CN209907149U - A municipal road drainage structure - Google Patents

A municipal road drainage structure Download PDF

Info

Publication number
CN209907149U
CN209907149U CN201920495261.3U CN201920495261U CN209907149U CN 209907149 U CN209907149 U CN 209907149U CN 201920495261 U CN201920495261 U CN 201920495261U CN 209907149 U CN209907149 U CN 209907149U
Authority
CN
China
Prior art keywords
water
drainage
road surface
water outlet
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920495261.3U
Other languages
Chinese (zh)
Inventor
冯小平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Daqin Construction Engineering Co Ltd
Original Assignee
Hubei Daqin Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Daqin Construction Engineering Co Ltd filed Critical Hubei Daqin Construction Engineering Co Ltd
Priority to CN201920495261.3U priority Critical patent/CN209907149U/en
Application granted granted Critical
Publication of CN209907149U publication Critical patent/CN209907149U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

A municipal road drainage structure comprises a kerbstone, wherein the kerbstone is arranged between a road surface and a green belt, the middle part of the kerbstone is provided with a water chute, one side of the water chute, facing the road surface, is provided with a first water inlet, one end of the first water inlet is connected with the water chute, and the other end of the first water inlet is positioned above the road surface; the drainage pipe is arranged in the stratum below the kerb, the first water outlet communicated with the drainage pipe is arranged at the bottom of the water guide groove, and one end of the drainage pipe is connected with the side wall of the sewer below the road surface. Adopt above-mentioned structure, can realize more efficient drainage purpose to solve the greenbelt ponding problem, guarantee the smooth and easy of drainage, avoid the drainage channel to block up the condition emergence that causes unable drainage.

Description

一种市政道路排水结构A municipal road drainage structure

技术领域technical field

本实用新型涉及市政施工领域,特别是一种市政道路排水结构。The utility model relates to the field of municipal construction, in particular to a municipal road drainage structure.

背景技术Background technique

市政道路施工中,道路的排水是非常重要的一项指标,现有的道路排水一般依靠水流在道路两侧流至下水道中以达到排水目的,但这种排水方式当雨水篦子被树叶垃圾阻挡之后,会导致排水效率严重降低,甚至会造成无法排水的情况;并且由于下水道是间隔一定距离设置的,在未设置下水道的路面位置很可能会造成积水,这部分积水的清理只能依靠人工扫除。In municipal road construction, road drainage is a very important indicator. Existing road drainage generally relies on water flow to the sewers on both sides of the road to achieve drainage purposes, but this drainage method occurs when the rainwater grate is blocked by leaves and garbage , it will lead to a serious reduction in drainage efficiency, and even cause the situation that drainage cannot be drained; and since the sewers are set at a certain distance, it is likely to cause water accumulation on the road surface where no sewers are installed, and the cleaning of this part of the water can only be done manually. remove.

发明内容SUMMARY OF THE INVENTION

本实用新型所要解决的技术问题是提供一种市政道路排水结构,能够实现更加高效的排水目的,并且解决绿化带积水问题,保证排水的顺畅,避免排水渠道堵塞造成无法排水的情况发生。The technical problem to be solved by the utility model is to provide a municipal road drainage structure, which can achieve the purpose of more efficient drainage, and solve the problem of water accumulation in the green belt, ensure smooth drainage, and avoid the situation that drainage cannot be drained due to clogging of drainage channels.

为解决上述技术问题,本实用新型所采用的技术方案是:一种市政道路排水结构,包括路缘石,路缘石设置在路面与绿化带之间,所述的路缘石中部设有导水槽,在导水槽朝向路面的一侧上设有第一进水口,第一进水口一端连接导水槽,另一端位于路面上方;In order to solve the above-mentioned technical problems, the technical scheme adopted by the present utility model is: a municipal road drainage structure, comprising curb stones, the curb stones are arranged between the road surface and the green belt, and a water guide groove is arranged in the middle of the curb stones, A first water inlet is arranged on the side of the water guide trough facing the road surface, one end of the first water inlet is connected to the water guide trough, and the other end is located above the road surface;

在路缘石下方的地层中设有排水管,导水槽底部设有与排水管连通的第一出水口,排水管一端连接位于路面下方的下水道侧壁。A drainage pipe is arranged in the stratum under the curb, and a first water outlet communicated with the drainage pipe is arranged at the bottom of the aqueduct, and one end of the drainage pipe is connected to the side wall of the sewer below the road surface.

优选的方案中,所述的排水管采用一端开口的管状结构,排水管的开口端为第二出水口,第二出水口与下水道连通,第二出水口上设有定位耳板,定位耳板上穿设有连接杆,连接杆远离第二出水口的一端上设有网板。In a preferred solution, the drainage pipe adopts a tubular structure with one end open, the open end of the drainage pipe is a second water outlet, the second water outlet is communicated with the sewer, the second water outlet is provided with a positioning lug plate, and the positioning lug plate A connecting rod is pierced through it, and a screen plate is provided on one end of the connecting rod away from the second water outlet.

优选的方案中,所述的网板尺寸与排水管的内部尺寸相同。In a preferred solution, the size of the mesh plate is the same as the internal size of the drain pipe.

优选的方案中,所述的绿化带包括位于底部的基层,基层上方设有碎石层,碎石层上方设有土壤层;In a preferred solution, the green belt includes a base layer at the bottom, a gravel layer is arranged above the base layer, and a soil layer is arranged above the gravel layer;

所述的基层是由第一组合块和第二组合块组成的板块状结构,其中第一组合块采用截面为直角梯形的板块状结构体,第二组合块采用截面为矩形的板块状结构体,第二组合块中直角梯形的斜腰朝上、直腰朝下设置,第二组合块固定设置在第一组合块的上底上,第二组合块上还设有竖直向的透水孔。The base layer is a plate-like structure composed of a first combination block and a second combination block, wherein the first combination block adopts a plate-shaped structure body with a right-angled trapezoid cross-section, and the second combination block adopts a plate-shaped structure body with a rectangular cross-section. , the oblique waist of the right-angled trapezoid in the second combination block is set up and the straight waist is facing down, the second combination block is fixedly arranged on the upper bottom of the first combination block, and the second combination block is also provided with vertical water-permeable holes .

优选的方案中,所述的排水管顶面上设有两个第二进水口,两个第二进水口分别与第一出水口、透水孔对齐设置。In a preferred solution, two second water inlets are provided on the top surface of the drainage pipe, and the two second water inlets are respectively arranged in alignment with the first water outlet and the permeable hole.

本实用新型所提供的一种市政道路排水结构,通过采用上述结构,具有以下有益效果:A municipal road drainage structure provided by the utility model, by adopting the above structure, has the following beneficial effects:

(1)通过路缘石内部的导水槽实现了路面各个区域的排水,避免了两个下水道之间的路面区域上的积水产生;(1) The drainage of each area of the road surface is realized through the water guide groove inside the curb stone, which avoids the generation of water accumulation on the road surface area between the two sewers;

(2)实现了绿化到积水的排放,避免了绿化带导致的雨水向地层中扩散,造成地层路基变软的情况;(2) The discharge from greening to stagnant water is realized, and the rainwater caused by the green belt is prevented from spreading into the stratum, resulting in the softening of the stratum roadbed;

(3)在排水管长期排水之后,堆积的垃圾淤泥可通过网板实现快速排出,实现了绿化带与下水道之间排水管快速清堵目的。(3) After the drainage pipe has been drained for a long time, the accumulated garbage and sludge can be quickly discharged through the mesh plate, and the purpose of quickly clearing the drainage pipe between the green belt and the sewer is realized.

附图说明Description of drawings

下面结合附图和实施例对本实用新型作进一步说明:Below in conjunction with accompanying drawing and embodiment, the utility model is further described:

图1为本实用新型的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure of the present invention.

图2为本实用新型的排水管结构示意图。Figure 2 is a schematic diagram of the structure of the drainage pipe of the present invention.

图3为本实用新型的排水管内部结构示意图。Figure 3 is a schematic diagram of the internal structure of the drain pipe of the present invention.

图4为本实用新型的基层结构示意图。4 is a schematic diagram of the basic structure of the present invention.

图中:路缘石1,导水槽2,第一进水口3,第一出水口4,排水管5,第二进水口501,下水道6,路面7,绿化带8,土壤层9,碎石层10,基层11,第一组合块111,第二组合块112,透水孔12,第二出水口13,连接杆14,定位耳板15,网板16。In the figure: curb 1, water guide 2, first water inlet 3, first water outlet 4, drain pipe 5, second water inlet 501, sewer 6, road surface 7, green belt 8, soil layer 9, gravel layer 10. Base layer 11, first combined block 111, second combined block 112, water permeable hole 12, second water outlet 13, connecting rod 14, positioning lug plate 15, mesh plate 16.

具体实施方式Detailed ways

如图1-4中,一种市政道路排水结构,包括路缘石1,路缘石1设置在路面7与绿化带8之间,所述的路缘石1中部设有导水槽2,在导水槽2朝向路面7的一侧上设有第一进水口3,第一进水口3一端连接导水槽2,另一端位于路面7上方;As shown in Figures 1-4, a municipal road drainage structure includes a curb stone 1. The curb stone 1 is arranged between the road surface 7 and the green belt 8. The curb stone 1 is provided with a water guide groove 2 in the middle. A first water inlet 3 is provided on the side facing the road surface 7, one end of the first water inlet 3 is connected to the water guide 2, and the other end is located above the road surface 7;

在路缘石1下方的地层中设有排水管5,导水槽2底部设有与排水管5连通的第一出水口4,排水管5一端连接位于路面7下方的下水道6侧壁。A drain pipe 5 is provided in the ground below the curb stone 1 , and a first water outlet 4 communicated with the drain pipe 5 is provided at the bottom of the water guide 2 .

优选的方案中,所述的排水管5采用一端开口的管状结构,排水管5的开口端为第二出水口13,第二出水口13与下水道6连通,第二出水口13上设有定位耳板15,定位耳板15上穿设有连接杆14,连接杆14远离第二出水口13的一端上设有网板16。In a preferred solution, the drainage pipe 5 adopts a tubular structure with one end open, and the open end of the drainage pipe 5 is the second water outlet 13, the second water outlet 13 is communicated with the sewer 6, and the second water outlet 13 is provided with a positioning The lug plate 15 is provided with a connecting rod 14 on the positioning lug plate 15 , and a mesh plate 16 is disposed on one end of the connecting rod 14 away from the second water outlet 13 .

优选的方案中,所述的网板16尺寸与排水管5的内部尺寸相同。In a preferred solution, the size of the mesh plate 16 is the same as the internal size of the drain pipe 5 .

优选的方案中,所述的绿化带8包括位于底部的基层11,基层11上方设有碎石层10,碎石层10上方设有土壤层9;In a preferred solution, the green belt 8 includes a base layer 11 at the bottom, a gravel layer 10 is arranged above the base layer 11, and a soil layer 9 is arranged above the gravel layer 10;

所述的基层11是由第一组合块111和第二组合块112组成的板块状结构,其中第一组合块111采用截面为直角梯形的板块状结构体,第二组合块112采用截面为矩形的板块状结构体,第二组合块112中直角梯形的斜腰朝上、直腰朝下设置,第二组合块112固定设置在第一组合块111的上底上,第二组合块112上还设有竖直向的透水孔12。The base layer 11 is a plate-like structure composed of a first combination block 111 and a second combination block 112, wherein the first combination block 111 adopts a plate-shaped structure with a right-angled trapezoid cross-section, and the second combination block 112 adopts a rectangular cross-section. The plate-like structure of the second combination block 112 is arranged with the oblique waist of the right-angled trapezoid facing upward and the straight waist facing downward, the second combination block 112 is fixedly arranged on the upper bottom of the first combination block 111, and the second combination block There are also vertical water permeable holes 12 .

优选的方案中,所述的排水管5顶面上设有两个第二进水口501,两个第二进水口501分别与第一出水口4、透水孔12对齐设置。In a preferred solution, two second water inlets 501 are provided on the top surface of the drainage pipe 5 , and the two second water inlets 501 are respectively arranged in alignment with the first water outlet 4 and the permeable hole 12 .

本新型的排水原理如下:The new drainage principle is as follows:

下雨时,下水道6附近的雨水顺着路面穿过雨水篦子流入下水道6中,而位于两个相邻下水道6之间区域内的雨水则穿过第一进水口3进入路缘石1中的导水槽2中,流至靠近下水道6的位置时,穿过导水槽2下方的第一出水口4后进入排水管5并最终排至下水道6中,有效避免了未设置下水道6的路面7区段内的积水产生;When it rains, the rainwater near the sewer 6 flows into the sewer 6 through the rain grate along the road, while the rainwater in the area between two adjacent sewers 6 passes through the first water inlet 3 and enters the guide in the curb 1. In the water tank 2, when it flows to the position close to the sewer 6, it passes through the first water outlet 4 under the water guide tank 2 and then enters the drain pipe 5 and finally discharges into the sewer 6, effectively avoiding the section of the road surface 7 where the sewer 6 is not provided. stagnant water inside;

绿化带8中的积水穿过碎石层10后顺着基层11流至透水孔12中并落入排水管5,达到绿化带8积水排放目的。The accumulated water in the green belt 8 passes through the gravel layer 10 and flows along the base layer 11 to the permeable hole 12 and falls into the drainage pipe 5 , so as to achieve the purpose of discharging the accumulated water in the green belt 8 .

当需要对排水管5进行清淤疏通作业时,打开雨水篦子并手动拉动连接杆14,使网板16带动淤泥垃圾落入下水道6中。When the drainage pipe 5 needs to be dredged and dredged, the rainwater grate is opened and the connecting rod 14 is manually pulled, so that the mesh plate 16 drives the silt garbage into the sewer 6 .

采用上述结构,通过路缘石内部的导水槽实现了路面各个区域的排水,避免了两个下水道之间的路面区域上的积水产生;实现了绿化到积水的排放,避免了绿化带导致的雨水向地层中扩散,造成地层路基变软的情况;在排水管长期排水之后,堆积的垃圾淤泥可通过网板实现快速排出,实现了绿化带与下水道之间排水管快速清堵目的。By adopting the above structure, the drainage of each area of the road surface is realized through the water guiding groove inside the curb stone, which avoids the generation of water accumulation on the road surface area between the two sewers; realizes the discharge from the greening to the accumulated water, and avoids the pollution caused by the green belt. Rainwater diffuses into the stratum, causing the subgrade of the stratum to become soft; after long-term drainage by the drainage pipe, the accumulated garbage and silt can be quickly discharged through the mesh plate, realizing the purpose of quickly clearing the drainage pipe between the green belt and the sewer.

Claims (5)

1.一种市政道路排水结构,包括路缘石(1),路缘石(1)设置在路面(7)与绿化带(8)之间,其特征是:所述的路缘石(1)中部设有导水槽(2),在导水槽(2)朝向路面(7)的一侧上设有第一进水口(3),第一进水口(3)一端连接导水槽(2),另一端位于路面(7)上方;1. A municipal road drainage structure, comprising a curb stone (1), and the curb stone (1) is arranged between a road surface (7) and a green belt (8), characterized in that: the curb stone (1) is provided in the middle part. There is a water guide groove (2), a first water inlet (3) is provided on the side of the water guide groove (2) facing the road surface (7), one end of the first water inlet (3) is connected to the water guide groove (2), and the other end is located in the Above the road surface (7); 在路缘石(1)下方的地层中设有排水管(5),导水槽(2)底部设有与排水管(5)连通的第一出水口(4),排水管(5)一端连接位于路面(7)下方的下水道(6)侧壁。A drain pipe (5) is provided in the stratum below the curb stone (1), and a first water outlet (4) communicated with the drain pipe (5) is arranged at the bottom of the water guide groove (2), and one end of the drain pipe (5) is connected to the drain pipe (5). Sewer (6) sidewall below the road surface (7). 2.根据权利要求1所述的一种市政道路排水结构,其特征在于:所述的排水管(5)采用一端开口的管状结构,排水管(5)的开口端为第二出水口(13),第二出水口(13)与下水道(6)连通,第二出水口(13)上设有定位耳板(15),定位耳板(15)上穿设有连接杆(14),连接杆(14)远离第二出水口(13)的一端上设有网板(16)。2. A municipal road drainage structure according to claim 1, characterized in that: the drainage pipe (5) adopts a tubular structure with one end open, and the open end of the drainage pipe (5) is the second water outlet (13). ), the second water outlet (13) is communicated with the sewer (6), the second water outlet (13) is provided with a positioning lug plate (15), and the positioning lug plate (15) is provided with a connecting rod (14), connecting the A screen plate (16) is provided on one end of the rod (14) away from the second water outlet (13). 3.根据权利要求2所述的一种市政道路排水结构,其特征在于:所述的网板(16)尺寸与排水管(5)的内部尺寸相同。3. A municipal road drainage structure according to claim 2, characterized in that: the size of the mesh plate (16) is the same as the internal size of the drainage pipe (5). 4.根据权利要求1所述的一种市政道路排水结构,其特征在于:所述的绿化带(8)包括位于底部的基层(11),基层(11)上方设有碎石层(10),碎石层(10)上方设有土壤层(9);4. A municipal road drainage structure according to claim 1, characterized in that: the green belt (8) comprises a base layer (11) at the bottom, and a gravel layer (10) is arranged above the base layer (11). , a soil layer (9) is arranged above the gravel layer (10); 所述的基层(11)是由第一组合块(111)和第二组合块(112)组成的板块状结构,其中第一组合块(111)采用截面为直角梯形的板块状结构体,第二组合块(112)采用截面为矩形的板块状结构体,第二组合块(112)中直角梯形的斜腰朝上、直腰朝下设置,第二组合块(112)固定设置在第一组合块(111)的上底上,第二组合块(112)上还设有竖直向的透水孔(12)。The base layer (11) is a plate-like structure composed of a first combined block (111) and a second combined block (112), wherein the first combined block (111) adopts a plate-like structure with a right-angled trapezoid cross-section, The second combination block (112) adopts a plate-like structure with a rectangular cross-section, the right-angled trapezoid in the second combination block (112) is arranged with the oblique waist up and the straight waist down, and the second combination block (112) is fixedly arranged on the first combination block (112). On the upper bottom of the combination block (111), the second combination block (112) is further provided with a vertical water permeable hole (12). 5.根据权利要求4所述的一种市政道路排水结构,其特征在于:所述的排水管(5)顶面上设有两个第二进水口(501),两个第二进水口(501)分别与第一出水口(4)、透水孔(12)对齐设置。5. A municipal road drainage structure according to claim 4, characterized in that: the top surface of the drainage pipe (5) is provided with two second water inlets (501), and the two second water inlets ( 501) are respectively aligned with the first water outlet (4) and the water permeable hole (12).
CN201920495261.3U 2019-04-12 2019-04-12 A municipal road drainage structure Expired - Fee Related CN209907149U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920495261.3U CN209907149U (en) 2019-04-12 2019-04-12 A municipal road drainage structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920495261.3U CN209907149U (en) 2019-04-12 2019-04-12 A municipal road drainage structure

Publications (1)

Publication Number Publication Date
CN209907149U true CN209907149U (en) 2020-01-07

Family

ID=69036201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920495261.3U Expired - Fee Related CN209907149U (en) 2019-04-12 2019-04-12 A municipal road drainage structure

Country Status (1)

Country Link
CN (1) CN209907149U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636274A (en) * 2020-05-28 2020-09-08 浙江士高环境建设工程有限公司 Town road drainage structures

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636274A (en) * 2020-05-28 2020-09-08 浙江士高环境建设工程有限公司 Town road drainage structures

Similar Documents

Publication Publication Date Title
CN103548601B (en) Tree pool and method for filtering runoff rainwater through tree pool
CN108104247B (en) Mixed flow non-concave biological detention pool with initial rainwater discarding function
CN102531282A (en) Device and method for quality-based rainwater collection, treatment and utilization
CN102926452A (en) Offline rainwater control system for road
CN108797756A (en) Rain penetration purifies savings system in a kind of landscape planting
CN111255042A (en) Ecological tree pool with floater for automatically controlling initial rainwater drainage and working method
CN211816758U (en) Irrigation system is collected to town road rainwater
CN207727657U (en) A kind of bottom flood control of slope course and Rainwater collection system
CN206245444U (en) rainwater infiltration system
CN108374477A (en) A kind of device collected for road initial rainwater with processing
CN201284492Y (en) Simple and practical overhead road rainwater utilization system
CN207469027U (en) A kind of road drainage structure
CN211112984U (en) Prevent ponding and prevent sponge urban road of jam
CN115787392B (en) A system for collecting, diverting and reducing rainwater runoff from slopes
CN107354990A (en) A kind of storage for roadside oozes net row's type rainwater reuse device
CN207582227U (en) A kind of improved road surface drainage device
CN207109988U (en) A kind of storm-water system
CN212689073U (en) Green energy-saving building rainwater collecting and processing system
CN209890992U (en) a drainage system
CN209556250U (en) Prefabricated standpipe abandoned stream module and the standpipe abandoned stream formula sponge device of rain water on roof disconnecting
CN216474327U (en) Urban road type pavement structure that permeates water
CN211446447U (en) Urban hardened road is with preventing blockking up hydrophobic means
CN201367590Y (en) Water permeable material
CN223017772U (en) Street drainage system
CN206337632U (en) Disposal pool

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200107

CF01 Termination of patent right due to non-payment of annual fee