CN209635709U - Tooling for the lifting of box type rod piece cluster - Google Patents

Tooling for the lifting of box type rod piece cluster Download PDF

Info

Publication number
CN209635709U
CN209635709U CN201920472302.7U CN201920472302U CN209635709U CN 209635709 U CN209635709 U CN 209635709U CN 201920472302 U CN201920472302 U CN 201920472302U CN 209635709 U CN209635709 U CN 209635709U
Authority
CN
China
Prior art keywords
steel plate
sling
box
suspender belt
tooling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920472302.7U
Other languages
Chinese (zh)
Inventor
于长彬
张敏
田波
孙立强
张呈呈
董健刚
扈晓立
田鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201920472302.7U priority Critical patent/CN209635709U/en
Application granted granted Critical
Publication of CN209635709U publication Critical patent/CN209635709U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model relates to large-scale steel structures to lift field, specifically a kind of tooling for the lifting of box type rod piece cluster, including steel plate suspender belt, bolt, pin, steel plate suspender belt is four, four steel plate suspender belts are respectively upper steel plate suspender belt, lower steel plate suspender belt, left plate suspender belt, right steel plate suspender belt, four steel plate suspender belts connect squarely by bolt or pin in box type rod piece surrounding, form binding posture to box type rod piece;Four steel plate suspender belt medial surfaces are equipped with rubber strip;Upper steel plate suspender belt lateral surface is welded with the upper steel plate suspender belt stiffener with it at T-type structure along center line, and upper steel plate suspender belt stiffener is equipped with suspension centre hole.The utility model is to move, is detachable, and structure is simple and convenient to operate;Abrasion of the box type rod piece to suspender belt can be reduced, and will not be slided, guarantee Hoisting Security.

Description

用于箱型杆件捆绑式吊装的工装Tooling for bundled hoisting of box-shaped rods

技术领域technical field

本实用新型涉及大型钢结构吊装领域,具体是一种用于箱型杆件捆绑式吊装的工装。The utility model relates to the field of large-scale steel structure hoisting, in particular to a tool for the binding hoisting of box-shaped rods.

背景技术Background technique

现有的大型钢结构桁架式桥梁、桁架式房屋及其他桁架式钢结构吊装,一般采用节段式整体吊装、桁片式或散件吊装的吊装方式,但对于单根杆件重达近百吨的杆件,施工中大都采用单杆件吊装。对于箱型杆件吊装,吊点的设计是吊装的关键。一般箱型杆件吊装采用在箱型杆件吊点位置设置吊耳的方式,而部分箱型杆件吊点位置处的箱体内部全部封闭,使用吊耳安装和拆除存在一定困难,需采用捆绑式吊装。目前施工领域捆绑式吊装均采用吊带钢丝绳直接捆绑,吊装过程中箱型杆件棱角部位会对吊带钢丝绳产生剪切磨损,使得吊带钢丝绳的使用寿命大大缩短,同时直接捆绑对于箱型杆件容易发生吊点滑动,产生一定的危险。The hoisting of existing large-scale steel structure truss bridges, truss houses and other truss steel structures generally adopts segmental overall hoisting, truss piece hoisting or loose piece hoisting, but for a single bar weighing nearly 100 Tons of rods are mostly hoisted by single rods during construction. For the hoisting of box-shaped rods, the design of the lifting point is the key to the hoisting. Generally, the hoisting of box-shaped poles adopts the method of setting lifting lugs at the lifting points of box-shaped poles. However, the inside of the box at the lifting points of some box-shaped poles is completely closed, and there are certain difficulties in installing and removing using lifting lugs. Bundled hoisting. At present, the bundled hoisting in the construction field is directly tied with the steel wire rope of the sling. During the hoisting process, the corners of the box-shaped pole will cause shear wear to the steel wire rope of the sling, which greatly shortens the service life of the steel wire rope of the sling. The hanging point slides, resulting in certain dangers.

实用新型内容Utility model content

本实用新型要解决的技术问题是提供一种用于箱型杆件捆绑式吊装的工装,该工装为可移动、可拆卸式,结构简单、操作方便;能够减小杆件对吊带的磨损,且不会滑动,保证吊装安全。The technical problem to be solved by the utility model is to provide a kind of tooling for the binding hoisting of box-shaped rods. The tooling is movable and detachable, with simple structure and convenient operation; And it will not slide, ensuring the safety of hoisting.

为解决上述技术问题,本实用新型采用的技术方案是:In order to solve the problems of the technologies described above, the technical solution adopted in the utility model is:

一种用于箱型杆件捆绑式吊装的工装,包括钢板吊带、螺栓、销栓,钢板吊带为四个,四个钢板吊带分别为上钢板吊带、下钢板吊带、左钢板吊带、右钢板吊带,四个钢板吊带在箱型杆件四周通过螺栓或销栓连接成方形,对箱型杆件形成捆绑姿态;四个钢板吊带内侧面设有橡胶带;上钢板吊带外侧面沿中心线焊接有与其成T型结构的上钢板吊带加劲板,上钢板吊带加劲板上设有吊点孔。A tooling for the bundled hoisting of box-shaped rods, including steel plate slings, bolts, and pins. There are four steel plate slings. , the four steel plate straps are connected around the box-shaped rods by bolts or pins to form a square shape, forming a binding posture for the box-shaped rods; the inner sides of the four steel straps are equipped with rubber belts; the outer side of the upper steel straps is welded along the center line. The upper steel plate sling stiffener of T-shaped structure is provided with hanging point holes on the upper steel plate sling stiffener.

采用上述技术方案的本实用新型,与现有技术相比,其有益效果是:Adopt the utility model of above-mentioned technical scheme, compared with prior art, its beneficial effect is:

上钢板吊带与左、右钢板吊带之间螺栓连接后可以不再拆卸,下钢板吊带与左钢板吊带之间通过螺栓连接,摘钩时可以松开螺栓,下钢板吊带与右钢板吊带之间采用销栓铰接,结构简单,安装、拆卸方便,吊装时只需将本工装与吊带用卡扣连接即可,摘钩时只需将下钢板吊带与左钢板吊带之间的螺栓摘除即可完成。钢板吊带内侧面通过设置橡胶带,对吊带、钢丝绳不会产生损伤,同时也对箱型杆件本身油漆面不会产生破坏。The bolt connection between the upper steel plate sling and the left and right steel plate slings can no longer be disassembled. The lower steel plate sling and the left steel plate sling are connected by bolts. The bolts can be loosened when unhooking. The pin bolt is hinged, the structure is simple, and the installation and disassembly are convenient. When hoisting, you only need to connect the tooling with the sling with a buckle. The inner side of the steel plate sling is provided with a rubber belt, which will not damage the sling and the steel wire rope, and will not damage the painted surface of the box-shaped rod itself.

进一步的,本实用新型优选方案是:Further, the preferred version of the utility model is:

上钢板吊带的T型结构的两端头分别焊接上钢板吊带端头板,上钢板吊带端头板上设有用以连接左钢板吊带、右钢板吊带的螺栓孔。The two ends of the T-shaped structure of the upper steel plate sling are respectively welded to the upper steel plate sling end plate, and the upper steel plate sling end plate is provided with bolt holes for connecting the left steel plate sling and the right steel plate sling.

左钢板吊带靠近上钢板吊带位置设有螺栓孔,用以连接上钢板吊带;左钢板吊带靠近下钢板吊带端头设置左钢板吊带端头板,左钢板吊带端头板上设有螺栓孔,用以连接下钢板吊带。The left steel plate sling is provided with a bolt hole close to the upper steel plate sling for connecting the upper steel sling; To connect the lower steel straps.

右钢板吊带靠近上钢板吊带位置设有螺栓孔,用以连接上钢板吊带;右钢板吊带靠近下钢板吊带位置设有两道连接板,连接板上设有铰接销栓孔,用以销栓铰接下钢板吊带。The right steel plate sling is provided with a bolt hole near the upper steel plate sling for connecting the upper steel plate sling; the right steel plate sling is provided with two connecting plates near the lower steel plate sling, and the connecting plate is provided with a hinge pin hole for pin bolt hinge Lower steel straps.

下钢板吊带沿中心线焊接下钢板吊带加劲板,下钢板吊带靠近左钢板吊带位置设有螺栓孔,用以连接左钢板吊带;下钢板吊带加劲板靠近右侧端头设置铰接销栓孔,用以销栓铰接右钢板吊带。The lower steel sling is welded along the center line to the lower steel sling stiffener, and the lower steel sling is provided with a bolt hole near the left steel sling for connecting the left steel sling; the lower steel sling stiffener is provided with a hinge pin hole near the right end for Hinge the right steel plate sling with a pin.

橡胶带通过自攻钉与钢板吊带固定。The rubber belt is fixed with the steel plate sling by self-tapping screws.

附图说明Description of drawings

图1是本实用新型实施例的断面示意图;Fig. 1 is the sectional schematic view of the utility model embodiment;

图2是上钢板吊带主视图;Fig. 2 is a front view of the upper steel plate sling;

图3是上钢板吊带侧视图;Fig. 3 is a side view of the upper steel plate sling;

图4是上钢板吊带俯视图;Fig. 4 is a plan view of the upper steel plate sling;

图5是左钢板吊带主视图;Fig. 5 is a front view of the left steel plate sling;

图6是左钢板吊带侧视图;Fig. 6 is a side view of the left steel plate suspender;

图7是左钢板吊带俯视图;Fig. 7 is a top view of the left steel plate suspender;

图8是右钢板吊带主视图;Fig. 8 is a front view of the right steel plate sling;

图9是右钢板吊带侧视图;Fig. 9 is a side view of the right steel plate suspender;

图10是下钢板吊带主视图;Figure 10 is a front view of the lower steel plate sling;

图11是下钢板吊带俯视图;Fig. 11 is a plan view of the lower steel plate sling;

图12是本实用新型实施例的三维组装示意图;Fig. 12 is a three-dimensional assembly schematic diagram of an embodiment of the utility model;

图13是本实用新型实施例吊装箱型杆件示意图;Fig. 13 is a schematic diagram of hoisting box-shaped rods according to the embodiment of the present invention;

图中:1、上钢板吊带;2、右钢板吊带;3、左钢板吊带;4、下钢板吊带;5、箱型杆件;6、橡胶带;7、吊点孔;8、上钢板吊带加劲板;9、上钢板吊带端头板;10、螺栓孔;11、销栓孔;12、连接板;13、左钢板吊带端头板;14、下钢板吊带加劲板;15、三角加劲板;螺栓16;销栓17。In the figure: 1. Upper steel plate sling; 2. Right steel plate sling; 3. Left steel plate sling; 4. Lower steel plate sling; Stiffening plate; 9. End plate of upper steel plate strap; 10. Bolt hole; 11. Pin hole; 12. Connecting plate; 13. End plate of left steel strap strap; 14. Stiffener plate of lower steel strap; 15. Triangular stiffening plate ; Bolt 16 ; Pin 17 .

具体实施方式Detailed ways

下面结合附图及实施例进一步说明本实用新型。Below in conjunction with accompanying drawing and embodiment further illustrate the utility model.

参见图1和图12,一种用于箱型杆件捆绑式吊装的工装,由上钢板吊带1、左钢板吊带3、右钢板吊带2、下钢板吊带4四个钢板吊带构成,四个钢板吊带通过螺栓16或销栓17连接成方形,四个钢板吊带内侧面通过自攻钉固定有橡胶带6。Referring to Fig. 1 and Fig. 12, a tooling for the bundled hoisting of box-shaped rods is composed of four steel plate slings: upper steel plate sling 1, left steel plate sling 3, right steel plate sling 2, and lower steel plate sling 4. The four steel plates The suspenders are connected into a square by bolts 16 or pins 17, and the inner surfaces of the four steel plate suspenders are fixed with rubber bands 6 by self-tapping screws.

参见图2、图3、图4,上钢板吊带1外侧面沿中心线焊接有与其成T型结构的上钢板吊带加劲板8,上钢板吊带加劲板8上设有吊点孔7,用以穿卡扣;上钢板吊带1的T型结构的两端头分别焊接上钢板吊带端头板9,上钢板吊带端头板9上设有用以连接左钢板吊带3、右钢板吊带2的螺栓孔10;上钢板吊带1与上钢板吊带加劲板8、上钢板吊带端头板9之间满焊连接。Referring to Fig. 2, Fig. 3 and Fig. 4, the outer surface of the upper steel strap 1 is welded with an upper steel strap stiffener 8 in a T-shaped structure along the center line, and the upper steel strap stiffener 8 is provided with a lifting point hole 7 for Wear buckles; the two ends of the T-shaped structure of the upper steel strap 1 are respectively welded to the upper steel strap end plate 9, and the upper steel strap end plate 9 is provided with bolt holes for connecting the left steel strap 3 and the right steel strap 2 10; The upper steel plate suspender 1 is fully welded and connected with the upper steel plate suspender stiffener 8 and the upper steel plate suspender end plate 9 .

参见图5、图6、图7,左钢板吊带3靠近上钢板吊带1位置设有螺栓孔10,用以连接上钢板吊带1;左钢板吊带3靠近下钢板吊带4端头设置左钢板吊带端头板13,左钢板吊带端头板13上设有螺栓孔10,用以连接下钢板吊带4;左钢板吊带端头板13与左钢板吊带3之间还设置三角加劲板15,左钢板吊带端头板13、三角加劲板15与左钢板吊带3之间采用满焊连接。Referring to Fig. 5, Fig. 6, and Fig. 7, the left steel strap 3 is provided with a bolt hole 10 close to the upper steel strap 1 for connecting the upper steel strap 1; the left steel strap 3 is provided with a left steel strap end near the end of the lower steel strap 4 Bolt holes 10 are provided on the head plate 13 and the end plate 13 of the left steel plate sling to connect the lower steel plate sling 4; a triangle stiffener 15 is also arranged between the left steel plate sling end plate 13 and the left steel plate sling 3, and the left steel plate sling Full welding connection is adopted between the end plate 13, the triangular stiffening plate 15 and the left steel plate suspender 3.

参见图8和图9,右钢板吊带2靠近上钢板吊带1位置设有螺栓孔10,用以连接上钢板吊带1;右钢板吊带2靠近下钢板吊带4位置设有两道连接板12,连接板12上设有铰接销栓的销栓孔11,用以销栓铰接下钢板吊带4。连接板12与右钢板吊带2之间采用满焊连接。Referring to Figure 8 and Figure 9, the right steel plate strap 2 is provided with bolt holes 10 near the upper steel strap 1 for connecting the upper steel strap 1; the right steel strap 2 is provided with two connecting plates 12 near the lower steel strap 4 for connecting Plate 12 is provided with the pin bolt hole 11 of hinge pin bolt, is used for pin bolt hinged lower steel plate suspender belt 4. Adopt full welding connection between the connecting plate 12 and the right steel plate suspender 2.

参见图10和图11,下钢板吊带4沿中心线焊接下钢板吊带加劲板14,下钢板吊带4靠近左钢板吊带3位置设有螺栓孔10,用以连接左钢板吊带3;下钢板吊带加劲板14靠近右侧端头设置铰接销栓的销栓孔11,用以销栓铰接右钢板吊带2。下钢板吊带4与下钢板吊带加劲板14之间采用满焊连接。Referring to Fig. 10 and Fig. 11, the lower steel sling 4 is welded with the lower steel sling stiffener 14 along the center line, and the lower steel sling 4 is provided with a bolt hole 10 near the left steel sling 3 for connecting the left steel sling 3; the lower steel sling is stiffened Plate 14 is provided with the pin bolt hole 11 of hinge pin bolt near the right side end, in order to pin bolt hinged right steel plate suspender belt 2. Adopt full welding connection between the lower steel plate suspender 4 and the lower steel plate suspender stiffener 14 .

参见图12和图13,利用本实用新型吊装箱型杆件5的操作方法如下:Referring to Fig. 12 and Fig. 13, the operation method of utilizing the utility model to hoist the box-shaped rod 5 is as follows:

吊装前,箱型杆件5置于起吊位置正下方,将上钢板吊带1与左钢板吊带3、右钢板吊带2按照图6利用螺栓16连接,连接螺栓16不用太紧;同时利用销栓17通过销栓孔11将右钢板吊带2与下钢板吊带4连接;如此组装两套本实用新型。将组装好的工装套于箱型杆件5上,并拧紧各部位螺栓16使得本工装紧扣固定于箱型杆件5两端。现场缆索吊机吊钩上挂吊带通过卡扣连接于本实用新型的吊点孔7内,缆索吊起钩即完成吊装。Before hoisting, place the box-shaped rod 5 directly below the hoisting position, and connect the upper steel plate sling 1 with the left steel plate sling 3 and the right steel plate sling 2 according to Fig. Right steel plate suspender 2 is connected with following steel plate suspender 4 by pin bolt hole 11; Two sets of the utility model are assembled in this way. Put the assembled tooling on the box-shaped bar 5, and tighten the bolts 16 of each part so that the tooling is fastened to both ends of the box-shaped bar 5. On-the-spot cable crane suspension hook hangs suspenders and is connected in the lifting point hole 7 of the present utility model by buckle, and the cable lifting hook promptly completes hoisting.

