CN209835486U - High-rise hoisting equipment - Google Patents

High-rise hoisting equipment Download PDF

Info

Publication number
CN209835486U
CN209835486U CN201920773004.1U CN201920773004U CN209835486U CN 209835486 U CN209835486 U CN 209835486U CN 201920773004 U CN201920773004 U CN 201920773004U CN 209835486 U CN209835486 U CN 209835486U
Authority
CN
China
Prior art keywords
hoisting
rope
rise
guide
hoist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920773004.1U
Other languages
Chinese (zh)
Inventor
龙志伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920773004.1U priority Critical patent/CN209835486U/en
Application granted granted Critical
Publication of CN209835486U publication Critical patent/CN209835486U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The embodiment of the utility model discloses high-rise hoisting equipment relates to hoist and mount construction technical field, and its technical scheme includes hoist and mount frame, carries out the hoist and mount subassembly that goes up and down and drive the first drive assembly of hoist and mount subassembly motion to hoist and mount frame, the hoist and mount subassembly is including setting up the first pulley on building body parapet and around establishing the jack-up rope on first pulley, the one end and the drive assembly fixed connection of jack-up rope, the other end is fixed with hoist and mount frame, the height that highly is less than building body parapet department that drive assembly located. The problem of conveying efficiency is low, poor stability and extravagant manpower and materials among the prior art is solved for.

Description

High-rise hoisting equipment
Technical Field
The embodiment of the utility model provides a relate to hoist and mount construction technical field, concretely relates to high-rise lifting device.
Background
With the development of science and technology and the continuous improvement of construction technology, high-rise buildings are increased gradually, and when goods need to be transported to a place with a higher floor, a manual carrying mode is usually adopted, but the mode not only wastes manpower, material resources and time, but also has lower transportation efficiency and poor safety, and workers are easily injured by carrying the goods upstairs and downstairs.
Still another mode of promoting the goods adopts small-size electric block hoist and mount technique, however, this kind of mode is when promoting the goods, and the anti-wind ability is little, and the goods rocks in the air easily, and poor stability is dangerous, and the in-process of promoting the goods causes the damage to the building body outer wall easily.
SUMMERY OF THE UTILITY MODEL
Therefore, the embodiment of the utility model provides a high-rise hoisting equipment to the problem of conveying efficiency is low, poor stability and extravagant manpower and materials among the solution prior art.
In order to achieve the above object, the embodiment of the present invention provides the following technical solutions:
according to the embodiment of the utility model provides a high-rise hoisting equipment, its technical scheme main points include hoist and mount frame, carry out the hoist and mount subassembly that goes up and down and drive the first drive assembly of hoist and mount subassembly motion to hoist and mount frame, hoist and mount subassembly is including setting up the first pulley on building body parapet and around establishing the jack-up rope on first pulley, the one end and the drive assembly fixed connection of jack-up rope, the other end is fixed with hoist and mount frame, the height that highly is less than building body parapet department that drive assembly located.
Further, the first drive assembly is a hoist winch.
Further, this lifting device still includes the direction subassembly that plays the guide effect to the lift and fall of hoisting frame.
Furthermore, the guide assembly comprises a pair of guide pulleys arranged at two ends of the hoisting frame, a pair of guide ropes wound on the two guide pulleys respectively, and a second driving assembly for driving the guide ropes to wind, wherein one end of each guide rope is fixed with the second driving assembly, and the other end of each guide rope is fixed with the parapet wall of the building body.
Further, the second driving assembly is a double-track screw winch.
Further, the fixed support that is provided with on building body parapet, the support includes that a pair of level sets up and the last bracing piece that is parallel to each other, bottom suspension mast and rigid coupling are at last bracing piece and bottom suspension mast between, first pulley is installed on the bottom suspension mast, the tip of direction rope is fixed with the both ends of last bracing piece.
Further, a truck is arranged on the ground, and the hoisting winch and the double-track spiral winch are both fixed on a truck girder.
Furthermore, a jack is arranged at the bottom of the truck and at the tail of the truck.
Furthermore, the hoisting rope is a steel wire rope.
Further, the diameter of the guide rope is 8-15 mm.
The embodiment of the utility model provides a have following advantage:
the embodiment of the utility model provides a through the hoist and mount frame that sets up, hoisting assembly and first drive assembly, can realize the lift to the goods, guide assembly through setting up, can lead to hoist and mount frame and be located the goods on the hoist and mount frame, make hoist and mount frame can only move along the direction rope, avoid the hoist and mount frame to rock in aerial production and cause the unnecessary to damage, freight train through setting up, the freight train plays certain traction, thereby can change the distance between direction rope and the building body, keep away from the building body when making the goods lift, the goods is close to the building body after reacing and puts into the building with the goods is smooth, also avoid causing the damage to the building body outer wall, jack through setting up, can jack up the afterbody of freight train, make the unable activity of freight train, improve the stability of goods lift in-process.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It should be apparent that the drawings in the following description are merely exemplary, and that other embodiments can be derived from the drawings provided by those of ordinary skill in the art without inventive effort.
The structure, ratio, size and the like shown in the present specification are only used for matching with the content disclosed in the specification, so as to be known and read by people familiar with the technology, and are not used for limiting the limit conditions which can be implemented by the present invention, so that the present invention has no technical essential significance, and any structure modification, ratio relationship change or size adjustment should still fall within the scope which can be covered by the technical content disclosed by the present invention without affecting the efficacy and the achievable purpose of the present invention.
Fig. 1 is a schematic view of an overall structure of a high-rise hoisting device according to an embodiment of the present invention;
fig. 2 is a front view of a high-rise hoisting device provided by an embodiment of the present invention.
In the figure: 1. a hoisting frame; 2. hoisting the assembly; 21. a support; 211. an upper support rod; 212. a lower support bar; 213. a force bearing rod; 22. a first pulley; 23. a hoisting rope; 3. a hoisting winch; 4. a truck; 5. a guide assembly; 51. a guide pulley; 52. a guide rope; 6. a double-track screw capstan; 7. a jack.
Detailed Description
The present invention is described in terms of specific embodiments, and other advantages and benefits of the present invention will become apparent to those skilled in the art from the following disclosure. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the present specification, the terms "upper", "lower", "left", "right", "middle", and the like are used for the sake of clarity only, and are not intended to limit the scope of the present invention, and changes or adjustments of the relative relationship thereof are also considered to be the scope of the present invention without substantial changes in the technical content.
A high-rise hoisting device is shown in figures 1 and 2 and comprises a hoisting frame 1, a hoisting assembly 2 for lifting the hoisting frame 1 and a first driving assembly for driving the hoisting assembly 2 to move. The hoisting assembly 2 comprises a bracket 21 arranged on the parapet wall of the building body, a first pulley 22 arranged at the bottom of the bracket 21 and a hoisting rope 23 wound on the first pulley 22. The first drive assembly is a hoisting winch 3. One end of the hoisting rope 23 is fixedly connected with the hoisting winch 3, the other end of the hoisting rope is fixed with the hoisting frame 1, and the height of the hoisting winch 3 is lower than that of the parapet of the building body. And starting the hoisting winch 3, wherein the hoisting winch 3 drives the hoisting rope 23 to wind or unreel, so that the hoisting frame 1 ascends and descends. The hoisting rope 23 is made of steel wire rope, is firm and firm, is not easy to damage, and ensures the safety in the hoisting process.
As shown in fig. 1 and 2, the bracket 21 includes a pair of upper support rods 211 and lower support rods 212 that are horizontally disposed and parallel to each other, and a force bearing rod 213 that is fixedly connected between the upper support rods 211 and the lower support rods 212, and the first pulley 22 is mounted on the lower support rods 212.
As shown in fig. 1 and 2, a truck 4 is provided on the ground, and a hoist winch 3 is fixed to a girder of the truck 4. The hoisting equipment also comprises a guide component 5 which plays a role in guiding the lifting of the hoisting frame 1. The guide assembly 5 comprises a pair of guide pulleys 51 arranged at two ends of the hoisting frame 1, a pair of guide ropes 52 respectively wound on the two guide pulleys 51, and a second driving assembly for driving the guide ropes 52 to wind. The second driving component is a double-track screw capstan 6, one end of each of the two guide ropes 52 is fixed to the double-track screw capstan 6, and the other end is fixed to two ends of an upper support rod 211 of the support 21. The diameter of the guide rope 52 is 8 mm-15 mm.
When the hoisting frame 1 ascends and descends, the guide ropes 52 rotate in the guide pulleys 51 at the two ends of the hoisting frame 1, so that a certain guide effect can be achieved on the lifting of the hoisting frame 1, and unnecessary damage caused by the fact that the hoisting frame 1 shakes in the air is avoided.
Through the freight train 4 that sets up, freight train 4 plays certain traction to can change the distance between direction rope 52 and the building body, keep away from the building body when making the goods lift, the goods arrives and is close to the building body and puts into the building smoothly with the goods in, also avoids causing the damage to the building body outer wall.
As shown in fig. 1, a jack 7 is provided at the bottom of the truck 4 at the rear of the vehicle. When hoisting the goods, the jack 7 is used for jacking the tail part of the truck 4, so that the truck 4 cannot move, and the stability of the goods in the lifting process is improved.
Although the invention has been described in detail with respect to the general description and the specific embodiments, it will be apparent to those skilled in the art that modifications and improvements can be made based on the invention. Therefore, such modifications and improvements are intended to be within the scope of the invention as claimed.

