CN209381034U - Napper is used in a kind of energy-saving prefabricated components production - Google Patents

Napper is used in a kind of energy-saving prefabricated components production Download PDF

Info

Publication number
CN209381034U
CN209381034U CN201821873273.7U CN201821873273U CN209381034U CN 209381034 U CN209381034 U CN 209381034U CN 201821873273 U CN201821873273 U CN 201821873273U CN 209381034 U CN209381034 U CN 209381034U
Authority
CN
China
Prior art keywords
plucking
napper
energy
prefabricated components
saving prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821873273.7U
Other languages
Chinese (zh)
Inventor
石超
花金堂
段志华
张俊玲
崔嘉中
秦若铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Zhongan Credit Reporting Construction Technology Co Ltd
Original Assignee
Henan Zhongan Credit Reporting Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Zhongan Credit Reporting Construction Technology Co Ltd filed Critical Henan Zhongan Credit Reporting Construction Technology Co Ltd
Priority to CN201821873273.7U priority Critical patent/CN209381034U/en
Application granted granted Critical
Publication of CN209381034U publication Critical patent/CN209381034U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a kind of energy-saving prefabricated components production napper, and napper includes workbench hanging bracket and the plucking workbench that is suspended under bracket, and plucking workbench includes main body mounting rack, plucking unit and spacing washer;Steel plate counterweight plucking work head is replaced using the plucking unit of reinforcing bar counterweight fixed frame and plucking work head composition composition, using simple bar bending technology generations for complicated steel plate cutting process production, adjustable plucking depth and plucking gap simultaneously, increase polyurethane bar as plucking work head, do not bond concrete, plucking stay in grade, cancel rectangle crossbeam, substantially mitigate self weight, optimization reduces components, largely use national standard accessory, it is easy to obtain, reduce production and application cost, suitable for different energy-saving prefabricated components working faces, plucking effect is good, stability is strong, it is applied widely, it safeguards easy to assembly.

Description

Napper is used in a kind of energy-saving prefabricated components production
Technical field
The utility model belongs to energy-saving prefabricated components production field, is related to field of surface treatment, and in particular to one kind Napper is used in energy-saving prefabricated components production.
Background technique
Reinforced concrete structure is supporting member most basic in various engineering structures, is applied in actual production in order to improve Work precision reduces difficulty of construction, many times selects energy-saving prefabricated components, the substantially production process of energy-saving prefabricated components is It is produced by plant produced mold, then on a large scale, finally transports to scene again and carry out modular assembly, can be improved in this way Product quality reduces pollution of the site operation for environment, energy conservation and environmental protection;It is needed in modular assembly to energy-saving prefabricated structure The contact surface of part carries out slip casting connection and needs to improve the assembling quality of junction in the energy-saving prefabricated components of plant produced When hair pulling treatment is carried out to the contact surfaces of energy-saving prefabricated components.
The work head of existing energy-saving prefabricated components flowing die station napper uses to be cut with a thickness of the steel plate of 12mm, Multiple work heads are arranged as a column, between each work head by the top circular hole that work head is passed through using a cylinder horizontal axis Spacing is 45mm, and cylinder horizontal axis is segmented connection integral hanging by a rectangle crossbeam and is got up, and makes large-scale door word with channel steel Bracket places a decelerating motor in the middle and upper part of door word bracket and drives coaxial double hoisting cylinder, double hoisting by The gear deceleration Roller is connected by pulley and the movable pulley at crossbeam both ends.In actual use, existing energy-saving prefabricated components flowing The defect of die station napper has: plucking work head counterweight is excessive, and the depth of plucking is too deep, and trench spacing is excessive, does not meet state The plucking rough surface area of family building standard 15G366-1 " truss bars concrete folding plate -60mm thickness bottom plate " is not less than combination 80% national standard in face.And plucking work head gap is non-adjustable, the deep-controlled inconvenience of plucking, plucking work head is easy to stick to be born water Mud, plucking effect unsightly, be integrally self-possessed larger, and processing assembling is inconvenient, higher cost by napper;It seriously affects energy-saving prefabricated The quality of popularization and the assembly of component.For rugged monolith concrete slab, each region needs the plate of independent plucking (such as Have the superimposed sheet of truss), existing napper can not carry out whole hair pulling treatment, seriously constrain energy-saving prefabricated components napper The scope of application.
Accordingly, it is desirable to provide a kind of be directed to the insufficient improved technology scheme of the above-mentioned prior art.
Utility model content
The purpose of the utility model is to overcome it is above-mentioned in the prior art to energy-saving prefabricated components contact surface hair pulling treatment when Work head gap is non-adjustable, the deep-controlled inconvenience of plucking, and plucking work head is easy to stick to bear water mud, plucking effect unsightly, napper The deficiencies of whole self weight is larger, and processing assembling is inconvenient, higher cost, proposes a kind of energy-saving prefabricated components production napper.
To achieve the goals above, the utility model provides the following technical solutions:
A kind of energy-saving prefabricated components production napper, the napper include:
Workbench hanging bracket, the workbench hanging bracket includes rack and hoisting mechanism;The rack is in door type, With support bearing effect;
Plucking workbench, the plucking workbench are hung in the rack by hoisting mechanism, for energy-saving pre- Component processed carries out hair pulling treatment;
The plucking workbench includes: main body mounting rack, and the main body mounting rack is totally in cross bar shape, is promoted for connecting Mechanism, and carry plucking unit and spacing washer;
Plucking unit, the plucking unit are assemblied on the main body mounting rack, and the plucking unit includes: spring hose Hoop, counterweight fixed frame and plucking work head;The counterweight fixed frame is a S-shaped reinforcing bar, and the plucking work head is circle Columnar bar, plucking work head are fixed on one end of the counterweight fixed frame by spring hose clamp, are convenient for plucking operation;
Spacing washer, the spacing washer be tube-in-tube structure, the spacing washer be set in two adjacent groups plucking unit it Between main body mounting rack on, spacing washer separately arranges multiple plucking cell spacings.
Energy-saving prefabricated components production napper as described above, it is preferable that the counterweight fixed frame includes:
First supporting part, first supporting part are located at an extension end of S-shaped counterweight fixed frame, are in a straight muscle, use In carrying plucking work head;
First circular arc is curved, and the curved one end with first supporting part of first circular arc is connect, for filling plucking unit Assigned on napper;
Interconnecting piece, one end of interconnecting piece other end curved with first circular arc are connect, and flat with the first supporting part Row;
Second circular arc is curved, and the curved one end of second circular arc is connect with the other end of the interconnecting piece, and carries with first Portion, the first circular arc are curved, interconnecting piece is in a plane, and the first circular arc is curved and the second circular arc crook connects in the plane that the two is formed The two sides of socket part;
Second supporting part, one end of second supporting part other end curved with second circular arc are connect, and with connection Portion is parallel.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that the main body mounting rack includes cross bar With the first movable pulley and the second movable pulley for being connected to cross bar both ends.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that the cross bar is a steel-tube construction.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that the cross bar and the first movable pulley, the It is bolted between two movable pulleys by U-tube hoop.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that the rack includes top beam and two Pillar beam, the both ends of top beam are connected with the top of two pillar beams respectively.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that the top beam and two pillar beams are equal For rectangular tube.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that the hoisting mechanism includes:
Capstan winch, the capstan winch is fixed on the lower edge of described top beam one end by pedestal, cylindrical;
Fixed pulley, the fixed pulley are fixed on the lower edge in the top beam middle position by pedestal;
Hole seat is lifted, the hole for hoist seat is located at the lower edge of the top beam other end, for fixing wirerope;
Wirerope, described wirerope one end are fixed on the lifting hole seat, and the other end sequentially passes through the second movable pulley, fixation Pulley and the first movable pulley, are wound on the winding drum of the capstan winch.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that first movable pulley and second moves Pulley is the land wheel of 1T.
A kind of energy-saving prefabricated components production napper as described above, it is preferable that the fixed pulley is the land wheel of 1T.
Compared with the immediate prior art, technical solution provided by the utility model has following excellent effect:
1, the utility model replaces steel plate counterweight plucking work head using reinforcing bar counterweight fixed frame, curved using simple reinforcing bar For bent technology generations for complicated steel plate cutting process production, manufacture craft is simple, and cost of manufacture is lower, cancels rectangle crossbeam, substantially Mitigate self weight, optimization reduces components, largely uses national standard accessory, be easy to obtain, reduce production and application cost;
2, increase polyurethane bar as plucking work head, do not bond concrete, plucking stay in grade;
3, the plucking unit that multiple adjustable lengths are arranged forms plucking workbench, is suitable for napper of different shapes Energy-saving prefabricated components working face, plucking effect is good, and stability is strong, applied widely, safeguards easy to assembly;It is adjustable simultaneously Plucking depth and plucking gap;
4, in the plucking work head of the both ends of counterweight fixed frame setting different size, convenient for being switched fast plucking work head, It realizes different plucking effects, meets diversified demand, improve replacement efficiency, saved manufacture and replacement cost;
5, the hand winch being arranged reduces production cost, simplifies device structure, substantially reduces failure rate, while Equipment not powered operation is realized, the safety of operation is improved, greatly expands the use environment of equipment.
Detailed description of the invention
Fig. 1 is the napper overall structure diagram in the utility model embodiment;
Fig. 2 is the workbench hanging bracket structural schematic diagram in the utility model embodiment;
Fig. 3 is the plucking Working table structure schematic diagram in the utility model embodiment;
Fig. 4 is the plucking cellular construction schematic diagram in the utility model embodiment;
Fig. 5 is the spring hose clamp structural schematic diagram in the utility model embodiment;
Fig. 6 is the spacing washer structural schematic diagram in the utility model embodiment;
Fig. 7 is the structural schematic diagram of counterweight fixed frame in the utility model embodiment;
Fig. 8 is the structural schematic diagram of plucking work head in the utility model embodiment;
Fig. 9 is the scheme of installation of plucking work head in the utility model embodiment;
Figure 10 is the scheme of installation of plucking unit in the utility model embodiment;
Figure 11 is the flow chart of napper application method in the utility model embodiment;
Figure 12 is the specific flow chart of the step S1 in Figure 11;
Figure 13 is the specific flow chart of the step S2 in Figure 11.
In figure: 11, rack;12, capstan winch;13, wirerope;14, fixed pulley;15, hole seat is lifted;21, main body mounting rack; 211, cross bar;212, the first movable pulley;213, the second movable pulley;22, plucking unit;221, counterweight fixed frame;2211, it first holds Load portion;2212, the first circular arc is curved;2213, interconnecting piece;2214, the second circular arc is curved;2215, the second supporting part;222, spring hose Hoop;223, plucking work head;23, spacing washer.
Specific embodiment
Below by the technical scheme in the utility model embodiment is clearly and completely described, it is clear that described Embodiment is only a part of the embodiment of the utility model, instead of all the embodiments.Based on the reality in the utility model Example is applied, those of ordinary skill in the art's every other embodiment obtained is fallen within the protection scope of the utility model.
The utility model will be described in detail below with reference to the accompanying drawings and embodiments.It should be noted that not conflicting In the case where, the feature in the embodiments of the present invention and embodiment can be combined with each other.
The orientation or positional relationship indicated in the description of the present invention, is that orientation based on the figure or position are closed System is merely for convenience of description the utility model rather than requires the utility model that must be constructed and operated in a specific orientation, Therefore it should not be understood as limiting the present invention.Term used in the utility model " connected ", " connection " should do broad sense Understand, for example, it may be being fixedly connected, may be a detachable connection;It can be directly connected, intermediate member can also be passed through It is indirectly connected, for the ordinary skill in the art, can understand the concrete meaning of above-mentioned term as the case may be.
Embodiment 1
As Figure 1-10 shows, the utility model provides a kind of energy-saving prefabricated components production napper, including workbench Hanging bracket and plucking workbench;
Workbench hanging bracket, workbench hanging bracket are totally in door type, for carrying plucking workbench;Workbench is outstanding Hanging bracket includes rack 11 and hoisting mechanism;Rack 11 is welded by rectangle pipe material, including a top beam and top beam both ends The bottom end of pillar beam, pillar beam is equipped with pedestal, and rack 11 is fixed on ground by expansion bolt.Hoisting mechanism includes capstan winch 12, fixed pulley 14, lifting hole seat 15 and wirerope 13.The lower edge at top beam both ends is connected separately with capstan winch 12 and lifting hole seat 15, the intermediate position lower edge of top beam is connected with fixed pulley 14, and in the present embodiment, fixed pulley 14 selects the land wheel of 1T, twists Disk 12 selects electric capstan 12.
Plucking workbench, plucking workbench is suspended below workbench hanging bracket by wirerope 13, for contacting The working face of energy-saving prefabricated components carries out hair pulling treatment;Plucking workbench include: main body mounting rack 21, plucking unit 22 and Dottle pin piece 23.
Main body mounting rack 21, main body mounting rack 21 include cross bar 211 and the first movable pulley for being connected to 211 both ends of cross bar 212 and second movable pulley 213,13 one end of wirerope of Ф 8mm is fixed on lifting hole seat 15, and the other end sequentially passes through second and dynamic slides Wheel 213, fixed pulley 14 and the first movable pulley 212, are wrapped on the winding drum of capstan winch 12, and then main body mounting rack 21 is hung In hoisting mechanism, is rotated by 12 winding drum of capstan winch, roll wirerope 13, drive the lifting of entire plucking workbench.In this reality It applies in example, the first movable pulley 212 and the second movable pulley 213 select the land wheel of 1T;Cross bar 211 selects the steel pipe of a DN50, It is bolted by U-tube hoop between cross bar 211 and the first movable pulley 212, the second movable pulley 213.
Plucking unit 22, as shown in Figure 10, curved 2212 suspension of the first circular arc that plucking unit 22 passes through counterweight fixed frame 221 On the cross bar 211 of main body mounting rack 21, as shown in figure 4, plucking unit 22 includes: that the spring hose clamp 222 of Ф 18mm, counterweight are solid Determine frame 221 and plucking work head 223.
As shown in fig. 7, counterweight fixed frame 221 is bent using the reinforcing bar of a Ф 10mm, the knot of overall similar S-shaped Structure, curved including three parallel straight muscle and two circular arcs, certain length is stretched out at the both ends of counterweight fixed frame 221, is easily carried drawing Hair work head 223;Counterweight fixed frame 221 includes:
First supporting part 2211, the first supporting part 2211 are located at an extension end of S-shaped counterweight fixed frame 221, are in one Straight muscle, for carrying plucking work head 223;
First circular arc curved 2212, the first circular arc curved 2212 are connect with one end of the first supporting part 2211, are used for plucking list Member 22 is assemblied on the cross bar 211 of napper;
Interconnecting piece 2213, one end of interconnecting piece 2213 are connect with the other end of the first circular arc curved 2212, and are carried with first Portion 2211 is parallel;
One end of second circular arc curved 2214, the second circular arc curved 2214 is connect with the other end of interconnecting piece 2213, and with first Supporting part 2211, the first circular arc are curved 2212, interconnecting piece 2213 is in a plane, and the first circular arc curved 2212 and the second circular arc are curved The two sides of interconnecting piece 2213 in 2214 planes in the two formation;
One end of second supporting part 2215, the second supporting part 2215 is connect with the other end of the second circular arc curved 2214, and with Interconnecting piece 2213 is parallel.
Plucking work head 223 selects the bar of the Ф 4mm of polyurethane material or other plastic materials, as shown in figure 9, three Plucking work head 223 is fixed on one end of counterweight fixed frame 221 by spring hose clamp 222, makes three plucking work heads 223 will The working face of entire 221 end of counterweight fixed frame is equally divided into two parts, is convenient for plucking;Select polyurethane material or modeling Charge bar material is as plucking work head 223, the non-sticky knot concrete in plucking, and plucking quality preservation is stablized.In the present embodiment, together Under equal pluckings worktable lifting height, show right side toward when the movement of left side from Fig. 1 when flowing die station, plucking depth is most shallow, flows mould Plucking depth is deeper when platform moves from left to right, can be the second of each plucking unit 22 if not being able to satisfy plucking depth requirements still Independent suspended counterweight at circular arc curved 2214, further increases plucking depth, while reducing plucking height of table and can also promote drawing Hair depth.
Spacing washer 23, spacing washer 23 are set on the cross bar 211 of main body mounting rack 21 using the sleeve of length 3mm, With 22 arranged for interval of plucking unit, the spacing with 3mm between each plucking unit 22 is made to be assemblied in the cross of main body mounting rack 21 On bar 211, to realize the plucking effect of plucking width 4mm, plucking groove interval 3mm.
When in use, plucking work head 223 is fixed on to the first carrying of counterweight fixed frame 221 by spring hose clamp 222 Portion 2211 forms a plucking unit 22;Then suitable spacing washer 23 is chosen to be spaced apart plucking unit 22, it is common to fill On cross bar 211 assigned in main body mounting rack 21, a plucking workbench is constituted;11 pedestal of rack is fixed on by expansion bolt Hoisting mechanism is fixed on 11 corresponding position of rack by ground;Then one end of wirerope 13 is fixed on lifting hole seat 15, it is another End sequentially passes through the second movable pulley 213, fixed pulley 14 and the first movable pulley 212, is wrapped on the winding drum of capstan winch 12, in turn Plucking workbench is hung on into hoisting mechanism, napper is used in the energy-saving prefabricated components production of composition one.
In the present embodiment, the second supporting part 2215 of plucking unit 22 is also equipped with plucking work head 223, and plucking work Make first 223 diameter and spacing it is different from the first supporting part 2211, it is when needing another plucking effect, the second circular arc is curved 2214 are suspended on cross bar 211, and the plucking work head 223 of the second supporting part 2215 carries out plucking operation, and such utilization is most simple Method, realize the multifarious technical effect of plucking effect.Easy to operate, time saving and energy saving, working efficiency greatly improves.
As figs 11-13, the embodiments of the present invention additionally provide energy-saving prefabricated components production napper Application method includes the following steps:
S1 assembles plucking workbench;Specific step is as follows:
S11 chooses the plucking work head 223 of suitable diameter according to the width of required plucking groove;
S12 chooses suitable counterweight fixed frame 221 according to the interval width of required plucking groove, with spring hose clamp 222 Plucking work head 223 is fixed on to the supporting part of counterweight fixed frame 221 according to corresponding width, forms satisfactory plucking list Member 22;
S13, according to the interval width of plucking groove, in conjunction with the counterweight fixed frame 221 of selection and point of plucking work head 223 Mode for cloth chooses suitable spacing washer 23;
S14 chooses appropriate number of plucking unit 22 and spacing washer 23, by plucking according to the overall width in plucking region Unit 22 and spacing washer 23 are spaced apart in the face width for forming, plucking unit 22 on cross bar 211 greater than energy-saving Prefabricated components working face needs total width in plucking region.
S2, adjustment napper to working condition;Specific step is as follows:
S21 places the flowing die station for needing plucking below rack 11, and height to the plucking for adjusting plucking workbench works First 223 close to working face to be processed;
S22 places an elongated tubing, by entire plucking battle array at the second circular arc curved 2214 of counterweight fixed frame 221 Column lock as an entirety;
S23 successively unclamps the spring hoop of each plucking unit 22, plucking work head 223 is made to contact face to be processed;
S24, removes the tubing at the second circular arc curved 2214, and plucking height of table is dropped to suitable height, plucking Workbench adjustment is completed.
S3, starting flowing die station, energy-saving prefabricated components to be processed are sequentially transmitted through napper, batch drawing is carried out Hair operation;In this step, before batch hair pulling treatment, the energy-saving prefabricated components of 5-10 (5,6,7,8,9,10) part are first handled Plucking validity check is carried out, carries out mass production again after passing the inspection;During batch production, inspect by random samples in time, Adjust the height of plucking workbench in time according to the abrasion of plucking work head 223, it is ensured that plucking quality.
Embodiment 2
In the present embodiment, in order to keep plucking depth deeper, plucking workbench is more stable, the second of plucking unit 2222 An elongated pole is placed at circular arc curved 2214.
The pole of placement locks 22 array of plucking unit of entire plucking workbench for an entirety, while can play The effect of counterweight, so that it is guaranteed that napper plucking depth is deeper, napper operation is more stable.Other implementation steps and embodiment 1 Identical, details are not described herein.
Embodiment 3
In the present embodiment, since 12 use of capstan winch is less frequent, in order to reduce production maintenance cost, realize equipment without electricity Operation, is changed to hand winch 12 for the electric capstan 12 in embodiment 1.
The hand winch 12 of setting reduces production cost, simplifies device structure, substantially reduces failure rate, while Equipment not powered operation is realized, the safety of operation is improved, greatly expands the use environment of equipment.Other implementation steps Same as Example 1, details are not described herein.
In conclusion the utility model replaces steel plate counterweight plucking work head using reinforcing bar counterweight fixed frame, using simple Bar bending technology generations for complicated steel plate cutting process production, while adjustable plucking depth and plucking gap increase Polyurethane bar does not bond concrete as plucking work head, and plucking stay in grade cancels rectangle crossbeam, substantially mitigates self weight, Optimization reduces components, largely uses national standard accessory, is easy to obtain, reduces production and application cost, suitable for different sections Energy type prefabricated components working face, plucking effect is good, and stability is strong, applied widely, safeguards easy to assembly.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this Within the spirit and principle of utility model, any modification, equivalent replacement, improvement and so on, in the pending power of the utility model Within the scope of benefit is claimed.

Claims (10)

1. a kind of energy-saving prefabricated components production napper, which is characterized in that the napper includes:
Workbench hanging bracket, the workbench hanging bracket includes rack and hoisting mechanism;The rack is in door type, is had Support bearing effect;
Plucking workbench, the plucking workbench are hung in the rack by hoisting mechanism, for energy-saving prefabricated structure Part carries out hair pulling treatment;
The plucking workbench includes: main body mounting rack, and the main body mounting rack is totally in cross bar shape, for connecting elevator Structure, and carry plucking unit and spacing washer;
Plucking unit, the plucking unit are assemblied on the main body mounting rack, and the plucking unit includes: spring hose clamp, matches Weight fixed frame and plucking work head;The counterweight fixed frame is a S-shaped reinforcing bar, and the plucking work head is columned Bar, plucking work head are fixed on one end of the counterweight fixed frame by spring hose clamp, are convenient for plucking operation;
Spacing washer, the spacing washer are tube-in-tube structure, and the spacing washer is set between two adjacent groups plucking unit On main body mounting rack, spacing washer separately arranges multiple plucking cell spacings.
2. energy-saving prefabricated components production napper as described in claim 1, which is characterized in that the counterweight fixed frame packet It includes:
First supporting part, first supporting part are located at an extension end of S-shaped counterweight fixed frame, are in a straight muscle, for holding Carry plucking work head;
First circular arc is curved, and the curved one end with first supporting part of first circular arc is connect, for plucking unit to be assemblied in On napper;
Interconnecting piece, one end of interconnecting piece other end curved with first circular arc are connect, and parallel with the first supporting part;
Second circular arc is curved, and the curved one end of second circular arc is connect with the other end of the interconnecting piece, and with the first supporting part, One circular arc is curved, interconnecting piece is in a plane, and the first circular arc is curved and the second circular arc crook is in interconnecting piece in the plane that the two is formed Two sides;
Second supporting part, one end of second supporting part other end curved with second circular arc are connect, and flat with interconnecting piece Row.
3. a kind of energy-saving prefabricated components production napper as described in claim 1, which is characterized in that the main body installation Frame includes cross bar and the first movable pulley and the second movable pulley for being connected to cross bar both ends.
4. a kind of energy-saving prefabricated components production napper as claimed in claim 3, which is characterized in that the cross bar is one Root steel-tube construction.
5. a kind of energy-saving prefabricated components production napper as claimed in claim 3, which is characterized in that the cross bar and the It is bolted between one movable pulley, the second movable pulley by U-tube hoop.
6. a kind of energy-saving prefabricated components production napper as claimed in claim 3, which is characterized in that the rack includes Top beam and two pillar beams, the both ends of top beam are connected with the top of two pillar beams respectively.
7. a kind of energy-saving prefabricated components production napper as claimed in claim 6, which is characterized in that the top beam and two A pillar beam is rectangular tube.
8. a kind of energy-saving prefabricated components production napper as claimed in claim 6, which is characterized in that the hoisting mechanism Include:
Capstan winch, the capstan winch is fixed on the lower edge of described top beam one end by pedestal, cylindrical;
Fixed pulley, the fixed pulley are fixed on the lower edge in the top beam middle position by pedestal;
Hole seat is lifted, the hole for hoist seat is located at the lower edge of the top beam other end, for fixing wirerope;
Wirerope, described wirerope one end are fixed on the lifting hole seat, and the other end sequentially passes through the second movable pulley, fixed pulley With the first movable pulley, it is wound on the winding drum of the capstan winch.
9. a kind of energy-saving prefabricated components production napper as claimed in claim 3, which is characterized in that the described first dynamic cunning Wheel and the second movable pulley are the land wheel of 1T.
10. a kind of energy-saving prefabricated components production napper as claimed in claim 8, which is characterized in that described fixed sliding Wheel is the land wheel of 1T.
CN201821873273.7U 2018-11-14 2018-11-14 Napper is used in a kind of energy-saving prefabricated components production Expired - Fee Related CN209381034U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821873273.7U CN209381034U (en) 2018-11-14 2018-11-14 Napper is used in a kind of energy-saving prefabricated components production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821873273.7U CN209381034U (en) 2018-11-14 2018-11-14 Napper is used in a kind of energy-saving prefabricated components production

Publications (1)

Publication Number Publication Date
CN209381034U true CN209381034U (en) 2019-09-13

Family

ID=67864598

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821873273.7U Expired - Fee Related CN209381034U (en) 2018-11-14 2018-11-14 Napper is used in a kind of energy-saving prefabricated components production

Country Status (1)

Country Link
CN (1) CN209381034U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109278171A (en) * 2018-11-14 2019-01-29 河南中安征信建筑科技有限公司 A kind of energy-saving prefabricated components production napper and its application method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109278171A (en) * 2018-11-14 2019-01-29 河南中安征信建筑科技有限公司 A kind of energy-saving prefabricated components production napper and its application method
CN109278171B (en) * 2018-11-14 2023-10-13 河南中安征信建筑科技有限公司 Energy-saving roughening machine for producing prefabricated parts and use method thereof

Similar Documents

Publication Publication Date Title
CN107178211B (en) Truss hanging system for installing steel structure
CN201459732U (en) Simple support guide device for pile casing sinking
CN201746779U (en) Prestressed tension jack moving frame
CN209381034U (en) Napper is used in a kind of energy-saving prefabricated components production
CN219213563U (en) Steel strand wire bundle penetrating auxiliary equipment
CN210048319U (en) A folding sky beam traction type construction hoist
CN202881858U (en) Jig frame used for vertical assembly construction of truss arc bridge
CN107186878B (en) Adjustable prefabricated U-shaped beam steel bar binding clamping fixture and construction method
CN202185966U (en) Novel U-shaped beam hydraulic internal mold
CN220886676U (en) Hoist with adjustable prefabricated assembled superimposed sheet is used
CN221971137U (en) A hydraulic lifting device for lifting steel corridor
CN109278171A (en) A kind of energy-saving prefabricated components production napper and its application method
CN208357679U (en) A kind of bar straightening bending hoop all-in-one machine
CN215160412U (en) A crane lifting mechanism
CN201208688Y (en) Fixture for welding large-sized H section steel structural part
CN210134655U (en) Steel reinforcement framework forming system
CN110469126B (en) Binding trolley for concrete reinforcing steel bars and binding construction method thereof
CN110700604B (en) Assembly type laminated slab mounting trolley and using method thereof
CN211107547U (en) Reinforcing steel bar transport vehicle
CN223397383U (en) A lightweight assembly and mobile installation tool for AAC autoclaved aerated concrete panels
CN113914608A (en) String tensioning template support
CN206376564U (en) A kind of counterforce device for adjusting Tall Frameworks post installation accuracy
CN222375223U (en) Girder dropping device of segment assembly bridge girder erection machine
CN223620020U (en) Auxiliary turning device for hoisting prestressed roof truss
CN221500365U (en) Steel construction flip-chip hoisting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190913

CF01 Termination of patent right due to non-payment of annual fee