CN209383292U - A tower crane - Google Patents

A tower crane Download PDF

Info

Publication number
CN209383292U
CN209383292U CN201821581975.8U CN201821581975U CN209383292U CN 209383292 U CN209383292 U CN 209383292U CN 201821581975 U CN201821581975 U CN 201821581975U CN 209383292 U CN209383292 U CN 209383292U
Authority
CN
China
Prior art keywords
sliding rail
tower crane
trolley
tower
crane device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821581975.8U
Other languages
Chinese (zh)
Inventor
李渊河
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of CN209383292U publication Critical patent/CN209383292U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • E04G11/24Construction of lifting jacks or climbing rods for sliding forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Jib Cranes (AREA)

Abstract

A tower crane device, its characterized in that: the device comprises at least one fixed beam, a first slide rail arranged at the top of the fixed beam, a movable beam arranged on the first slide rail and capable of moving along the first slide rail, a first driving mechanism for driving the movable beam, a second slide rail arranged on the movable beam, a trolley arranged on the second slide rail and capable of moving along the second slide rail, a second driving mechanism for driving the trolley and a crane arranged on the trolley; the first slide rail is perpendicular to the second slide rail. Through setting up mutually perpendicular's first slide rail and second slide rail, the loop wheel machine can transversely and longitudinal movement, consequently can set up shorter jib loading boom, just can realize building construction scope's full coverage to can guarantee the lifting capacity, and tower crane device simple structure, the practicality is high.

Description

一种塔吊装置A tower crane

技术领域technical field

本实用新型涉及建筑施工领域,尤其是一种塔吊装置。The utility model relates to the field of building construction, in particular to a tower hoisting device.

背景技术Background technique

塔吊是建筑工地上最常用的一种起重设备 又名“塔式起重机”,用来吊施工用的钢筋、木楞、混凝土、钢管等施工的原材料。塔吊是工地上一种必不可少的设备。Tower crane is the most commonly used lifting equipment on construction sites, also known as "tower crane". The tower crane is an indispensable equipment on the construction site.

建筑施工区域面积大,塔吊需要具备很大的作业范围,目前的塔吊由塔身、起重臂和平衡臂等部件组成,这就需要起重臂要有足够的臂长来保证其覆盖范围,同时又要保证能其起吊能力,这对塔吊本身材料和结构的强度提出了很大的要求。The construction area is large, and the tower crane needs to have a large operating range. The current tower crane is composed of components such as the tower body, the boom and the balance arm. This requires the boom to have enough arm length to ensure its coverage. At the same time, it is necessary to ensure its lifting capacity, which puts forward great requirements on the strength of the tower crane itself and its structure.

实用新型内容Utility model content

本实用新型目的是提供一种结构简单、作业范围大、又能有效保证强度的塔吊装置,为达到上述目的,本实用新型采用如下技术方案:The purpose of this utility model is to provide a tower crane with a simple structure, a large operating range, and an effective guarantee of strength. In order to achieve the above purpose, the utility model adopts the following technical solutions:

一种塔吊装置,包括至少一条固定梁、设置在固定梁顶部的第一滑轨、设在第一滑轨上并能沿第一滑轨移动的移动梁、用于驱动移动梁的第一驱动机构、设在移动梁上的第二滑轨、设置在第二滑轨上并能沿所述第二滑轨移动的小车、用于驱动小车的第二驱动机构以及设在小车上的吊机;所述第一滑轨与所述第二滑轨垂直。A tower crane includes at least one fixed beam, a first sliding rail arranged on the top of the fixed beam, a moving beam arranged on the first sliding rail and capable of moving along the first sliding rail, and a first drive for driving the moving beam mechanism, a second sliding rail provided on the moving beam, a trolley provided on the second sliding rail and capable of moving along the second sliding rail, a second driving mechanism for driving the trolley, and a hoist provided on the trolley ; The first slide rail is perpendicular to the second slide rail.

进一步的,所述固定梁数量为两条,两固定梁平行设置。Further, the number of the fixed beams is two, and the two fixed beams are arranged in parallel.

进一步的,所述吊机包括旋转座、设在旋转座上的支撑柱、设在支撑柱顶部的吊臂、设在支撑柱顶部的平衡臂、设在吊臂伸出端的吊绳以及设在平衡臂伸出端的起重电机。Further, the crane includes a swivel base, a support column set on the swivel base, a boom set on the top of the support column, a balance arm set on the top of the support column, a suspending rope set at the extension end of the hoist arm, and a boom set on the top of the support column. Lifting motor at the extended end of the balance arm.

进一步的,所述移动梁底部设有与所述第一滑轨相匹配的第一滚轮机构。Further, the bottom of the moving beam is provided with a first roller mechanism matched with the first slide rail.

进一步的,所述小车底部设有与所述第二滑轨相匹配的第二滚轮机构。Further, the bottom of the trolley is provided with a second roller mechanism matched with the second slide rail.

进一步的,所述小车底部设有机械手。Further, a manipulator is provided at the bottom of the trolley.

进一步的,所述机械手包括与小车连接的伸缩臂、设在伸缩臂底部的抓手臂以及设在抓手臂伸出端的吸附体;所述抓手臂可绕所述伸缩臂旋转,所述吸附体为永磁吸盘或电磁吸盘;所述移动梁的中间设有避让机械手的通槽。通过在底部设置机械手,能够抓取建筑模板等其他金属物件,当吊机从固定梁的一端移动到另一端时,机械手需先移动到通槽内部,避免其与固定梁干涉。Further, the manipulator includes a telescopic arm connected to the trolley, a grab arm provided at the bottom of the telescopic arm, and an adsorption body provided at the extension end of the grab arm; the grab arm can rotate around the telescopic arm, and the adsorption body is A permanent magnet suction cup or an electromagnetic suction cup; a through slot for avoiding the manipulator is arranged in the middle of the moving beam. By setting a manipulator at the bottom, it can grab other metal objects such as building templates. When the crane moves from one end of the fixed beam to the other end, the manipulator needs to move into the through slot first to avoid interference with the fixed beam.

进一步的,所述固定梁的底部设有若干升降立柱组件。Further, the bottom of the fixed beam is provided with several lifting column assemblies.

进一步的,所述升降立柱组件包括顶升笼、液压缸、底座和若干塔节;所述塔节之间上下连接,最下方的塔节设置在所述底座上;所述顶升笼固定在所述底座上,所述顶升笼内设有容纳一节塔节的容纳空间,位于最下方的所述塔节设置在所述容纳空间内;所述塔节上设有抵撑槽孔,所述底座上设有若干枢接部,所述液压缸基座枢接在所述枢接部,所述液压缸活塞杆端部连接在所述抵撑槽孔上。通过液压缸将塔节向上顶升一个塔节高度后,位于最下方的顶升笼内安装新的塔节,通过上述方式来实现塔吊的整体提升。Further, the lifting column assembly includes a jacking cage, a hydraulic cylinder, a base and a number of tower sections; the tower sections are connected up and down, and the lowermost tower section is arranged on the base; the jacking cage is fixed on the base. On the base, a accommodating space for accommodating a tower section is arranged in the jacking cage, and the tower section located at the bottom is arranged in the accommodating space; the tower section is provided with a supporting slot hole, The base is provided with a plurality of pivoting parts, the hydraulic cylinder base is pivotally connected to the pivoting parts, and the end of the piston rod of the hydraulic cylinder is connected to the abutting slot hole. After the tower section is jacked up by one tower section height through the hydraulic cylinder, a new tower section is installed in the lowermost jacking cage, and the overall lifting of the tower crane is realized by the above method.

通过采用上述技术方案,可达到的有益效果是,通过设置相互垂直的第一滑轨和第二滑轨,吊机可以横向和纵向移动,因此可以设置较短的起重臂,就能实现建筑施工范围的全覆盖,并能保证起重能力,且塔吊装置结构简单,实用性高。另外,塔吊装置主体以若干升降立柱组件作为支撑并实现整体提升,并通过顶部的固定梁和移动梁彼此连接成一个整体,相对目前常用的单塔身结构,稳定性显著增强,特别是在刮台风等恶劣天气,抗风性强。By adopting the above technical solution, the beneficial effect that can be achieved is that by setting the first slide rail and the second slide rail that are perpendicular to each other, the crane can move laterally and vertically, so a shorter boom can be set, and the construction can be realized. The construction scope is fully covered, and the lifting capacity can be guaranteed, and the tower crane has a simple structure and high practicability. In addition, the main body of the tower crane is supported by several lifting column components and realizes the overall lifting, and is connected to each other through the fixed beam and movable beam at the top to form a whole. Compared with the single tower structure commonly used at present, the stability is significantly enhanced, especially in scraping Strong wind resistance in severe weather such as typhoons.

附图说明Description of drawings

图1是塔吊装置的示意图。Figure 1 is a schematic diagram of a tower crane.

图2是图1的俯视图。FIG. 2 is a plan view of FIG. 1 .

图3是机械手缩进通槽中的示意图。Figure 3 is a schematic diagram of a manipulator retracting into a through slot.

具体实施方式Detailed ways

如图1、2所示,一种塔吊装置,包括两条平行设置的固定梁1、设在固定梁1底部两端的升降立柱组件7、设置在固定梁1顶部的第一滑轨2、设在第一滑轨2上并能沿第一滑轨2移动的移动梁3、用于驱动移动梁3的第一驱动机构、设在移动梁3上的第二滑轨4、设置在第二滑轨4上并能沿第二滑轨4移动的小车8、用于驱动小车8的第二驱动机构以及设在小车8上的吊机5;第一滑轨2与第二滑轨4垂直移动梁底部设有与第一滑轨2相匹配的第一滚轮机构32,小车底部设有与第二滑轨2相匹配的第二滚轮机构81。As shown in Figures 1 and 2, a tower crane includes two fixed beams 1 arranged in parallel, lifting column assemblies 7 arranged at both ends of the bottom of the fixed beam 1, a first slide rail 2 arranged on the top of the fixed beam 1, A moving beam 3 on the first sliding rail 2 and movable along the first sliding rail 2, a first driving mechanism for driving the moving beam 3, a second sliding rail 4 provided on the moving beam 3, a second sliding rail 4 provided on the second sliding rail 3 The trolley 8 on the sliding rail 4 and can move along the second sliding rail 4, the second driving mechanism for driving the trolley 8, and the crane 5 provided on the trolley 8; the first sliding rail 2 is perpendicular to the second sliding rail 4 The bottom of the moving beam is provided with a first roller mechanism 32 matched with the first slide rail 2 , and the bottom of the trolley is provided with a second roller mechanism 81 matched with the second slide rail 2 .

吊机5包括旋转座51、设在旋转座51上的支撑柱52、设在支撑柱52顶部的吊臂53、设在支撑柱52顶部的平衡臂54、设在吊臂53伸出端的吊绳55以及设在平衡臂54伸出端的起重电机56。The crane 5 includes a swivel base 51 , a support column 52 arranged on the swivel base 51 , a boom 53 arranged on the top of the support column 52 , a balance arm 54 arranged at the top of the support column 52 , and a crane arranged at the extension end of the boom 53 . The rope 55 and the hoisting motor 56 provided at the extended end of the balance arm 54.

小车8底部设有机械手6,机械手6包括与吊机5底部连接的伸缩臂61、设在伸缩臂61底部的抓手臂62以及设在抓手臂62伸出端的吸附体63;抓手臂62可绕伸缩臂61旋转,吸附体63为永磁吸盘或电磁吸盘;移动梁3的中间设有避让机械手6的通槽31。通过在底部设置机械手6,能够抓取建筑模板等其他金属物件。如图3所示,当吊机5从固定梁1的一端移动到另一端时,机械手6需先移动到空腔通槽31内部,避免其与固定梁1干涉。The bottom of the trolley 8 is provided with a manipulator 6. The manipulator 6 includes a telescopic arm 61 connected to the bottom of the crane 5, a grab arm 62 provided at the bottom of the telescopic arm 61, and an adsorption body 63 provided at the extension end of the grab arm 62; the grab arm 62 can be wound around The telescopic arm 61 rotates, and the adsorption body 63 is a permanent magnet chuck or an electromagnetic chuck; the middle of the moving beam 3 is provided with a through slot 31 for avoiding the manipulator 6 . By arranging the manipulator 6 at the bottom, other metal objects such as building templates can be grasped. As shown in FIG. 3 , when the crane 5 moves from one end of the fixed beam 1 to the other end, the manipulator 6 needs to move into the cavity through groove 31 first to avoid interference with the fixed beam 1 .

升降立柱组件7包括顶升笼71、液压缸74、底座72和若干塔节73;塔节73之间上下连接,最下方的塔节73设置在底座72上;顶升笼71固定在底座72上,顶升笼71内设有容纳一节塔节73的容纳空间,位于最下方的塔节73设置在容纳空间内;塔节73上设有抵撑槽孔75,底座72上设有若干枢接部76,液压缸74的基座枢接在枢接部76,液压缸74活塞杆端部连接在抵撑槽孔75上。通过液压缸74将塔节73向上顶升一个塔节73高度后,位于最下方的顶升笼71内安装新的塔节73,通过上述方式来实现塔吊的整体提升。The lifting column assembly 7 includes a jacking cage 71, a hydraulic cylinder 74, a base 72 and a number of tower sections 73; the tower sections 73 are connected up and down, and the lowermost tower section 73 is arranged on the base 72; the jacking cage 71 is fixed on the base 72 On the top, the jacking cage 71 is provided with a accommodating space for accommodating a tower section 73, and the tower section 73 located at the bottom is set in the accommodating space; the tower section 73 is provided with a supporting slot 75, and the base 72 is provided with several The pivot portion 76 is pivotally connected to the base of the hydraulic cylinder 74 on the pivot portion 76 , and the end of the piston rod of the hydraulic cylinder 74 is connected to the abutting slot 75 . After the tower section 73 is lifted up by one tower section 73 height through the hydraulic cylinder 74, a new tower section 73 is installed in the lowermost jacking cage 71, and the overall lifting of the tower crane is achieved by the above method.

采取上述技术方案,通过设置相互垂直的第一滑轨2和第二滑轨4,吊机5可以横向和纵向移动,因此可以设置较短的吊臂53,就能实现建筑施工范围的全覆盖,并能保证起重能力,且塔吊装置结构简单,实用性高。另外,塔吊装置主体以四个升降立柱组件7作为支撑并实现整体提升,并通过顶部的固定梁1和移动梁3彼此连接成一个整体,相对目前常用的单塔身结构,稳定性显著增强,特别是在刮台风等恶劣天气,抗风性强。By adopting the above technical solution, by setting the first slide rail 2 and the second slide rail 4 that are perpendicular to each other, the crane 5 can move laterally and longitudinally, so a shorter boom 53 can be set to achieve full coverage of the construction scope , and can ensure the lifting capacity, and the tower crane has a simple structure and high practicability. In addition, the main body of the tower crane is supported by four lifting column assemblies 7 to achieve overall lifting, and is connected to each other through the top fixed beam 1 and movable beam 3 to form a whole. Compared with the currently commonly used single tower structure, the stability is significantly enhanced. Especially in bad weather such as typhoons, it has strong wind resistance.

此外,可以在固定梁1上设置多个移动梁3和吊机5,以此来提高作业效率。In addition, a plurality of moving beams 3 and hoists 5 can be provided on the fixed beam 1, thereby improving work efficiency.

以上仅为本实用新型的优选实施例而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改、组合和变化。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的权利要求范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications, combinations and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the scope of the claims of the present invention.

Claims (9)

1. a kind of tower crane device, it is characterised in that: including at least one fixed beam, the first sliding rail being arranged at the top of fixed beam, It is located at the moving beam that can be moved on the first sliding rail and along the first sliding rail, the first driving mechanism for driving moving beam, is located at shifting The second sliding rail on dynamic beam, be arranged on the second sliding rail and can along the trolley that second sliding rail moves, for driving trolley Second driving mechanism and the loop wheel machine being located on trolley;First sliding rail is vertical with second sliding rail.
2. tower crane device according to claim 1, it is characterised in that: the fixed beam quantity is two, two fixed Liangpings Row setting.
3. tower crane device according to claim 1, it is characterised in that: the loop wheel machine includes rotating seat, is located on rotating seat Support column, be located at the top of support column boom, be located at the top of support column counter-jib, be located at boom extension end lifting rope and It is located at the bridge motor of counter-jib extension end;The rotating seat is arranged on trolley.
4. tower crane device according to claim 1, it is characterised in that: the moving beam bottom is equipped with and first sliding rail The first idler wheel mechanism to match.
5. tower crane device according to claim 1, it is characterised in that: the trolley bottom is equipped with and the second sliding rail phase Matched second idler wheel mechanism.
6. tower crane device according to claim 1, it is characterised in that: the trolley bottom is equipped with manipulator.
7. tower crane device according to claim 6, it is characterised in that: the manipulator include connect with trolley it is flexible Arm, the handgrip arm for being located at telescopic arm bottom and the adsorbent for being located at handgrip arm extension end;The handgrip arm can be around described flexible Arm rotation, the adsorbent are permanent magnetic chuck or magnechuck;The centre of the moving beam is equipped with the through slot of evacuation manipulator.
8. tower crane device according to claim 1, it is characterised in that: the bottom of the fixed beam is equipped with several lifting columns Component.
9. tower crane device according to claim 8, it is characterised in that: the lifting column component includes jacking cage, hydraulic Cylinder, pedestal and several tower sections;It is vertically connected between the tower section, the tower section setting of bottom is on the base;The jacking Cage is fixed on the base, the accommodation space for accommodating a Jie Tajie is equipped in the jacking cage, positioned at the tower of bottom Section is arranged in the accommodation space;The tower section, which is equipped with, supports slot, and the pedestal is equipped with several articulated sections, the liquid Cylinder pressure pedestal is articulated in the articulated section, and the hydraulic cylinder piston rod end portion is connected to described support on slot.
CN201821581975.8U 2018-08-08 2018-09-27 A tower crane Expired - Fee Related CN209383292U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2018108963161 2018-08-08
CN201810896316 2018-08-08

Publications (1)

Publication Number Publication Date
CN209383292U true CN209383292U (en) 2019-09-13

Family

ID=67869996

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201821581975.8U Expired - Fee Related CN209383292U (en) 2018-08-08 2018-09-27 A tower crane
CN201811134215.7A Expired - Fee Related CN110821149B (en) 2018-08-08 2018-09-27 A mold-taking device and a mold-taking method applied to a house sliding mold forming device
CN201821582011.5U Expired - Fee Related CN209384639U (en) 2018-08-08 2018-09-27 A mold taking device applied to a house sliding mold forming device

Family Applications After (2)

Application Number Title Priority Date Filing Date
CN201811134215.7A Expired - Fee Related CN110821149B (en) 2018-08-08 2018-09-27 A mold-taking device and a mold-taking method applied to a house sliding mold forming device
CN201821582011.5U Expired - Fee Related CN209384639U (en) 2018-08-08 2018-09-27 A mold taking device applied to a house sliding mold forming device

Country Status (1)

Country Link
CN (3) CN209383292U (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN209383292U (en) * 2018-08-08 2019-09-13 李宜君 A tower crane
CN114908969A (en) * 2020-08-21 2022-08-16 上海欧跃建筑安装工程有限公司 A method for synchronizing concrete pouring on the same floor of a building machine beam and slab lag wall column
CN112112415B (en) * 2020-09-21 2022-02-22 山东方圆建筑材料有限公司 Floor building device and working method
CN112177320B (en) * 2020-09-28 2021-10-22 厦门安科科技有限公司 An attachment structure for climbing formwork body
CN115653289B (en) * 2022-09-30 2025-06-24 中国建筑第七工程局有限公司 A bay window template reinforcement system and construction method thereof

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH669423A5 (en) * 1988-05-16 1989-03-15 Otto Heinzle Formwork installation for cylindrical, reinforced concrete structure - uses crane to lift panels, connected to curved top and bottom supports, into position
TW252176B (en) * 1994-12-20 1995-07-21 Wen-Yuan Lii Working process and device for module of building floor
JPH10212820A (en) * 1997-01-30 1998-08-11 Kawatetsu Kizai Kogyo Kk Temporary working platform rising method
CN102979304B (en) * 2012-12-13 2015-05-20 中铁二局股份有限公司 Construction method of double shear wall formworks at deformation joint of high-rise building
FR3000121B1 (en) * 2012-12-26 2015-01-02 Sateco Sa FORMWORK BANK OF A CONCRETE WALL AND METHOD FOR DISPLACING SUCH A BANK
CN103225389B (en) * 2013-04-12 2015-04-01 山东电力建设第二工程公司 Device for mould hoisting machine of concrete cylinder wall construction top lifting platform
CN103334583B (en) * 2013-07-18 2015-07-15 中国华西企业有限公司 Integrated core-tube inner mould base system
CN204804338U (en) * 2015-06-01 2015-11-25 象山商博电子商务有限公司 Building templates unloads registration arm device
CN108263959A (en) * 2016-12-31 2018-07-10 福州市鼓楼区奇韵通自动化设备有限公司 A kind of cantilever crane with lifting truck and telescopic arm running trolley
CN207526101U (en) * 2017-11-06 2018-06-22 天津二建水电安装工程有限公司 A kind of sliding formwork overlay film health preserving equipment
CN209383292U (en) * 2018-08-08 2019-09-13 李宜君 A tower crane

Also Published As

Publication number Publication date
CN209384639U (en) 2019-09-13
CN110821149B (en) 2022-10-14
CN110821149A (en) 2020-02-21

Similar Documents

Publication Publication Date Title
CN209383292U (en) A tower crane
CN202369282U (en) Movable crane
CN103848360B (en) A kind of group tower tower crane being provided with packaged type balance weight system
CN111606214A (en) A container gantry crane
CN108928757A (en) A kind of lifting machine and its construction method of packaged type
CN110759283A (en) container side loader
CN102001582B (en) Engineering machine and log lifting appliance thereof
CN104444865A (en) Lifting equipment
CN204848038U (en) Roll over cantilever crane
CN204848017U (en) Swing crane; derrick
CN202558505U (en) Super-lift device and crane
CN211496818U (en) Container side loader
CN203474321U (en) Tower crane used for constructing and erecting electric transmission line iron towers
CN205971018U (en) Vehicle transporter
CN202296907U (en) Suspension arm balanced movable arm tower crane capable of luffing based on steel rope traction
CN108275584B (en) A multifunctional straight rail super-large lifting equipment
CN106938826B (en) A kind of crawler type crane of balance and stability
CN116462108B (en) Mobile crane for road construction
CN105883640B (en) Electric power Special Hoisting Equipment
CN108412441A (en) A kind of guide device
CN210105438U (en) Pole setting mechanical arm vehicle set for electrified railway construction
CN108078479A (en) A kind of full hydraulic drive telescopic boom window cleaning equipment
CN220245388U (en) Supporting structure of crane boom
CN209091151U (en) A telescopic arm type window cleaner
CN207209830U (en) For the hoisting tooling at Bridge Beam bottom and pier stud small space

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190913

Termination date: 20200927

CF01 Termination of patent right due to non-payment of annual fee