Claims (10)

1. A high-rise hoisting equipment is characterized in that: including hoisting frame (1), hoist and mount subassembly (2) and the first drive assembly of drive hoisting subassembly (2) motion that goes up and down hoisting frame (1), hoisting assembly (2) are including setting up first pulley (22) on building body parapet and around hoisting rope (23) of establishing on first pulley (22), the one end and the drive assembly fixed connection of hoisting rope (23), the other end is fixed with hoisting frame (1), the height that highly is less than building body parapet and locates that drive assembly locates.
2. The high-rise hoisting device according to claim 1, characterized in that: the first driving component is a hoisting winch (3).
3. The high-rise hoisting device according to claim 2, characterized in that: the hoisting equipment also comprises a guide component (5) which plays a role in guiding the lifting of the hoisting frame (1).
4. A high-rise hoisting device according to claim 3, characterized in that: the guide assembly (5) comprises a pair of guide pulleys (51) arranged at two ends of the hoisting frame (1), a pair of guide ropes (52) respectively wound on the two guide pulleys (51) and a second driving assembly for driving the guide ropes (52) to wind, one end of each guide rope (52) is fixed with the second driving assembly, and the other end of each guide rope is fixed with a parapet of the building body.
5. The high-rise hoisting device according to claim 4, characterized in that: the second driving component is a double-track screw winch (6).
6. The high-rise hoisting device according to claim 4, characterized in that: fixed support (21) that is provided with on building body parapet, support (21) include a pair of level setting and last bracing piece (211) that is parallel to each other, lower support rod (212) and rigid coupling bearing pole (213) between last bracing piece (211) and lower support rod (212), first pulley (22) are installed on lower support rod (212), the tip of direction rope (52) is fixed with the both ends of last bracing piece (211).
7. The high-rise hoisting device according to claim 5, characterized in that: a truck (4) is arranged on the ground, and the hoisting winch (3) and the double-track spiral winch (6) are fixed on a girder of the truck (4).
8. The high-rise hoisting device according to claim 7, characterized in that: and a jack (7) is arranged at the bottom of the truck (4) and at the tail of the truck.
9. The high-rise hoisting device according to claim 1, characterized in that: the hoisting rope (23) is a steel wire rope.
10. The high-rise hoisting device according to claim 4, characterized in that: the diameter of the guide rope (52) is 8-15 mm.
CN201920773004.1U 2019-05-27 2019-05-27 High-rise hoisting equipment Active CN209835486U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920773004.1U CN209835486U (en) 2019-05-27 2019-05-27 High-rise hoisting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920773004.1U CN209835486U (en) 2019-05-27 2019-05-27 High-rise hoisting equipment

Publications (1)

Publication Number Publication Date
CN209835486U true CN209835486U (en) 2019-12-24

Family

ID=68898012

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920773004.1U Active CN209835486U (en) 2019-05-27 2019-05-27 High-rise hoisting equipment

Country Status (1)

Country Link
CN (1) CN209835486U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113401809A (en) * 2021-07-29 2021-09-17 中青建安建设集团有限公司 Curtain wall unit body hoisting system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113401809A (en) * 2021-07-29 2021-09-17 中青建安建设集团有限公司 Curtain wall unit body hoisting system

Similar Documents

Publication Publication Date Title
CN208352858U (en) Control adjustable length high-altitude power equipment maintaining takes sundries
CN209835486U (en) High-rise hoisting equipment
CN214879790U (en) Movable arm tower crane
CN201495051U (en) Crane jib for flat-top tower crane
CN212374757U (en) Tower crane stable in installation
CN201183702Y (en) Novel silo hoisting device using movable pulley
CN210795435U (en) Synchronous construction elevator
CN105645275B (en) Cable hoist and its construction method
CN201411334Y (en) Simple traveling crane
CN215924103U (en) Underneath type telescopic assembling top beam for elevator
CN215798047U (en) Special crane for grinding roller
CN212687285U (en) Special lift of building installation engineering
CN201762053U (en) Simple automatic derrick
CN212581362U (en) High-efficient material hoist for building engineering
CN212612602U (en) Offshore wind power suction tube jacket installation device
CN210559078U (en) Small-size material lifting machine
CN203624932U (en) Portable indoor material lifter
CN218114875U (en) Building material lifting machine
CN218058173U (en) Boom convenient to disassemble and assemble for construction elevator
CN104261278B (en) Bipod mast lifting system with flexible guide rail and hanging method
CN206014260U (en) Support rope structure
CN211078293U (en) High-altitude hoisting prefabricated part symmetrical equipment
CN220376298U (en) Hanging basket lifting device
CN214935431U (en) Gantry crane with anti-rolling function
CN216155257U (en) Traction construction elevator

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant