CN209723226U - A kind of large span steel structure roof entirety lift structure - Google Patents

A kind of large span steel structure roof entirety lift structure Download PDF

Info

Publication number
CN209723226U
CN209723226U CN201920234943.9U CN201920234943U CN209723226U CN 209723226 U CN209723226 U CN 209723226U CN 201920234943 U CN201920234943 U CN 201920234943U CN 209723226 U CN209723226 U CN 209723226U
Authority
CN
China
Prior art keywords
steel
leading truck
twisted wire
roof
lift
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920234943.9U
Other languages
Chinese (zh)
Inventor
冉聪
陈建华
李松晏
朱永新
郑捷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN201920234943.9U priority Critical patent/CN209723226U/en
Application granted granted Critical
Publication of CN209723226U publication Critical patent/CN209723226U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of large span steel structure roof entirety lift structure, including flexible steel twisted wire, hydraulic rockshaft and leading truck, hydraulic rockshaft is set to the side of leading truck, the lift side of hydraulic rockshaft is fixed in one end of flexible steel twisted wire, the other end of flexible steel twisted wire is bypassed by the upper end of leading truck, and for being connected with steel structural roof, steel structural roof is drawn as load-bearing rigging.The problems such as required precision height big to avoid steel structural overhead weld job amount, assembled, security protection difficulty is big, and it is complex to construct, and difficulty is big.Belong to construction and assists novel technical field of construction.

Description

A kind of large span steel structure roof entirety lift structure
Technical field
The utility model relates to a kind of large span steel structure roof entirety lift structures, belong to construction and assist novel apply Work technical field.
Background technique
With the development of the social economy, steel construction structures are more and more, the difficulty of construction of steel construction is increasingly Greatly.Traditional Construction of Steel Structure method has installation at high altitude etc., but installation at high altitude is for Construction of Steel Structure, in safety assurance There is biggish difficulty in terms of quality control on construction.
Summary of the invention
The purpose of this utility model is that: a kind of large span steel structure roof entirety lift structure is provided, to avoid steel knot Structure overhead welding workload is big, and assembled required precision is high, and security protection difficulty is big, and it is complex to construct, and difficulty is big etc. asks Topic.
To solve the above problems, such a large span steel structure roof entirety lift structure of proposed adoption, including flexible steel Twisted wire, hydraulic rockshaft and leading truck, hydraulic rockshaft are set to the side of leading truck, and liquid is fixed in one end of flexible steel twisted wire The lift side of lifter is pressed, the other end of flexible steel twisted wire is bypassed by the upper end of leading truck, and for being connected with steel structural roof, Steel structural roof is drawn as load-bearing rigging.
Compared with prior art, the utility model uses flexible rigging load-bearing, as long as there is reasonable load-bearing suspension centre, is promoted high It spends unrestricted;Automation degree of equipment is high, and flexible operation, safety is good, and high reliablity, use is wide, versatile;It saves The operation of large-scale crane can greatly save mechanical equipment, human resources;Using whole promotion, spelled on ground in face of steel construction Dress and welding, smaller safety management and quality testing difficulty and while convenient for control construction quality, reduce difficulty of construction And can make full use of Contraction in Site face, shorten the whole duration.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is computer control principle figure.
Specific embodiment
To keep the purpose of this utility model, technical solution and advantage clearer, the utility model will be made into one below The detailed description of step.
Embodiment:
Referring to attached drawing 1 and Fig. 2, the present embodiment provides a kind of large span steel structure roof entirety lift structures, including flexibility Steel strand wires 1, hydraulic rockshaft 2 and leading truck 3, hydraulic rockshaft 2 are core-theaded type structure, and hydraulic rockshaft 2 is set to leading truck 3 Side, one end of flexible steel twisted wire 1 is fixed on the lift side of hydraulic rockshaft 2, and the other end of flexible steel twisted wire 1 is by leading truck 3 upper end bypasses, and for being connected with steel structural roof (truss lift unit), is promoted as load-bearing rigging traction truss single Member, every good leading truck 3 of 2 configured in advance of hydraulic rockshaft, the export for facilitating its top to reserve excessive steel strand wires are smooth.Extra Steel strand wires can freely be dredged backward, downwards along platform is promoted.Hydraulic pump source system is that hydraulic rockshaft 2 provides power, and passes through Controller is controlled and is adjusted to more or separate unit hydraulic rockshaft 2, and hydraulic synchronizing lifting computer control system is executed Instruct simultaneously feedback data.
Its comprehensive construction method is as follows:
Step 1: installation hydraulic synchronizing lifting system equipment, including hydraulic pump source system, hydraulic rockshaft 2 and sensor, Hydraulic pump source system is that hydraulic rockshaft 2 provides power, and sensor includes anchorage sensor, displacement sensor and pressure sensing Device debugs hydraulic synchronizing lifting system, tensioning flexible steel twisted wire 1, so that 1 uniform stressed of all flexible steel twisted wires;
Step 2: whether all interim measures of inspection truss lift unit and hydraulic synchronizing lifting, which meet design, is wanted It asks;Confirm it is errorless after, according to the 20% of design load, 40%, 60%, 70%, 80%, 90%, 95%, 100% sequence by Grade load, until lift unit is detached from platform for lining;
Step 3: after roof truss promotes about 150mm, pause is promoted;The absolute altitude for finely tuning each suspension centre of lift unit, makes It is in level, and stands 4~12 hours, checks again for truss lift unit and hydraulic synchronizing lifting interim measure is no different Often, after confirming situation without exception, start formal promoted;
Step 4: the whole roof truss lift unit that promoted is promoted to close to installed height mark pause;
Step 5: measurement truss lift unit each point actual size after checking and handle with design value, reduces and promotes speed Degree continues to lift up roof truss close to design position, and each " fine tuning, crawl " function of promoting suspension centre and pass through computer system makes Each suspension centre that promoted reaches design position, meets docking and requires;
Step 6: after roof truss mating operation, each suspension centre sequence of hydraulic lifting system is unloaded, and turns roof system self weight It moves in main structure, reaches design point;Hydraulic lifting device is removed, it is entire to promote operation completion.
Above embodiments are only to illustrate rather than limit the technical solution of the utility model, although referring to above-described embodiment pair The utility model is described in detail, it will be apparent to an ordinarily skilled person in the art that: still can to the utility model into Row modification or equivalent replacement should all without departing from any modification or partial replacement of the spirit and scope of the utility model Cover in the scope of the claims of the utility model.

Claims (1)

1. a kind of large span steel structure roof entirety lift structure, it is characterised in that: including flexible steel twisted wire (1), hydraulic pressure lift Device (2) and leading truck (3), hydraulic rockshaft (2) are set to the side of leading truck (3), and one end of flexible steel twisted wire (1) is fixed on The other end of the lift side of hydraulic rockshaft (2), flexible steel twisted wire (1) is bypassed by the upper end of leading truck (3), and is used for and steel knot Structure roof system is connected, and draws steel structural roof as load-bearing rigging.
CN201920234943.9U 2019-02-25 2019-02-25 A kind of large span steel structure roof entirety lift structure Active CN209723226U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920234943.9U CN209723226U (en) 2019-02-25 2019-02-25 A kind of large span steel structure roof entirety lift structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920234943.9U CN209723226U (en) 2019-02-25 2019-02-25 A kind of large span steel structure roof entirety lift structure

Publications (1)

Publication Number Publication Date
CN209723226U true CN209723226U (en) 2019-12-03

Family

ID=68683884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920234943.9U Active CN209723226U (en) 2019-02-25 2019-02-25 A kind of large span steel structure roof entirety lift structure

Country Status (1)

Country Link
CN (1) CN209723226U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109868902A (en) * 2019-02-25 2019-06-11 中建四局第一建筑工程有限公司 A kind of large span steel structure roof entirety lift structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109868902A (en) * 2019-02-25 2019-06-11 中建四局第一建筑工程有限公司 A kind of large span steel structure roof entirety lift structure

Similar Documents

Publication Publication Date Title
CN107012949B (en) A kind of method for improving of large-span steel vestibule
CN106437178B (en) A kind of multi-storey steel structure vestibule construction method for lifting whole and device
CN101746675B (en) Crane super lifting device, control system and control method thereof
CN104631839B (en) Ultra-high overweight large span aerial vestibule construction method for lifting whole
CN106193618B (en) A kind of aerial steel structure truss construction of Long span
CN102094489B (en) Double-layer bidirectional prestressed cable truss and construction method thereof
CN110344501A (en) A kind of construction method that Steel corridor is integrally promoted
CN102168405B (en) Construction method of steel-concrete mixed Y-shaped tower of low-pylon cable-stayed bridge
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN107060105B (en) A kind of lifting construction method of multiple steel vestibules between high building
CN107445084A (en) Large-scale vestibule steel structure hoisting instrument and hoisting
CN103075025A (en) Wholly lifting construction method for asymmetric structure of huge overhang steel of high-rise building
CN103395695A (en) Super-lifting winch control method and system for crane
CN103967284B (en) The steel column installation method of reserved stigma docking
CN209723226U (en) A kind of large span steel structure roof entirety lift structure
CN109868902A (en) A kind of large span steel structure roof entirety lift structure
CN103243726A (en) Construction method for integrally and downward putting cofferdam ring beams by means of continuous jack method
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
CN206428974U (en) A kind of multi-storey steel structure vestibule integral hoisting construction device
CN205474849U (en) Cable -stay bridge king -tower steel anchor beam and steel corbel integral hoisting special lifting device
CN104532753A (en) Lifting device suitable for lifting and installing suspension bridge stiffening girders
CN203938406U (en) A kind of tower machine jacking trim monitored control system and monitor
CN201924579U (en) Safety protection device for attached lifting scaffolds
CN104045010B (en) A kind of tower machine jacking trim monitored control system, monitoring method and monitor
CN105040592B (en) A kind of horizontal drawing cable bridge and its erection method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant