CN209411654U - Double rocking arm set tower pole lifting power-equipments - Google Patents

Double rocking arm set tower pole lifting power-equipments Download PDF

Info

Publication number
CN209411654U
CN209411654U CN201821928413.6U CN201821928413U CN209411654U CN 209411654 U CN209411654 U CN 209411654U CN 201821928413 U CN201821928413 U CN 201821928413U CN 209411654 U CN209411654 U CN 209411654U
Authority
CN
China
Prior art keywords
lifting
tower pole
brake
pulley
rocking arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821928413.6U
Other languages
Chinese (zh)
Inventor
刘力强
张景辉
高立鹏
肖中华
周柏杨
赵国栋
王永利
黄璇
赵晔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Hebei Electric Power Co Ltd
Hebei Power Transmission and Transformation Co Ltd
State Grid Corp of China SGCC
Original Assignee
State Grid Hebei Electric Power Co Ltd
Hebei Power Transmission and Transformation Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Hebei Electric Power Co Ltd, Hebei Power Transmission and Transformation Co Ltd, State Grid Corp of China SGCC filed Critical State Grid Hebei Electric Power Co Ltd
Priority to CN201821928413.6U priority Critical patent/CN209411654U/en
Application granted granted Critical
Publication of CN209411654U publication Critical patent/CN209411654U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

本实用新型提供了一种双摇臂组塔抱杆起重动力设备,涉及供电辅助设备技术领域,两个起升设备以及控制器,起升设备包括滑轮组、钢丝绳起吊组件、卷扬机、制动器。本实用新型提供的双摇臂组塔抱杆起重动力设备,能够利用卷扬机对设置在组塔抱杆两侧的两组钢丝绳起吊组件进行收卷实现钢丝绳在滑轮组上的移动,带动自由端的电力铁塔组件上升,并利用制动器对钢丝绳的位置进行制动,保持提升端的位置稳定,该装置利用单人进行方便的起升操作,操作方便省力,降低人力劳动强度,提高工作效率,满足工程施工需要,且该设备运行稳定性高,不易出现设备故障和刹车跑磨现象,提高了双摇臂抱杆施工作业安全程度。

The utility model provides a lifting power equipment with a double-rocker group tower holding a pole, which relates to the technical field of power supply auxiliary equipment, two lifting equipment and a controller, and the lifting equipment includes a pulley block, a wire rope lifting assembly, a hoist, and a brake. The utility model provides the lifting power equipment of the double rocker group tower holding pole, which can use the hoist to rewind the two sets of steel wire rope hoisting components arranged on both sides of the tower holding pole to realize the movement of the steel wire rope on the pulley block and drive the electric power at the free end. The iron tower assembly rises, and the brake is used to brake the position of the wire rope to keep the position of the lifting end stable. The device uses a single person to carry out convenient lifting operations, which is convenient and labor-saving to operate, reduces labor intensity, improves work efficiency, and meets the needs of engineering construction. , and the equipment has high operational stability, and is not prone to equipment failure and brake running and grinding, which improves the safety of double-rocker arm holding pole construction operations.

Description

双摇臂组塔抱杆起重动力设备Double rocker arm group tower holding pole lifting power equipment

技术领域technical field

本实用新型属于供电辅助设备技术领域,更具体地说,是涉及一种双摇臂组塔抱杆起重动力设备。The utility model belongs to the technical field of power supply auxiliary equipment, and more specifically relates to a lifting power equipment with a double rocker arm group tower holding poles.

背景技术Background technique

目前,电网基建逐渐从人工作用转化成机械化施工作业,机具的安全可靠对保障工程建设的安全具有重要意义。针对输电线路工程机械化作业的高速发展,输电线路施工双摇臂组塔抱杆,使用十分频繁。双摇臂组塔抱杆作为输电线路杆塔工程主要施工机具,其施工效率以及技术性能对工程施工有着举足轻重的作用。At present, power grid infrastructure is gradually transforming from manual work to mechanized construction work. The safety and reliability of machinery and tools is of great significance to ensure the safety of engineering construction. In view of the rapid development of mechanized operations in transmission line engineering, the use of double rocker arms to set up towers and poles in transmission line construction is very frequent. As the main construction equipment for the transmission line tower project, the double rocker group tower holding pole has a decisive effect on the construction efficiency and technical performance of the project.

然而,目前大部分输电线路施工单位使用的抱杆起吊与变幅的动力源为双滚筒机动绞磨,且需要占用较多的人工、工作效率低,影响着供电建设的整体进度,同时也具有不安全因素。However, at present, the power source for pole-holding and luffing used by most transmission line construction units is a double-drum motorized winch mill, which requires more labor and low work efficiency, which affects the overall progress of power supply construction. Insecurity.

实用新型内容Utility model content

本实用新型的目的在于提供一种双摇臂组塔抱杆起重动力设备,以解决现有技术中存在的双摇臂组塔抱杆施工设备效率低、占用人工多、安全性差的技术问题。The purpose of the utility model is to provide a lifting power equipment with a double rocker arm group tower holding a pole to solve the technical problems existing in the prior art that the double rocker arm group tower holding pole construction equipment has low efficiency, takes up a lot of manpower, and has poor safety .

为实现上述目的,本实用新型采用的技术方案是:提供一种双摇臂组塔抱杆起重动力设备,包括两个设置于组塔抱杆两侧的起升设备以及与起升设备电连接的控制器,起升设备包括设置于组塔抱杆外侧且主轴沿前后方向设置的滑轮组、平行于组塔抱杆的外边缘且与滑轮组滚动连接的钢丝绳起吊组件、与钢丝绳起吊组件的输入端相连的卷扬机、用于驱动卷扬机的驱动组件以及设置于驱动组件上的制动器,驱动组件和制动器分别与控制器电连接。In order to achieve the above purpose, the technical solution adopted by the utility model is: to provide a kind of lifting power equipment for double-rocker group tower holding poles, including two lifting devices arranged on both sides of the tower holding poles and electrically connected to the lifting equipment. The connected controller, the hoisting equipment includes a pulley set arranged on the outside of the tower holding pole and the main shaft is arranged along the front and back direction, a wire rope lifting assembly parallel to the outer edge of the tower holding pole and rollingly connected with the pulley block, and an input to the wire rope lifting assembly The end-connected hoist, the drive assembly for driving the hoist, and the brake arranged on the drive assembly, the drive assembly and the brake are respectively electrically connected to the controller.

作为进一步的优化,钢丝绳起吊组件包括钢丝绳和设置于钢丝绳的自由端且用于提升电力铁塔组件的提升钩,钢丝绳的另一端与卷扬机固接且用于缠绕于卷扬机的外周。As a further optimization, the wire rope hoisting assembly includes a wire rope and a lifting hook arranged at the free end of the wire rope for lifting the power tower assembly, and the other end of the wire rope is fixedly connected to the winch and is used to wind around the outer circumference of the winch.

作为进一步的优化,驱动组件包括驱动电机、一端与驱动电机的输出端相连的联轴器以及与联轴器的另一端相连的减速机,制动器设置在联轴器上位于减速机的一侧。As a further optimization, the driving assembly includes a driving motor, a shaft coupling connected at one end to the output end of the driving motor, and a reducer connected to the other end of the coupling, and the brake is arranged on the coupling at one side of the reducer.

作为进一步的优化,滑轮组包括设置于组塔抱杆底部外侧的第一滑轮、设置于组塔抱杆上部外侧节点处的第二滑轮以及设置与组塔抱杆顶部下侧的第三滑轮,钢丝绳分别与第一滑轮、第二滑轮以及第三滑轮滚动连接。As a further optimization, the pulley block includes the first pulley arranged outside the bottom of the tower holding pole, the second pulley arranged at the upper outer node of the tower holding pole, and the third pulley arranged on the lower side of the top of the tower holding pole, and the steel wire rope They are respectively in rolling connection with the first pulley, the second pulley and the third pulley.

作为进一步的优化,驱动电机与减速机之间通过浮动轴连接。As a further optimization, the drive motor and the reducer are connected through a floating shaft.

作为进一步的优化,减速机采用四级封闭式齿轮减速箱。As a further optimization, the reducer adopts a four-stage closed gear reducer.

作为进一步的优化,驱动电机为变频电机,变频电机与控制器电连接。As a further optimization, the drive motor is a variable frequency motor, and the variable frequency motor is electrically connected to the controller.

作为进一步的优化,制动器外部设有密封壳体。As a further optimization, a sealed housing is provided outside the brake.

作为进一步的优化,还包括用于容纳控制器的控制柜以及与控制柜电连接的操作平台。As a further optimization, it also includes a control cabinet for accommodating the controller and an operation platform electrically connected with the control cabinet.

本实用新型提供的双摇臂组塔抱杆起重动力设备的有益效果在于:本实用新型提供的双摇臂组塔抱杆起重动力设备,能够利用卷扬机对设置在组塔抱杆两侧的两组钢丝绳起吊组件进行收卷实现钢丝绳在滑轮组上的移动,带动自由端的电力铁塔组件上升,并利用制动器对钢丝绳的位置进行制动,保持提升端的位置稳定,该装置利用单人进行方便的起升操作,操作方便省力,降低人力劳动强度,提高工作效率,满足工程施工需要,且该设备运行稳定性高,不易出现设备故障和刹车跑磨现象,提高了双摇臂抱杆施工作业安全程度。The beneficial effect of the lifting power equipment of the double-rocker group tower with the poles provided by the utility model is that the lifting power equipment with the double-rocker groups of the towers with the poles provided by the utility model can be arranged on both sides of the tower with the poles by means of the hoist The two sets of wire rope hoisting components are rewound to realize the movement of the wire rope on the pulley block, driving the power tower assembly at the free end to rise, and using the brake to brake the position of the wire rope to keep the position of the lifting end stable. This device uses a single person to carry out convenient lifting Lifting operation, convenient and labor-saving operation, reduces labor intensity, improves work efficiency, and meets the needs of engineering construction, and the equipment has high operating stability, and is not prone to equipment failure and brake running, which improves the safety of double rocker arm holding pole construction operations degree.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the utility model, the following will briefly introduce the accompanying drawings that are required in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only the practical For some novel embodiments, those skilled in the art can also obtain other drawings based on these drawings without any creative work.

图1为本实用新型实施例提供的双摇臂组塔抱杆起重动力设备的结构示意图;Fig. 1 is a structural schematic diagram of the double-rocker group tower holding rod lifting power equipment provided by the embodiment of the utility model;

图2为本实用新型实施例图1中卷扬机和驱动组件的左视结构示意图;Fig. 2 is a left view structural diagram of the winch and the driving assembly in Fig. 1 of the embodiment of the utility model;

其中,图中各附图标记:Wherein, each reference sign in the figure:

110-第一滑轮;120-第二滑轮;130-第三滑轮;200-钢丝绳起吊组件;210-钢丝绳;220-提升钩;300-卷扬机;400-驱动组件;410-驱动电机;420-联轴器;430-减速机;440-制动器;500-组塔抱杆。110-the first pulley; 120-the second pulley; 130-the third pulley; 200-wire rope lifting assembly; 210-wire rope; Shaft device; 430-reducer; 440-brake; 500-group tower holding pole.

具体实施方式Detailed ways

为了使本实用新型所要解决的技术问题、技术方案及有益效果更加清楚明白,以下结合附图及实施例,对本实用新型进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本实用新型,并不用于限定本实用新型。In order to make the technical problems, technical solutions and beneficial effects to be solved by the utility model clearer, the utility model will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model, and are not intended to limit the utility model.

请一并参阅图1至图2,现对本实用新型提供的双摇臂组塔抱杆起重动力设备进行说明。双摇臂组塔抱杆起重动力设备,包括两个设置于组塔抱杆500两侧的起升设备以及与起升设备电连接的控制器,起升设备包括设置于组塔抱杆500外侧且主轴沿前后方向设置的滑轮组、平行于组塔抱杆500的外边缘且与滑轮组滚动连接的钢丝绳起吊组件200、与钢丝绳起吊组件200的输入端相连的卷扬机300、用于驱动卷扬机300的驱动组件400以及设置于驱动组件400上的制动器440,驱动组件400和制动器440分别与控制器电连接。需要说明的是,当元件被称为“设置于”另一个元件,它可以直接在另一个元件上或者间接在该另一个元件上。术语“上”、“下”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。Please refer to Fig. 1 to Fig. 2 together, and now the power equipment for hoisting with double rocker arm groups and towers with poles provided by the utility model will be described. The double rocker arm tower holding pole lifting power equipment includes two lifting equipment arranged on both sides of the tower holding pole 500 and a controller electrically connected to the lifting equipment. The pulley set on the outside and the main shaft is arranged in the front-back direction, the wire rope hoisting assembly 200 parallel to the outer edge of the tower holding pole 500 and rollingly connected with the pulley block, the hoisting machine 300 connected to the input end of the wire rope hoisting assembly 200, and the hoisting machine 300 for driving The driving assembly 400 and the brake 440 disposed on the driving assembly 400 are electrically connected to the controller respectively. It should be noted that when an element is referred to as being “disposed on” another element, it may be directly on the other element or indirectly on the other element. The orientations or positional relationships indicated by the terms "upper", "lower", "top", "bottom", "inner" and "outer" are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention. Novel and simplified descriptions do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be construed as limiting the utility model.

本实用新型提供的双摇臂组塔抱杆起重动力设备,与现有技术相比,本实用新型提供的双摇臂组塔抱杆起重动力设备,能够利用卷扬机300对设置在组塔500两侧的两组钢丝绳起吊组件进行收卷实现钢丝绳在滑轮组上的移动,带动自由端的电力铁塔组件上升,并利用制动器对钢丝绳的位置进行制动,保持提升端的位置稳定,该装置利用单人进行方便的起升操作,操作方便省力,降低人力劳动强度,提高工作效率,满足工程施工需要,且该设备运行稳定性高,不易出现设备故障和刹车跑磨现象,提高了双摇臂抱杆施工作业安全程度。Compared with the prior art, the double rocker arm group tower holding rod lifting power equipment provided by the utility model can use 300 pairs of winches to be arranged on the tower group. The two sets of wire rope lifting components on both sides of the 500 are rewound to realize the movement of the wire rope on the pulley block, driving the power tower assembly at the free end to rise, and using the brake to brake the position of the wire rope to keep the position of the lifting end stable. This device uses a single person The lifting operation is convenient, the operation is convenient and labor-saving, the labor intensity is reduced, the work efficiency is improved, and the construction needs are met, and the equipment has high operation stability, and it is not easy to have equipment failure and brake grinding, which improves the double rocker arm holding rod. Safety level of construction work.

请一并参阅图1至图2,作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,钢丝绳起吊组件200包括钢丝绳210和设置于钢丝绳210的自由端且用于提升电力铁塔组件的提升钩220,钢丝绳210的另一端与卷扬机300固接且用于缠绕于卷扬机300的外周。钢丝绳起吊组件200的钢丝绳210通过卷扬机300驱动实现其卷曲在卷扬机300以带动钢丝绳210另一端的提升钩220上移的效果,同时结合组塔抱杆500上部两臂可以开合的特点,还可以实现变幅操作,完成电力铁塔组件在水平方向的位置移动。Please refer to Fig. 1 to Fig. 2 together. As a specific embodiment of the double rocker group tower holding rod lifting power equipment provided by the utility model, the wire rope lifting assembly 200 includes a wire rope 210 and a free end arranged on the wire rope 210 and The lifting hook 220 is used to lift the power tower assembly, and the other end of the wire rope 210 is fixedly connected to the winch 300 and is used to be wound around the outer periphery of the winch 300 . The wire rope 210 of the wire rope hoisting assembly 200 is driven by the winch 300 to realize the effect of being curled on the winch 300 to drive the hoisting hook 220 at the other end of the wire rope 210 to move upwards, and at the same time combined with the characteristics that the upper two arms of the tower holding pole 500 can be opened and closed, it can also Realize the amplitude-changing operation and complete the position movement of the power tower components in the horizontal direction.

请一并参阅图1至图2,作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,驱动组件400包括驱动电机410、一端与驱动电机410的输出端相连的联轴器420以及与联轴器420的另一端相连的减速机430,制动器440设置在联轴器420上位于减速机430的一侧。制动器440安装在联轴器420上,这样将制动器440设置在高速轴上的形式所需要的制动力矩小,相应的制动器尺寸小,重量轻。本实施例中采用将制动器440设置在联轴器420位于减速机430高速轴上的形式,即使联轴器420被损坏,制动器440也可把卷扬机300制动住,以确保机构的安全。驱动电机410正转或反转时,制动器440松开,通过联轴器420带动减速机430的高速轴也就是输入轴运转,经减速机430减速后由低速轴也就是减速机430的输出轴带动卷扬机300的卷筒旋转,使钢丝绳在卷筒上绕进或放出,从而使重物起升或下降。驱动电机410停止转动时,驱动电机410将信号传输给控制器,控制器接收到信号后进行处理,并控制制动器440将减速机430的高速轴制动刹住,使卷扬机300停止动作,进而使钢丝绳210的自由端悬吊的重物停止在空中。Please refer to Fig. 1 to Fig. 2 together. As a specific embodiment of the double rocker arm group tower holding rod lifting power equipment provided by the present invention, the drive assembly 400 includes a drive motor 410, one end and the output end of the drive motor 410. The connected shaft coupling 420 and the speed reducer 430 connected with the other end of the shaft coupling 420 , and the brake 440 is arranged on the shaft coupling 420 at one side of the speed reducer 430 . The brake 440 is installed on the shaft coupling 420, so that the brake 440 arranged on the high-speed shaft requires a small braking torque, and the corresponding brake is small in size and light in weight. In this embodiment, the brake 440 is arranged on the shaft coupling 420 on the high-speed shaft of the reducer 430. Even if the coupling 420 is damaged, the brake 440 can brake the winch 300 to ensure the safety of the mechanism. When the drive motor 410 rotates forward or reverse, the brake 440 is released, and the high-speed shaft of the reducer 430, which is the input shaft, is driven by the coupling 420 to rotate, and after being decelerated by the reducer 430, the low-speed shaft, which is the output shaft of the reducer 430 Drive the reel of the winch 300 to rotate, so that the steel wire rope is wound in or released on the reel, so that the heavy object is lifted or lowered. When the drive motor 410 stops rotating, the drive motor 410 transmits the signal to the controller, and the controller processes the signal after receiving the signal, and controls the brake 440 to brake the high-speed shaft of the reducer 430, so that the winch 300 stops, and then The weight suspended by the free end of the wire rope 210 stops in the air.

请一并参阅图1至图2,作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,滑轮组包括设置于组塔抱杆500底部外侧的第一滑轮110、设置于组塔抱杆500上部外侧节点处的第二滑轮120以及设置与组塔抱杆500顶部下侧的第三滑轮130,钢丝绳210分别与第一滑轮110、第二滑轮120以及第三滑轮130滚动连接。术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。第一滑轮110设置在组塔抱杆500的底部位置与钢丝绳210滚动连接,并将钢丝绳从水平方向导向为向上的方向,第二滑轮120设置在折点处,实现钢丝绳210向外侧的导向,第三滑轮130设置在最外端,钢丝绳210绕过第三滑轮130后,其自由端向下用于起吊重物。第一滑轮110采用与组塔抱杆500的底座相连的形式,且能够在水平面上进行旋转,便于对钢丝绳210进行导向支撑。Please refer to Fig. 1 to Fig. 2 together. As a specific embodiment of the lifting power equipment of the double rocker group tower holding pole provided by the utility model, the pulley block includes the first pulley 110 arranged outside the bottom of the tower holding pole 500 , the second pulley 120 arranged at the upper outer node of the group tower holding pole 500 and the third pulley 130 arranged on the lower side of the group tower holding pole 500 top, the steel wire rope 210 is respectively connected with the first pulley 110, the second pulley 120 and the third The pulley 130 is rollingly connected. The terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features. The first pulley 110 is arranged at the bottom position of the tower holding pole 500 and is rollingly connected with the steel wire rope 210, and guides the steel wire rope from the horizontal direction to the upward direction, and the second pulley 120 is arranged at the inflection point to realize the guidance of the steel wire rope 210 to the outside. The third pulley 130 is arranged at the outermost end, and after the wire rope 210 walks around the third pulley 130, its free end is used to lift heavy objects downward. The first pulley 110 is connected to the base of the tower pole 500 and can rotate on a horizontal plane, so as to guide and support the wire rope 210 .

作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,驱动电机410与减速机430之间通过浮动轴连接。为使机构布置方便并增大补偿能力,在电动机与减速机之间可用浮动轴连接。As a specific implementation of the double rocker arm group tower holding pole lifting power equipment provided by the utility model, the drive motor 410 and the reducer 430 are connected through a floating shaft. In order to facilitate the layout of the mechanism and increase the compensation capacity, a floating shaft connection can be used between the motor and the reducer.

作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,减速机430采用四级封闭式齿轮减速箱。在驱动电机410与卷扬机300之间通常采用效率较高的标准两级减速机。本实施例中,由于在重物提升过程中,要求采用较低的速度,所以可采用四级大传动比减速机。As a specific implementation of the double rocker arm tower holding pole lifting power equipment provided by the utility model, the reducer 430 adopts a four-stage closed gear reducer. A standard two-stage reducer with high efficiency is usually used between the drive motor 410 and the winch 300 . In this embodiment, since a lower speed is required during the lifting of heavy objects, a four-stage speed reducer with a large transmission ratio can be used.

作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,驱动电机410为变频电机,变频电机与控制器电连接本实施例中采用的动力装置为变频电机,变频电机的通用性高、结构紧凑、体积小、重量轻、起重大、使用转移方便,在设计或选择制动器时,主要依据是制动力矩。As a specific implementation of the double-rocker group tower holding pole lifting power equipment provided by the utility model, the drive motor 410 is a frequency conversion motor, and the frequency conversion motor is electrically connected to the controller. The power device used in this embodiment is a frequency conversion motor. The variable frequency motor has high versatility, compact structure, small size, light weight, heavy lifting, and convenient use and transfer. When designing or selecting a brake, the main basis is the braking torque.

作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,制动器440外部设置的密封壳体,便于很好的保证其外部封闭的形式,制动力矩应保证有足够的制动安全系数,保证良好的制动有效性。该设备的运行稳定性高,不易出现设备故障和刹车跑磨现象,提高了双摇臂抱杆施工作业安全程度。As a specific implementation of the double rocker arm group tower holding pole lifting power equipment provided by the utility model, the sealed casing outside the brake 440 is convenient to ensure its external closed form, and the braking torque should be ensured. Sufficient braking safety factor ensures good braking effectiveness. The equipment has high operational stability, and is not prone to equipment failure and brake running and grinding, which improves the safety of double rocker arm holding pole construction operations.

作为本实用新型提供的双摇臂组塔抱杆起重动力设备的一种具体实施方式,还包括用于容纳控制器的控制柜以及与控制柜电连接的操作平台。控制柜用于容纳电器元件,避免野外作业环境多变造成设备的损坏,操作平台上述设置多个与控制器电连接的控制按钮,用于控制设备的启停,具有方便操作,占用人工少的优势。As a specific embodiment of the lifting power equipment of the double rocker group tower with poles provided by the utility model, it also includes a control cabinet for accommodating the controller and an operation platform electrically connected with the control cabinet. The control cabinet is used to accommodate electrical components to avoid equipment damage caused by changing field operating environments. The operating platform is equipped with multiple control buttons electrically connected to the controller to control the start and stop of the equipment, which is convenient for operation and requires less labor. Advantage.

本实用新型提供的双摇臂组塔抱杆起重动力设备,能够利用卷扬机对设置在组塔抱杆两侧的两组钢丝绳起吊组件进行收卷实现钢丝绳在滑轮组上的移动,带动自由端的电力铁塔组件上升,并利用制动器对钢丝绳的位置进行制动,保持提升端的位置稳定,该装置利用单人进行方便的起升操作,操作方便省力,降低人力劳动强度,提高工作效率,满足工程施工需要,且该设备运行稳定性高,不易出现设备故障和刹车跑磨现象,提高了双摇臂抱杆施工作业安全程度。The utility model provides the lifting power equipment of the double rocker group tower holding pole, which can use the hoist to rewind the two sets of steel wire rope hoisting components arranged on both sides of the tower holding pole to realize the movement of the steel wire rope on the pulley block and drive the electric power at the free end. The iron tower assembly rises, and the brake is used to brake the position of the wire rope to keep the position of the lifting end stable. The device uses a single person to carry out convenient lifting operations, which is convenient and labor-saving to operate, reduces labor intensity, improves work efficiency, and meets the needs of engineering construction. , and the equipment has high operational stability, and is not prone to equipment failure and brake running and grinding, which improves the safety of double-rocker arm holding pole construction operations.

以上仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本实用新型的保护范围之内。The above are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present utility model should be included in the utility model. within the scope of protection.

Claims (9)

1. pair rocking arm set tower pole lifting power-equipment, it is characterised in that: be set to described group of tower pole (500) two including two The erecting equipment of side and the controller being electrically connected with the erecting equipment, the erecting equipment include being set to described group of tower to embrace On the outside of bar (500) and pulley blocks that main shaft is arranged along the longitudinal direction, be parallel to described group of tower pole (500) outer edge and with institute State that pulley blocks roll wirerope lifting component (200) of connection, the input terminal for lifting by crane component (200) with the wirerope is connected It hoist engine (300), the driving assembly (400) for driving the hoist engine (300) and is set to the driving component (400) On brake (440), the driving component (400) and the brake (440) are electrically connected with the controller respectively.
2. double rocking arm set tower pole lifting power-equipments as described in claim 1, it is characterised in that: the wirerope lifting group Part (200) includes wirerope (210) and the free end for being set to the wirerope (210) and is used to promote electric power tower component The other end of hoist hook (220), the wirerope (210) is affixed with the hoist engine (300) and for being wound in the elevator The periphery of machine (300).
3. double rocking arm set tower pole lifting power-equipments as described in claim 1, it is characterised in that: the driving component (400) include shaft coupling (420) that driving motor (410), one end are connected with the output end of the driving motor (410) and with The connected speed reducer (430) of the other end of the shaft coupling (420), the brake (440) are arranged in the shaft coupling (420) The upper side close to the speed reducer (430).
4. double rocking arm set tower pole lifting power-equipments as claimed in claim 3, it is characterised in that: the pulley blocks include setting It is placed in the first pulley (110) of described group of tower pole (500) bottom outside, is set to described group of tower pole (500) upper outside Second pulley (120) and setting and the third pulley (130) of downside at the top of described group of tower pole (500) at node, it is described Wirerope (210) is rolled with the first pulley (110), the second pulley (120) and the third pulley (130) respectively Connection.
5. double rocking arm set tower pole lifting power-equipments as claimed in claim 3, it is characterised in that: the driving motor (410) pass through floating axis connection between the speed reducer (430).
6. double rocking arm set tower pole lifting power-equipments as claimed in claim 3, it is characterised in that: the speed reducer (430) Using level Four closed-end gear reduction gearbox.
7. double rocking arm set tower pole lifting power-equipments as claimed in claim 3, it is characterised in that: the driving motor It (410) is variable-frequency motor, the variable-frequency motor is electrically connected with the controller.
8. double rocking arm set tower pole lifting power-equipments as claimed in claim 7, it is characterised in that: the brake (440) Outside is respectively equipped with seal casinghousing.
9. double rocking arm set tower pole lifting power-equipments as described in claim 1, it is characterised in that: further include for accommodating The operating platform stating the control cabinet of controller and being electrically connected with the control cabinet.
CN201821928413.6U 2018-11-21 2018-11-21 Double rocking arm set tower pole lifting power-equipments Active CN209411654U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821928413.6U CN209411654U (en) 2018-11-21 2018-11-21 Double rocking arm set tower pole lifting power-equipments

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821928413.6U CN209411654U (en) 2018-11-21 2018-11-21 Double rocking arm set tower pole lifting power-equipments

Publications (1)

Publication Number Publication Date
CN209411654U true CN209411654U (en) 2019-09-20

Family

ID=67934704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821928413.6U Active CN209411654U (en) 2018-11-21 2018-11-21 Double rocking arm set tower pole lifting power-equipments

Country Status (1)

Country Link
CN (1) CN209411654U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112461288A (en) * 2020-10-26 2021-03-09 国网福建省电力有限公司建设分公司 Pole working state monitoring device and monitoring method thereof
CN114279343A (en) * 2021-12-31 2022-04-05 江苏省送变电有限公司 Computer vision-based displacement monitoring method for double-flat-arm holding pole construction process

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112461288A (en) * 2020-10-26 2021-03-09 国网福建省电力有限公司建设分公司 Pole working state monitoring device and monitoring method thereof
CN114279343A (en) * 2021-12-31 2022-04-05 江苏省送变电有限公司 Computer vision-based displacement monitoring method for double-flat-arm holding pole construction process

Similar Documents

Publication Publication Date Title
CN201288030Y (en) Balanced type energy conservation crane
CN217808382U (en) Steel cable stabilizing device for bridge crane for industrial silicon production
CN209411654U (en) Double rocking arm set tower pole lifting power-equipments
CN202358850U (en) Light lift-type cantilever crane
CN217867645U (en) Steel box girder overhead hoist
CN213569302U (en) Boiler installation overhead hoist
CN220866943U (en) Crane with anti-swing device
CN219730342U (en) An auxiliary lifting device
CN203558395U (en) Hoisting mechanism of stacker loading platform
CN203255902U (en) Multi-pulley-block four-winch linkage derrick lifting platform
CN218538917U (en) Mine hoisting device
CN102745598B (en) Tower crane
CN101938106B (en) Variable frequency driven cable reeling device
CN209702131U (en) A new type of magnification conversion device for tower cranes
CN212222281U (en) A new type of double drum electric hoist
CN209853587U (en) The hoisting wire rope winding system and hoisting mechanism of the traditional quay crane with an external trolley
CN115676617A (en) A truss type steel coil lifting device
CN106684760B (en) The dragger that a kind of aerial work uses
CN223824015U (en) A high-safety single-girder bridge erecting machine girder lifting trolley
CN221894585U (en) A construction hoisting equipment for installing a wind turbine
CN218841172U (en) Energy-saving machine-building draw gear
CN205023758U (en) Modified is small -size decides pillar jib crane
CN204823897U (en) Pillar jib crane is decided to convenient to use small -size
CN211644443U (en) Suspension wire storage device for crane
CN211998506U (en) Mining crane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant