CN209334655U - Preceding bridge I-beam is poured blank - Google Patents

Preceding bridge I-beam is poured blank Download PDF

Info

Publication number
CN209334655U
CN209334655U CN201920044591.0U CN201920044591U CN209334655U CN 209334655 U CN209334655 U CN 209334655U CN 201920044591 U CN201920044591 U CN 201920044591U CN 209334655 U CN209334655 U CN 209334655U
Authority
CN
China
Prior art keywords
blank
cross gate
riser
ontology
preceding bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920044591.0U
Other languages
Chinese (zh)
Inventor
王占成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gucheng Donghua Machinery Hubei Ltd By Share Ltd
Original Assignee
Gucheng Donghua Machinery Hubei Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gucheng Donghua Machinery Hubei Ltd By Share Ltd filed Critical Gucheng Donghua Machinery Hubei Ltd By Share Ltd
Priority to CN201920044591.0U priority Critical patent/CN209334655U/en
Application granted granted Critical
Publication of CN209334655U publication Critical patent/CN209334655U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Molds, Cores, And Manufacturing Methods Thereof (AREA)

Abstract

The utility model relates to I-beam technical fields, more particularly to a kind of preceding bridge I-beam is poured blank, two blank ontologies including parallel side-by-side setting, running channel, four riser, the running channel includes sprue, cross gate, the cross gate is U-shaped, the lower end of the sprue is connect with the middle part of the cross gate, side below the spring perch of the blank ontology close to bottom is connect with the cross gate, four riser are respectively arranged at blank ontology position corresponding with spring perch, highest point of the highest point of the cross gate not higher than countersink in the middle part of blank ontology.The utility model casts two pieces blank simultaneously, improve casting efficiency, molten steel enters below spring perch close to the side of bottom when casting, and gradually filled-type chamber, by the position of running channel and riser, the sequence of Adjusting Shape molten steel solidification, when solidification, bottom, the both ends of blank first solidify, so as to improve the castability of preceding bridge I-beam, casting flaw is avoided.

Description

Preceding bridge I-beam is poured blank
Technical field
The utility model relates to I-beam technical fields, are poured blank more particularly to a kind of preceding bridge I-beam.
Background technique
Automotive axle is connected by suspension with vehicle frame (or monocoque body), and wheel is installed at both ends.The effect of vehicle bridge It is subject to the load of automobile, maintains normally travel of the automobile on road.Preceding bridge include I-beam, knuckle, track rod, The parts such as wheel hub, brake.Wherein, preceding bridge I-beam section is in " I " fonts, therefore claims " I-beam ".Preceding bridge I-beam and preceding steel Plate spring holder is integrally formed, and to avoid interfering with other component (such as engine sump tank), has downward drop in the middle part of I-beam.
I-beam is generally Integral die-forged forming, and for part engineering truck, such as fork truck, pump truck, body structure uses item Part and passenger car difference are larger, therefore Ye You producer processes preceding bridge I-beam using casting technique.Since I-beam size is larger, Overall weight is big, and when casting is more prone to produce mass defect, such as shrinkage porosite, misrun.
Summary of the invention
The purpose of this utility model is that in view of the deficiencies of the prior art, and a kind of preceding bridge I-beam casting blank is provided, It is by the design of position, shape to running channel and riser, so that from both ends to intermediate setup when casting is cooling, bridge work before improving The castability of word beam.
The technical scheme adopted by the utility model to solve the technical problem is as follows: a kind of preceding bridge I-beam is poured blank, Two blank ontologies, running channel, four riser including parallel side-by-side setting, the running channel includes sprue, cross gate, the cross Running channel is U-shaped, and the lower end of the sprue is connect with the middle part of the cross gate, under the spring perch of the blank ontology Side is connect close to the side of bottom with the cross gate, and four riser are respectively arranged at blank ontology and spring perch pair The position answered, the highest point of the cross gate are not higher than the highest point of countersink in the middle part of blank ontology.
The length along axial direction of the riser horizontal cross-section is greater than twice of the length along automobile direction of advance.
The cross gate vertical section is greater than length in the horizontal direction in the length of vertical direction.
Height of the height not less than the blank ontology of the sprue, riser, the sum of the volume of four riser The half of the sum of volume for two blank ontologies
The beneficial effects of the utility model are: a kind of preceding bridge I-beam is poured blank comprising the two of parallel side-by-side setting A blank ontology, running channel, four riser, the running channel include sprue, cross gate, and the cross gate is U-shaped, described directly to pour The lower end in road is connect with the middle part of the cross gate, side and institute below the spring perch of the blank ontology close to bottom Cross gate connection is stated, four riser are respectively arranged at blank ontology position corresponding with spring perch, the cross gate Highest point not higher than countersink in the middle part of blank ontology highest point.The utility model casts two pieces blank simultaneously, improves casting Make efficiency, side of the molten steel below spring perch close to bottom enters when casting, and gradually filled-type chamber, by running channel and The position of riser, Adjusting Shape molten steel solidification sequence, when solidification, bottom, the both ends of blank first solidify, so as to improve preceding bridge work The castability of word beam, avoids casting flaw.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the preceding bridge I-beam casting blank of the utility model.
Fig. 2 is the front view of preceding bridge I-beam casting blank in Fig. 1.
Fig. 3 is the right view of preceding bridge I-beam casting blank in Fig. 2.
Description of symbols:
1 --- blank ontology 2 --- running channel
21 --- sprue 22 --- cross gates
3 --- riser.
Specific embodiment
The utility model is described in further detail in the following with reference to the drawings and specific embodiments, is not that this is practical Novel practical range limited to this.
As shown in Figure 1, Figure 2, Figure 3 shows, the preceding bridge I-beam of the present embodiment is poured blank comprising the two of parallel side-by-side setting 2, four a blank ontology 1, running channel riser 3, the arranged direction of two blanks is consistent, and spacing is the width of a blank ontology, The running channel includes sprue 21, cross gate 22, and the cross gate 22 is the U-shaped being arranged symmetrically, under the sprue 21 End connect with the middle part of the cross gate 22, the side of the close bottom in the spring perch of the blank ontology 1 lower section with it is described Cross gate 22 connects, and selects the position for the joint of running channel and type chamber, first is that molten steel can be made to flow to blank bottom as early as possible, Second is that considering easy to operate when the running channel on excision blank.Four riser 3 are respectively arranged at blank ontology 1 and leaf spring The corresponding position of seat, the highest point of the cross gate 22 are not higher than the highest point of 1 middle part countersink of blank ontology, four riser 3 need milling flat with joint later period of blank ontology 1, and the position thickness is larger, and position is higher, and far from end, are conducive to Metal is full of the both ends of blank, carries out feeding to the position while cooling, improves product quality.
Further, the length along axial direction of 3 horizontal cross-section of riser is greater than the length along automobile direction of advance Twice, the left and right directions along axial direction, that is, Fig. 2, the direction of vertical paper in automobile direction of advance, that is, Fig. 2 can from Fig. 1 To find out, the other parts in addition to upper end of riser 3 are offset flat shape, are conducive to carrying out feeding in longer length.
Further, 22 vertical section of cross gate is greater than length in the horizontal direction in the length of vertical direction.
Further, not less than the height of the blank ontology 1, described four emit the height of the sprue 21, riser 3 The sum of volume of mouth 3 is the half of the sum of volume of two blank ontologies 1.
Finally it should be noted that above embodiments are only to illustrate the technical solution of the utility model, rather than to this reality With the limitation of novel protected range, although being explained in detail referring to preferred embodiment to the utility model, this field it is general Lead to it will be appreciated by the skilled person that can be with the technical solution of the present invention is modified or equivalently replaced, without departing from this The spirit and scope of utility model technical solution.

Claims (4)

1. bridge I-beam is poured blank before, it is characterised in that: two blank ontologies (1), running channels including parallel side-by-side setting (2), four riser (3), the running channel include sprue (21), cross gate (22), and the cross gate (22) is U-shaped, described The lower end of sprue (21) is connect with the middle part of the cross gate (22), is leaned below the spring perch of the blank ontology (1) The side of nearly bottom is connect with the cross gate (22), and four riser (3) are respectively arranged at blank ontology (1) and steel plate bullet The corresponding position of spring abutment, the highest point of the cross gate (22) are not higher than the highest point of countersink in the middle part of blank ontology (1).
2. preceding bridge I-beam according to claim 1 is poured blank, it is characterised in that: riser (3) horizontal cross-section It is greater than twice of the length along automobile direction of advance along the length of axial direction.
3. preceding bridge I-beam according to claim 1 is poured blank, it is characterised in that: cross gate (22) vertical section It is greater than length in the horizontal direction in the length of vertical direction.
4. preceding bridge I-beam according to claim 1 is poured blank, it is characterised in that: the sprue (21), riser (3) Height be not less than the blank ontology (1) height, the sum of volume of four riser (3) be two blank ontologies (1) The sum of volume half.
CN201920044591.0U 2019-01-10 2019-01-10 Preceding bridge I-beam is poured blank Expired - Fee Related CN209334655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920044591.0U CN209334655U (en) 2019-01-10 2019-01-10 Preceding bridge I-beam is poured blank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920044591.0U CN209334655U (en) 2019-01-10 2019-01-10 Preceding bridge I-beam is poured blank

Publications (1)

Publication Number Publication Date
CN209334655U true CN209334655U (en) 2019-09-03

Family

ID=67761449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920044591.0U Expired - Fee Related CN209334655U (en) 2019-01-10 2019-01-10 Preceding bridge I-beam is poured blank

Country Status (1)

Country Link
CN (1) CN209334655U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116372102A (en) * 2023-04-01 2023-07-04 福建铁驰马轻量车桥有限公司 A manufacturing method of a cast vehicle axle provided with a reinforced bridge plate

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116372102A (en) * 2023-04-01 2023-07-04 福建铁驰马轻量车桥有限公司 A manufacturing method of a cast vehicle axle provided with a reinforced bridge plate
CN116372102B (en) * 2023-04-01 2025-09-30 福建铁驰马轻量车桥有限公司 Method for manufacturing a cast vehicle axle with reinforced bridge plate

Similar Documents

Publication Publication Date Title
CN104768840B (en) Modular system for automobile rear frame
CN102730018B (en) Radial steering rack for secondary framework
CN112810697A (en) Extrusion section bar and casting combined type electric vehicle front auxiliary frame
CN205395687U (en) Novel passenger train air suspension
CN104554324A (en) Integrated framework and bogie
CN209535205U (en) Subframe and the automobile for applying it
US20190061820A1 (en) Auxiliary frame for motor vehicles
CN209334655U (en) Preceding bridge I-beam is poured blank
CN201457403U (en) Air spring truck frame without swing bolster
CN207140720U (en) A kind of lightweight integrated balancing suspension
CN208947405U (en) An integral casting hollow aluminum alloy front subframe
CN111216795A (en) A New Type Aluminum Full Frame Rear Subframe
CN213323115U (en) I-beam type bogie frame of straddle type monorail vehicle
CN202480872U (en) Automotive oil tank
CN109178099A (en) A kind of integrally casting hollow aluminium alloy fore sub frame
CN211943498U (en) Novel aluminum full-frame type rear auxiliary frame
CN208053015U (en) A kind of riding automobile-used control arm
CN203681186U (en) Aluminum alloy semi-trailer suspension
CN207029295U (en) A kind of light-duty vehicle subframe
CN202491653U (en) Air suspension with novel transverse stabilization device
CN215204338U (en) Axle bottom bracket
CN203172387U (en) Balanced suspension system used for heavy commercial vehicle
CN204341074U (en) Diesel locomotive frame and diesel locomotive
CN109849959B (en) Bogie frame of straddle type monorail vehicle
CN209650281U (en) The bogie frame of straddle-type single-track vehicle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190903

Termination date: 20210110

CF01 Termination of patent right due to non-payment of annual fee