本实用新型结构简单,刚度大,适用性强,安装作业可在缆索吊钩就位之前完成,尽量少占用缆索吊资源;并且本工装有效减少了箱型杆件5对吊带的磨损,同时也减少了吊带钢丝绳对油漆面的磨损;最重要的是解决了箱型杆件5内部封闭空间内不能安装吊耳的困难。适用于体型较大、重量较重、内部封闭空间的箱型杆件捆绑式吊装。The utility model has the advantages of simple structure, high rigidity and strong applicability. The installation work can be completed before the cable hook is in place, and the resources of the cable hanger are minimized; and the tooling effectively reduces the wear of the box-shaped bar 5 pairs of suspenders, and at the same time Reduced wear and tear on the paint surface by the sling steel wire rope; the most important thing is to solve the difficulty that lifting lugs cannot be installed in the closed space inside the box-shaped rod 5. It is suitable for binding hoisting of box-shaped rods with large size, heavy weight and internal closed space.

以上仅为本实用新型的具体实施方式,但本实用新型的保护不限于此,任何本技术领域的技术人员所能想到的与本技术方案技术特征等同的变化或替代,都涵盖在本实用新型的保护范围之内。The above is only a specific embodiment of the present utility model, but the protection of the present utility model is not limited thereto, and any changes or substitutions equivalent to the technical features of the technical solution conceivable by those skilled in the art are covered by the present utility model. within the scope of protection.

Claims (6)

1.一种用于箱型杆件捆绑式吊装的工装,包括钢板吊带、螺栓、销栓,其特征在于:钢板吊带为四个,四个钢板吊带分别为上钢板吊带、下钢板吊带、左钢板吊带、右钢板吊带,四个钢板吊带在箱型杆件四周通过螺栓或销栓连接成方形,对箱型杆件形成捆绑姿态;四个钢板吊带内侧面设有橡胶带;上钢板吊带外侧面沿中心线焊接有与其成T型结构的上钢板吊带加劲板,上钢板吊带加劲板上设有吊点孔。1. A tooling for the bundled hoisting of box-shaped rods, including steel plate slings, bolts, and pins. It is characterized in that: there are four steel plate slings, and the four steel plate slings are respectively an upper steel plate sling, a lower Steel plate slings, right steel plate slings, four steel plate slings are connected into a square by bolts or pins around the box-shaped rods, forming a binding posture for the box-shaped rods; the inner sides of the four steel plate slings are equipped with rubber belts; the outer sides of the upper steel slings are The side is welded along the central line with an upper steel plate sling stiffening plate forming a T-shaped structure, and the upper steel plate sling stiffening plate is provided with hanging point holes. 2.根据权利要求1所述的用于箱型杆件捆绑式吊装的工装,其特征在于:上钢板吊带的T型结构的两端头分别焊接上钢板吊带端头板,上钢板吊带端头板上设有用以连接左钢板吊带、右钢板吊带的螺栓孔。2. The tooling for the bundled hoisting of box-shaped rods according to claim 1, characterized in that: the two ends of the T-shaped structure of the upper steel plate sling are respectively welded to the end plate of the steel plate sling, and the upper end of the steel plate sling Bolt holes for connecting the left and right steel plate slings are arranged on the plate. 3.根据权利要求1所述的用于箱型杆件捆绑式吊装的工装,其特征在于:左钢板吊带靠近上钢板吊带位置设有螺栓孔,用以连接上钢板吊带;左钢板吊带靠近下钢板吊带端头设置左钢板吊带端头板,左钢板吊带端头板上设有螺栓孔,用以连接下钢板吊带。3. The tooling for the bundled hoisting of box-shaped rods according to claim 1, characterized in that: the left steel plate sling is provided with bolt holes near the upper steel plate sling for connecting the upper steel plate sling; the left steel plate sling is close to the lower The end of the steel plate sling is provided with a left steel plate sling end plate, and the left steel plate sling end plate is provided with bolt holes for connecting the lower steel plate sling. 4.根据权利要求1所述的用于箱型杆件捆绑式吊装的工装,其特征在于:右钢板吊带靠近上钢板吊带位置设有螺栓孔,用以连接上钢板吊带;右钢板吊带靠近下钢板吊带位置设有两道连接板,连接板上设有铰接销栓孔,用以销栓铰接下钢板吊带。4. The tooling for the bundled hoisting of box-shaped rods according to claim 1, characterized in that: the right steel plate sling is provided with bolt holes near the upper steel plate sling for connecting the upper steel plate sling; the right steel plate sling is close to the lower The position of the steel plate sling is provided with two connecting plates, and the connecting plate is provided with a hinge pin hole for pin bolts to hinge the lower steel plate sling. 5.根据权利要求1所述的用于箱型杆件捆绑式吊装的工装,其特征在于:下钢板吊带沿中心线焊接下钢板吊带加劲板,下钢板吊带靠近左钢板吊带位置设有螺栓孔,用以连接左钢板吊带;下钢板吊带加劲板靠近右侧端头设置铰接销栓孔,用以销栓铰接右钢板吊带。5. The tooling for bundled hoisting of box-shaped rods according to claim 1, characterized in that: the lower steel plate sling is welded to the lower steel plate sling stiffener along the center line, and the lower steel plate sling is provided with a bolt hole near the left steel plate sling , to connect the left steel strap; the lower steel strap stiffener is provided with a hinge pin hole near the right end for pin bolts to hinge the right steel strap. 6.根据权利要求1所述的用于箱型杆件捆绑式吊装的工装,其特征在于:橡胶带通过自攻钉与钢板吊带固定。6. The tooling for the bundled hoisting of box-shaped poles according to claim 1, wherein the rubber belt is fixed to the steel plate suspension belt by self-tapping screws.
CN201920472302.7U 2019-04-09 2019-04-09 Tooling for the lifting of box type rod piece cluster Expired - Fee Related CN209635709U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920472302.7U CN209635709U (en) 2019-04-09 2019-04-09 Tooling for the lifting of box type rod piece cluster

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920472302.7U CN209635709U (en) 2019-04-09 2019-04-09 Tooling for the lifting of box type rod piece cluster

Publications (1)

Publication Number Publication Date
CN209635709U true CN209635709U (en) 2019-11-15

Family

ID=68497374

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920472302.7U Expired - Fee Related CN209635709U (en) 2019-04-09 2019-04-09 Tooling for the lifting of box type rod piece cluster

Country Status (1)

Country Link
CN (1) CN209635709U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113682941A (en) * 2021-09-08 2021-11-23 中建八局第二建设有限公司 Large-scale air duct loading and unloading hanging bracket and manufacturing and using method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113682941A (en) * 2021-09-08 2021-11-23 中建八局第二建设有限公司 Large-scale air duct loading and unloading hanging bracket and manufacturing and using method thereof

Similar Documents

Publication Publication Date Title
CN110510506A (en) A kind of width type block hanging method of thin-wall construction
CN201923772U (en) Hoisting device for track slab
CN202465022U (en) Hoisting tool
CN209635709U (en) Tooling for the lifting of box type rod piece cluster
JP2015054777A (en) Hoisting accessory for jib
CN208980155U (en) A kind of suspender of mill housing installation
CN203513086U (en) Special lifting appliance for long-bundle-shaped material
CN201678360U (en) An equipment hoisting device
CN205034957U (en) I -steel is hoist for handling
CN204281039U (en) A kind of special hanger lifting box plate
CN222138451U (en) Hoisting structure suitable for single-baffle steel box girder
CN203781677U (en) Trial mass device of crane
CN204265218U (en) A kind of power station unit internal head cover special hanger
CN203946779U (en) Loose steel pipe operation combined sling
CN201686393U (en) Grill pole lifting tooling
CN201587793U (en) A New Type of Soft Cable Compression Rod Type Box Girder Spreader
CN106480824B (en) A kind of lifting method of steel cable tower
CN116101881A (en) Counterweight Hoisting Method of Adjustable Combined Balance Beam for Crane
CN209337953U (en) A kind of more suspension hook Hoisting Balance Beam of Crane of adjustable lifting length
CN203765246U (en) Device for assisting in assembly and disassembly of cargo boom of all-terrain crane
CN204310681U (en) A kind of power station unit top cover suspender
CN222730374U (en) Totally-enclosed hanging basket protection structure for bridge construction
CN212403134U (en) Hoisting mechanism of electromagnetic crane
CN205527316U (en) City rail U type liangmen hoist device
CN205114127U (en) Automatic open and merge material jar at end

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191115

CF01 Termination of patent right due to non-payment of annual fee