CN209423269U - A tail flue gas elimination tower of wet desulfurization - Google Patents

A tail flue gas elimination tower of wet desulfurization Download PDF

Info

Publication number
CN209423269U
CN209423269U CN201821953686.6U CN201821953686U CN209423269U CN 209423269 U CN209423269 U CN 209423269U CN 201821953686 U CN201821953686 U CN 201821953686U CN 209423269 U CN209423269 U CN 209423269U
Authority
CN
China
Prior art keywords
tower body
tower
flue gas
inner cylinder
condensation segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821953686.6U
Other languages
Chinese (zh)
Inventor
郭志刚
屈振乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Chaoyang Environmental Protection Technology Group Co Ltd
Original Assignee
Aerospace Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Aerospace Environmental Engineering Co Ltd filed Critical Aerospace Environmental Engineering Co Ltd
Priority to CN201821953686.6U priority Critical patent/CN209423269U/en
Application granted granted Critical
Publication of CN209423269U publication Critical patent/CN209423269U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

本实用新型涉及一种湿法脱硫尾部烟气消白塔,所述消白塔包括塔体、排水口、进口烟道、匀流装置、冷凝段、风机、除雾段、内筒和顶部出口,所述塔体的底部同轴相连通设置排水口,该塔体的顶部同轴相连通设置顶部出口,所述排水口上方的塔体上同轴间隔设置匀流装置,该匀流装置上方的塔体上同轴间隔设置冷凝段,该冷凝段的下底面的外侧通过密封板与塔体的内壁紧密相连接设置,所述内筒同轴设置于冷凝段、顶部出口之间的塔体内。本消白塔能降低除湿法脱硫后的烟气中水含量和烟气温度,使排入大气中的烟气不再有肉眼能识别的白色烟羽,极大地降低了消白系统的投资和运维,提高了效益,达到了节能减排的目的。

The utility model relates to a white removal tower for flue gas at the tail of wet desulfurization. The white removal tower includes a tower body, a drain outlet, an inlet flue, a uniform flow device, a condensation section, a fan, a defogging section, an inner cylinder and a top outlet , the bottom of the tower body is coaxially connected to set a water outlet, the top of the tower body is coaxially connected to set a top outlet, and the tower body above the water outlet is coaxially spaced with a flow uniform device, above the flow uniform device Condensation section is coaxially arranged on the tower body at intervals, and the outer side of the lower bottom surface of the condensation section is closely connected with the inner wall of the tower body through a sealing plate, and the inner cylinder is coaxially arranged in the tower body between the condensation section and the top outlet . This whitening tower can reduce the water content and flue gas temperature in the flue gas after desulfurization by dehumidification method, so that the flue gas discharged into the atmosphere no longer has white plumes that can be recognized by the naked eye, which greatly reduces the investment and cost of the whitening system. Operation and maintenance have improved efficiency and achieved the goal of energy saving and emission reduction.

Description

一种湿法脱硫尾部烟气消白塔A tail flue gas elimination tower of wet desulfurization

技术领域technical field

本实用新型属于化工、环保技术领域,尤其是一种湿法脱硫尾部烟气消白塔。The utility model belongs to the technical fields of chemical industry and environmental protection, in particular to a flue gas elimination tower at the tail of wet desulfurization.

背景技术Background technique

湿法脱硫后排放的烟气携带大量的水蒸气,湿烟气进入温度较低的环境大气中,造成大量水资源的浪费,还会形成“白烟”现象,产生视觉污染,为企业带来巨大的社会舆论压力。当前,国内85%以上的燃煤电厂和钢铁烧结采用了湿法脱硫工艺,排放的湿烟气温度在45℃~55℃,含湿量近饱和状态。The flue gas discharged after wet desulfurization carries a large amount of water vapor, and the wet flue gas enters the ambient atmosphere with a lower temperature, causing a large amount of waste of water resources, and the phenomenon of "white smoke" will also be formed, resulting in visual pollution and bringing Huge pressure from public opinion. At present, more than 85% of domestic coal-fired power plants and steel sintering adopt wet desulfurization process, and the temperature of the discharged wet flue gas is between 45°C and 55°C, and the moisture content is close to saturation.

应用较广的湿法烟气消白技术为烟气降温再热消白技术。此技术主要有三级换热器组成,第一组换热器将进入主引风机前的烟气进行一次降温,通常使用2005合金材质的换热器,使烟气由原来的120℃~150℃之间的温度降低到80℃~90℃范围内。第二组换热器在主引风机后,进行一次降温使烟气温度降至60℃。第三组换热器在脱硫塔后,将烟气温度由40℃升高到65℃,实现热量平衡,因此处工作环境在烟气露点温度以下,会有少量SO3酸性气体凝结,采用氟塑料或者镍铬合金材质,整个系统要稳定运行还需要设置一台小型凉水塔用于调节系统热平衡。整套系统改造工程量较大,投资高,运行费用高和运行过程中故障点多的特点。The widely used wet flue gas whitening technology is flue gas cooling and reheating whitening technology. This technology is mainly composed of three-stage heat exchangers. The first group of heat exchangers will cool the flue gas before entering the main induced draft fan. Usually, the heat exchanger made of 2005 alloy is used to make the flue gas change from the original 120°C to 150°C. The temperature between ℃ is reduced to the range of 80℃~90℃. After the main induced draft fan, the second group of heat exchangers conducts a cooling down to reduce the flue gas temperature to 60°C. After the desulfurization tower, the third group of heat exchangers raises the flue gas temperature from 40°C to 65°C to achieve heat balance. Therefore, the working environment is below the flue gas dew point temperature, and a small amount of SO 3 acid gas will condense. Fluorine It is made of plastic or nickel-chromium alloy. To ensure the stable operation of the whole system, a small cooling tower is required to adjust the thermal balance of the system. The entire system has the characteristics of large amount of reconstruction work, high investment, high operating costs and many fault points during operation.

通过检索,尚未发现与本实用新型专利申请相关的专利公开文献。Through searching, no patent publication related to the utility model patent application has been found yet.

发明内容Contents of the invention

本实用新型的目的在于克服现有消白技术的不足之处,提供一种湿法脱硫尾部烟气消白塔,该消白塔能降低除湿法脱硫后的烟气中水含量和烟气温度,使排入大气中的烟气不再有肉眼能识别的白色烟羽,极大地降低了消白系统的投资和运维,提高了效益,达到了节能减排的目的。The purpose of this utility model is to overcome the shortcomings of the existing whitening technology, and provide a wet desulfurization tail flue gas whitening tower, which can reduce the water content and flue gas temperature in the flue gas after dehumidification desulfurization , so that the flue gas discharged into the atmosphere no longer has a white plume that can be recognized by the naked eye, which greatly reduces the investment and operation and maintenance of the whitening system, improves efficiency, and achieves the purpose of energy saving and emission reduction.

本实用新型解决其技术问题是采取以下技术方案实现的:The utility model solves its technical problem and realizes by taking the following technical solutions:

一种湿法脱硫尾部烟气消白塔,所述消白塔包括塔体、进口烟道、冷凝段、内筒和顶部出口,所述塔体的顶部同轴相连通设置顶部出口,该塔体的下部相连通设置进口烟道,该进口烟道上方的塔体内同轴设置冷凝段;A wet desulfurization tail flue gas whitening tower, the whitening tower includes a tower body, an inlet flue, a condensation section, an inner cylinder and a top outlet, the top of the tower body is coaxially connected with a top outlet, the tower The lower part of the body is connected with an inlet flue, and the tower body above the inlet flue is coaxially provided with a condensation section;

所述内筒同轴设置于冷凝段、顶部出口之间的塔体内,该内筒的顶部设置于顶部出口的下方,该内筒与塔体内部之间设置空气流动腔,该空气流动腔与冷凝段的输出端、内筒上方的塔体均相连通设置,所述冷凝段的上表面的外侧同轴紧密连接设置内筒的底部;The inner cylinder is coaxially arranged in the tower body between the condensation section and the top outlet, the top of the inner cylinder is arranged below the top outlet, and an air flow chamber is arranged between the inner cylinder and the inside of the tower body, and the air flow chamber is connected to the inside of the tower body. The output end of the condensing section and the tower above the inner cylinder are connected and arranged, and the outer side of the upper surface of the condensing section is coaxially tightly connected to the bottom of the inner cylinder;

所述冷凝段的下底面的外侧通过密封板与塔体的内壁紧密相连接设置,所述冷凝段的输入端能够输入空气,该冷凝段的介质为空气,该冷凝段的输出端与空气流动腔相连通设置,换热后的空气能够进入空气流动腔内并最终与从内筒的出口输出的处理后烟气在内筒上方的塔体顶部汇合在一起,并从顶部出口排出。The outer side of the lower bottom surface of the condensing section is closely connected with the inner wall of the tower body through a sealing plate, the input end of the condensing section can input air, the medium of the condensing section is air, and the output end of the condensing section flows with the air. The cavities are connected, and the heat-exchanged air can enter the air flow cavity and finally merge with the treated flue gas output from the outlet of the inner cylinder at the top of the tower above the inner cylinder, and be discharged from the top outlet.

而且,所述消白塔还包括排水口、匀流装置、风机和除雾段,所述塔体的底部同轴相连通设置排水口,所述排水口、冷凝段之间的塔体上同轴间隔设置匀流装置,该匀流装置、排水口之间的塔体上设置进口烟道;Moreover, the whitening tower also includes a drain outlet, a flow uniform device, a fan and a defogging section, the bottom of the tower body is coaxially connected with a drain outlet, and the tower body between the drain outlet and the condensation section is the same Equilibrium devices are arranged at intervals between shafts, and inlet flues are arranged on the tower body between the equilibrators and the drains;

所述内筒的下部内同轴紧密设置除雾段,该除雾段设置于冷凝段的上方且与冷凝段相间隔设置;The lower part of the inner cylinder is coaxially and tightly provided with a defogging section, and the defogging section is arranged above the condensing section and spaced apart from the condensing section;

所述风机与冷凝段的入口相连接设置,该风机能够将空气输入冷凝段内。The fan is connected with the inlet of the condensing section, and the fan can input air into the condensing section.

而且,所述冷凝段为列管换热器。Moreover, the condensation section is a shell and tube heat exchanger.

而且,所述消白塔还包括冲洗水系统,所述冲洗水系统包括冲洗水输出端,该冲洗水输出端设置于冷凝段、除雾段之间的塔体上,该冲洗水输出端输出的冲洗水能够冲洗掉冷凝段析出的水到塔体底部。Moreover, the whitening tower also includes a flushing water system, the flushing water system includes a flushing water output end, the flushing water output end is arranged on the tower body between the condensation section and the defogging section, and the flushing water output end outputs The flushing water can wash away the water precipitated in the condensation section to the bottom of the tower body.

而且,所述除雾段为气动高效除尘除雾器。Moreover, the demisting section is a pneumatic high-efficiency dedusting and mist eliminator.

而且,所述排水口通过排水泵、排水管道与脱硫塔内相连接设置。Moreover, the drain port is connected to the inside of the desulfurization tower through a drain pump and a drain pipe.

如上所述的湿法脱硫尾部烟气消白塔在烟气消白方面中的应用。The application of the above-mentioned wet desulfurization tail flue gas whitening tower in flue gas whitening.

本实用新型取得的优点和积极效果是:The advantages and positive effects obtained by the utility model are:

