CN209585099U - A kind of substation truss assembled pile foundation using flanged joint - Google Patents

A kind of substation truss assembled pile foundation using flanged joint Download PDF

Info

Publication number
CN209585099U
CN209585099U CN201822123173.9U CN201822123173U CN209585099U CN 209585099 U CN209585099 U CN 209585099U CN 201822123173 U CN201822123173 U CN 201822123173U CN 209585099 U CN209585099 U CN 209585099U
Authority
CN
China
Prior art keywords
pile
stand
stand column
column
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822123173.9U
Other languages
Chinese (zh)
Inventor
李冰阳
韩选民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Construction Group Huazhong Electric Power Design Research Institute Co Ltd
Original Assignee
China Electric Power Construction Group Huazhong Electric Power Design Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Construction Group Huazhong Electric Power Design Research Institute Co Ltd filed Critical China Electric Power Construction Group Huazhong Electric Power Design Research Institute Co Ltd
Priority to CN201822123173.9U priority Critical patent/CN209585099U/en
Application granted granted Critical
Publication of CN209585099U publication Critical patent/CN209585099U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

The utility model discloses a kind of substation truss assembled pile foundations using flanged joint, it is characterized by: structure stand steel pipe column is fixedly connected by flange and high-strength bolt with stand column pile, flange is arranged in the stake top of stand column pile, structure stand steel pipe column and the inclined angle of stand column pile;It is connected by coupling beam between column stake top between adjacent structure stand steel pipe column and under structure stand steel pipe column.Assembled pile foundation provided by the utility model, adaptable strong, the high feature of batch production degree is advantageously implemented the assembled construction of structure bracket basis, realize " one pile for one column " formula assembled pile foundation, the full assembled construction of Lai Shixian structure bracket ground, underground;Using the assembled pile foundation of flanged joint, it is advantageously implemented mechanized construction, improves construction efficiency, shortens project duration, saves engineering cost, is worth promoting the use of in the power transformation engineering that modularization is built.

Description

A kind of substation truss assembled pile foundation using flanged joint
Technical field
The utility model belongs to substation truss field, and in particular to a kind of substation truss using flanged joint Assembled pile foundation.
Background technique
In recent years, it is further in-depth capital construction Standardization Construction, strengthens engineering construction overall process lean management, improve engineering Safe mass, efficiency benefit, State Grid Corporation of China gradually implement modularization construction mode, group in each voltage class intelligent substation It knits establishment and promotes and applies the construction universal design of intelligent substation modularization, carry out " standardized designs, industrialized production, assembly Formula construction, mechanized construction ", achieves biggish economic benefit and social benefit.But existing substation's construction of structures is general to be set The emphasis of meter scheme still concentrates on the assembled construction aspect of superstructure, and corresponding basis is still with designer According to the basic role power of different constructions of structures, based on designed, designed, versatility is poor.
Currently, the structure rack module construction scheme of intelligent substation mainly uses cast in situ concrete foundation or cushion cap etc. The mode of pre-embedded anchoring bolts realizes the assembled construction of structure frame upper structure, and there are still a large amount of for the basis of structure bracket The workloads such as excavation of foundation pit, precipitation and wet construction, have not been able to the assembled construction for realizing structure bracket basis, influence construction efficiency And project duration.
Utility model content
For above-mentioned the technical problems existing in the prior art, connected the purpose of the utility model is to provide a kind of using flange The substation truss assembled pile foundation connect.
The purpose of this utility model is achieved through the following technical solutions.
A kind of substation truss assembled pile foundation using flanged joint, the assembled pile foundation include several vertical Stanchion and the structure stand steel pipe column connecting with stand column pile, structure stand steel pipe column pass through flange and high-strength bolt and stand column pile It is fixedly connected, flange is arranged in the stake top of stand column pile, structure stand steel pipe column and the inclined angle of stand column pile;Adjacent structure bracket steel It is connected by coupling beam between column stake top between tubing string and under structure stand steel pipe column.
The stand column pile is pile for prestressed pipe, and column pile head is provided with pile protection hoop and welding point end plate, pile protection cuff Connect at the pile crown of stand column pile, welding point end plate is arranged in the stake top of stand column pile, pile protection hoop and welding point end plate one at Type, flange are arranged in the upper surface of welding point end plate.
The pile protection hoop is the cylindric or regular polygon prism-shaped that roll of steel plate is pressed into, and is pressed with annular detent on pile protection hoop, Dent spacing 50mm~100mm.
The welding point end plate is set as upper layer and lower layer, and lower plywood is positive polygon or round ring flat-plate, lower plywood and stake Cuff is fixedly connected, and lower plywood is circumferentially provided with stand column pile reinforcing bar consent;Top plate is solid circles, top plate and lower plywood It is fixedly connected by steel pipe and annular ribbed stiffener.
The stand column pile is prefabricated piling bar, and welding point end plate is provided in column stake top, and flange setting connects in welding The upper surface of head end plate.
The coupling beam is H profile steel, and coupling beam is fixedly connected by welding or bolt with stand column pile.
The intensity of the high-strength bolt is not less than 8.8 grades.
The flange uses steel flange.
The utility model has the following beneficial effects: what substation truss provided by the utility model was directly connected to using flange Assembled pile foundation, adaptable strong, the high feature of batch production degree, the assembled for being advantageously implemented structure bracket basis is built If by " one pile for one column " formula assembled pile foundation, the full assembled construction of Lai Shixian structure bracket ground, underground.With shallow foundation Compare, pile foundation has the characteristics that bearing capacity is high, sedimentation is small, is more suitable for mechanized construction, the length and setting method of stake and The working method of stake can vary widely, it is easy to adapt to the different of foundation engineering and require, be advantageously implemented structure bracket base The General design and standardized production of plinth;Using the assembled pile foundation of flanged joint, it is advantageously implemented mechanized construction, is mentioned High construction efficiency shortens project duration, saves engineering cost, is worth promoting the use of in the power transformation engineering that modularization is built.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the column pile head connection schematic diagram of the utility model embodiment one.
Fig. 3 is the partial enlarged view of the utility model embodiment one.
Fig. 4 is the partial enlarged view of the utility model embodiment one.
Fig. 5 is the column pile head connection schematic diagram of the utility model embodiment two.
Fig. 6 is the partial enlarged view of the utility model embodiment two.
In figure, 1 is stand column pile, and 2 be structure stand steel pipe column, and 3 be flange, and 4 be coupling beam, and 5 be pile protection hoop, and 6 be welding point End plate.
Specific embodiment
As shown in Figure 1, a kind of substation truss assembled pile foundation using flanged joint, for modularization construction It is used in substation truss engineering.
Embodiment one
As shown in figures 1-4, stand column pile 1 is pile for prestressed pipe, and 1 pile crown of stand column pile is provided with pile protection hoop 5 and welding point end Plate 6, pile protection hoop 5 are socketed at the pile crown of stand column pile 1, and the stake top of stand column pile 1, pile protection hoop 5 and weldering is arranged in welding point end plate 6 Connector end plate 6 is integrally formed, and flange 3 is arranged in the upper surface of welding point end plate 6.
The fixed company of high-strength bolt and stand column pile 1 that structure stand steel pipe column 2 passes through steel flange 3 and 8.8 grades of intensity or more It connects, structure stand steel pipe column 2 and the inclined angle of stand column pile 1.
It is fixedly connected between adjacent stand column pile 1 or structure stand steel pipe column 2 by H profile steel coupling beam 4.
Pile protection hoop 5 is the cylindric or regular polygon prism-shaped that roll of steel plate is pressed into, and is pressed with annular detent on pile protection hoop 5, recessed Trace spacing 50mm~100mm.
Welding point end plate 6 is set as upper layer and lower layer, and lower plywood is positive polygon or round ring flat-plate, lower plywood and pile protection hoop 5 are fixedly connected, and lower plywood is circumferentially provided with stand column pile reinforcing bar consent, and lower plywood passes through stand column pile reinforcing bar consent and stand column pile master Muscle is fixedly connected;Top plate is solid circles, and top plate is fixedly connected with lower plywood by steel pipe and annular ribbed stiffener.
The working principle of the present embodiment one are as follows: when construction substation truss assembled pile foundation, precast prestressed column Pile protection hoop 5 and welding point end plate 6 are arranged on pile crown, protects before piling to pile crown, prestressing force stand column pile 1 is beaten for stake 1 Enter underground, leak out the pile crown of prestressing force stand column pile 1, measures pile crown deviation, flange 3 is welded on welding point end plate 6, is passed through Structure stand steel pipe column 2 is fixedly connected by high-strength bolt with prestressing force stand column pile 1;Adjacent prestressing force stand column pile 1 and adjacent structure branch It is fixedly connected between frame steel pipe column 2 by coupling beam 4, each stake is linked to be an entirety, shared superstructure load is reduced pre- The horizontal loading that stress stand column pile 1 is subject to.
Embodiment two
As shown in Fig. 1, Fig. 5, Fig. 6, stand column pile 1 is prefabricated piling bar, is provided with welding at prefabricated 1 pile crown of piling bar stand column pile and connects Head end plate 6, with embodiment one the difference is that: welding point end plate 6 only have top plate, prefabricated piling bar stand column pile 1 directly lead to It crosses circumferential ribbed stiffener to be fixedly connected with top plate, other are referring to embodiment one.
Other technologies are referring to the prior art.
The above is only preferred embodiments of the present invention, is not the limit to technical solutions of the utility model It is fixed, it is noted that those skilled in the art can also make further under the premise of technical solutions of the utility model Improvement and change, these improvement and change should all be covered within the protection scope of the present utility model.

Claims (8)

1. a kind of substation truss assembled pile foundation using flanged joint, it is characterised in that: the assembled pile foundation Pass through flange including several stand column pile (1) and the structure stand steel pipe column (2) connecting with stand column pile (1), structure stand steel pipe column (2) (3) and high-strength bolt is fixedly connected with stand column pile (1), and flange (3) is arranged in the stake top of stand column pile (1), structure bracket steel Tubing string (2) and stand column pile (1) inclined angle;It is vertical between adjacent structure stand steel pipe column (2) and under structure stand steel pipe column (2) It is connected by coupling beam (4) between stanchion (1) stake top.
2. the substation truss assembled pile foundation according to claim 1 using flanged joint, it is characterised in that: institute Stating stand column pile (1) is pile for prestressed pipe, and stand column pile (1) pile crown is provided with pile protection hoop (5) and welding point end plate (6), pile protection hoop (5) it is socketed at the pile crown of stand column pile (1), the stake top in stand column pile (1), pile protection hoop (5) and weldering is arranged in welding point end plate (6) Connector end plate (6) is integrally formed, and flange (3) is arranged in the upper surface of welding point end plate (6).
3. the substation truss assembled pile foundation according to claim 2 using flanged joint, it is characterised in that: institute Stating pile protection hoop (5) is the cylindric or regular polygon prism-shaped that roll of steel plate is pressed into, and pile protection hoop is pressed with annular detent, dent on (5) Spacing 50mm~100mm.
4. the substation truss assembled pile foundation according to claim 3 using flanged joint, it is characterised in that: institute It states welding point end plate (6) and is set as upper layer and lower layer, lower plywood is positive polygon or round ring flat-plate, lower plywood and pile protection hoop (5) It is fixedly connected, lower plywood is circumferentially provided with stand column pile reinforcing bar consent;Top plate is solid circles, and top plate passes through with lower plywood Steel pipe and annular ribbed stiffener are fixedly connected.
5. the substation truss assembled pile foundation according to claim 1 using flanged joint, it is characterised in that: institute Stating stand column pile (1) is prefabricated piling bar, is provided with welding point end plate (6) in stand column pile (1) stake top, and flange (3) setting is being welded The upper surface of connector end plate (6).
6. the substation truss assembled pile foundation according to claim 1 using flanged joint, it is characterised in that: institute Stating coupling beam (4) is H profile steel, and coupling beam (4) is fixedly connected by welding or bolt with stand column pile (1) or structure stand steel pipe column (2).
7. the substation truss assembled pile foundation according to claim 1 using flanged joint, it is characterised in that: institute The intensity of high-strength bolt is stated not less than 8.8 grades.
8. the substation truss assembled pile foundation according to claim 1 using flanged joint, it is characterised in that: institute Flange (3) are stated using steel flange.
CN201822123173.9U 2018-12-18 2018-12-18 A kind of substation truss assembled pile foundation using flanged joint Expired - Fee Related CN209585099U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822123173.9U CN209585099U (en) 2018-12-18 2018-12-18 A kind of substation truss assembled pile foundation using flanged joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822123173.9U CN209585099U (en) 2018-12-18 2018-12-18 A kind of substation truss assembled pile foundation using flanged joint

Publications (1)

Publication Number Publication Date
CN209585099U true CN209585099U (en) 2019-11-05

Family

ID=68350063

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822123173.9U Expired - Fee Related CN209585099U (en) 2018-12-18 2018-12-18 A kind of substation truss assembled pile foundation using flanged joint

Country Status (1)

Country Link
CN (1) CN209585099U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281864A (en) * 2020-10-16 2021-01-29 上海建工集团股份有限公司 Connecting joint structure for solving one-column-one-pile deviation and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281864A (en) * 2020-10-16 2021-01-29 上海建工集团股份有限公司 Connecting joint structure for solving one-column-one-pile deviation and construction method thereof

Similar Documents

Publication Publication Date Title
CN201151909Y (en) Deep foundation pit composite structure annular inner support
CN101775813B (en) Composite foundation of power transmission line iron tower
CN108412128A (en) A kind of connection structure of steel core concrete column
CN104929148B (en) The upside-down mounting hardened system of generation power foundation of wind power ring group plinth and reinforcement means thereof
CN105926775A (en) Novel concrete-filled steel tube beam column joint
CN111236294A (en) Combined cylinder structure fan foundation
CN112412707A (en) Assembled wind turbine generator system circle cross section concrete bearing structure
CN209585099U (en) A kind of substation truss assembled pile foundation using flanged joint
CN201924349U (en) Anchor ear type connecting clamp for uplift pipe piles
CN101881029B (en) Detachable tower foundation
CN109457868B (en) Steel pipe concrete column base joint and construction method thereof
CN216194894U (en) Cylindrical structure fan foundation with inverted convex bearing platform structure and wind turbine generator
CN110468870A (en) One kind can have enough to meet the need Tower Crane Foundation by Steel Lattice Column structure
CN202755368U (en) Long span pre-stressing force fish-belly beam used for retaining and protecting foundation pit
CN201924350U (en) Bolt-type mechanical connecting clamp for pulling-resistant pipe pile
CN103726505B (en) Offshore wind plant wind turbine foundation
CN210031482U (en) Prestressed assembled UHPC trestle column structure
CN210439163U (en) Diagonal joist supporting structure applicable to assembly and disassembly of continuous beam
CN204125957U (en) Flange transition interconnection system single-pile foundation structure
CN210712909U (en) Can have enough to meet need steel lattice column tower crane foundation structure
CN209723015U (en) A kind of power line tower composite foundation
CN207277864U (en) A kind of concrete temporary support moulding bed for large-scale steel structure assembly
CN206902719U (en) Preassembling support beam combines support system
CN201730106U (en) Power transmission tower composite foundation
CN206204985U (en) A kind of environment-friendly type assembled grouting behind shaft or drift lining steel cylinder pile foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191105