CN209413406U - A kind of electric power tower main material bracing means - Google Patents
A kind of electric power tower main material bracing means Download PDFInfo
- Publication number
- CN209413406U CN209413406U CN201821930891.0U CN201821930891U CN209413406U CN 209413406 U CN209413406 U CN 209413406U CN 201821930891 U CN201821930891 U CN 201821930891U CN 209413406 U CN209413406 U CN 209413406U
- Authority
- CN
- China
- Prior art keywords
- main material
- material plate
- bolt
- reinforcing strip
- electric power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The utility model discloses a kind of electric power tower main material bracing means, including main material plate, reinforcing strip is provided on the inside of the main material plate, the bottom and left side of the main material plate are provided through the first bolt, one end of first bolt is arranged with the first gasket, and the first gasket is located at side of the main material plate far from reinforcing strip.The utility model passes through setting reinforcing strip, first bolt, first gasket and thread groove are used cooperatively, solve the problems, such as that existing electric power tower main material bracing means installation operation is comparatively laborious, the electric power tower main material bracing means, have and advantage easy to operate is installed, during installation, it is operated woth no need to a large amount of tool, it can complete to install using spanner, it avoids welding it using bonding machine, reduce the workload of operator, also the time of installation is shortened, it prevents from bringing the personal safety of operator certain risk using bonding machine, convenient for the use of operator.
Description
Technical field
The utility model relates to power supply unit technical field, specially a kind of electric power tower main material bracing means.
Background technique
For transmission line of electricity as lifeline engineering, safety and stability is related to the security of the lives and property of people, in addition, along with
The development of mechanics of communication, in commission communications tower upgrade expanding problem becomes the most important thing, currently, many electric power pylons or communication
Tower be when building according at that time technical standard, be designed and construct based on functional requirement and service performance, put into
After many years, under new use condition, load or force path etc. change, or under extraneous environmental activity,
There is inevitably damage and defect, cause the deterioration of macro-mechanical property, buries disastrous effect for engineering accident, because
This, is transformed existing steel tower reinforcement and strengthening extremely urgent.
Electric power pylon is the important equipment in power transmission engineering, in recent years due to significantly improving to electrical energy demands, is needed
To increase more insulator chains and sensor on steel tower, increase the steel tower load to be born, and since many towers are
According to the manufacture of old edition Specification Design, performance indicator has not adapted to now the needs of increasingly rugged environment yet, always
Electric power pylon can be strengthened by increasing new component, allow to bear bigger load action, to spend less
Expense can realize that the reinforcing to steel tower upgrades, this is saved much than building a new tower line again at however existing
Electric power tower main material bracing means there is a problem that installation operation is comparatively laborious, during installation, need a large amount of
Tool is operated, and is also needed to weld it using bonding machine, is increased the workload of operator, also extend installation
Time, while spark can be also generated during welding installation, certain risk is brought to the personal safety of operator,
It is not easy to the use of operator.
Utility model content
The purpose of this utility model is to provide a kind of electric power tower main material bracing means, and it is excellent easily to operate to have installation
Point solves the problems, such as that existing electric power tower main material bracing means installation operation is comparatively laborious.
To achieve the above object, the utility model provides the following technical solutions: a kind of electric power tower main material bracing means, packet
Main material plate is included, reinforcing strip is provided on the inside of the main material plate, the bottom and left side of the main material plate are provided through first
Bolt, one end of first bolt is arranged with the first gasket, and the first gasket is located at side of the main material plate far from reinforcing strip, institute
The bottom and left side for stating reinforcing strip offer thread groove, and the other end of the first bolt extends to the inside of thread groove, described
The surface of first bolt and the inner thread of thread groove connect.
Preferably, the shape of the main material plate is L-type, the shape of the reinforcing strip be it is triangular prism shaped, the main material plate with
Reinforcing strip is made of stainless steel material.
Preferably, the reinforcing strip is provided with connecting plate far from the side of main material plate, and the connecting plate is far from reinforcing strip
Side is provided with the second bolt, and the surface of second bolt is arranged with the second gasket, and connecting plate by the second bolt and adds
Gu item is fixedly connected.
Preferably, the connecting plate is fixedly connected with notch board, and the right side and top of main material plate close to the side of main material plate
It is respectively positioned on the inside of notch board.
Preferably, the front-end and back-end on the notch board surface offer the first through slot, the front end on the right side of the main material plate
The second through slot is offered with the front-end and back-end at rear end and top, and threaded rod, the spiral shell are provided on the outside of the main material plate
One end of rasp bar is socketed with non-slip mat, and the other end of the threaded rod sequentially passes through the first through slot and the second through slot and extends to master
The inside of material plate is provided with nut on the inside of the main material plate, and the inner wall of nut is threadedly coupled with the surface of threaded rod.
Compared with prior art, the beneficial effects of the utility model are as follows:
1, the utility model being used cooperatively by setting reinforcing strip, the first bolt, the first gasket and thread groove, solves
Existing electric power tower main material bracing means installation operates comparatively laborious problem, which has
Advantage easy to operate is installed, during installation, is operated woth no need to a large amount of tool, can be completed using spanner
Installation, is avoided welding it using bonding machine, reduces the workload of operator, also shorten the time of installation, is prevented
Certain risk is only brought to the personal safety of operator using bonding machine, convenient for the use of operator.
2, the utility model is triangular prism shaped by the way that reinforcing strip to be arranged to, and can effectively save raw material, be also convenient for simultaneously
The inside of insertion main material plate can effectively enhance the connection effect of connecting plate and reinforcing strip, the company of preventing by the way that the second bolt is arranged
Occur gap between fishplate bar and reinforcing strip, by the way that notch board is arranged, notch board can be made to snap onto the edge of main material plate, prevent from reinforcing
The phenomenon that item shakes can effectively enhance the fixed effect between notch board and main material plate by setting threaded rod and nut.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model structure bottom view;
Fig. 3 is the partial enlargement diagram in the utility model Fig. 1 at A;
Fig. 4 is the partial enlargement diagram in the utility model Fig. 1 at B.
In figure: 1 main material plate, 2 reinforcing strips, 3 first bolts, 4 first gaskets, 5 thread grooves, 6 connecting plates, 7 second bolts, 8
Second gasket, 9 notch boards, 10 first through slots, 11 second through slots, 12 threaded rods, 13 non-slip mats, 14 nuts.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4, a kind of electric power tower main material bracing means, including main material plate 1 are please referred to, the shape of main material plate 1 is L-type,
The shape of reinforcing strip 2 be it is triangular prism shaped, main material plate 1 is made with reinforcing strip 2 of stainless steel material, by the way that reinforcing strip 2 to be arranged
At triangular prism shaped, raw material can be effectively saved, while being also convenient for the inside of insertion main material plate 1, the inside of main material plate 1 is provided with
Reinforcing strip 2, reinforcing strip 2 are provided with connecting plate 6 far from the side of main material plate 1, and connecting plate 6 is provided with far from the side of reinforcing strip 2
Second bolt 7, the surface of the second bolt 7 is arranged with the second gasket 8, and connecting plate 6 is fixed by the second bolt 7 and reinforcing strip 2
Connection can effectively enhance the connection effect of connecting plate 6 Yu reinforcing strip 2, prevent connecting plate 6 and add by the way that the second bolt 7 is arranged
Gu occurring gap between item 2, connecting plate 6 is fixedly connected with notch board 9, and the right side and top of main material plate 1 close to the side of main material plate 1
Portion is respectively positioned on the inside of notch board 9, by the way that notch board 9 is arranged, notch board 9 can be made to snap onto the edge of main material plate 1, prevent reinforcing strip
2 the phenomenon that shaking, the front-end and back-end on 9 surface of notch board offer the first through slot 10, the front end on 1 right side of main material plate and after
The front-end and back-end at end and top offer the second through slot 11, and the outside of main material plate 1 is provided with threaded rod 12, threaded rod 12
One end is socketed with non-slip mat 13, and the other end of threaded rod 12 sequentially passes through the first through slot 10 and the second through slot 11 and extends to main material
The inside of plate 1, the inside of main material plate 1 is provided with nut 14, and the inner wall of nut 14 is threadedly coupled with the surface of threaded rod 12, leads to
Setting threaded rod 12 and nut 14 are crossed, the fixed effect between notch board 9 and main material plate 1, the bottom of main material plate 1 can be effectively enhanced
The first bolt 3 is provided through with left side, one end of the first bolt 3 is arranged with the first gasket 4, and the first gasket 4 is located at master
Side of the material plate 1 far from reinforcing strip 2, the bottom and left side of reinforcing strip 2 offer thread groove 5, and the other end of the first bolt 3
The inside of thread groove 5 is extended to, the surface of the first bolt 3 is connect with the inner thread of thread groove 5, passes through setting reinforcing strip 2, the
One bolt 3, the first gasket 4 and thread groove 5 are used cooperatively, and solve existing electric power tower main material bracing means installation operation
Comparatively laborious problem, the electric power tower main material bracing means have and install advantage easy to operate, during installation,
It is operated woth no need to a large amount of tool, can complete to install using spanner, avoided welding it using bonding machine, subtract
Lack the workload of operator, also shortened the time of installation, prevents the personal safety band using bonding machine to operator
Carry out certain risk, convenient for the use of operator.
In use, reinforcing strip 2 to be embedded in 1 inside, so that the first bolt 3 is rotated through main material plate 1 and be screwed into reinforcing strip 2
It in thread groove 5, and brings into after connecting plate 6 and notch board 9 are welded to high altitude operation, notch board 9 is made to be connected to the edge of main material plate 1
Place is fixed on the surface of reinforcing strip 2 to connecting plate 6 using the second bolt 7, then is inserted into the first through slot 10 and second with threaded rod 12
After through slot 11, finally threaded rod 12 is attached with nut 14 and is tightened, can prevent reinforcing strip 2 from showing for inclination shaking occur
As by experimental test, when actual wind speed is less than 28m/s, horizontal span is less than 320m, when vertical span is less than 450m, should add
It is fixedly mounted with to set and is fully able to meet requirement, so as to reach installation purpose easy to operate.
In summary: the electric power tower main material bracing means, by the way that reinforcing strip 2, the first bolt 3,4 and of the first gasket is arranged
Thread groove 5 is used cooperatively, and solves the problems, such as that existing electric power tower main material bracing means installation operation is comparatively laborious.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (5)
1. a kind of electric power tower main material bracing means, including main material plate (1), it is characterised in that: set on the inside of the main material plate (1)
It is equipped with reinforcing strip (2), the bottom and left side of the main material plate (1) are provided through the first bolt (3), first bolt
(3) one end is arranged with the first gasket (4), and the first gasket (4) is located at the side of main material plate (1) far from reinforcing strip (2), described
The bottom and left side of reinforcing strip (2) offer thread groove (5), and the other end of the first bolt (3) extends to thread groove (5)
The surface of inside, first bolt (3) is connect with the inner thread of thread groove (5).
2. a kind of electric power tower main material bracing means according to claim 1, it is characterised in that: the main material plate (1)
Shape is L-type, the shape of the reinforcing strip (2) be it is triangular prism shaped, the main material plate (1) and reinforcing strip (2) are by stainless steel
Matter is made.
3. a kind of electric power tower main material bracing means according to claim 1, it is characterised in that: the reinforcing strip (2) is remote
Side from main material plate (1) is provided with connecting plate (6), and the connecting plate (6) is provided with the second spiral shell far from the side of reinforcing strip (2)
The surface of bolt (7), second bolt (7) is arranged with the second gasket (8), and connecting plate (6) by the second bolt (7) and is reinforced
Item (2) is fixedly connected.
