CN209228070U - A kind of innovative panellised wall installs the operating platform - Google Patents
A kind of innovative panellised wall installs the operating platform Download PDFInfo
- Publication number
- CN209228070U CN209228070U CN201821745157.7U CN201821745157U CN209228070U CN 209228070 U CN209228070 U CN 209228070U CN 201821745157 U CN201821745157 U CN 201821745157U CN 209228070 U CN209228070 U CN 209228070U
- Authority
- CN
- China
- Prior art keywords
- operating platform
- installs
- shingle nail
- innovative panellised
- fixture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model relates to a kind of innovative panellised walls to install the operating platform, including steel column, purlin, operating platform, shingle nail and boom hoist cable, it is linked together between the steel column by purlin and forms building sides, the side of building sides is erected with operating platform, the bottom of the operating platform is equipped with lower margin pulley, and Overthrow preventing device is respectively set with middle part at the top of operating platform, the bottom of the shingle nail is installed by collet, the top installs fixture of shingle nail, fixed pulley is installed at the top of the operating platform, the bottom of operating platform is equipped with bottle gouard moved by hands, passing through on bottle gouard moved by hands has boom hoist cable, the other end of the boom hoist cable is connected on collet around the fixture on fixed pulley pass through wall surface plate.The utility model construction safety, can guarantee indeformable in wallboard installation process, reduce the effect of construction cost.
Description
Technical field
The utility model relates to build constructing technology field, installed the operating platform more particularly, to a kind of innovative panellised wall.
Background technique
Since wallboard weight is larger, intensity is insufficient, and in addition on-site construction road is narrow, the total cost of incorporation engineering, work
Phase and actual situations of construction, according to the installation method of conventional manual's lifting, wallboard is easily broken, leads to not sling installation;If adopting
With automobile crane operation, construction operation is difficult to operate, and the economic benefit is not high, and in addition the duration opposite will extend.
The Chinese patent that existing Authorization Notice No. is CN203359889 discloses a kind of wallboard and is promoted and installation integration behaviour
Make platform comprising mobile door-type scaffold, hoist engine, guide wheel, wirerope, suspension hook and clump weight, clump weight, hoist engine are set to
Mobile door-type scaffold bottom, guide wheel are set at the top of mobile door-type scaffold, and wirerope passes through guide wheel, and one end is connect with hoist engine,
Other end suspension hook.Using means of transport by by conveying sheet to mobile door-type scaffold side, pass through suspension hook using hoist engine
By plate with regard to mentioning on the ground, plate dropping place to installation point is corrected fixation by hand fit, in this way, facilitate the installation of plate,
Operation in place, in this way, the installation for wallboard provides convenience.
Prior art among the above has the following deficiencies: 1, when plate wallboard weight is excessive, and clump weight can not reach
To the effect for pushing down mobile door-type scaffold, it is easy to cause the generation for the contingencies such as scaffold collapses;2, only using suspension hook into
Row promotes wallboard, not can guarantee wallboard vertical ascent, not easy to install;3, it is easy to cause wallboard to fracture.
Utility model content
The purpose of the utility model is to provide a kind of innovative panellised walls to install the operating platform, with construction safety, Neng Goubao
It is indeformable in card wallboard installation process, reduce the effect of construction cost.
The above-mentioned purpose of utility model of the utility model has the technical scheme that
A kind of innovative panellised wall installs the operating platform, including steel column, purlin, operating platform, shingle nail and boom hoist cable, institute
It states to link together between steel column by purlin and forms building sides, the side of building sides is erected with operating platform, and the operation is flat
The bottom of platform is equipped with lower margin pulley, and Overthrow preventing device, the bottom of the shingle nail is respectively arranged with middle part at the top of operating platform
Collet is installed, the top installs fixture of shingle nail is equipped with fixed pulley, the bottom peace of operating platform at the top of the operating platform
Equipped with bottle gouard moved by hands, passing through on bottle gouard moved by hands has boom hoist cable, and the other end of the boom hoist cable passes through wall around fixed pulley
Fixture on panel is connected on collet.
By using above-mentioned technical proposal, operating platform is fixed on building sides side using Overthrow preventing device, pulling mentions
Reinforcing bar rope is risen, lifting reinforcing bar rope slowly pulls collet under the action of bottle gouard moved by hands, so that being mounted on the metope on collet
Plate is slowly promoted, and when shingle nail is promoted to scheduled height, is fixed on shingle nail along purlin, is then removed wall
Collet and fixture on panel promote and fix in the same way second piece of shingle nail, second piece of shingle nail side edge
Snapping, elevation line alignment, left and right alignment, adjustment plate surface evenness, such one piece one piece of installation, until factory are used with the 1st block of plate
After the wallboard of one side elevation of room is installed, uniformly does dado and bear down on one.
The utility model is further arranged to: the operating platform is the Slidable space being assembled by upright bar and cross bar
Truss structure, and operating platform longitudinal direction is provided with vertical bracing every three steps.
By using above-mentioned technical proposal, facilitate the installation and disassembly of operating platform, and the setting of vertical bracing makes
Whole device it is more stable, safety is higher.
The utility model is further arranged to: the lower margin pulley is specially two-way lower margin pulley, and is set on lower margin pulley
It is equipped with braking service brake.
By using above-mentioned technical proposal, guarantee that braking service brake is in tight shape of stopping before operating platform sliding and after in place
State guarantees the personal safety of construction personnel, and enable to metope to guarantee that operating platform will not just moved in the course of work
The positioning of plate is more accurate, improves construction efficiency.
The utility model is further arranged to: the Overthrow preventing device includes safe steel wire steel tube fastener, operating platform
Two sides steel column is snapped with steel tube fastener, and the both ends of safety steel cable are connected on steel tube fastener, and safety steel cable is trapped among behaviour
Make on the outside of platform.
By using above-mentioned technical proposal, prevent whole operation platform from toppling over, and safety steel cable can be flat with operation
The movement of platform and slide on the operational platform, guarantee safety in the case where do not influence construction efficiency.
The utility model is further arranged to: the shingle nail is fastened on purlin by self-tapping screw.
By using above-mentioned technical proposal, guaranteeing that shingle nail is fastened on building sides will not loosen.
The utility model is further arranged to: the setting of two sides at the top of the shingle nail is set on the fixture there are two fixture
It is equipped with through-hole, boom hoist cable is divided into the through-hole that two are each passed through two fixtures above shingle nail and is connected on collet.
By using above-mentioned technical proposal, front panel is promoted in the case where enabling boom hoist cable to pull collet, and
Collet can be dismantled very easily with fixture, convenient for the installation of next piece of shingle nail, promote working efficiency.
The utility model is further arranged to: the cross bar is connected using sleeve couple, sleeve couple interlaced arrangement, up and down
The spreading position of upright bar is staggeredly arranged.
By using above-mentioned technical proposal, so that whole operation platform is more firm, security performance is improved.
The utility model is further arranged to: it is equipped with bamboo sheathing scaffold board on the operating platform, the four of bamboo sheathing scaffold board
Guardrail, staircase and safety net are installed in week.
By using above-mentioned technical proposal, guardrail and safety net can prevent from worker from slipping during the work time falling, help
Ladder can facilitate on the operational platform up and down.
In conclusion the advantageous effects of the utility model are as follows:
1, installation quality is greatly improved, guarantees that plate is indeformable in installation process, it is ensured that installation verticality, flatness;
2, Overthrow preventing device can be avoided operating platform and collapse, and improve the safety of construction, can avoid crosshead collapsing, people
Member such as falls at the generations of accidents;
3, by manually with mechanical bond in the way of operated, reduce construction cost, reduce plate fracture;
4, operating platform integral installation method is simple, quickly grasps convenient for construction personnel, to accelerate construction progress.
Detailed description of the invention
Fig. 1 is that a kind of innovative panellised wall of the utility model installs the operating platform front schematic view;
Fig. 2 is that a kind of innovative panellised wall of the utility model installs the operating platform sectional view;
Fig. 3 is that a kind of innovative panellised wall of the utility model installs the operating platform top view.
In figure, 1, steel column;2, purlin;3, operating platform;4, shingle nail;5, boom hoist cable;6, Overthrow preventing device;7, bottom
Support;8, fixture;9, bottle gouard moved by hands;10, fixed pulley;11, lower margin pulley;12, safety steel cable.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
A kind of innovative panellised wall disclosed by the utility model installs the operating platform, referring to Fig.1 comprising operating platform 3 and builds
Face is built, operating platform 3 is mounted on the side of building sides, steel column 1 and purlin 2 are provided on building sides, in the present embodiment, adjacent
It is connected between steel column 1 by purlin 2.
Referring to Figures 1 and 2,3 bottom of operating platform is equipped with lower margin pulley 11, and the top of operating platform 3, which is equipped with, determines cunning
Wheel 10, in the present embodiment, lower margin pulley 11 are specially two-way lower margin pulley 11, and are provided with brake shoe on lower margin pulley 11
It stops.
Referring to Fig.1, shingle nail 4 is mounted on collet 7, and the top of shingle nail 4 is equipped with fixture 8, in the present embodiment,
Through-hole is provided on fixture 8.