1、本消白塔包括塔体、进口烟道、冷凝段、内筒和顶部出口,在使用时,烟气通过进口烟道进入塔体,然后进入冷凝段以降低烟气温度,析出的水落入塔体底部,烟气经过内筒、用于冷凝的空气经过空气流动腔,最后烟气与用于冷凝的空气会合后排入大气中;内筒分开烟气与空气可防止烟气中的冷凝水沿空气流动腔进入冷凝器,使烟气在上升过程中产生的大液滴被内筒壁板捕捉,减少烟气中大液滴夹带;另外,内筒上方烟气与空气接触会产生小液滴,在烟囱内经过一段距离到达烟囱顶部之前,非饱和烟气混合气再次蒸发这些小液滴,使排放到大气中的混合烟气不再有白色羽烟,该消白塔能降低除湿法脱硫后的烟气中水含量和烟气温度,使排入大气中的烟气不再有肉眼能识别的白色烟羽,极大地降低了消白系统的投资和运维,提高了效益,达到了节能减排的目的。1. The whitening tower includes a tower body, an inlet flue, a condensation section, an inner cylinder and a top outlet. When in use, the flue gas enters the tower body through the inlet flue, and then enters the condensation section to reduce the temperature of the flue gas, and the precipitated water Falling into the bottom of the tower body, the flue gas passes through the inner cylinder, the air for condensation passes through the air flow chamber, and finally the flue gas and the air for condensation are combined and discharged into the atmosphere; the inner cylinder separates the flue gas and air to prevent the flue gas from The condensed water enters the condenser along the air flow chamber, so that the large liquid droplets generated during the rising process of the flue gas are captured by the wall plate of the inner cylinder, reducing the entrainment of large liquid droplets in the flue gas; in addition, the contact between the flue gas above the inner cylinder and the air will Small droplets are produced, and before reaching the top of the chimney after a certain distance, the unsaturated flue gas mixture evaporates these small droplets again, so that the mixed flue gas discharged into the atmosphere no longer has white plumes, and the whitening tower can Reduce the water content and flue gas temperature in the flue gas after desulphurization by dehumidification, so that the flue gas discharged into the atmosphere no longer has a white plume that can be recognized by the naked eye, which greatly reduces the investment and operation and maintenance of the whitening system, and improves the efficiency. benefit, to achieve the purpose of energy saving and emission reduction.

2、本消白塔包括塔体、排水口、进口烟道、匀流装置、冷凝段、风机、除雾段、内筒和顶部出口,在使用时,烟气可以水平或垂直进入匀流装置,经过匀流后烟气进入冷凝段以降低烟气温度,析出的水经塔体底部排水口流出,烟气再经过除雾段除去部分水滴,最后烟气与用于冷凝的空气会合后排入大气中,该消白塔能降低除湿法脱硫后的烟气中水含量和烟气温度,使排入大气中的烟气不再有肉眼能识别的白色烟羽,极大地降低了消白系统的投资和运维,提高了效益,达到了节能减排的目的。2. The whitening tower includes the tower body, drain outlet, inlet flue, uniform flow device, condensation section, fan, defogging section, inner cylinder and top outlet. When in use, the flue gas can enter the uniform flow device horizontally or vertically After uniform flow, the flue gas enters the condensation section to reduce the temperature of the flue gas, the precipitated water flows out through the drain at the bottom of the tower body, and the flue gas passes through the demisting section to remove some water droplets, and finally the flue gas meets the air for condensation and is discharged The whitening tower can reduce the water content and flue gas temperature in the flue gas after desulphurization by dehumidification method, so that the flue gas discharged into the atmosphere no longer has white plumes that can be recognized by the naked eye, which greatly reduces the whitening. The investment and operation and maintenance of the system have improved the efficiency and achieved the goal of energy saving and emission reduction.

附图说明Description of drawings

图1为本实用新型消白塔的结构连接主视图;Fig. 1 is the structural connection front view of the white tower of the utility model;

图2为图1中冷凝段中的空气流向的俯视示意图。FIG. 2 is a schematic top view of the air flow in the condensation section in FIG. 1 .

具体实施方式Detailed ways

下面结合通过具体实施例对本实用新型作进一步详述,以下实施例只是描述性的,不是限定性的,不能以此限定本实用新型的保护范围。The utility model will be further described in detail below in conjunction with specific examples. The following examples are only descriptive, not restrictive, and cannot limit the protection scope of the utility model.

本实用新型未具体详细描述的结构,均可以理解为本领域的常规结构。The structures not described in detail in this utility model can be understood as conventional structures in the art.

一种湿法脱硫尾部烟气消白塔,如图1和图2所示,所述消白塔包括塔体3、进口烟道10、冷凝段6、内筒2和顶部出口1,所述塔体的顶部同轴相连通设置顶部出口,该塔体的下部相连通设置进口烟道,该进口烟道上方的塔体内同轴设置冷凝段。A wet desulfurization tail flue gas whitening tower, as shown in Figure 1 and Figure 2, the whitening tower includes a tower body 3, an inlet flue 10, a condensation section 6, an inner cylinder 2 and a top outlet 1, the The top of the tower body is coaxially connected with a top outlet, the lower part of the tower body is connected with an inlet flue, and the tower body above the inlet flue is coaxially arranged with a condensation section.

