CN209309459U - Pipeline balance briquetting - Google Patents

Pipeline balance briquetting Download PDF

Info

Publication number
CN209309459U
CN209309459U CN201822038661.XU CN201822038661U CN209309459U CN 209309459 U CN209309459 U CN 209309459U CN 201822038661 U CN201822038661 U CN 201822038661U CN 209309459 U CN209309459 U CN 209309459U
Authority
CN
China
Prior art keywords
lacing wire
pipeline
concrete substrate
connection ring
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822038661.XU
Other languages
Chinese (zh)
Inventor
郝永峰
樊培
厍艳茹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN201822038661.XU priority Critical patent/CN209309459U/en
Application granted granted Critical
Publication of CN209309459U publication Critical patent/CN209309459U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a kind of pipeline balance briquettings, comprising: concrete substrate, U-shaped lacing wire, lateral lacing wire, hanging ring;U-shaped lacing wire, lateral lacing wire are arranged inside concrete substrate, and U-shaped lacing wire, lateral lacing wire cross one another connection, and hanging ring is connected to the top of concrete substrate;Concrete substrate is provided with groove body in bottom, and the top of groove body is cylinder, is open as horn opening.The utility model can effectively solve the problem that the orientation problem for growing defeated buried pipeline in the prior art, and pipeline is avoided to float, while destruction can be mined with protective conduit.

Description

Pipeline balance briquetting
Technical field
The utility model relates to a kind of buried pipelines, specifically, are related to a kind of pipeline balance briquetting.
Background technique
After the excavation groove of long defeated buried pipeline meets the requirements, in mounted lifting pipeline to groove, after pipeline location It is backfilled.When the locations such as Pipeline Crossing Program river, wetland and rich groundwater, since pipeline weight is less than buoyancy, trench backfill Vacant duct will float afterwards, to not can guarantee buried depth of pipeline, cause engineering quality defects, will waste a large amount of manpower and material resources and do over again Processing, increases construction cost.
Buried pipeline On The Floating is avoided, the buoyancy or pipeline location of water need to be solved, the buoyancy difficulty for solving water is larger, The buoyancy of water can not be reduced for a long time, to increase pipeline weight, so that pipeline weight is greater than buoyancy, and permanent positioning is by pipeline Most economical method.
Utility model content
The technical issues of the utility model is solved is to provide a kind of pipeline balance briquetting, can effectively solve the problem that the prior art The orientation problem of the middle defeated buried pipeline of length, and avoid pipeline from floating, while destruction can be mined with protective conduit.
Technical solution is as follows:
A kind of pipeline balance briquetting, comprising: concrete substrate, U-shaped lacing wire, lateral lacing wire, hanging ring;U-shaped lacing wire is laterally drawn Muscle is arranged inside concrete substrate, and U-shaped lacing wire, lateral lacing wire cross one another connection, and hanging ring is connected to the top of concrete substrate Portion;Concrete substrate is provided with groove body in bottom, and the top of groove body is cylinder, is open as horn opening.
Further, the end of hanging ring extends to form bar to two sides, and bar is connected in lateral lacing wire.
Further, the inner wall of groove body is provided with insulation rubber mat.
Further, the side of concrete substrate is provided with the first connection ring and the second connection ring, the first connection ring and second Connection ring is in different height;After first connection ring of two neighboring concrete substrate and the overlapping of the second connection ring, connect first It connects ring and the second connection ring is equipped with fixed pin.
The utility model technical effect includes:
The utility model production is simple, easy for installation, can effectively solve the problem that the positioning for growing defeated buried pipeline in the prior art Problem, and avoid pipeline from floating, while destruction can be mined with protective conduit.
Detailed description of the invention
Fig. 1 is the positive structure diagram of pipeline balance briquetting in the utility model;
Fig. 2 is the side structure schematic view of pipeline balance briquetting in the utility model;
Fig. 3 is the overlooking structure diagram of pipeline balance briquetting in the utility model;
Fig. 4 is the structural schematic diagram of fixed pin in the utility model.
Specific embodiment
The specific embodiment for fully showing the utility model is described below, to enable those skilled in the art to reality It tramples and reproduces.
As shown in Figure 1, being the schematic view of the front view of pipeline balance briquetting in the utility model;As shown in Fig. 2, being this reality With the side structure schematic view of novel middle pipeline balance briquetting;As shown in figure 3, being that pipeline balance briquetting is bowed in the utility model Depending on structural schematic diagram.
The structure of pipeline balance briquetting includes: concrete substrate 1, U-shaped lacing wire 2, lateral lacing wire 3, hanging ring 4;U-shaped lacing wire 2, Lateral lacing wire 3 is arranged inside concrete substrate 1, and U-shaped lacing wire 2, lateral lacing wire 3 cross one another connection, and hanging ring 4 is connected to coagulation The top of soil matrix body 1.
When cast in situs pipeline balance briquetting, U-shaped lacing wire 2, lateral lacing wire 3 intersect and with silk binding are tied up, and hanging ring 4 is connected At the top of U-shaped lacing wire 2, it is then placed in mold casting concrete, forms pipeline balance briquetting after concrete setting molding.
The end of hanging ring 4 extends to form bar 41 to two sides, and bar 41 is connected in lateral lacing wire 3.Concrete substrate 1 exists Bottom is provided with groove body 11, and the top of groove body 11 is cylinder, is open as horn opening, for protective conduit external anti-corrosion layer, 11 inner wall of groove body is provided with insulation rubber mat.
2 material of U-shaped lacing wire is 14 reinforcing bar of φ, and lateral 3 material of lacing wire is 10 reinforcing bar of φ, and 4 material of hanging ring is 16 reinforcing bar of φ.It is mixed Solidifying soil is C30 concrete, the rubber mat that insulate with a thickness of 5mm.
As shown in figure 4, being the structural schematic diagram of fixed pin 5 in the utility model.
In order to increase the connection of two neighboring pipeline balance briquetting, to increase overall stability, in the side of concrete substrate 1 Portion is provided with the first connection ring 11 and the second connection ring 12, and the first connection ring 11 and the second connection ring 12 are in different height.When After the completion of the lifting of two pipeline balance briquettings, the first connection ring 11 and the overlapping of the second connection ring 12, in the first connection ring 11 and the Two connection rings 12 wear fixed pin 5, and the first connection ring 11 and the second connection ring 12 are connected.
In the work progress for passing through the locations buried-pipe laying pipeline such as river, wetland and rich groundwater, when pipeline weight When less than buoyancy, pipeline balance briquetting can be such that pipeline permanently positions.Pipeline balance briquetting can be separately installed, can also combine It installs, pipeline balance briquetting is lifted on pipeline, after pipeline sinks under water together, so that it may place pipeline movement, positioning Pipeline balance briquetting can be removed after completing and filling, repetitive cycling uses.
It should be understood that above description be only it is exemplary and explanatory, the utility model, this reality can not be limited With the novel structure for being not limited to be described above and be shown in the accompanying drawings, and can carry out without departing from the scope it is each Kind modifications and changes.The scope of the utility model is only limited by the accompanying claims.

Claims (4)

1. a kind of pipeline balance briquetting characterized by comprising concrete substrate, U-shaped lacing wire, lateral lacing wire, hanging ring;U-shaped is drawn Muscle, lateral lacing wire are arranged inside concrete substrate, and U-shaped lacing wire, lateral lacing wire cross one another connection, and hanging ring is connected to concrete The top of matrix;Concrete substrate is provided with groove body in bottom, and the top of groove body is cylinder, is open as horn opening.
2. pipeline balance briquetting as described in claim 1, which is characterized in that the end of hanging ring extends to form bar to two sides, gear Bar is connected in lateral lacing wire.
3. pipeline balance briquetting as described in claim 1, which is characterized in that the inner wall of groove body is provided with insulation rubber mat.
4. pipeline balance briquetting as described in claim 1, which is characterized in that the side of concrete substrate is provided with the first connection ring With the second connection ring, the first connection ring and the second connection ring are in different height;First connection of two neighboring concrete substrate After ring and the overlapping of the second connection ring, fixed pin is equipped in the first connection ring and the second connection ring.
CN201822038661.XU 2018-12-05 2018-12-05 Pipeline balance briquetting Active CN209309459U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822038661.XU CN209309459U (en) 2018-12-05 2018-12-05 Pipeline balance briquetting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822038661.XU CN209309459U (en) 2018-12-05 2018-12-05 Pipeline balance briquetting

Publications (1)

Publication Number Publication Date
CN209309459U true CN209309459U (en) 2019-08-27

Family

ID=67675858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822038661.XU Active CN209309459U (en) 2018-12-05 2018-12-05 Pipeline balance briquetting

Country Status (1)

Country Link
CN (1) CN209309459U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112197068A (en) * 2020-07-30 2021-01-08 中国电建集团华东勘测设计研究院有限公司 Frame type inverted U-shaped counterweight device for large underwater pipeline and pipeline installation method
CN113154131A (en) * 2021-03-17 2021-07-23 深圳海油工程水下技术有限公司 U-shaped counterweight structure for laying deepwater dynamic pipe cable

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112197068A (en) * 2020-07-30 2021-01-08 中国电建集团华东勘测设计研究院有限公司 Frame type inverted U-shaped counterweight device for large underwater pipeline and pipeline installation method
CN113154131A (en) * 2021-03-17 2021-07-23 深圳海油工程水下技术有限公司 U-shaped counterweight structure for laying deepwater dynamic pipe cable

Similar Documents

Publication Publication Date Title
CN100412275C (en) Waterproof and plugging construction method for precipitation well in foundation pit
CN209309459U (en) Pipeline balance briquetting
CN106988343A (en) A kind of town road pipeline protection structure and its construction method
CN102535441A (en) Construction method of underground diaphragm wall
CN208280185U (en) A kind of post-cast strip advanced water-stopping construction
CN107059881A (en) The foundation pit supporting method that a kind of campshed is combined with steel sheet pile
CN207268004U (en) Toilet leakage protective system
CN104652495A (en) Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate
CN204185845U (en) A kind of water-proof pile board wall supporting and protection structure
CN209642270U (en) A kind of novel power cable protection pipe
CN205093378U (en) Ecological fish pond structure
CN203768925U (en) Seal device for dewatering well in foundation pit
CN103422499B (en) Casing construction method inside and outside a kind of permafrost region pile foundation
CN205116220U (en) Pour cable pit after assembly of L type precast concrete spare
CN204676607U (en) Poured band of outer wall of basement plugging structure
CN208933976U (en) A kind of plant-growing type eco-concrete slope protection
CN204174496U (en) A kind of novel town road structure
CN207003440U (en) Foundation pit spring hole water treatment system
CN108894206A (en) Shoal sewage pipe, well anti-floating system and construction method
CN110359495A (en) Comprehensive pipe gallery structure seam construction and its construction method
CN207160063U (en) A kind of prefabricated box culvert structure for riding pipeline and pipeline water conservancy project supporter
CN104912057B (en) Construction method of underground continuous wall
CN104775414A (en) Super-soft dredger fill surface layer solidification crusting and foundation treatment method
CN205990627U (en) Bury waterstop in connected entrance and fixing and protection integrated device is installed
CN204370463U (en) Ultra-soft cob brick loose tool assists suspended deck structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant