CN209298712U - prefabricated container - Google Patents

prefabricated container Download PDF

Info

Publication number
CN209298712U
CN209298712U CN201822213568.8U CN201822213568U CN209298712U CN 209298712 U CN209298712 U CN 209298712U CN 201822213568 U CN201822213568 U CN 201822213568U CN 209298712 U CN209298712 U CN 209298712U
Authority
CN
China
Prior art keywords
substation
air
prefabricated container
air inlet
cabinet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822213568.8U
Other languages
Chinese (zh)
Inventor
王峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Svolt Energy Technology Co Ltd
Original Assignee
Svolt Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Svolt Energy Technology Co Ltd filed Critical Svolt Energy Technology Co Ltd
Priority to CN201822213568.8U priority Critical patent/CN209298712U/en
Application granted granted Critical
Publication of CN209298712U publication Critical patent/CN209298712U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Patch Boards (AREA)

Abstract

The utility model provides a kind of prefabricated container, has substation's element for saving, which includes the internal cabinet for being formed with chamber, and air inlet is equipped on cabinet, and air outlet is equipped at the top of it;Deflector is equipped between air inlet and substation's element, to guide air flow direction substation component base, and chamber is separated to form cooling duct by deflector, and the portion of keeping off the rain is equipped with above air outlet, and is equipped with after driving flows through cooling duct by the air-flow that air inlet flows into and is discharged in cooling duct.Prefabricated container described in the utility model, under the driving of driving portion, the bottom of substation's element can be flowed to by deflector by the air-flow that air inlet flows into, and it is discharged after flowing up through whole transformer station element by air outlet, the cooling uniformity fruit of substation's element can be improved in it, solve the problems, such as that the heat dissipation performance of substation's element is poor, to be conducive to extend the service life of substation's element.

Description

预制式集装箱prefabricated container

技术领域technical field

本实用新型涉及储电系统技术领域,特别涉及一种预制式集装箱。The utility model relates to the technical field of electricity storage systems, in particular to a prefabricated container.

背景技术Background technique

近年来,在应对电网中断或大面积停电等突发事件,改善风力发电、太阳能发电受季节、气候影响大,发电功率随机性大等诸多因素,储能电站成为较好的解决方案,目前也成为国际、国内相关行业研究的热点。储能电站是由模块化的电池集装箱和变流器集装箱拼接组成。储能电站通常为高压10kV或 35kV接入,需要在变流器集装箱内安装高压隔离变压器,将集装箱分隔一个单独的变压器室,并将高压隔离变压器安装在变压器室。当系统运行时,隔离变压器由于本身的阻抗损耗散发出大量的热量,需要在集装箱内设置强迫风冷风机,将热空气排到变压器室外,并将冷空气带到室内,降低变压器的运行温度。In recent years, in response to emergencies such as grid interruptions or large-scale power outages, and to improve wind power generation, solar power generation is greatly affected by seasons, climate, and power generation randomness and many other factors, energy storage power stations have become a better solution. It has become a hot spot of international and domestic related industry research. The energy storage power station is composed of modular battery containers and converter containers spliced together. The energy storage power station is usually connected to high-voltage 10kV or 35kV. It is necessary to install a high-voltage isolation transformer in the converter container, separate the container into a separate transformer room, and install the high-voltage isolation transformer in the transformer room. When the system is running, the isolation transformer emits a lot of heat due to its own impedance loss. It is necessary to set up a forced air cooling fan in the container to discharge the hot air to the outside of the transformer and bring the cold air indoors to reduce the operating temperature of the transformer.

现有的储能电站,对变压器的冷却多采用变压器室设备门安装通风百叶和过滤网,在设备门对面的墙体上安装强迫排风机。此种冷却方式会造成变压器的迎风面温度较低,背风面温度较高,影响变压器的使用寿命,且经常会造成变压器高温报警。In the existing energy storage power station, the transformer room equipment door is often used to install ventilation louvers and filter screens to cool the transformer, and a forced exhaust fan is installed on the wall opposite to the equipment door. This cooling method will cause the temperature of the windward side of the transformer to be lower and the temperature of the leeward side of the transformer to be higher, which will affect the service life of the transformer and often cause high temperature alarms of the transformer.

实用新型内容Utility model content

有鉴于此,本实用新型旨在提出一种预制式集装箱,以能够对集装箱内的变电站元件进行冷却,以提高变电站元件的使用效果。In view of this, the present utility model aims to provide a prefabricated container, which can cool the components of the substation in the container, so as to improve the use effect of the components of the substation.

为达到上述目的,本实用新型的技术方案是这样实现的:In order to achieve the above object, the technical scheme of the present utility model is achieved in this way:

一种预制式集装箱,用于储装有变电站元件,其特征在于所述预制式集装箱包括:A prefabricated container for storing substation components, characterized in that the prefabricated container includes:

箱体,于所述箱体内形成有腔室,以收容所述变电站元件,并于所述箱体上构造有进风口,于所述箱体的顶部设有出风口;a box body, a cavity is formed in the box body to accommodate the substation components, an air inlet is constructed on the box body, and an air outlet is arranged on the top of the box body;

导流板,设于所述进风口与所述变电站元件之间,以隔开所述变电站元件与所述进风口,并于所述导流板的下部设有导风通道,以引导从所述进风口流入的气流流向所述变电站元件的底部,而于所述腔室内形成冷却通道;A deflector is arranged between the air inlet and the substation element to separate the substation element and the air inlet, and an air guiding channel is arranged at the lower part of the deflector to guide the air from the air inlet. The airflow flowing into the air inlet flows to the bottom of the substation element to form a cooling channel in the chamber;

挡雨部,具有覆盖所述出风口的遮挡面,所述遮挡面位于所述出风口的上方,并与所述箱体间隔设置;The rain shield has a shielding surface covering the air outlet, the shielding surface is located above the air outlet and is spaced from the box body;

驱动部,设于所述冷却通道内,以驱使由所述进风口流入的气流流经所述冷却通道后排出。The driving part is arranged in the cooling channel to drive the airflow flowing in from the air inlet to flow through the cooling channel and then be discharged.

进一步的,于所述变电站元件的外表面与所述腔室以及所述导流板之间围构有间隙通道,并于所述间隙通道内封堵有挡板,以阻挡所述气流直接由所述间隙通道内流出。Further, a gap channel is formed between the outer surface of the substation element, the chamber and the deflector, and a baffle is blocked in the gap channel to prevent the airflow from directly passing through the air flow. outflow in the interstitial channel.

进一步的,所述导流板由所述腔室的顶部向下延伸设置。Further, the baffle plate extends downward from the top of the chamber.

进一步的,于所述导风通道的进风口设有滤芯。Further, a filter element is provided at the air inlet of the air guide channel.

进一步的,对应于所述滤芯,于所述箱体上可拆卸安装有堵盖,以构成对所述滤芯于所述箱体内的封堵。Further, corresponding to the filter element, a blocking cover is detachably installed on the box body to form a blockage of the filter element in the box body.

进一步的,对应于所述滤芯,于所述腔室的底部设有安装槽,所述滤芯的底部安装于所述安装槽内。Further, corresponding to the filter element, an installation groove is provided at the bottom of the chamber, and the bottom of the filter element is installed in the installation groove.

进一步的,所述安装槽的截面成U字形。Further, the cross section of the installation groove is U-shaped.

进一步的,于所述箱体的侧面上开设有安装口,于所述安装口的至少一边的所述箱体上枢转设有安装门,所述安装口可因所述安装门的枢转而开度可调。Further, an installation port is opened on the side of the box body, and an installation door is pivoted on at least one side of the box body of the installation port, and the installation port can be pivoted due to the installation door. The opening is adjustable.

进一步的,于所述进风口处安装有通风百叶。Further, ventilation louvers are installed at the air inlet.

进一步的,在所述出风口处安装有钢网。Further, a steel mesh is installed at the air outlet.

相对于现有技术,本实用新型具有以下优势:Compared with the prior art, the utility model has the following advantages:

(1)本实用新型所述的预制式集装箱,在驱动部的驱使下,由进风口流入的气流可通过导流板流到变电站元件的底部,并向上流经整个变电站元件后由出风口排出,其可提高变电站元件冷却的均匀性,解决因高变电站元件发热量大,局部温度过高而报警并造成系统停机的问题;同时,变电站元件的散热性能的提高,也有利于延长变电站元件的使用寿命。(1) In the prefabricated container of the present invention, driven by the driving part, the air flow from the air inlet can flow to the bottom of the substation element through the deflector, and flow upward through the entire substation element and then be discharged from the air outlet , which can improve the uniformity of the cooling of substation components, and solve the problem of alarming and system shutdown due to high heat generation of substation components and excessive local temperature; service life.

(2)通过在间隙通道内设置挡板,可阻挡由导风通道流入的气流的由间隙通道内流入,从而引导气流由变电站元件的底部流入,并经由整个变电站元件后流出,从而实现对整个变电站元件的散热,有利于提高冷却效率。(2) By arranging baffles in the gap channel, the inflow of the air flow from the air guide channel from the gap channel can be blocked, so as to guide the air flow from the bottom of the substation element to flow out through the entire substation element, so as to realize the flow of the entire substation element. The heat dissipation of the substation components is beneficial to improve the cooling efficiency.

(3)导流板的结构简单,容易安装,并具有较好的导流效果。(3) The structure of the deflector is simple, easy to install, and has a good deflecting effect.

(4)滤芯能够对流入腔室内的空气进行过滤,从而防止因异物飞人,而导致变电站元件发生损坏,进而影响变电站元件的使用安全性。(4) The filter element can filter the air flowing into the chamber, so as to prevent the substation components from being damaged due to the flying of foreign objects, thereby affecting the safety of the substation components.

(5)堵盖可对安装后的滤芯进行保护,并且便于滤芯在腔室内的安装和拆卸。(5) The cover can protect the installed filter element and facilitate the installation and disassembly of the filter element in the chamber.

(6)安装槽的结构简单,能够对滤芯进行固定,提高滤芯的使用效果。(6) The structure of the installation groove is simple, the filter element can be fixed, and the use effect of the filter element can be improved.

(7)安装门的设置,可便于对腔室内的变电站元年进行安装和维修。(7) The setting of the installation door can facilitate the installation and maintenance of the substation in the chamber in the first year.

(8)通风百叶引导气流流入腔室内,并起到一定程度的过滤效果,其结构成熟,使用效果好。(8) The ventilation louver guides the airflow into the chamber, and has a certain degree of filtering effect. Its structure is mature and the use effect is good.

(9)钢网有效防止变电站元年运行过程中,因虫鸟的进入腔室,而导致系统运行中的安全隐患。(9) The steel mesh can effectively prevent the safety hazard in the operation of the system due to the entry of insects and birds into the chamber during the first year of operation of the substation.

附图说明Description of drawings

构成本实用新型的一部分的附图用来提供对本实用新型的进一步理解,本实用新型的示意性实施例及其说明用于解释本实用新型,并不构成对本实用新型的不当限定。在附图中:The accompanying drawings that constitute a part of the present invention are used to provide further understanding of the present invention, and the schematic embodiments and descriptions of the present invention are used to explain the present invention and do not constitute an improper limitation of the present invention. In the attached image:

图1为本实用新型实施例所述的预制式集装箱的结构示意图;FIG. 1 is a schematic structural diagram of a prefabricated container according to an embodiment of the present utility model;

图2为本实用新型实施例所述的通风百叶的结构示意图;Fig. 2 is the structural representation of the ventilation louver described in the embodiment of the present utility model;

图3为本实用新型实施例所述的安装门的结构示意图;3 is a schematic structural diagram of the installation door according to the embodiment of the present utility model;

图4为本实用新型实施例所述的腔室内气流流动的示意图;4 is a schematic diagram of the airflow in the chamber according to the embodiment of the present invention;

附图标记说明:Description of reference numbers:

1-箱体,101-进风口,102-出风口;1-box, 101-air inlet, 102-air outlet;

2-挡雨罩,3-轴流风机,4-电池集装箱,5-变压器,6-滤芯,7-挡板,8-导流板,9-安装门,10-通风百叶。2-rain shield, 3-axial flow fan, 4-battery container, 5-transformer, 6-filter element, 7-baffle plate, 8-deflector, 9-installation door, 10-ventilation louver.

具体实施方式Detailed ways

需要说明的是,在不冲突的情况下,本实用新型中的实施例及实施例中的特征可以相互组合。It should be noted that the embodiments of the present invention and the features of the embodiments may be combined with each other under the condition of no conflict.

下面将参考附图并结合实施例来详细说明本实用新型。The present utility model will be described in detail below with reference to the accompanying drawings and in conjunction with the embodiments.

本实施例涉及一种预制式集装箱,用于储装有变电站元件,该预制式集装箱包括箱体1,如图1中所示的,在箱体1内形成有腔室,变电站元件收容在腔室内,并在箱体1的一侧构造有进风口101,在箱体1的顶部构造有出风口 102。其中,本实施例所述的变电站元件安为高压隔离变压器5,另外,在箱体1的一侧还拼接安装有电池集装箱4,以用于收容电池模组。This embodiment relates to a prefabricated container for storing substation components. The prefabricated container includes a box body 1. As shown in FIG. 1, a cavity is formed in the box body 1, and the substation components are accommodated in the cavity. In the room, an air inlet 101 is formed on one side of the box body 1 , and an air outlet 102 is formed on the top of the box body 1 . Among them, the substation components described in this embodiment are installed as high-voltage isolation transformers 5, and in addition, a battery container 4 is spliced and installed on one side of the box body 1 for accommodating battery modules.

相对于电池集装箱4,前述的进风口101设置在箱体1的另一侧,为了提高气流的流入效果,本实施例中,在进风口101处安装有通风百叶10,且通风百叶10的安装方式如图2中所示,此处,通风百叶10的结构成熟,安装和使用效果较好,可引导气流流向腔室的底部。Compared with the battery container 4, the aforementioned air inlet 101 is arranged on the other side of the box body 1. In order to improve the inflow effect of airflow, in this embodiment, a ventilation louver 10 is installed at the air inlet 101, and the ventilation louver 10 is installed. The method is shown in FIG. 2 , where the ventilation louver 10 has a mature structure, good installation and use effects, and can guide the airflow to the bottom of the chamber.

为提高气流对变电压器的冷却效果,在进风口101与变压器5之间设有导流板8,以隔开进风口101和变压器5,并在导流板8的下部设有导风通道,以引导从进风口101流入的气流流向变压器5的底部,而于腔室内形成冷却通道。具体结构上,如图1中所示,前述的导流板8由腔室的顶部向下延伸设置,且其自由端与腔室底部形成有间隙,即导风通道。如此设置可实现将气流引流到变压器5的底部,从而有利于对变压器5进行降温。In order to improve the cooling effect of the air flow on the transformer, a deflector 8 is provided between the air inlet 101 and the transformer 5 to separate the air inlet 101 and the transformer 5, and an air guiding channel is arranged at the lower part of the deflector 8 , so as to guide the air flow from the air inlet 101 to the bottom of the transformer 5 to form a cooling channel in the cavity. In terms of specific structure, as shown in FIG. 1 , the aforesaid deflector 8 extends downward from the top of the chamber, and a gap is formed between its free end and the bottom of the chamber, that is, an air guide channel. With such arrangement, the airflow can be led to the bottom of the transformer 5 , which is beneficial to the cooling of the transformer 5 .

另外,为了防止气流中的异物飞入变压器5内,而影响变压器5的工作,本实施例中,在导流通道的左侧安装有滤芯6,而为了便于对滤芯6进行安装和拆卸,对应于滤芯6,在箱体1的前侧面上设有滤芯6安装通孔,且安装通孔的形状与滤芯6的厚度方向上的形状相适配,滤芯6可通过安装通孔安装在腔室内。同时,为了提高滤芯6在腔室内的固定效果,本实施例中,在腔室的底部安装有安装槽,该安装槽的截面成U字形,滤芯6的底部可安装在安装槽内进行固定。In addition, in order to prevent foreign objects in the airflow from flying into the transformer 5 and affecting the operation of the transformer 5, in this embodiment, a filter element 6 is installed on the left side of the diversion channel, and in order to facilitate the installation and removal of the filter element 6, the corresponding For the filter element 6, a through hole for the filter element 6 is provided on the front side of the box body 1, and the shape of the installation through hole is adapted to the shape of the filter element 6 in the thickness direction, and the filter element 6 can be installed in the chamber through the installation through hole. . At the same time, in order to improve the fixing effect of the filter element 6 in the chamber, in this embodiment, a mounting groove is installed at the bottom of the chamber, the cross-section of the mounting groove is U-shaped, and the bottom of the filter element 6 can be installed in the mounting groove for fixing.

另外,此处的滤芯6并沿箱体1的宽度方向延伸布置,以覆盖整个导风通道的气流进入端,最大程度的起到过滤的效果。此外,滤芯6便于拆卸后进行清洗,也有利于滤芯6的反复利用。In addition, the filter element 6 here is extended and arranged along the width direction of the box body 1 to cover the airflow entry end of the entire air guide channel, and to maximize the filtering effect. In addition, the filter element 6 is easy to be disassembled and cleaned, which is also beneficial to the repeated use of the filter element 6 .

为了使冷却通道内的气流仅仅流经变压器5,最大程度的提高冷却效率,本实施例中,在变压器5的外表面与腔室以及导流板8之间围构有间隙通道,并在间隙通道内封堵有挡板7,以阻挡气流直接由间隙通道内流出。在此值得注意的是,挡板7采用耐高压的绝缘材料制成。In order to make the airflow in the cooling channel only flow through the transformer 5 and maximize the cooling efficiency, in this embodiment, a gap channel is formed between the outer surface of the transformer 5 and the cavity and the guide plate 8, and a gap channel is formed in the gap. A baffle 7 is blocked in the channel to prevent the airflow from directly flowing out of the gap channel. It is worth noting here that the baffle 7 is made of a high-voltage-resistant insulating material.

通过挡板7和导流板8的设置,实现了气流仅流过变压器5,进而最大程度的实现对变压器5的冷却效果,器结构简单,使用方便。Through the arrangement of the baffle 7 and the deflector 8 , the airflow only flows through the transformer 5 , thereby maximizing the cooling effect on the transformer 5 . The device has a simple structure and is easy to use.

前述的预制式集装箱还包括挡雨部,该挡雨部具有覆盖出风口102的遮挡面,遮挡面位于出风口102的上方,并与箱体1间隔设置。基于挡雨部的设计思想,并结合图1图2中所示,本实施例中的挡雨部为设置在出风口102上方的挡雨罩2,可防止下雨时,雨水可经由出风口102流入到腔室内,引发安全事故。此外,在出风口102处安装有钢网,以防止箱体1外虫鸟的进入到腔室内,造成系统运行安全问题。The aforementioned prefabricated container further includes a rain shield, the rain shield has a shielding surface covering the air outlet 102 , and the shielding surface is located above the air outlet 102 and is spaced from the box 1 . Based on the design idea of the rain shield and in combination with FIG. 1 and FIG. 2 , the rain shield in this embodiment is the rain shield 2 arranged above the air outlet 102 , which can prevent rainwater from passing through the air outlet when it rains. 102 flows into the chamber, causing a safety accident. In addition, a steel mesh is installed at the air outlet 102 to prevent insects and birds from outside the box body 1 from entering the chamber, thereby causing a safety problem in the operation of the system.

在使用时,按照变压器5的通风换气量,考虑箱体1进风口101实际的通风面积,计算出穿过通风百叶10的实际风速,选择挡雨罩2,在具备145MPH 的风速下,有效防止雨水的能力,即可满足IPx4的要求。When in use, according to the ventilation volume of the transformer 5 and considering the actual ventilation area of the air inlet 101 of the box 1, the actual wind speed passing through the ventilation louvers 10 is calculated, and the rain cover 2 is selected. The ability to prevent rain can meet the requirements of IPx4.

前述的预制式集装箱还包括驱动部,该驱动部设于冷却通道内,以驱使由进风口101流入的气流流经冷却通道后排出,具体来讲,如图1中所示,本实施例中的驱动部为轴流风机3,且轴流风机3为靠近出风口102,安装在腔室内的两台,以提高整个气流的空气流量,实现强制通风冷却的目的。The aforementioned prefabricated container also includes a driving part, the driving part is arranged in the cooling channel, so as to drive the airflow flowing in from the air inlet 101 to flow through the cooling channel and then be discharged. Specifically, as shown in FIG. 1 , in this embodiment, the The driving part is the axial flow fan 3, and the axial flow fan 3 is close to the air outlet 102 and installed in the chamber to improve the air flow of the entire airflow and achieve the purpose of forced ventilation and cooling.

除此之外,参照图3,在箱体1的侧面上开设有安装口,变压器5可通过安装口安装在腔室内。本实施例中在安装口左右两边的箱体1上分别枢转设有安装门9,使得安装口可因两安装门9的枢转而开度可调。Besides, referring to FIG. 3 , an installation opening is opened on the side surface of the box body 1 , and the transformer 5 can be installed in the cavity through the installation opening. In this embodiment, installation doors 9 are respectively pivoted on the box body 1 on the left and right sides of the installation opening, so that the opening of the installation opening can be adjusted due to the pivoting of the two installation doors 9 .

结合图4,本实施例所述的预制式集装箱,在轴流风机3的驱使下,由进风口101流入的气流可通过导流板8和滤芯6流到变压器5的底部,并在挡板 7的作用下向上流经整个变压器5后由出风口102排出,其可提高变电站元件冷却的均匀效果,解决因高变电站元件发热量大,局部温度过高而报警并造成系统停机的问题;同时,变电站元件的散热性能的提高,也有利于延长变电站元件的使用寿命。4, in the prefabricated container described in this embodiment, driven by the axial flow fan 3, the air flow from the air inlet 101 can flow to the bottom of the transformer 5 through the deflector 8 and the filter element 6, and is at the bottom of the baffle plate. Under the action of 7, it flows upward through the entire transformer 5 and then is discharged from the air outlet 102, which can improve the uniform effect of cooling the components of the substation, and solve the problem of alarming and system shutdown due to the high heat generation of the components in the high substation and the high local temperature; , The improvement of the heat dissipation performance of the substation components is also beneficial to prolong the service life of the substation components.

以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the within the scope of protection of the present invention.

Claims (10)

1. a kind of prefabricated container has substation's element for saving, it is characterised in that the prefabricated container includes:
Cabinet (1), Yu Suoshu cabinet (1) is interior to be formed with chamber, to accommodate substation's element, and on the cabinet (1) It is configured with air inlet (101), the top of Yu Suoshu cabinet (1) is equipped with air outlet (102);
Deflector (8), be set between the air inlet (101) and substation's element, with separate substation's element and The air inlet (101), and it is equipped with air-guiding aisle in the lower part of the deflector (8), it is flowed with guidance from the air inlet (101) The bottom of substation's element described in the air flow direction entered, and in forming cooling duct in the chamber;
It keeps off the rain portion, there is the shielding surface for covering the air outlet (102), the shielding surface is located at the upper of the air outlet (102) Side, and be spaced and be arranged with the cabinet (1);
Driving portion is set in the cooling duct, logical to drive the air-flow flowed by the air inlet (101) to flow through the cooling It is discharged behind road.
2. prefabricated container according to claim 1, it is characterised in that: the outer surface of Yu Suoshu substation element and institute It states and encloses structure between chamber and the deflector (8) and have a clearance channel, and have baffle (7) in blocking in the clearance channel, with Stop the air-flow directly by flowing out in the clearance channel.
3. prefabricated container according to claim 1, it is characterised in that: the deflector (8) by the chamber top Portion extends downwardly setting.
4. prefabricated container according to claim 1, it is characterised in that: the air inlet (101) of Yu Suoshu air-guiding aisle Equipped with filter core (6).
5. prefabricated container according to claim 4, it is characterised in that: correspond to the filter core (6), Yu Suoshu cabinet (1) blanking cover is detachably installed, to constitute to the closure in the filter core (6) Yu Suoshu cabinet (1) on.
6. prefabricated container according to claim 4, it is characterised in that: correspond to the filter core (6), Yu Suoshu chamber Bottom be equipped with mounting groove, the bottom of the filter core (6) is installed in the mounting groove.
7. prefabricated container according to claim 6, it is characterised in that: the section of the mounting groove is at U-shaped.
8. prefabricated container according to claim 1, it is characterised in that: offered on the side of Yu Suoshu cabinet (1) Installing port pivots on the cabinet (1) at least one side of Yu Suoshu installing port and is equipped with installation door (9), and the installing port can be because The pivot of the installation door (9) and aperture is adjustable.
9. prefabricated container according to claim 1, it is characterised in that: be equipped at Yu Suoshu air inlet (101) logical Wind blinds (10).
10. prefabricated container according to any one of claim 1 to 9, it is characterised in that: in the air outlet (102) steel mesh is installed at.
CN201822213568.8U 2018-12-26 2018-12-26 prefabricated container Active CN209298712U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822213568.8U CN209298712U (en) 2018-12-26 2018-12-26 prefabricated container

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822213568.8U CN209298712U (en) 2018-12-26 2018-12-26 prefabricated container

Publications (1)

Publication Number Publication Date
CN209298712U true CN209298712U (en) 2019-08-23

Family

ID=67649134

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822213568.8U Active CN209298712U (en) 2018-12-26 2018-12-26 prefabricated container

Country Status (1)

Country Link
CN (1) CN209298712U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110676726A (en) * 2019-09-24 2020-01-10 特变电工湖南电气有限公司 Water photovoltaic substation and its substation box
CN115347489A (en) * 2022-07-20 2022-11-15 国网江苏省电力有限公司灌云县供电分公司 A substation with intelligent cooling function

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110676726A (en) * 2019-09-24 2020-01-10 特变电工湖南电气有限公司 Water photovoltaic substation and its substation box
CN115347489A (en) * 2022-07-20 2022-11-15 国网江苏省电力有限公司灌云县供电分公司 A substation with intelligent cooling function

Similar Documents

Publication Publication Date Title
CN210468539U (en) Indoor ventilation system of transformer substation
CN209298712U (en) prefabricated container
CN103533813A (en) High-heat-dissipation generating set box body
CN114867314B (en) GIS cabinet applied to precise air supply control
CN204189047U (en) Electric power outdoor cabinet temperature control system
CN203326425U (en) Dustproof heat-dissipating box transformer substation for wind electricity
CN208923607U (en) A box-type substation that prevents blockage of heat dissipation ports
CN112713510A (en) Safety protection device for electric power system
CN207459494U (en) A kind of bottom for switchgear is into common case guide type the forced air cooling
CN207926025U (en) A kind of ventilation device for European-type box substation
CN206401765U (en) A kind of separation radiator structure of high-tension switch cabinet
CN205355605U (en) Ventilation cooling structure of container of integrated electrical equipment cabinet
CN213151400U (en) Transformer control box with heat dissipation fire extinguishing function
CN212011893U (en) Box-type substation with uniform heat dissipation
CN213584703U (en) Novel safe and reliable high-low voltage switch cabinet
CN207165995U (en) Double case becomes charging equipment
CN218733869U (en) Outdoor frequency converter
CN213878942U (en) European box transformer substation with strong ventilation performance
CN221176487U (en) Non-walk-in energy storage container
CN206379654U (en) A kind of outdoor integrated distribution box
CN111900640A (en) Outdoor power distribution cabinet
CN218096429U (en) Air purification device capable of supplying air in multiple directions
CN217769255U (en) Semi-buried prefabricated box-type substation
CN217844240U (en) Energy consumption control device for cooling tower of high-efficiency cold station refrigeration system
CN221530748U (en) Ventilation structure, regulator cubicle and energy storage container

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No.8899 Xincheng Avenue, Jintan District, Changzhou City, Jiangsu Province

Patentee after: SVOLT Energy Technology Co.,Ltd.

Country or region after: China

Address before: 213200 168 Huacheng Road, Jintan District, Changzhou, Jiangsu

Patentee before: SVOLT Energy Technology Co.,Ltd.

Country or region before: China