Referring to Figures 1 and 2,3 bottom of operating platform is provided with bottle gouard moved by hands 9, and passing through on bottle gouard moved by hands 9 has lifting steel wire
Rope, the lifting wirerope are connected on collet 7 around the through-hole for passing through fixture 8 after fixed pulley 10.In the present embodiment, pulling mentions
Wirerope 5 is risen so that boom hoist cable 5 mentions shingle nail 4 vertically in the effect promotion collet 7 of chain block
It rises.
Referring to Fig.1, the outside of operating platform 3 is provided with Overthrow preventing device 6, in the present embodiment, the two of Overthrow preventing device 6
End is connected on steel column 1.
Referring to Fig.1, the operating platform 3 is the Slidable space truss structure being assembled by upright bar and cross bar, and is grasped
Make 3 longitudinal direction of platform and three steps are provided with vertical bracing, in the present embodiment, cross bar is connected using sleeve couple, to buckle
Part interlaced arrangement, the connector of two adjacent crossbars should not be arranged in it is synchronous or with across interior, it is asynchronous or different adjacent across two
The distance that head is staggered in the horizontal direction is no less than 500mm;The distance of each connector center to nearest host node is not preferably greater than advance
1/3.The spreading position of upper sheer pole is staggeredly arranged, and the distance that is staggered is not less than the 1/3 of advance.The lap of splice is not less than 1m,
And 3 rotary buckles of spaced set are fixed.
Referring to Fig.1, be equipped with bamboo sheathing scaffold board on operating platform 3, the surrounding of bamboo sheathing scaffold board be equipped with guardrail, staircase and
Safety net.
Referring to Fig. 3, Overthrow preventing device 6 includes safety steel cable 12 and steel tube fastener, and the two sides steel column 1 of operating platform 3 is equal
It is snapped with steel tube fastener, the both ends of safety steel cable 12 are connected on steel tube fastener, and safety steel cable 12 is trapped among operating platform 3
Outside, in the present embodiment, safety steel cable 12 are constantly in light tension, it is ensured that when oblique pull wallboard, will not topple.
Referring to Fig.1, shingle nail 4 is fastened on purlin 2 by self-tapping screw.
The implementation principle of the present embodiment are as follows: when needing to carry out the installation of shingle nail 4, carry out setting up for operating platform 3, benefit first
The Slidable space truss structure being assembled into upright bar and cross bar, is then equipped with bamboo sheathing scaffold board, bamboo on operating platform 3
The surrounding of basketry scaffold board is equipped with guardrail, staircase and safety net, is connected to the steel pipe on steel column 1 followed by safety steel cable 12
Overthrow preventing device 6 is made on fastener, Overthrow preventing device 6 is wound on 3 outside of operating platform, puts 4 bottom of shingle nail into collet 7 at this time
Interior, 4 top installs fixture 8 of shingle nail passes through fixture 8 using boom hoist cable 5 at this time and is connected on collet 7, boom hoist cable 5
The other end be connected in bottle gouard moved by hands 9 around fixed pulley 10, boom hoist cable 5 is manually pulled at this time, in the work of bottle gouard moved by hands 9
With lower slow promotion shingle nail 4, shingle nail 4 is promoted to after predetermined position, artificial to carry out sideline alignment, checks plate face flatness,
Be adjusted to after meeting the requirements, fixed along purlin 2 with self-tapping screw on shingle nail 4, at this time by front panel fixture 8 and bottom
Support 7 removes, and unclamps after boom hoist cable 5 falls collet 7 and fixture 8 and installs second piece of shingle nail 4, mentions in the same way
Second piece of shingle nail 4 is risen and fixes, second piece of 4 side of shingle nail uses snapping, elevation line alignment, left and right along with the 1st block of plate
Alignment, adjustment plate surface evenness, such one piece one piece of installation, until uniformly being done after the wallboard of one side elevation of workshop is installed
Dado bears down on one.
The embodiment of present embodiment is the preferred embodiment of the utility model, and not limitation is originally practical new according to this
The protection scope of type, therefore: the equivalence changes that all structures, shape, principle according to the utility model are done should all be covered by practical
Within novel protection scope.
Claims (8)
1. a kind of innovative panellised wall installs the operating platform, including steel column (1), purlin (2), operating platform (3), shingle nail (4) and mention
It rises wirerope (5), is linked together between the steel column (1) by purlin (2) and form building sides, the side of building sides is erected with
Operating platform (3), it is characterised in that: the bottom of the operating platform (3) is equipped with lower margin pulley (11), and operating platform (3)
Top and middle part are respectively arranged Overthrow preventing device (6), and collet (7) are installed in the bottom of the shingle nail (4), the top of shingle nail (4)
Installs fixture (8) is equipped with fixed pulley (10) at the top of the operating platform (3), and the bottom of operating platform (3) is equipped with manually
Cucurbit (9), across there is boom hoist cable (5) on bottle gouard moved by hands (9), the other end of the boom hoist cable (5) bypasses fixed pulley
(10) fixture (8) on pass through wall surface plate (4) is connected on collet (7).
2. a kind of innovative panellised wall according to claim 1 installs the operating platform, it is characterised in that: the operating platform (3)
The Slidable space truss structure being assembled by upright bar and cross bar, and operating platform (3) be longitudinally provided with every three steps it is vertical
Scissors straight support.
3. a kind of innovative panellised wall according to claim 1 installs the operating platform, it is characterised in that: the lower margin pulley (11)
Specially two-way lower margin pulley (11), and braking service brake is provided on lower margin pulley (11).
4. a kind of innovative panellised wall according to claim 1 installs the operating platform, it is characterised in that: the Overthrow preventing device
It (6) include safety steel cable (12) and steel tube fastener, the two sides steel column (1) of operating platform (3) is snapped with steel tube fastener, safety
The both ends of wirerope (12) are connected on steel tube fastener, and safety steel cable (12) is trapped among on the outside of operating platform (3).
5. a kind of innovative panellised wall according to claim 1 installs the operating platform, it is characterised in that: the shingle nail (4) is logical
Self-tapping screw is crossed to be fastened on purlin (2).
6. a kind of innovative panellised wall according to claim 1 installs the operating platform, it is characterised in that: shingle nail (4) top
There are two the two sides settings in portion fixture (8), is provided with through-hole on the fixture (8), boom hoist cable (5) is above shingle nail (4)
It is divided into the through-hole that two are each passed through two fixtures (8) to be connected on collet (7).
7. a kind of innovative panellised wall according to claim 2 installs the operating platform, it is characterised in that: the cross bar is using docking
Fastener connection, the spreading position of sleeve couple interlaced arrangement, upper and lower upright bar is staggeredly arranged.
8. a kind of innovative panellised wall according to claim 1 installs the operating platform, it is characterised in that: the operating platform (3)
On be equipped with bamboo sheathing scaffold board, the surrounding of bamboo sheathing scaffold board is equipped with guardrail, staircase and safety net.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821745157.7U CN209228070U (en) | 2018-10-25 | 2018-10-25 | A kind of innovative panellised wall installs the operating platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821745157.7U CN209228070U (en) | 2018-10-25 | 2018-10-25 | A kind of innovative panellised wall installs the operating platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209228070U true CN209228070U (en) | 2019-08-09 |
Family
ID=67500869
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821745157.7U Active CN209228070U (en) | 2018-10-25 | 2018-10-25 | A kind of innovative panellised wall installs the operating platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209228070U (en) |
-
2018
- 2018-10-25 CN CN201821745157.7U patent/CN209228070U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106958346B (en) | Intelligent attached lifting scaffold equipment for curved surface super high-rise building and construction method | |
CN201506699U (en) | Electric lifting bridge rack for construction | |
CN201826525U (en) | Climbing shuttering system device for buildings | |
CN206053274U (en) | The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose | |
CN111021749A (en) | Simple hoisting mechanism for bare concrete exterior wall cladding and construction method thereof | |
CN116136122A (en) | Integrated attached type inclined lifting climbing frame system and use method thereof | |
CN209703984U (en) | A kind of high-altitude mobile security platform for structure for steel structure roof inner slab installation | |
JP2006299559A (en) | Self climbing scaffold and self climbing method by use of it | |
CN209228070U (en) | A kind of innovative panellised wall installs the operating platform | |
CN213418443U (en) | Self-climbing type elevator shaft operation platform | |
CN113062584A (en) | Multipoint elevator shaft construction lifting platform and construction method | |
CN209568688U (en) | A kind of elevating construction platform | |
CN111851982A (en) | Scaffold frame liftable prevents weighing down safety device | |
CN110817709A (en) | High-rise tower crane driver climbing device | |
CN211923574U (en) | Construction device for constructing top floor of building | |
CN113120785A (en) | Safety device attached to climbing frame for people on tower crane | |
CN208648493U (en) | A kind of no scaffold installation elevator operation platform device | |
CN2209702Y (en) | Saffold | |
CN210655915U (en) | Connecting device for climbing frame and tower crane | |
CN216196742U (en) | A wallboard installation device for position is striden to height | |
CN112376885A (en) | Track climbing type integral building construction scaffold convenient to disassemble | |
CN220393054U (en) | Unit plate lifting carrier suitable for circular rail curtain wall | |
CN210857952U (en) | Novel attached lifting scaffold | |
CN205933127U (en) | Erection equipment of various steel inner panel in factory building roof | |
CN219118718U (en) | Climbing frame horizontal protection |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |