical support rod 32 are respectively penetrated into the channel 21, and the transverse support rod 31 and the vertical support rod The rod 32 is welded with the connection of the outer anchoring head, and the connecting joints on the two anchoring heads 2 that are at the top angle of each other are connected by the diagonal shear bars 4, and the shear diagonal bars 4 are prestressed and fixed, and a layer of a layer is sprayed on the surface of the slope. After the concrete layer is solidified, a drainage hole 6 is dug on the surface of the side slope, and an aqueduct 5 is dug on the horizontal ground above the side slope.

最后应说明的是:以上实施例仅用以说明本实用新型的技术方案,而非对其限制;尽管参照前述实施例对本实用新型进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本实用新型实施例技术方案的精神和范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present utility model, but not to limit them; although the present utility model has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: It is still possible to modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements to some of the technical features; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions in the embodiments of the present invention. .

Claims (6)

1.一种基坑边坡支护结构,其特征在于,主要包括锚固杆(1)、锚固头(2)、支护网架(3)、剪斜筋(4)、导水渠(5)和排水孔(6);1. a foundation pit slope support structure, is characterized in that, mainly comprises anchoring rod (1), anchoring head (2), support grid (3), shearing rib (4), aqueduct (5) and drainage holes (6); 所述锚固杆(1)共有多个,呈矩阵分别垂直夯入基坑边坡内,锚固杆(1)的外端露出坡面;There are a plurality of said anchor rods (1), which are vertically rammed into the slope of the foundation pit in a matrix, and the outer ends of the anchor rods (1) are exposed on the slope; 所述锚固头(2)共有多个,锚固头(2)的底面与锚固杆(1)外端固定连接,锚固头(2)内部均设有十字型的通道(21),且锚固头(2)的顶面设有连接头(22);There are multiple anchoring heads (2), the bottom surface of the anchoring head (2) is fixedly connected with the outer end of the anchoring rod (1), and a cross-shaped channel (21) is provided inside the anchoring head (2), and the anchoring head ( 2) The top surface is provided with a connector (22); 所述支护网架(3)包括横支护架(31)和竖支护架(32),所述横支护架(31)共有多条,分别水平贯穿所述通道(21),所述竖支护架(32)共有多条,分别竖直贯穿通道(21);The support net frame (3) includes a transverse support frame (31) and a vertical support frame (32). There are a plurality of the vertical support frames (32), which vertically penetrate the passages (21) respectively; 所述剪斜筋(4)共有多条,分别连接在互为顶角的连接头(22)之间;There are a plurality of said diagonal shear ribs (4), which are respectively connected between the connecting heads (22) which are vertices of each other; 所述导水渠(5)设置在基坑边坡上方的水平地面上;The aqueduct (5) is arranged on the horizontal ground above the slope of the foundation pit; 所述排水孔(6)共有多个,分别水平设置在边坡的内部,且排水孔(6)的出口位于支护网架(3)内。There are a plurality of the drainage holes (6), which are respectively arranged horizontally inside the side slope, and the outlet of the drainage holes (6) is located in the support grid (3). 2.根据权利要求1所述的一种基坑边坡支护结构,其特征在于,所述基坑表面喷洒有混凝土保护层。2 . The foundation pit slope support structure according to claim 1 , wherein a concrete protective layer is sprayed on the surface of the foundation pit. 3 . 3.根据权利要求1所述的一种基坑边坡支护结构,其特征在于,所述横支护架(31)、竖支护架(32)与基坑边坡外层锚固头(2)固定焊接。3. A kind of foundation pit slope support structure according to claim 1, is characterized in that, described transverse support frame (31), vertical support frame (32) and foundation pit slope outer layer anchoring head ( 2) Fixed welding. 4.根据权利要求1所述的一种基坑边坡支护结构,其特征在于,所述横支护架(31)、竖支护架(32)的直径均小于通道(21)直径的二分之一。4. A foundation pit slope support structure according to claim 1, characterized in that the diameters of the transverse support frame (31) and the vertical support frame (32) are both smaller than the diameter of the passage (21) Half. 5.根据权利要求1所述的一种基坑边坡支护结构,其特征在于,所述剪斜筋(4)上施加有预应力。5 . A foundation pit slope support structure according to claim 1 , wherein prestressing is applied to the diagonal shear bars ( 4 ). 6 . 6.根据权利要求1所述的一种基坑边坡支护结构,其特征在于,所述导水渠(5)与基坑边坡上端边缘平行。6 . The foundation pit slope support structure according to claim 1 , wherein the aqueduct ( 5 ) is parallel to the upper edge of the foundation pit slope. 7 .
CN201920634324.9U 2019-05-06 2019-05-06 Foundation pit slope supporting structure Expired - Fee Related CN209989819U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920634324.9U CN209989819U (en) 2019-05-06 2019-05-06 Foundation pit slope supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920634324.9U CN209989819U (en) 2019-05-06 2019-05-06 Foundation pit slope supporting structure

Publications (1)

Publication Number Publication Date
CN209989819U true CN209989819U (en) 2020-01-24

Family

ID=69293292

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920634324.9U Expired - Fee Related CN209989819U (en) 2019-05-06 2019-05-06 Foundation pit slope supporting structure

Country Status (1)

Country Link
CN (1) CN209989819U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356242A (en) * 2021-06-25 2021-09-07 江西省交通科学研究院有限公司 Slope supporting device and slope supporting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356242A (en) * 2021-06-25 2021-09-07 江西省交通科学研究院有限公司 Slope supporting device and slope supporting method
CN113356242B (en) * 2021-06-25 2022-10-14 江西省交通科学研究院有限公司 Slope supporting device and slope supporting method

Similar Documents

Publication Publication Date Title
CN108755377B (en) Construction method of deepwater non-covering layer steel trestle
CN106759376B (en) For closing on the construction method of the Anchored Sheet Pile Wall for Excavation system of existing underground structure
CN103498475B (en) Foundation pit supporting structure for controlling existing building deformation and construction method for excavating foundation pit
CN202208904U (en) Semi-mobile combined flood-control dam
CN204825914U (en) A reinforced concrete roof beam and fish belly sill combined supporting structure for complicated plane foundation ditch
CN205975658U (en) Steel platform tower crane foundation
CN203498839U (en) Foundation pit retaining structure for controlling deformation of existing building
CN209989819U (en) Foundation pit slope supporting structure
CN107476316B (en) Building foundation pit internal and external support structure and construction method
CN212452695U (en) Novel deep foundation pit side slope supporting structure
CN206418464U (en) A kind of Bailey bracket support system
CN210104765U (en) A tall and large retaining structure for weak geological slopes
CN204645058U (en) A kind ofly be provided with the H type Double-row-piles Structure adding core rotary churning pile
CN220099797U (en) Square skeleton slope protection structure is assembled fast
CN203034466U (en) High slope supporting structure closely attached to underground structure external wall
CN203583496U (en) Novel double-row-pile-beam vertical anchor supporting system
CN203498842U (en) Pile beam vertical anchor supporting system used for foundation pit supporting
CN206408631U (en) Anchored Sheet Pile Wall for Excavation system for closing on existing underground structure
CN111075452A (en) Geotechnical mixed vertical shaft engineering supporting system and vertical shaft construction method
CN216275721U (en) Soil-retaining back-pressure diagonal bracing combined foundation pit supporting structure
CN204401462U (en) For the support of pier prestressed cap beam with extra length Construction Supporting System in water
CN210562214U (en) Stable structure for preventing high fill side slope landslide
CN210031845U (en) Steel pipe pile anchor and slope releasing cooperative supporting structure
CN209523202U (en) Foundation pit supporting anchor pulling structure
CN219973247U (en) Supporting structure of high slope

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200124

Termination date: 20210506