CN209353770U - High-altitude suspension formwork protective shed - Google Patents

High-altitude suspension formwork protective shed Download PDF

Info

Publication number
CN209353770U
CN209353770U CN201822268911.9U CN201822268911U CN209353770U CN 209353770 U CN209353770 U CN 209353770U CN 201822268911 U CN201822268911 U CN 201822268911U CN 209353770 U CN209353770 U CN 209353770U
Authority
CN
China
Prior art keywords
steel pipe
suspension scaffold
girder
floor
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822268911.9U
Other languages
Chinese (zh)
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Southwest Construction Project Parent Co
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201822268911.9U priority Critical patent/CN209353770U/en
Application granted granted Critical
Publication of CN209353770U publication Critical patent/CN209353770U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开一种高空悬挑支模防护棚,悬挑架主梁应当上倾,主梁定型化调倾块设在楼板端部,用于调整悬挑架主梁的倾向角度,悬挑架次梁搭设在悬挑架主梁上方,悬挑架主梁一端固定在楼板上,另一端利用防护棚的斜拉钢丝绳拉紧卸载,防护棚的斜拉钢丝绳固定在楼板处的预埋件上;所述的满铺安全网应在悬挑架次梁上满铺,满铺安全网上铺设减震木方,减震方木上布设满铺脚手板;所述的悬挑架主梁上方设有上层钢管网架,悬挑架主梁侧面等距设有钢管网架竖向撑杆,上层钢管网架与钢管网架竖向撑杆之间挂满密目式安全网进行防护,满铺铁网片应铺满上层钢管网架上部的悬挑架次梁,可有效防止坠物从防护棚往下坠落,减小了外架搭设中的安全风险,有利于安全施工。

The utility model discloses a high-altitude cantilever formwork support shed. The main girder of the cantilever frame should be tilted up, and the shaped tilting block of the main girder is arranged at the end of the floor to adjust the inclination angle of the main girder of the cantilever frame. The secondary beam is erected above the main beam of the cantilever frame, one end of the main beam of the cantilever frame is fixed on the floor, and the other end is unloaded by the cable-stayed wire rope of the protective shed, and the cable-stayed steel wire rope of the protective shed is fixed on the embedded part at the floor ; The full-spread safety net should be fully-spread on the cantilevered sub-beam, and the shock-absorbing wooden square is laid on the full-spread safety net, and the full-spread scaffolding board is laid on the shock-absorbing square wood; The upper steel pipe network frame, the side of the main beam of the cantilever frame is equidistantly equipped with steel pipe network frame vertical struts, the upper steel pipe network frame and the steel pipe network vertical support rods are covered with dense mesh safety nets for protection, and the iron The mesh should be covered with the cantilevered sub-beams on the upper part of the upper steel pipe grid, which can effectively prevent falling objects from falling down from the protective shed, reduce the safety risk in the erection of the outer frame, and facilitate safe construction.

Description

高空悬挑支模防护棚High-altitude suspension formwork protective shed

技术领域technical field

本实用新型涉及土木工程领域,特别涉及一种高空悬挑支模防护棚,特别适用于高空悬挑支模防护棚施工。The utility model relates to the field of civil engineering, in particular to a high-altitude cantilever formwork support shed, which is particularly suitable for the construction of a high-altitude cantilever formwork support shed.

背景技术Background technique

近年来,随着城市建筑的日益增多,脚手架的形式也呈多样化的发展趋势,而悬挑脚手架以它的可容作业范围大、节省材料、造价低、搭设简单方便、安全可靠而得到广泛的使用。传统悬挑架采用钢管作为支承机构,稳定性较差,近年来悬挑架均采用型钢作为支承,悬挑型钢钢梁的固定做法各异,大部分采用传统的圆钢套环,弯制时通常达不到要求,施工不便而且稳定性较差,浪费大,成本投入多,本工法采用新型可拆锚固装置式悬挑脚手架,其锚固装置可拆卸,周转使用,无浪费,投入成本较大,但周转后平均成本低,且安全性能强,保障了外架的使用安全性,具有良好的经济效益和社会效益,具有良好的推广使用价值。In recent years, with the increasing number of urban buildings, the form of scaffolding is also showing a trend of diversification, and cantilevered scaffolding is widely used for its large operating range, material saving, low cost, simple and convenient erection, safety and reliability. usage of. The traditional cantilever frame uses steel pipes as the supporting mechanism, which has poor stability. In recent years, the cantilever frames all use section steel as the support. The fixing methods of the cantilever section steel beams are different. Usually it does not meet the requirements, the construction is inconvenient and the stability is poor, the waste is large, and the cost investment is high. This construction method adopts a new type of detachable anchoring device cantilevered scaffolding. The anchoring device is detachable and can be used in turnover without waste. , but the average cost after turnover is low, and the safety performance is strong, which ensures the safety of the outer frame, has good economic and social benefits, and has good promotion and use value.

目前普遍采用的型钢悬挑式脚手架的构造形式分为上悬斜拉式和下斜撑式,上悬斜拉式是在由结构伸出的型钢挑梁端部加钢丝绳斜拉(或在楼板上预埋钢筋环,外伸的横梁插入环内,在横向水平构件上搭设架子),进而悬挑外部的架体。该方法需要的型钢较多,在剪力墙和柱的部位需要留设较大洞口不便于以后外墙的装修,且由于型钢非常的长,拆除不便、易发生危险。下斜撑式悬挑脚手架是在型钢挑梁端部下面加一斜支撑。从型钢悬挑脚手架所用的材料、制作、安拆、用工情况等方面分析,上悬斜拉式效果好于下斜撑式,但在使用方面上悬斜拉式不如下斜撑式方便。At present, the structural forms of steel cantilevered scaffolds commonly used are divided into upper-hanging cable-stayed and lower-slanted bracing. The reinforced ring is pre-embedded on the top, and the outstretched beam is inserted into the ring, and a shelf is built on the horizontal horizontal member), and then the external frame is suspended. This method requires a lot of section steel, and large holes need to be left at the positions of the shear walls and columns, which is not convenient for the decoration of the outer wall in the future, and because the section steel is very long, it is inconvenient to dismantle and is prone to danger. The lower slanted cantilever scaffolding is to add a slanted support under the end of the steel cantilever beam. From the analysis of the materials, production, installation and dismantling, and labor conditions of the steel cantilevered scaffolding, the effect of the upper-hung cable-stayed scaffolding is better than that of the lower-slanted brace, but the upper-hung cable-stayed type is not as convenient as the lower-slanted brace in terms of use.

为了解决建筑物悬挑脚手架体系的高空坠落问题,减小外架搭设中的安全风险,亟需提出一种可以防止坠物的结构。In order to solve the problem of high-altitude falling of the building's cantilevered scaffolding system and reduce the safety risk in the erection of the outer frame, it is urgent to propose a structure that can prevent falling objects.

实用新型内容Utility model content

本实用新型的目的在于提供一种高空悬挑支模防护棚,借采用高空悬挑支模双层防护棚,可有效防止坠物从防护棚往下坠落,减小了外架搭设中的安全风险,有利于安全施工。The purpose of the utility model is to provide a high-altitude cantilevered formwork protective shed, which can effectively prevent falling objects from falling from the protective shed by adopting a high-altitude cantilevered formwork support shed, which reduces the safety during the erection of the outer frame. Risk, conducive to safe construction.

为了实现以上任一实用新型目的,本实用新型公开一高空悬挑支模防护棚,包括:悬挑架主梁、悬挑架次梁以及上层钢管网架;所述悬挑架次梁搭设在所述悬挑架主梁上方,拼接悬挑架;所述悬挑架主梁一端固定在楼板上,另一端利用斜拉钢丝绳拉紧卸载,所述悬挑架主梁通过置于所述楼板上的主梁定型化调倾块上实现上倾设置;所述悬挑架主梁上方设有上层钢管网架,所述悬挑架主梁侧面等距设有钢管网架竖向撑杆,所述上层钢管网架与所述钢管网架竖向撑杆之间挂满密目式安全网进行防护。In order to achieve the purpose of any of the above utility models, the utility model discloses a high-altitude cantilevered formwork protective shed, including: a cantilever main beam, a cantilevered sub-beam and an upper steel pipe grid; the cantilevered sub-beam is erected on the Above the main girder of the cantilever frame, a cantilever frame is spliced; one end of the main girder of the cantilever frame is fixed on the floor, and the other end is tensioned and unloaded by a cable-stayed steel wire rope, and the main girder of the cantilever frame passes through the The up-tilt setting is realized on the main girder shaped tilting block; the upper steel pipe network frame is arranged above the main girder of the cantilever frame, and the vertical struts of the steel pipe network frame are equidistantly arranged on the side of the main girder of the cantilever frame. Close-meshed safety nets are hung between the upper steel pipe grid and the vertical struts of the steel pipe grid for protection.

在一些实施例中,所述悬挑架次梁端部还设有斜拉钢管,所述斜拉钢管另一端固定在楼板上,所述斜拉钢丝绳和所述斜拉钢管隔一布一设置。In some embodiments, a cable-stayed steel pipe is provided at the end of the cantilevered sub-beam, the other end of the cable-stayed steel pipe is fixed on the floor, and the cable-stayed steel wire rope and the cable-stayed steel pipe are separated by a cloth.

在一些实施例中,所述悬挑架次梁和所述上层钢管网架端部设有封闭式钢管架侧防护。In some embodiments, the ends of the cantilevered secondary beam and the upper steel pipe network frame are provided with closed steel pipe frame side protection.

在一些实施例中,所述悬挑架次梁和所述上层钢管网架端部的位置还设有钢管斜撑,所述钢管斜撑一端与所述斜拉钢管连接,另一端与所述封闭式钢管架侧防护连接。In some embodiments, the position of the cantilevered secondary beam and the end of the upper steel pipe network frame is also provided with a steel pipe brace, one end of the steel pipe brace is connected to the cable-stayed steel pipe, and the other end is connected to the closed Type steel pipe frame side protective connection.

在一些实施例中,所述斜拉钢丝绳固定在设置在所述楼板处的预埋件上;所述斜拉钢管另一端通过设置在所述楼板上的悬挑架主梁预埋固定螺栓和悬挑架主梁固定螺帽固定在所述楼板上。In some embodiments, the cable-stayed steel wire rope is fixed on the embedded part arranged at the floor; the other end of the cable-stayed steel pipe is embedded with fixing bolts and The main beam fixing nut of the cantilever frame is fixed on the floor.

在一些实施例中,所述主梁定型化调倾块设在所述楼板的端部,所述主梁定型化调倾块垫在所述悬挑架主梁下部,用悬挑架主梁预埋固定螺栓和悬挑架主梁固定螺帽将所述悬挑架主梁固定在所述楼板上。In some embodiments, the shaped tilting block of the main beam is arranged at the end of the floor slab, and the shaped tilting block of the main beam is placed on the lower part of the cantilevered main beam, and the cantilevered main beam The pre-embedded fixing bolts and the fixing nuts of the main beam of the cantilever frame fix the main beam of the cantilever frame on the floor.

在一些实施例中,在所述悬挑架次梁上铺满铺满安全网,所述满铺安全网上铺设减震木方,所述减震方木上布设满铺脚手板。In some embodiments, the cantilevered sub-beams are fully paved with safety nets, the shock-absorbing wooden squares are laid on the fully-paved safety nets, and the shock-absorbing square logs are fully paved with scaffolding boards.

在一些实施例中,在所述上层钢管网架上铺满铺满铁网片。In some embodiments, iron mesh sheets are fully covered on the upper steel pipe network frame.

在一些实施例中,所述封闭式钢管架侧防护外侧设有警示条。In some embodiments, a warning strip is provided on the outer side of the side protection of the closed steel pipe frame.

本实用新型具有以下的特点和有益效果:The utility model has the following characteristics and beneficial effects:

1本实用新型涉及的高空悬挑支模防护棚,借采用高空悬挑支模双层防护棚,可有效防止坠物从防护棚往下坠落,减小了外架搭设中的安全风险,有利于安全施工。1. The high-altitude cantilevered formwork protective shed involved in the utility model can effectively prevent falling objects from falling from the protective shed by adopting the high-altitude cantilevered formwork support shed, which reduces the safety risk in the erection of the outer frame. Conducive to safe construction.

2本实用新型涉及的主梁定型化调倾块,可以快速实现悬挑架次梁倾斜度的调节,加快了施工进度,提高了防护棚的安装效率。2. The main girder stereotyped tilting block involved in the utility model can quickly realize the adjustment of the inclination of the cantilevered secondary girder, speed up the construction progress, and improve the installation efficiency of the protective shed.

3本实用新型涉及的防护棚的斜拉钢丝绳和斜拉钢管隔一布一设置,主要起到承受拉、撑荷载,可以起到间隔卸荷的作用,有效地将防护棚上坠物的荷载传递到楼板上,确保了防护棚的安全。3. The cable-stayed steel wire ropes and cable-stayed steel pipes of the protective shed involved in the utility model are set at intervals, mainly to bear the tension and support loads, and can play the role of unloading at intervals, effectively reducing the load of the falling objects on the protective shed. Passed to the floor to ensure the safety of the shelter.

4本实用新型涉及的高空悬挑支模防护棚由上、下两层钢管网架组合而成,结构设计新颖、合理,满足结构受力和安全性要求,可防止坠落物二次反弹坠落,为主体工程的外部安全防护提供了保障。4. The high-altitude cantilevered formwork protection shed involved in the utility model is composed of upper and lower two-layer steel pipe grids. The structural design is novel and reasonable, which meets the structural stress and safety requirements, and can prevent falling objects from rebounding and falling twice. It provides a guarantee for the external safety protection of the main project.

附图说明Description of drawings

图1是根据本实用新型的一实施例的高空悬挑支模防护棚的安装示意图。Fig. 1 is a schematic diagram of installation of a high-altitude cantilevered formwork protection shed according to an embodiment of the present invention.

图2是根据本实用新型的一实施例的双层防护棚的构造示意图。Fig. 2 is a schematic diagram of the structure of a double-layer protective shed according to an embodiment of the present invention.

图3是根据本实用新型的一实施例的主梁定型化调倾块的安装示意图。Fig. 3 is a schematic diagram of installation of the main girder stereotyped tilting block according to an embodiment of the present invention.

图4是是根据本实用新型的一实施例的双层防护棚支模的安装示意图;Fig. 4 is a schematic diagram of installation of a double-layer protective shed support formwork according to an embodiment of the present invention;

图中:2-楼板、41-单元式立杆固定杆、44-脚手架横杆、61-悬挑架主梁、62-主梁定型化调倾块、63-悬挑架次梁、64-满铺安全网、65-减震木方、66-满铺脚手板、67-上层钢管网架、68-钢管网架竖向撑杆、69-满铺铁网片、70-封闭式钢管架侧防护、71-防护棚的斜拉钢丝绳、72-斜拉钢管、97-脚手架纵杆、104-预埋件、105-悬挑架主梁预埋固定螺栓、106-悬挑架主梁固定螺帽、107-钢管斜撑、108-警示条、109-密目式安全网。In the figure: 2-floor, 41-unit vertical pole fixing rod, 44-scaffolding cross bar, 61-cantilever frame main beam, 62-main beam stereotyped tilting block, 63-cantilevered secondary beam, 64-full Laying safety nets, 65-shock-absorbing wooden squares, 66-full pavement scaffolding, 67-upper steel pipe grid, 68-vertical struts of steel pipe grid, 69-full pavement iron mesh, 70-closed steel pipe frame side Protection, 71-cable-stayed steel wire rope of protective shed, 72-cable-stayed steel pipe, 97-scaffold longitudinal rod, 104-embedded parts, 105-cantilever frame main beam pre-embedded fixing bolt, 106-cantilever frame main beam fixing screw Cap, 107-steel pipe diagonal brace, 108-warning strip, 109-close-meshed safety net.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. All other embodiments obtained by persons of ordinary skill in the art based on the embodiments of the present invention belong to the protection scope of the present invention.

本领域技术人员应理解的是,在本实用新型的揭露中,术语“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”等指示的方位或位置关系是基于附图所示的方位或位置关系,其仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此上述术语不能理解为对本实用新型的限制。Those skilled in the art should understand that, in the disclosure of the present utility model, the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", The orientations or positional relationships indicated by "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. are based on the orientation or positional relationship shown in the drawings, which are only for the convenience of describing the present invention. The novel and simplified descriptions do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, so the above terms should not be construed as limiting the utility model.

可以理解的是,术语“一”应理解为“至少一”或“一个或多个”,即在一个实施例中,一个元件的数量可以为一个,而在另外的实施例中,该元件的数量可以为多个,术语“一”不能理解为对数量的限制。It can be understood that the term "a" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element can be one, while in another embodiment, the number of the element The quantity can be multiple, and the term "a" cannot be understood as a limitation on the quantity.

如图1到图4所示,根据本实用新型的一实施例的高空悬挑支模防护棚的结构被展示,所述高空悬挑支模防护棚包括悬挑架主梁(61)、主梁定型化调倾块(62)、悬挑架次梁(63)、满铺安全网(64)、减震木方(65)、满铺脚手板(66)、上层钢管网架(67)、钢管网架竖向撑杆(68)、满铺铁网片(69)、封闭式钢管架侧防护(70)、防护棚的斜拉钢丝绳(71)、斜拉钢管(72)、预埋件(104)、悬挑架主梁预埋固定螺栓(105)、悬挑架主梁固定螺帽(106)、钢管斜撑(107)、警示条(108)、密目式安全网(109)。As shown in Figures 1 to 4, the structure of the high-altitude cantilevered formwork protection shed according to an embodiment of the present invention is shown, and the high-altitude cantilever formwork protection shed includes a cantilever main beam (61), a main Beam stereotyped tilting block (62), cantilevered sortie beam (63), full pavement safety net (64), shock-absorbing wooden square (65), full pavement scaffolding board (66), upper steel pipe grid frame (67), Vertical struts (68) of the steel pipe network frame, full pavement of iron mesh (69), side protection of the closed steel pipe frame (70), cable-stayed steel wire ropes (71) of the protective shed, cable-stayed steel pipes (72), embedded parts (104), cantilever frame main beam pre-embedded fixing bolts (105), cantilever frame main beam fixing nuts (106), steel pipe diagonal braces (107), warning strips (108), dense mesh safety nets (109) .

悬挑架主梁(61)一端固定在楼板(2)上,另一端利用防护棚的斜拉钢丝绳(71)拉紧卸载,所述悬挑架主梁(61)上倾设置,主要通过设置在所述楼板(2)上的主梁定型化调倾块(62)来实现,悬挑架主梁(61)的一端置于所述主梁定型化调倾块(62)上。One end of the main girder (61) of the cantilever frame is fixed on the floor (2), and the other end is tensioned and unloaded by the cable-stayed wire rope (71) of the protective shed. It is realized by the shaped tilting block (62) of the main beam on the floor (2), and one end of the main beam (61) of the cantilever frame is placed on the shaped tilting block (62) of the main beam.

悬挑架次梁(63)搭设在悬挑架主梁(61)上方,拼接悬挑架;防护棚的斜拉钢丝绳(71)固定在设置在楼板(2)处的预埋件(104)上,所述预埋件(104)从所述楼板(2)表面凸起。The cantilevered sub-beam (63) is erected on the top of the main beam (61) of the cantilevered frame, and the cantilevered frame is spliced; the cable-stayed steel wire rope (71) of the protective shed is fixed on the embedded part (104) arranged at the floor (2) , the embedded part (104) protrudes from the surface of the floor (2).

悬挑架主梁(61)上方设有上层钢管网架(67),悬挑架主梁(61)侧面等距设有钢管网架竖向撑杆(68),上层钢管网架(67)与钢管网架竖向撑杆(68)之间挂满密目式安全网(109)进行防护。The upper steel pipe network frame (67) is arranged above the main girder (61) of the cantilever frame, and the vertical struts (68) of the steel pipe network frame are arranged equidistantly on the side of the main girder (61) of the cantilever frame, and the upper steel pipe network frame (67) Dense-mesh safety nets (109) are hung up between the vertical struts (68) of the steel pipe network frame for protection.

如图1所示,悬挑架次梁(63)端部还设有斜拉钢管(72),主要起到承受拉、撑荷载,确保防护棚的安全,斜拉钢管(72)另一端通过设置在楼板(2)上的悬挑架主梁预埋固定螺栓(105)和悬挑架主梁固定螺帽(106)固定在楼板(2)上;防护棚的斜拉钢丝绳(71)和斜拉钢管(72)隔一布一设置,可以起到间隔卸荷的作用。As shown in Figure 1, a cable-stayed steel pipe (72) is also provided at the end of the cantilevered secondary beam (63), which mainly plays a role in bearing tension and supporting loads and ensures the safety of the shelter. The other end of the cable-stayed steel pipe (72) passes through the The main beam of the suspension frame on the floor (2) is fixed on the floor (2) with the embedded fixing bolt (105) and the fixing nut (106) of the main beam of the suspension frame (2); Draw steel pipe (72) to set at intervals of one cloth, can play the effect of interval unloading.

如图1和图2所示,悬挑架次梁(63)和上层钢管网架(67)端部附近还设有钢管斜撑(107),以增强悬挑架次梁(63)和上层钢管网架(67)的整体稳定性,同时钢管斜撑(107)一端与斜拉钢管(72)连接,另一端与封闭式钢管架侧防护(70)连接,倾斜设置。As shown in Figures 1 and 2, steel pipe diagonal braces (107) are also provided near the ends of the cantilevered secondary beam (63) and the upper steel pipe network frame (67) to strengthen the cantilevered secondary beam (63) and the upper steel pipe network. The overall stability of frame (67), while steel pipe diagonal brace (107) one end is connected with cable-stayed steel pipe (72), and the other end is connected with closed steel pipe frame side protection (70), and is inclined to set.

如图1和图3所示,主梁定型化调倾块(62)设在楼板(2)端部,用于调整悬挑架主梁(61)的倾向角度,主梁定型化调倾块(62)垫在悬挑架主梁(61)下部,调到合适角度后,用悬挑架主梁预埋固定螺栓(105)和悬挑架主梁固定螺帽(106)将悬挑架主梁(61)固定在楼板(2)上。As shown in Figures 1 and 3, the main girder shaped tilting block (62) is arranged at the end of the floor (2) to adjust the inclination angle of the main girder (61) of the cantilever frame, and the main girder shaped tilting block (62) Pad the lower part of the main beam of the cantilever frame (61). After adjusting to a suitable angle, use the pre-embedded fixing bolts (105) Main beam (61) is fixed on the floor (2).

如图4所示,满铺安全网(64)应在悬挑架次梁(63)上满铺,满铺安全网(64)上铺设减震木方(65),减震方木(65)上布设满铺脚手板(66);满铺铁网片(69)应铺满上层钢管网架(67)上部的悬挑架次梁(63);悬挑架次梁(63)和上层钢管网架(67)端部设有封闭式钢管架侧防护(70),封闭式钢管架侧防护(70)外侧设有警示条(108)。As shown in Figure 4, the fully paved safety net (64) should be fully paved on the cantilevered secondary beam (63), and the fully paved safety net (64) is laid with shock-absorbing wooden squares (65), and the shock-absorbing square timber (65) Scaffold boards (66) are laid on the top; the iron mesh sheet (69) should be covered with the cantilevered sub-beams (63) on the upper part of the upper steel pipe grid (67); the cantilevered sub-beams (63) and the upper steel pipe grid (67) end is provided with closed steel pipe frame side protection (70), and the outside of closed steel pipe frame side protection (70) is provided with warning bar (108).

本实用新型不局限于上述最佳实施方式,任何人在本实用新型的启示下都可得出其他各种形式的产品,但不论在其形状或结构上作任何变化,凡是具有与本申请相同或相近似的技术方案,均落在本实用新型的保护范围之内。The utility model is not limited to the above-mentioned best implementation mode, anyone can draw other various forms of products under the enlightenment of the utility model, but no matter make any changes in its shape or structure, all have the same features as the application Or similar technical schemes all fall within the protection scope of the present utility model.

Claims (9)

1. high-altitude overhanging formwork protection canopy characterized by comprising
Suspension scaffold girder (61), suspension scaffold secondary beam (63) and upper layer steel pipe rack (67);
The suspension scaffold secondary beam (63) rides upon above the suspension scaffold girder (61), splices suspension scaffold;
Described suspension scaffold girder (61) one end is fixed on floor (2), and the other end tenses unloading, institute using oblique pull wirerope (71) It states suspension scaffold girder (61) and is inclined by the girder regularization tune being placed on the floor (2) and realize updip setting on block (62);
The upper layer steel pipe rack (67) is equipped with above the suspension scaffold girder (61), suspension scaffold girder (61) side is equidistant Equipped with the vertical strut of steel pipe rack (68), hung between the upper layer steel pipe rack (67) and the vertical strut of steel pipe rack (68) Full closely-knitted safety net (109) are protected.
2. high-altitude overhanging formwork protection canopy according to claim 1, which is characterized in that suspension scaffold secondary beam (63) end Be additionally provided with oblique pull steel pipe (72), oblique pull steel pipe (72) other end is fixed on floor (2), the oblique pull wirerope (71) and The oblique pull steel pipe (72) is arranged every a cloth one.
3. high-altitude overhanging formwork protection canopy according to claim 2, which is characterized in that the suspension scaffold secondary beam (63) and institute Upper layer steel pipe rack (67) end is stated equipped with closed steel pipe frame side protection (70).
4. high-altitude overhanging formwork protection canopy according to claim 3, which is characterized in that close to the suspension scaffold secondary beam (63) It is additionally provided with steel pipe diagonal brace (107) with the position of upper layer steel pipe rack (67) end, described steel pipe diagonal brace (107) one end and institute Oblique pull steel pipe (72) connection is stated, the other end is connect with the closed steel pipe frame side protection (70).
5. according to any high-altitude overhanging formwork protection canopy of claim 2 to 4, which is characterized in that the oblique pull wirerope (71) it is fixed on the built-in fitting (104) being arranged at the floor (2);Oblique pull steel pipe (72) other end is existed by setting The pre-buried fixing bolt of suspension scaffold girder (105) and suspension scaffold girder hold-doun nut (106) on the floor (2) are fixed on described On floor (2).
6. according to claim 1 to 4 any high-altitude overhanging formwork protection canopies, which is characterized in that the girder regularization The tune block (62) that inclines is located at the ends of the floor (2), and the girder regularization tune inclines block (62) pad in the suspension scaffold girder (61) lower part, with the pre-buried fixing bolt of suspension scaffold girder (105) and suspension scaffold girder hold-doun nut (106) by the suspension scaffold master Beam (61) is fixed on the floor (2).
7. according to claim 1 to 4 any high-altitude overhanging formwork protection canopies, which is characterized in that in the overhanging sortie The full paving safety net (64) in beam (63) upper berth, described completely spread on safety net (64) are laid with damping flitch (65), the damping lumps of wood (65) completely paving scaffold board (66) is laid on.
8. according to claim 1 to 4 any high-altitude overhanging formwork protection canopies, which is characterized in that in the upper layer steel pipe The full paving iron net sheet (69) in rack (67) upper berth.
9. according to any high-altitude overhanging formwork protection canopy of claim 3 to 4, which is characterized in that the closed steel pipe Frame side is protected on the outside of (70) and is equipped with warning strip (108).
CN201822268911.9U 2018-12-29 2018-12-29 High-altitude suspension formwork protective shed Expired - Fee Related CN209353770U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822268911.9U CN209353770U (en) 2018-12-29 2018-12-29 High-altitude suspension formwork protective shed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822268911.9U CN209353770U (en) 2018-12-29 2018-12-29 High-altitude suspension formwork protective shed

Publications (1)

Publication Number Publication Date
CN209353770U true CN209353770U (en) 2019-09-06

Family

ID=67802267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822268911.9U Expired - Fee Related CN209353770U (en) 2018-12-29 2018-12-29 High-altitude suspension formwork protective shed

Country Status (1)

Country Link
CN (1) CN209353770U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924700A (en) * 2019-12-12 2020-03-27 重庆建工住宅建设有限公司 Building protective structure
CN113622508A (en) * 2020-05-08 2021-11-09 中国建筑设计研究院有限公司 Overhanging type shed body and construction method thereof
CN116181098A (en) * 2023-04-06 2023-05-30 中建八局第四建设有限公司 Overhanging protection shed and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924700A (en) * 2019-12-12 2020-03-27 重庆建工住宅建设有限公司 Building protective structure
CN113622508A (en) * 2020-05-08 2021-11-09 中国建筑设计研究院有限公司 Overhanging type shed body and construction method thereof
CN116181098A (en) * 2023-04-06 2023-05-30 中建八局第四建设有限公司 Overhanging protection shed and construction method

Similar Documents

Publication Publication Date Title
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN202227476U (en) High-altitude large-span overhung corridor-type reinforced concrete structure
CN212175496U (en) Super gravity anchor cantilever formwork system
CN202416184U (en) Construction device for formwork for longitudinal wet joint of box girder
CN209353770U (en) High-altitude suspension formwork protective shed
CN204126230U (en) Assembly scaffold unit
CN102661019A (en) Heat preservation and decoration integrated construction method for outer wall of building
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN109653484B (en) An installation structure of an external hanging basket for a roof super-high-air curtain wall project
CN104480922A (en) Space truss formwork supporting system and construction method thereof
CN104674997B (en) A kind of supporting construction and its construction method on timber buildings roof modelled after an antique
CN206581577U (en) Using housing construction builder's jack
CN102454292A (en) Supporting steel frame of high altitude large-span cantilever structure mold frame
CN103015713B (en) High-altitude-spanned steel reinforced concrete truss template
CN204876577U (en) Building construction system
CN207296361U (en) A kind of regularization assembled overhanging protection canopy
CN203334643U (en) Tower crane standard knot and structural steel combination high-altitude large-span operation frame device
CN208152532U (en) A kind of construction scaffold
CN201943350U (en) Supporting steel frame for die holder of high-altitude large span overhanging structure
CN202559727U (en) Load-bearing support structure of template of overhead long-span floor slab of building
CN205444891U (en) Building carrier plate cast in situ concrete truss support system
CN211228141U (en) A New Type of T-beam Diaphragm Construction Platform Cross Bracing
CN211644382U (en) Tower crane attached stay bar walkway platform system
CN212642080U (en) An adjustable cantilever scaffolding structure
CN204876579U (en) Building construction system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191230

Address after: Qingyang District of Chengdu City, Sichuan province 618300 Jade Road No. 80

Patentee after: CHINA NUCLEAR SOUTHWEST CONSTRUCTION PROJECT PARENT Co.

Address before: 310003 room 1901, unit 3, 3 Wanda Commercial Center, Gongshu District, Hangzhou, Zhejiang.

Patentee before: HANGZHOU JIANGRUN TECHNOLOGY Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190906