CN209307915U - A kind of highway barrier - Google Patents

A kind of highway barrier Download PDF

Info

Publication number
CN209307915U
CN209307915U CN201822106602.1U CN201822106602U CN209307915U CN 209307915 U CN209307915 U CN 209307915U CN 201822106602 U CN201822106602 U CN 201822106602U CN 209307915 U CN209307915 U CN 209307915U
Authority
CN
China
Prior art keywords
fixed column
sideline
wirerope
highway barrier
additional
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822106602.1U
Other languages
Chinese (zh)
Inventor
杭淼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Exhibition Road Construction Co Ltd
Original Assignee
Anhui Exhibition Road Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Exhibition Road Construction Co Ltd filed Critical Anhui Exhibition Road Construction Co Ltd
Priority to CN201822106602.1U priority Critical patent/CN209307915U/en
Application granted granted Critical
Publication of CN209307915U publication Critical patent/CN209307915U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of highway barriers, including the first sideline fixed column, second sideline fixed column and additional fixed column, the additional fixed column is equipped with several, and it is evenly spaced on the position between the first sideline fixed column and the second sideline fixed column, first sideline fixed column and the second sideline fixed column sidewalls vertical direction are welded with three buckles being evenly spaced on, three wirerope have been connected by a snap between first sideline fixed column and the second sideline fixed column, several additional fixed column sidewalls vertical directions offer three through-holes being evenly spaced on, three wirerope run through three through-holes in several additional fixed columns, the equal fixing sleeve of the outer wall of three wirerope is connected to reinforcing sleeve.The utility model has good impact resistance and corrosion resistance, changes traditional guardrail protection method, further increases security performance.

Description

A kind of highway barrier
Technical field
The utility model relates to municipal works correlative technology field, specially a kind of highway barrier.
Background technique
Municipal works refer to urban operating mechanism construction project.In China, urban operating mechanism refers to be built in metropolitan district, town (township) planning If being arranged in range, providing the various buildings of paid or free public product and service based on government responsibility and obligation for resident Object, structures, equipment etc..The matched various public infrastructure developments of urban life belong to municipal works scope.We know Road, generally on highway, in order to separate pavement and car lane, or motor vehicle is being sent out in order to prevent in road both sides After raw traffic accident, car lane is sailed out of, secondary injury is caused, is on the one hand system so guardrail can all be arranged on separator bar About motor vehicle safety that pedestrian is travelled and influenced on non-motorized lane, on the other hand also for ensureing and improve entire road Road traffic safety and reasonability, guarantee have a good transport and communication network without hindrance, but existing guardrail exists during actual use Certain defect, because the travel speed of motor vehicle decides finally to the size of the impact force of guardrail, in real life, when Have and the phenomenon that motor vehicle breaks through guardrail, second accident occurs, leads to casualties occurs, that is, in the performance of cushion impact forces It is to be improved and itself protective capacities it is also to be improved, so here design produce a kind of highway barrier, in order to solve The certainly above problem.
Utility model content
The purpose of this utility model is to provide a kind of highway barriers, to solve the problems mentioned in the above background technology.
In order to solve the above technical problems, the utility model provides the following technical solutions: a kind of highway barrier, including the first side Line fixed column, the second sideline fixed column and additional fixed column, the additional fixed column is equipped with several, and is evenly spaced on Position between first sideline fixed column and the second sideline fixed column, first sideline fixed column and the second sideline fixed column side Wall vertical direction is welded be evenly spaced on three buckles, first sideline fixed column and the second sideline fixed column it Between be connected by a snap three wirerope, several additional fixed column sidewalls vertical directions offer and are evenly spaced on Three through-holes, three wirerope run through three through-holes in several additional fixed columns, three steel wires The equal fixing sleeve of the outer wall of rope is connected to reinforcing sleeve.
Preferably, first sideline fixed column and the second sideline fixed column are located at the left and right ends of installation site.
Preferably, the fixed weldering of the bottom face of first sideline fixed column, the second sideline fixed column and additional fixed column It is connected to mounting disc.
Preferably, first sideline fixed column, the second sideline fixed column and additional fixed column are located in same horizontal line.
Preferably, run through between three reinforcing sleeves and be socketed with the stiffening plate.
Preferably, the stiffening plate is equipped with several pieces.
Preferably, the top and bottom of several pieces of stiffening plates are plugged with fastening bolt by threaded hole rotation, and The tip of fastening bolt is contacted with upper and lower two wirerope side walls.
Preferably, the reinforcing sleeve and stiffening plate have adopted MGE material, and the MGE material is alloy engineering plastics.
Compared with prior art, the utility model has the beneficial effects that
1. the utility model, by the way that the first sideline fixed column, the second sideline fixed column and additional fixed column is successively uniform Interval is mounted on highway sideway face, then by the card at the both ends of three wirerope and the first sideline fixed column and the second sideline fixed column Button is fixedly connected, and runs through the through-hole of several additional fixed columns, plays the role of a barrier in this way.
2. the utility model has good rotproofness, impact resistance and lower temperature resistance by setting reinforcing sleeve, into One step improves the safety of guardrail, by the way that several groups stiffening plate is arranged, for further enhancing anti-impact force.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model embodiment;
Fig. 2 is the partial structural diagram of the utility model embodiment;
Fig. 3 is structural schematic diagram at A in Fig. 1 of the utility model embodiment.
In figure: 1, the first sideline fixed column;2, wirerope;3, it buckles;4, stiffening plate;5, reinforcing sleeve;6, fixed column is added; 7, the second sideline fixed column;8, mounting disc;9, through-hole;10, fastening bolt.
Specific embodiment
For the ease of using, the utility model embodiment provides a kind of highway barrier.Below in conjunction with the utility model Attached drawing in embodiment, the technical scheme in the utility model embodiment is clearly and completely described, it is clear that described Embodiment be only the utility model a part of the embodiment, instead of all the embodiments.Based on the reality in the utility model Example is applied, every other embodiment obtained by those of ordinary skill in the art without making creative efforts all belongs to In the range of the utility model protection.
Embodiment 1
Fig. 1-3 is please referred to, a kind of highway barrier is present embodiments provided, including the first sideline fixed column 1, the second sideline are consolidated Fixed column 7 and additional fixed column 6 add fixed column 6 and are equipped with several, and be evenly spaced in the first sideline fixed column 1 and the Position between two sideline fixed columns 7, the first sideline fixed column 1 are welded with 7 sidewalls vertical direction of the second sideline fixed column Three buckles 3 being evenly spaced on, are connected with three by buckle 3 between the first sideline fixed column 1 and the second sideline fixed column 7 Root wirerope 2, several additional 6 sidewalls vertical directions of fixed column offer three through-holes 9 being evenly spaced on, three steel wires Three through-holes 9 of the rope 2 in several additional fixed columns 6, the equal fixing sleeve of the outer wall of three wirerope 2 are connected to reinforcing sleeve 5.
In the present embodiment, according to actual installation length, to determine the length of wirerope 2, and can be according to actual peace Dress demand determines the radical of additional fixed column 6, by the first sideline fixed column 1, the second sideline fixed column 7 and additional fixed column 6 Successively uniform intervals are mounted on highway side, by consolidating at the both ends of three wirerope 2 with the second sideline with the first sideline fixed column 1 The buckle 3 of fixed column 7 is fixedly connected, and runs through the through-hole 9 of several additional fixed columns 6, plays the role of a barrier in this way, According to actual installation requirements, the overall length of wirerope 2 is longer, so also having corresponding cushion performance, also prevents certain When one position is hit, car lane is gone out after severing additional fixed column 6, causes second accident, this is also to adopt with traditional Metal plate is used to further improve security performance as the improvements of protective fence, in addition, having by setting reinforcing sleeve 5 Good rotproofness, impact resistance and lower temperature resistance, further increase the safety of guardrail.
Embodiment 2
Fig. 1-3 is please referred to, is further improved on the basis of embodiment 1: the first sideline fixed column 1 and the second sideline Fixed column 7 is located at the left and right ends of installation site, and the first sideline fixed column 1 and the second sideline fixed column 7 are used as the leftmost side With the connecting column of the rightmost side, it is used to connecting steel wire ropes 2, the first sideline fixed column 1, the second sideline fixed column 7 and additional fixed column 6 Bottom face be fixedly welded with mounting disc 8, be convenient for by mounting disc 8 by the first sideline fixed column 1, the second sideline fixed column 7 It is fixed on highway pavement with additional fixed column 6, the first sideline fixed column 1, the second sideline fixed column 7 and additional fixed column 6 In in same horizontal line, not influencing the stretching of wirerope 2 in this way, runs through between three reinforcing sleeves 5 and be socketed with stiffening plate 4, reinforce Plate 4 is equipped with several pieces, and the top and bottom of several pieces of stiffening plates 4 are plugged with fastening bolt 10 by threaded hole rotation, and tight The tip of fixing bolt 10 is contacted with 2 side wall of upper and lower two wirerope, by the way that several groups stiffening plate 4 is arranged, for enhancing anti-impact Power is hit, is convenient for for stiffening plate 4 being fixed on the specific location of wirerope 2 by fastening bolt 10, difficult to slide, 5 He of reinforcing sleeve Stiffening plate 4 has adopted MGE material, and MGE material is alloy engineering plastics, the material have good rotproofness, impact resistance with And lower temperature resistance.
In this practical description, it should be noted that the orientation of the instructions such as term "vertical", "upper", "lower", "horizontal" or Person's positional relationship is orientation based on the figure or positional relationship, is merely for convenience of this practical and simplified description of description, Rather than the device or element of instruction or hint meaning must have a particular orientation, and are constructed and grasped with specific orientation Make, therefore should not be understood as the limitation practical to this.In addition, " first ", " second ", " third ", " the 4th " are only used for description mesh , and should not be understood as indicating or implying relative importance.
In this practical description, it is also necessary to explanation, unless otherwise specific regulation and limitation, term " setting ", " peace Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally Connection, can be mechanical connection, is also possible to be electrically connected, can be and be directly connected to, and be also possible to be connected by intermediary, can To be the connection inside two elements.For the ordinary skill in the art, can understand as the case may be above-mentioned Concrete meaning of the term in this is practical.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (8)

1. a kind of highway barrier, including the first sideline fixed column (1), the second sideline fixed column (7) and additional fixed column (6), Be characterized in that: the additional fixed column (6) is equipped with several, and is evenly spaced in the first sideline fixed column (1) and second Position between sideline fixed column (7), first sideline fixed column (1) and second sideline fixed column (7) sidewalls vertical direction Be welded with three buckles (3) being evenly spaced on, first sideline fixed column (1) and the second sideline fixed column (7) it Between by buckle (3) be connected with three wirerope (2), several additional fixed column (6) the sidewalls vertical directions offer Even three be spaced apart through-hole (9), three wirerope (2) run through three on several additional fixed columns (6) The equal fixing sleeve of outer wall of a through-hole (9), three wirerope (2) is connected to reinforcing sleeve (5).
2. a kind of highway barrier according to claim 1, it is characterised in that: first sideline fixed column (1) and second Sideline fixed column (7) is located at the left and right ends of installation site.
3. a kind of highway barrier according to claim 1, it is characterised in that: first sideline fixed column (1), the second side The bottom face of line fixed column (7) and additional fixed column (6) is fixedly welded with mounting disc (8).
4. a kind of highway barrier according to claim 1, it is characterised in that: first sideline fixed column (1), the second side Line fixed column (7) and additional fixed column (6) are located in same horizontal line.
5. a kind of highway barrier according to claim 1, it is characterised in that: through set between three reinforcing sleeves (5) It is connected to stiffening plate (4).
6. a kind of highway barrier according to claim 5, it is characterised in that: the stiffening plate (4) is equipped with several pieces.
7. a kind of highway barrier according to claim 5, it is characterised in that: the upper end of several pieces of stiffening plates (4) and Lower end by threaded hole rotation be plugged with fastening bolt (10), and the tip of fastening bolt (10) with upper and lower two wirerope (2) side wall contacts.
8. a kind of highway barrier according to claim 5, it is characterised in that: the reinforcing sleeve (5) and stiffening plate (4) are adopted There is MGE material, the MGE material is alloy engineering plastics.
CN201822106602.1U 2018-12-15 2018-12-15 A kind of highway barrier Expired - Fee Related CN209307915U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822106602.1U CN209307915U (en) 2018-12-15 2018-12-15 A kind of highway barrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822106602.1U CN209307915U (en) 2018-12-15 2018-12-15 A kind of highway barrier

Publications (1)

Publication Number Publication Date
CN209307915U true CN209307915U (en) 2019-08-27

Family

ID=67677066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822106602.1U Expired - Fee Related CN209307915U (en) 2018-12-15 2018-12-15 A kind of highway barrier

Country Status (1)

Country Link
CN (1) CN209307915U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114000449A (en) * 2021-11-21 2022-02-01 包头北方安全防护装备制造有限公司 An impact-resistant prefabricated road dividing guardrail

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114000449A (en) * 2021-11-21 2022-02-01 包头北方安全防护装备制造有限公司 An impact-resistant prefabricated road dividing guardrail

Similar Documents

Publication Publication Date Title
CN109371815B (en) Beam-body corrugated steel combined protective shed frame and manufacturing method thereof
CN101818470A (en) Method for optimally setting expressway traffic safety facilities
CN210288214U (en) Wave form roof beam combination formula guardrail and concrete guardrail transition structure
CN209307915U (en) A kind of highway barrier
CN101560751B (en) Overpass having characteristic of upper arch and lower tunnel combination
CN206486846U (en) Full assembling shaped steel guardrail
CN208545666U (en) A kind of transition section apparatus of Bridge guardrail and roadbed corrugated beam barrier
CN106758741B (en) Modular box type plate beam structure and pontic erection method based on box type plate beam structure
CN205242308U (en) Strenghthened type road guardrail with wave form roof beam and crossbeam
US20220341108A1 (en) Road Safety Barrier
CN111968392A (en) Method for managing and controlling tide lanes of double-hole six-lane and above tunnel
CN209194320U (en) A kind of beam body waveform steel combination protecting canopy frame
CN212103805U (en) A concrete guardrail and corrugated beam guardrail steel structure wing wall transition section
CN201310076Y (en) Improved single-piece concrete guardrail for highway
CN212688810U (en) Lane isolation guardrail
CN114441131A (en) Real vehicle collision test method for rigid heightened guardrail
CN211872617U (en) Permanent isolation guardrail for urban bridge
CN211200209U (en) Transition section between bridge pier anti-collision device in highway central separation strip and separation strip
CN206635689U (en) A kind of anticollision barrier for preventing distant light irradiation, there is prompt facility
CN209025021U (en) A rapid installation of anti-collision device for urban bridge piers
CN202369955U (en) Collision-prevention device for middle pier of highway overpass bridge
CN115621904B (en) Cross crossing method for power transmission line
CN201649003U (en) Active powder concrete column and steel pipe combination rail structure
CN215801273U (en) Assembled hard and soft combined rotor isolation anti-dazzle guardrail
CN219175099U (en) Flexible anticollision highway guardrail

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190827

Termination date: 20201215