本实用新型的创新点在于:The innovation point of the present utility model is:

所述内筒同轴设置于冷凝段、顶部出口之间的塔体内,该内筒的顶部设置于顶部出口的下方,该内筒与塔体内部之间设置空气流动腔4,该空气流动腔与冷凝段的输出端、内筒上方的塔体均相连通设置,所述冷凝段的上表面的外侧同轴紧密连接设置内筒的底部;The inner cylinder is coaxially arranged in the tower body between the condensation section and the top outlet, the top of the inner cylinder is arranged below the top outlet, and an air flow chamber 4 is arranged between the inner cylinder and the inside of the tower body, and the air flow chamber It is connected with the output end of the condensation section and the tower above the inner cylinder, and the outer side of the upper surface of the condensation section is coaxially tightly connected to the bottom of the inner cylinder;

所述冷凝段的下底面的外侧通过密封板7与塔体的内壁紧密相连接设置,所述冷凝段的输入端能够输入空气,该冷凝段的介质为空气,该冷凝段的输出端与空气流动腔相连通设置,换热后的空气能够进入空气流动腔内并最终与从内筒的出口输出的处理后烟气在内筒上方的塔体顶部汇合在一起,并从顶部出口排出。The outer side of the lower bottom surface of the condensing section is closely connected with the inner wall of the tower body through a sealing plate 7. The input end of the condensing section can input air, the medium of the condensing section is air, and the output end of the condensing section is connected with the air. The flow chambers are communicated, and the heat-exchanged air can enter the air flow chamber and finally merge with the treated flue gas output from the outlet of the inner cylinder at the top of the tower above the inner cylinder, and be discharged from the top outlet.

本消白塔包括塔体、进口烟道、冷凝段、内筒和顶部出口,在使用时,烟气通过进口烟道进入塔体,然后进入冷凝段以降低烟气温度,析出的水落入塔体底部,烟气经过内筒、用于冷凝的空气经过空气流动腔,最后烟气与用于冷凝的空气会合后排入大气中;内筒分开烟气与空气可防止烟气中的冷凝水沿空气流动腔进入冷凝器,使烟气在上升过程中产生的大液滴被内筒壁板捕捉,减少烟气中大液滴夹带;另外,内筒上方烟气与空气接触会产生小液滴,在烟囱内经过一段距离到达烟囱顶部之前,非饱和烟气混合气再次蒸发这些小液滴,使排放到大气中的混合烟气不再有白色羽烟,该消白塔能降低除湿法脱硫后的烟气中水含量和烟气温度,使排入大气中的烟气不再有肉眼能识别的白色烟羽,极大地降低了消白系统的投资和运维,提高了效益,达到了节能减排的目的。The whitening tower includes a tower body, an inlet flue, a condensation section, an inner cylinder and an outlet at the top. When in use, the flue gas enters the tower body through the inlet flue, and then enters the condensation section to reduce the temperature of the flue gas, and the precipitated water falls into the At the bottom of the tower body, the flue gas passes through the inner cylinder, the air used for condensation passes through the air flow chamber, and finally the flue gas meets the air used for condensation and is discharged into the atmosphere; the inner cylinder separates the flue gas and air to prevent condensation in the flue gas The water enters the condenser along the air flow chamber, so that the large liquid droplets generated during the rising process of the flue gas are captured by the wall plate of the inner cylinder, reducing the entrainment of large liquid droplets in the flue gas; in addition, the contact between the flue gas above the inner cylinder and the air will produce small Liquid droplets, before reaching the top of the chimney after a certain distance in the chimney, the unsaturated flue gas mixture evaporates these small droplets again, so that the mixed flue gas discharged into the atmosphere no longer has white plumes, and the whitening tower can reduce dehumidification. The water content and temperature of the flue gas after desulfurization by the desulfurization method make the flue gas discharged into the atmosphere no longer have a white plume that can be recognized by the naked eye, which greatly reduces the investment and operation and maintenance of the whitening system, and improves the efficiency. Achieved the purpose of energy saving and emission reduction.

在本实施例中,所述消白塔还包括排水口9、匀流装置8、风机(图中未示出)和除雾段5,所述塔体的底部同轴相连通设置排水口,用于排出冷凝段、除雾段流下的水,所述排水口、冷凝段之间的塔体上同轴间隔设置匀流装置,该匀流装置、排水口之间的塔体上设置进口烟道;In this embodiment, the white removal tower also includes a drain 9, a flow equalizer 8, a fan (not shown in the figure) and a defogging section 5, and the bottom of the tower body is coaxially connected with a drain, It is used to discharge the water flowing down from the condensing section and the demisting section. A uniform flow device is arranged coaxially on the tower body between the drain outlet and the condensation section, and an inlet smoke is installed on the tower body between the flow uniform device and the drain road;

所述内筒的下部内同轴紧密设置除雾段,该除雾段设置于冷凝段的上方且与冷凝段相间隔设置;The lower part of the inner cylinder is coaxially and tightly provided with a defogging section, and the defogging section is arranged above the condensing section and spaced apart from the condensing section;

所述风机与冷凝段的入口相连接设置,该风机能够将空气输入冷凝段内。The fan is connected with the inlet of the condensing section, and the fan can input air into the condensing section.

本消白塔还包括排水口、匀流装置、风机和除雾段,在使用时,烟气可以水平或垂直进入匀流装置,经过匀流后烟气进入冷凝段以降低烟气温度,析出的水经塔体底部排水口流出,烟气再经过除雾段除去部分水滴,最后烟气与用于冷凝的空气会合后排入大气中,该消白塔能降低除湿法脱硫后的烟气中水含量和烟气温度,使排入大气中的烟气不再有肉眼能识别的白色烟羽,极大地降低了消白系统的投资和运维,提高了效益,达到了节能减排的目的。The whitening tower also includes a drain, a uniform flow device, a fan and a defogging section. When in use, the flue gas can enter the uniform flow device horizontally or vertically. After the uniform flow, the smoke enters the condensation section to reduce the temperature of the flue gas and precipitate The water flows out through the drain outlet at the bottom of the tower body, and the flue gas passes through the demisting section to remove part of the water droplets. Finally, the flue gas meets the air for condensation and is discharged into the atmosphere. The content of reclaimed water and the temperature of the flue gas make the flue gas discharged into the atmosphere no longer have a white plume that can be recognized by the naked eye, which greatly reduces the investment and operation and maintenance of the whitening system, improves the efficiency, and achieves the goal of energy saving and emission reduction. Purpose.

在本实施例中,所述冷凝段为列管换热器。In this embodiment, the condensation section is a tube-and-tube heat exchanger.

在本实施例中,所述消白塔还包括冲洗水系统(图中未示出),所述冲洗水系统包括冲洗水输出端,该冲洗水输出端设置于冷凝段、除雾段之间的塔体上,该冲洗水输出端输出的冲洗水能够冲洗掉冷凝段析出的水到塔体底部。In this embodiment, the whitening tower also includes a flushing water system (not shown in the figure), and the flushing water system includes a flushing water output end, and the flushing water output end is arranged between the condensation section and the defogging section On the tower body, the flushing water output from the flushing water output end can flush the water precipitated in the condensation section to the bottom of the tower body.

在本实施例中,所述除雾段为气动高效除尘除雾器。In this embodiment, the demist section is a pneumatic high-efficiency dust and mist eliminator.

在本实施例中,所述排水口通过排水泵、排水管道(图中未示出)与脱硫塔内相连接设置。In this embodiment, the drain port is connected to the inside of the desulfurization tower through a drain pump and a drain pipe (not shown in the figure).

本湿法脱硫尾部烟气消白塔的一种工作过程是:A working process of the wet desulfurization tail flue gas elimination tower is:

烟气通过进口烟道进入塔体底部,向上穿过匀流装置使烟气均匀后进入冷凝段(可以为列管换热器),在冷凝段析出的水(经冲洗水被冲洗水冲到)流到塔体底部,经排水口流出(可以经排水泵、排水管道返回脱硫塔内),烟气再经过内筒进入除雾段除去部分水滴,沿内筒上升一段距离,在冷凝段由鼓风机(鼓风机可以设置为对称布置)将空气从塔体外送入冷凝段,经过冷凝段后的空气进入外筒沿内筒与外筒之间空间(即空气流动腔)上升一段距离,在内筒顶部空气与处理后的烟气会合后排入大气中,特别地,冷却用空气和减温后的空气用内筒隔开后再汇合排入大气中。The flue gas enters the bottom of the tower body through the inlet flue, passes upward through the uniform flow device to make the flue gas uniform, and then enters the condensation section (which can be a tube heat exchanger), and the water precipitated in the condensation section (washed by the flushing water to the ) flows to the bottom of the tower body, and flows out through the drain (it can be returned to the desulfurization tower through the drainage pump and drainage pipe). The blower (the blower can be set to be symmetrically arranged) sends the air from the outside of the tower to the condensation section, and the air after passing through the condensation section enters the outer cylinder and rises for a distance along the space between the inner cylinder and the outer cylinder (that is, the air flow chamber). The top air is combined with the treated flue gas and then discharged into the atmosphere. In particular, the cooling air and the desuperheated air are separated by the inner cylinder and then combined and discharged into the atmosphere.

尽管为说明目的公开了本实用新型的实施例,但是本领域的技术人员可以理解:在不脱离本实用新型及所附权利要求的精神和范围内,各种替换、变化和修改都是可能的,因此,本实用新型的范围不局限于实施例所公开的内容。Although the embodiment of the present utility model is disclosed for the purpose of illustration, those skilled in the art will understand that various replacements, changes and modifications are possible without departing from the spirit and scope of the present utility model and the appended claims Therefore, the scope of the present utility model is not limited to the content disclosed in the embodiment.

Claims (6)

  1. White Tower 1. a kind of wet desulphurization tail flue gas disappears, the described White Tower that disappears include tower body, inlet flue duct, condensation segment, inner cylinder and top Portion outlet, the top of the tower body, which is coaxially connected, is arranged top exit, and the lower part of the tower body, which is connected, is arranged inlet flue duct, should Condensation segment is coaxially disposed in tower body above inlet flue duct, it is characterised in that:
    The inner cylinder coaxial arrangement is set to top exit at the top of the inner cylinder in the tower body between condensation segment, top exit Lower section, air flow lumen is set between the inner cylinder and tower body inside, on the output end of the air flow lumen and condensation segment, inner cylinder The tower body of side is connected setting, and coaxially closely the bottom of inner cylinder is arranged in connection in the outside of the upper surface of the condensation segment;
    The outside of the bottom surface of the condensation segment connects setting by the way that the inner wall of sealing plate and tower body is closely coupled, the condensation segment Input terminal can input air, the medium of the condensation segment is air, and the output end of the condensation segment is connected with air flow lumen to be set Set, the air after heat exchange be able to enter in air flow lumen and finally with from flue gas after the processing of the outlet output of inner cylinder in inner cylinder It merges together at the top of the tower body of top, and is discharged from top exit.
  2. White Tower 2. wet desulphurization tail flue gas according to claim 1 disappears, it is characterised in that: the described White Tower that disappears further includes row The mouth of a river, flow-harmonization device, blower and demisting section, the bottom of the tower body, which is coaxially connected, is arranged discharge outlet, the discharge outlet, condensation Flow-harmonization device is arranged in coaxial spaced on tower body between section, and inlet flue duct is arranged on the tower body between the flow-harmonization device, discharge outlet;
    Coaxial close setting demisting section in the lower part of the inner cylinder, the demisting section be set to the top of condensation segment and with condensation segment phase Interval setting;
    The blower is connected setting with the entrance of condensation segment, which can input air in condensation segment.
  3. White Tower 3. wet desulphurization tail flue gas according to claim 1 disappears, it is characterised in that: the condensation segment changes for tubulation Hot device.
  4. White Tower 4. wet desulphurization tail flue gas according to claim 1 disappears, it is characterised in that: the described White Tower that disappears further includes punching Wash water system, the flushing water system includes flushing water output end, which is set between condensation segment, demisting section Tower body on, the flushing water of flushing water output end output can rinse out the water of condensation segment precipitation to tower body bottom.
  5. White Tower 5. wet desulphurization tail flue gas according to claim 2 disappears, it is characterised in that: the demisting section is pneumatic high Imitate dedusting demister.
  6. White Tower 6. wet desulphurization tail flue gas according to claim 2 disappears, it is characterised in that: the discharge outlet passes through draining Be connected setting in pump, drainage pipeline and desulfurizing tower.
CN201821953686.6U 2018-11-26 2018-11-26 A tail flue gas elimination tower of wet desulfurization Active CN209423269U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821953686.6U CN209423269U (en) 2018-11-26 2018-11-26 A tail flue gas elimination tower of wet desulfurization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821953686.6U CN209423269U (en) 2018-11-26 2018-11-26 A tail flue gas elimination tower of wet desulfurization

Publications (1)

Publication Number Publication Date
CN209423269U true CN209423269U (en) 2019-09-24

Family

ID=67969644

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821953686.6U Active CN209423269U (en) 2018-11-26 2018-11-26 A tail flue gas elimination tower of wet desulfurization

Country Status (1)

Country Link
CN (1) CN209423269U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109200741A (en) * 2018-11-26 2019-01-15 航天环境工程有限公司 A kind of wet desulphurization tail flue gas disappears White Tower and application

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109200741A (en) * 2018-11-26 2019-01-15 航天环境工程有限公司 A kind of wet desulphurization tail flue gas disappears White Tower and application

Similar Documents

Publication Publication Date Title
CN207641242U (en) A kind of wet flue gas flue heat exchange eliminating white smoke and condensate water recovery device
CN109364730A (en) A system and method for collecting water and eliminating white smoke from wet desulfurization tail gas in all working conditions
CN208704475U (en) A kind of flue gas for coking industry wet desulphurization takes off white system
CN108465340B (en) White smoke plume eliminating device and method
CN107398161A (en) Coal-fired power station boiler flue gas moisture reclaims and the system and method for fine particle removing
CN110882611B (en) Boiler flue gas whitening system
CN104819571A (en) Condensed gas waste heat recovery device
CN211274153U (en) A boiler flue gas dewhitening device
CN210206387U (en) Self-heating flue gas white eliminating device
CN206935061U (en) A kind of wet desulfurization flue gas processing unit
CN108458334A (en) A kind of device and method of novel thermal power plant's low temperature heat and eliminating white smoke
CN113926291A (en) Smoke forced air cooling white light eliminating system and white light eliminating method
CN209423269U (en) A tail flue gas elimination tower of wet desulfurization
CN109200741A (en) A kind of wet desulphurization tail flue gas disappears White Tower and application
CN209361892U (en) A kind of flue gas takes off white except water treatment system
CN105698549A (en) Smoke rotational flow condensation type heat exchange device and method for aluminum oxide calcining kiln
CN109737439B (en) Water cooling-whitening device for removing condensable pollutants and recycling water in flue gas
CN203963990U (en) A kind of based on flue gas waste heat recovery and the boiler energy-saving emission-reduction system of thermal technology again
CN207237684U (en) Coal-fired power station boiler flue gas moisture recycles and the system of fine particle removing
CN110141942A (en) A flue gas deep cooling, condensation and collaborative whitening system
CN108916901A (en) A kind of auto-controlled energy-saving type eliminates the device of plume
CN212309281U (en) Smoke forced air cooling white elimination system
CN204543878U (en) A kind of system eliminating boiler desulfurization gypsum rain phenomenon
CN204372958U (en) The smoke gas treatment of gas fired-boiler modular and the full retracting device of heat energy
CN210570043U (en) Converter primary flue gas ultra-low emission and cooling and dehumidification system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20250901

Address after: 300380 North 2nd floor, 502-1, Haitai West Road, Xiqing District, Tianjin

Patentee after: Tianjin Chaoyang Environmental Protection Technology Group Co.,Ltd.

Country or region after: China

Address before: 300301 Tianjin City Xiqing District Binhai High-tech Zone Binhai Science and Technology Park Rixin Road 188, Building 1, Room 1052

Patentee before: AEROSPACE ENVIRONMENTAL ENGINEERING Co.,Ltd.

Country or region before: China