4. a kind of electric power tower main material bracing means according to claim 3, it is characterised in that: the connecting plate (6) is leaned on
The side of nearly main material plate (1) is fixedly connected with notch board (9), and the right side of main material plate (1) and top are respectively positioned on the interior of notch board (9)
Portion.
5. a kind of electric power tower main material bracing means according to claim 4, it is characterised in that: notch board (9) surface
Front-end and back-end offer the first through slot (10), the front end of front-end and back-end and top on the right side of the main material plate (1) and
Rear end offers the second through slot (11), is provided with threaded rod (12) on the outside of the main material plate (1), the threaded rod (12)
One end is socketed with non-slip mat (13), and the other end of the threaded rod (12) sequentially passes through the first through slot (10) and the second through slot (11)
And extend to the inside of main material plate (1), be provided with nut (14) on the inside of the main material plate (1), and the inner wall of nut (14) with
The surface of threaded rod (12) is threadedly coupled.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821930891.0U CN209413406U (en) | 2018-11-22 | 2018-11-22 | A kind of electric power tower main material bracing means |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821930891.0U CN209413406U (en) | 2018-11-22 | 2018-11-22 | A kind of electric power tower main material bracing means |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209413406U true CN209413406U (en) | 2019-09-20 |
Family
ID=67934737
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821930891.0U Active CN209413406U (en) | 2018-11-22 | 2018-11-22 | A kind of electric power tower main material bracing means |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209413406U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112983041A (en) * | 2021-03-16 | 2021-06-18 | 贵州电网有限责任公司 | Method for improving anti-icing capacity of power transmission line iron tower |
-
2018
- 2018-11-22 CN CN201821930891.0U patent/CN209413406U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112983041A (en) * | 2021-03-16 | 2021-06-18 | 贵州电网有限责任公司 | Method for improving anti-icing capacity of power transmission line iron tower |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205677251U (en) | The anti-buckling bracing means of steel tower corner iron | |
CN106784502A (en) | A kind of battery framework used for electric vehicle and installation, the method for unloading battery | |
CN209413406U (en) | A kind of electric power tower main material bracing means | |
CN206532808U (en) | A kind of movable battery framework used for electric vehicle | |
CN201490195U (en) | Solar panel mounting rack used on iron tower | |
CN200961442Y (en) | High voltage operation insulation ladder | |
CN207553572U (en) | Scaffold protection network | |
CN209277668U (en) | A kind of reinforced electric wire cross-arm | |
CN201457691U (en) | Manhole safety guardrail | |
CN201298095Y (en) | Floor-type cable cross-connection cabinet of substation | |
CN110424807A (en) | A kind of lightweight composite material emergency first-aid repair electric pole | |
CN203260986U (en) | Special framework for arrester and online monitoring instrument on 10kV bus bridge | |
CN211447732U (en) | Attached lifting scaffold is with hoist and mount subassembly | |
CN204921576U (en) | Steel structure platform fixes subassembly | |
CN209723672U (en) | Portable faces side hole guard rail | |
CN211691794U (en) | Protective structure for power equipment | |
CN203312665U (en) | Disconnecting link examination and repair frame | |
CN208776187U (en) | A kind of wooden frame lifting device | |
CN209071947U (en) | A kind of replacement conductor spacer specific purpose tool | |
CN205172036U (en) | Formwork support equipment for building engineering | |
CN204793776U (en) | GW4 type isolator overhauls work platform | |
CN206053414U (en) | Distribution Board for Construction Site protection canopy | |
CN221193306U (en) | Concrete precast pile connecting device | |
CN211201133U (en) | Supporting plate for attached lifting scaffold | |
CN211473021U (en) | Roof truss for box-type substation with prevent snow and object that falls from high altitude |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |