Prior art keywords
hydraulic pressure
water
booster pump
supply system
secondary water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821491383.7U
Other languages
Chinese (zh)
Inventor
薛金山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Youchainjia (chongqing) Technology Co Ltd
Original Assignee
Youchainjia (chongqing) Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Youchainjia (chongqing) Technology Co Ltd filed Critical Youchainjia (chongqing) Technology Co Ltd
Priority to CN201821491383.7U priority Critical patent/CN209162930U/en
Application granted granted Critical
Publication of CN209162930U publication Critical patent/CN209162930U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Control Of Positive-Displacement Pumps (AREA)

Abstract

Energy saver based on secondary water supply system pipeline tip hydraulic pressure, with Switching Power Supply, hydraulic pressure probe, one-chip computer module, data transmitting equipment, separate unit booster pump, subassembly wrapper, second control power output end of PLC is connected with small-power separate unit booster pump power input by conducting wire, connecting tube is mounted on user pipe tip extreme higher position side tapping, Switching Power Supply, hydraulic pressure probe, one-chip computer module, data transmitting equipment are mounted in subassembly wrapper and connect through conducting wire, and hydraulic pressure probe, connecting tube are inserted into connection hose both ends respectively.The utility model is equipped with hydraulic pressure probe in user pipe tip extreme higher position, guarantee that tip pressure is constant, with water ebb section, guarantee supply equipment water outlet in hydraulic pressure during water use peak 85% setting pressure, and only pass through a pressurization pump work it is ensured that hydraulic pressure needs in user pipe, reach energy saving purpose, while improving low pressure water spot user with water comfort, moreover it is possible to prevent booster pump frequent start-stop from leading to waste of energy and damage.

Description

Energy saver based on secondary water supply system pipeline tip hydraulic pressure
Technical field
The utility model relates to secondary water-supply apparatus fields, especially a kind of to be based on secondary water supply system pipeline tip hydraulic pressure Energy saver.
Background technique
In secondary water supply system, existing no negative pressure skyscraper secondary water-supply equipment working method is all in associated mechanisms Under effect, after the low pressure tap water of input is pressurized by the booster pump being mounted between inlet and outlet pipes, Resident's pipeline is then input to enable users to just commonly use water.After hydraulic pressure reaches the pressure value of setting in resident's pipeline in order to prevent, The booster pump of secondary water-supply equipment, which works always, causes one side hydraulic pressure of user pipe excessively high, and prevents the increasing of secondary water-supply equipment Press pump, which works always, causes waste of energy and damage, and the control system of secondary water-supply equipment can be according to the water of user pipe side The working condition of the pressure data control booster pump for being input to secondary water-supply apparatus control system host computer press, detected, when When being input to the hydraulic pressure of user pipe more than the numerical value that upper computer control system is arranged, host computer controls booster pump through PLC module Power failure work, when being input to the hydraulic pressure of user pipe lower than the numerical value that upper computer control system is arranged, host computer is through PLC module Booster pump work once electrified is controlled, so that the hydraulic pressure of user pipe side be made to be maintained at stable state.
In fact, since user's evening water consumption is few, hydraulic pressure needed for pipeline is lower than water use peak in secondary water supply system (such as water use peak on daytime phase supply equipment water outlet hydraulic pressure 1.2MPa, it is ensured that uppermost storey occupies can be used normally in phase Domestic use of water, then with water low peak period supply equipment water outlet pipeline hydraulic pressure 1.05MPa or so, due to user's water flow and pressure It is small, it is ensured that uppermost storey urbanite water consumption);But due to existing secondary water supply system user pipe hydraulic pressure number collected According to from the user pipe pressure sensor adjacent with booster pump, pressure sensor is unable to actual response user pipe least significant end Hydraulic pressure, and existing secondary water supply system setting operating mode be exactly no matter water use peak phase or slack hours section, One side hydraulic pressure of water outlet user pipe can be kept to be in constant state, and the preset hydraulic pressure in user pipe side is based on peak Phase is needed with water hydraulic pressure, therefore in this case, water during guaranteeing water use peak in water slack hours section user pipe Pressure undoubtedly will cause pressurization, and pump operation time is too long, excessively Fraquent start leads to booster pump reduced service life.In practical operation, It is up to a hundred to the distance to tip pressure spot from underground chamber controller if arranging pressure sensor in user pipe tip pressure spot Rice is even longer, and analog signal decaying is uncontrollable, and cable wiring manufacture difficulty is big, at high cost, therefore seldom uses in practical application.
Its booster pump of existing secondary water supply system is usually more used in parallel, and when work works together, one when stopping It rises and stops working.This operating mode, due to more booster pump Fraquent starts in parallel, impacts especially with during water ebb Electric current not only causes greatly waste of energy, and is easy to cause complete supply equipment service life to reduce and may cause water pump damage It is bad (it is slightly lower with user pipe hydraulic pressure during water ebb, more days booster pumps in parallel will work once electrified, and due to being used during ebb Water is few, in fact, more pressurization pump work very short times can mend user pipe hydraulic pressure water enough, so can frequently open Dynamic, during the water use peak phase, since water consumption is big, more booster pump long-plays in parallel just can guarantee user's water, institute With there is no use water slack hours section frequent starting).
Utility model content
In order to overcome drawback present in existing no negative pressure skyscraper secondary water-supply equipment water supply, the utility model is mentioned It has supplied that hydraulic pressure probe is installed in the tip extreme higher position of user pipe, hydraulic pressure probe passes through the water pressure data of acquisition wirelessly in real time Mobile network passes to host computer in control cabinet, and transmission signal is reliable, does not need wired connection between hydraulic pressure probe and host computer, Construction and installation are more convenient, to be host computer under the function of setting themselves, with (such as 12 points to the at night of water ebb section Two days 6:00 AM periods), the PLC(programmable logic controller (PLC) through being located in control cabinet) effect, only guarantee in user pipe Hydraulic pressure 85% hydraulic pressure during water use peak, and only pass through a pressurization pump work it is ensured that in user pipe hydraulic pressure needs, from And reach energy saving purpose, moreover it is possible to prevent booster pump frequent start-stop from waste of energy and booster pump service life being caused to reduce or damage The energy saver based on secondary water supply system pipeline tip hydraulic pressure.
The technical scheme adopted by the utility model to solve the technical problem is as follows:
Based on the energy saver of secondary water supply system pipeline tip hydraulic pressure, host computer, PLC including secondary water supply system, First control power output end of PLC and more booster pump power inputs of secondary water supply system parallel connection are connected by conducting wire It connects, upper function receives the digital signals such as the pressure sent through mobile radio network and control strategy, and can will be at digital signal Output order is to PLC after reason, it is characterised in that also have Switching Power Supply, hydraulic pressure probe, one-chip computer module, data transmitting equipment, Separate unit booster pump, subassembly wrapper, the second control power output end and small-power separate unit booster pump power input of PLC is by leading Line connection, the water inlet pipe of separate unit booster pump are connected with municipal tap water pipeline by pipeline and pipe joint, separate unit booster pump Outlet conduit connected by pipeline, pipe joint with more booster pump outlet conduits of secondary water supply system parallel connection, secondary There is a tool internal thread aperture in the side of the tip extreme higher position of water system user pipe, has external screw thread by one Connecting tube screw in aperture on internal screw thread in, connecting tube is mounted on user pipe tip extreme higher position side tapping, is opened On circuit boards, circuit board is mounted in subassembly wrapper, member for powered-down source, hydraulic pressure probe, one-chip computer module, data transmitting equipment installation Part box is installed on the ground or on wall by expansion bolt, and subassembly wrapper left-hand end has an aperture, the insertion of connection hose one end Hydraulic pressure probe air pressure input pipe, connection the hose other end be inserted into connecting tube, the power input both ends of Switching Power Supply respectively and 220V AC power source the two poles of the earth are connected by conducting wire, the power supply output both ends of Switching Power Supply and hydraulic pressure probe, one-chip computer module, data The power input both ends of sending device are connected by conducting wire respectively, hydraulic pressure probe signal output end and the input of one-chip computer module signal End is connected by conducting wire, and one-chip computer module signal output end and data transmitting equipment signal input part are connected by RS485 data line It connects.
The Switching Power Supply is that alternating current 220V turns 5V direct-current switch power supply module finished product, and there are two ac power input ends for tool 1 and 2 feet, two DC power output ends 3 and 4 feet.
The hydraulic pressure probe is pressure drag type pressure Sensitive Apparatus, and model is XGZP, when the water of pressure drag type pressure Sensitive Apparatus When pressure input pipe inputs different pressure signals, the pressure experience face of pressure drag type pressure Sensitive Apparatus receives different pressures signal Afterwards, 5 foot of signal output end can export 1 to the voltage analog signal changed between 4.5V, and the two of pressure drag type pressure Sensitive Apparatus A 2 foot of cathode power supply input terminal and 4 feet are connected by conducting wire, two negative power supply input terminals 3 of pressure drag type pressure Sensitive Apparatus By wired earth, operating voltage is direct current 5V for foot and 6 feet.
The one-chip computer module is the one-chip computer module finished product that main control chip is STM32F103C8T6, and there are two power supplys for tool Input terminal, all the way signal input part, all the way RS485 signal output port, operating voltage are direct current 5V.
The data transmitting equipment is GPRS module finished product, and model is Air202T, and there are two electricity for GPRS module finished product tool Source input terminal, all the way signal input part, SIM card holder has the SIM card of a unique identification telephone number, work in GPRS module finished product It is direct current 5V as voltage.
Input has different control data in the PLC, needs to set according to user, when Water District domain ebb is with the water time In section, out-put supply does not enter more booster pumps of secondary water supply system parallel connection to first of PLC control power output end, only Second control power output end out-put supply of PLC enters separate unit booster pump;In the water period of Water District domain peak, First of PLC control power output end out-put supply enters more booster pumps of secondary water supply system parallel connection, and the second of PLC Out-put supply does not enter separate unit booster pump to a control power output end;Setting is supplying in the ebb water period of Water District domain When pressure in wetting system water outlet is higher than 85% during water use peak, second control power output end of PLC is just no longer exported Power supply enters separate unit booster pump power input, when the pressure in supply equipment water outlet is lower than 85% during water use peak, Second control power output end out-put supply of PLC enters separate unit booster pump power input, once separate unit is pressurized pump operation Certain time, when pressure is still below peak period 85%, first control power output end out-put supply of PLC enters secondary confession More booster pumps of water system parallel connection start more pressurization pump operation
The utility model beneficial effect is: the utility model before use, in PLC input have different control data, according to making User needs to set, as (such as at night 12 points to 6 periods of the next morning) in the ebb water period of Water District domain, Out-put supply does not enter more booster pumps of secondary water supply system parallel connection to first of PLC control power output end, only PLC's Second control power output end out-put supply enters separate unit booster pump;When (such as early in the water period of Water District domain peak Upper 6 points are arrived 12 periods at night), first control power output end out-put supply of PLC enters secondary water supply system parallel connection More booster pumps, out-put supply does not enter separate unit booster pump to second control power output end of PLC;Water District is worked as in setting In the ebb water period of domain (such as at night 12 points to 6 periods of the next morning), the pressure in supply equipment water outlet When higher than 85% during water use peak (for example peak period hydraulic pressure is 1.2MPa or so, then hydraulic pressure is 1.05MPa during ebb Left and right), just no longer out-put supply enters separate unit booster pump power input to second control power output end of PLC, is supplying water When pressure is lower than 85% during water use peak in equipment water outlet (for example peak period hydraulic pressure is 1.2MPa or so, then low peak period Between hydraulic pressure be 1.05MPa or so), second control power output end out-put supply of PLC enters separate unit booster pump power input End, that is to say, that with water slack hours section, under PLC, separate unit pressurization pumping action, it is high with water for only keeping user pipe hydraulic pressure 85% or so during peak.In use, the hydraulic pressure probe of the utility model acquires the tip of secondary water supply system user pipe most in real time Hydraulic pressure in high position, by one-chip computer module by after data processing, data transmitting equipment is through mobile radio network by data-signal It sends in real time, when host computer receives no line number in the secondary water supply system equipment box for establishing connection with data transmitting equipment It is believed that number after, with water slack hours section, if in the secondary water supply system supply equipment water outlet that hydraulic pressure probe acquires in real time Hydraulic pressure lower than 85% during water use peak when, under host computer, PLC effect, second control power output end of PLC will Out-put supply enters separate unit booster pump power input, if the secondary water supply system supply equipment that hydraulic pressure probe acquires in real time goes out When hydraulic pressure in the mouth of a river is equal to or higher than 85% during water use peak, under host computer, PLC effect, second control of PLC is electric Source output terminal no longer out-put supply enters separate unit booster pump power input, in this way, under associated mechanisms collective effect, with water Slack hours section, user pipe hydraulic pressure remain 85% or so during water use peak.The water use peak period restores normal water Pressure.The utility model due in ebb water period user pipe hydraulic pressure only keep 85% or so during water use peak, in this way increase Press pump only needs the less working time it is ensured that hydraulic balance, so can reach energy-efficient purpose;Due to small only with one Power separate unit booster pump is user pipe pressurization, starting a period of time when small-power separate unit booster pump works in slack hours section Afterwards, due to flow is small, relative to more booster pump longevity of service, every time for that can work the long period when user pipe pressurization, So will not frequent starting, dash current is small, will not lead to waste of energy because of frequent starting and be easy to cause booster pump Damage, moreover, the water pressure data of acquisition is passed to host computer in control cabinet, hydraulic pressure through mobile radio network in real time by hydraulic pressure probe Wired connection is not needed between probe and host computer, construction and installation are more convenient.Based on above-mentioned, so the utility model has Application prospect.
Detailed description of the invention
The utility model is described further with reference to the accompanying drawings and examples.
Fig. 1 is the utility model structure diagram.
Fig. 2 is the structural schematic diagram between the utility model secondary water supply system and separate unit booster pump.
Fig. 3 is the utility model circuit diagram.
Fig. 4 is the circuit diagram between the utility model secondary water supply system and separate unit booster pump.
Specific embodiment
Fig. 1, shown in 2, a kind of energy saver based on secondary water supply system tip hydraulic pressure, including secondary water supply system Host computer 1, PLC2, first control power output end of PLC2 and more 3 power supplys of booster pump of secondary water supply system parallel connection are defeated Entering end to connect by conducting wire, host computer 1 can receive the digital signals such as the pressure sent through mobile radio network and control strategy, and Can also have Switching Power Supply 4, hydraulic pressure probe 5, one-chip computer module 6, data hair by output order after Digital Signal Processing to PLC2 Send equipment 7, separate unit booster pump 8, subassembly wrapper 12,8 electricity of second control power output end and small-power separate unit booster pump of PLC2 Source input terminal is connected by conducting wire, and the water inlet pipe and municipal tap water pipeline 9 of separate unit booster pump 8 pass through pipeline and pipe joint The outlet conduit of connection, separate unit booster pump 8 is discharged by more booster pumps of pipeline, pipe joint and secondary water supply system parallel connection Pipeline 10 connects, and has a tool internal thread aperture in the side of the tip extreme higher position of secondary water supply system user pipe 10 10-1 is screwed in the internal screw thread on aperture 10-1 with externally threaded connecting tube 11 by one, connecting tube 11 is mounted on use 10 tip extreme higher position side tapping of family pipeline, Switching Power Supply 4, hydraulic pressure probe 5, one-chip computer module 6, data transmitting equipment 7 On circuit boards, circuit board is mounted in subassembly wrapper 12 for installation, subassembly wrapper 12 by expansion bolt installation on the ground or wall Upper (needing waterproof rain-proof), 12 left-hand end of subassembly wrapper have an aperture, connection 13 one end of hose insertion hydraulic pressure probe 5 air pressures input Pipe, connection 13 other end of hose be inserted into connecting tube 11, the power input both ends of Switching Power Supply 4 respectively with 220V AC power source the two poles of the earth Connected by conducting wire, the power supply of Switching Power Supply 4 output both ends and hydraulic pressure probe 5, one-chip computer module 6, data transmitting equipment 7 electricity Source inputs both ends and is connected respectively by conducting wire, and hydraulic pressure 5 signal output ends of probe and 6 signal input part of one-chip computer module pass through conducting wire Connection, 6 signal output end of one-chip computer module are connected with 7 signal input part of data transmitting equipment by RS485 data line.
Fig. 1, shown in 2, the utility model before use, in PLC2 input have different control data, according to user's needs Setting, as (such as at night 12 points to 6 periods of the next morning) in the ebb water period of Water District domain, the first of PLC2 Out-put supply does not enter more 3 power inputs of booster pump of secondary water supply system parallel connection to a control power output end, only Second control power output end out-put supply of PLC2 enters separate unit booster pump 8;When in the water period of Water District domain peak (such as 6:00 AM at night 12 periods), first control power output end out-put supply of PLC2 enters secondary water-supply More booster pumps 3 of system parallel connection, out-put supply does not enter the small flow pressurization of separate unit to second control power output end of PLC2 Pump 8;Setting (such as at night 12 points to 6 periods of the next morning) in the ebb water period of Water District domain, water supply is set When pressure only has 85% during water use peak in standby water outlet (for example peak period hydraulic pressure is 1.2MPa or so, then during ebb Hydraulic pressure is 1.05MPa or so), just no longer out-put supply enters 8 electricity of separate unit booster pump to second control power output end of PLC2 Source input terminal, when supply equipment water outlet (namely booster pump water outlet) interior pressure is lower than 85% during water use peak (such as Peak period hydraulic pressure is 1.2MPa or so, then hydraulic pressure is 1.05MPa or so during ebb), second control power supply of PLC2 Output end out-put supply enters 8 power input of separate unit water flow booster pump, that is to say, that with water slack hours section, Under the small flow booster pump 8 of PLC2, separate unit acts on, 85% or so during only holding user pipe hydraulic pressure is water use peak.
Fig. 1, shown in 2, in use, behind the power input both ends of 220V AC power source access switch power supply 4, Switching Power Supply 4 power supply output both ends can export the power supply that 5V DC power supply enters hydraulic pressure probe 5, one-chip computer module 6, data transmitting equipment 7 Both ends are inputted, then, hydraulic pressure probe 5, one-chip computer module 6, data transmitting equipment 4 are in obtain electric standby mode;User pipe 10 Interior hydraulic pressure can enter the air pressure input pipe of hydraulic pressure probe 5 through connection hose 13 in real time, thus the pressure experience face in hydraulic pressure probe 5 Under effect, the voltage signal that the signal output end of hydraulic pressure probe 5 can export 1-4.5V variation in real time enters 6 signal of one-chip computer module The analog voltage signal of input is converted to digital signal by input terminal, one-chip computer module 6, is input to data from its signal output end 7 signal input part of sending device, when host computer 1 connects in the secondary water supply system equipment box for establishing connection with data transmitting equipment 7 After receiving wireless data signal, with water slack hours section, if the secondary water supply system water supply that hydraulic pressure probe 5 acquires in real time is set When hydraulic pressure is lower than 85% during water use peak in standby water outlet, under host computer 1, PLC2 effect, second control power supply of PLC2 Output end will out-put supply enter 8 power input of separate unit booster pump, if 5 supply equipment that acquires in real time of hydraulic pressure probe goes out When hydraulic pressure is equal to or higher than 85% during water use peak in the mouth of a river, under host computer 1, PLC2 effect, the second control electricity of PLC2 Source output terminal no longer out-put supply enters 8 power input of separate unit booster pump, in this way, using water under associated mechanisms collective effect Slack hours section, 10 hydraulic pressure of user pipe are 85% or so during remaining water use peak;The water use peak period restores normal Hydraulic pressure.The utility model is since 10 hydraulic pressure of ebb water period user pipe is only kept 85% or so during water use peak, such separate unit Booster pump 8 need less working times it is ensured that hydraulic pressure, so can reach energy-efficient purpose;Due to only with a small function Rate separate unit booster pump 8 is user pipe pressurization, starting a period of time when small-power separate unit booster pump 8 works in slack hours section Afterwards, due to flow is small, relative to more 3 longevity of service of booster pump, every time for that can work the long period when user pipe pressurization, So will not frequent starting, dash current is small, will not lead to waste of energy because of frequent starting, electrical machinery life reduce and It is easy to cause separate unit booster pump 8 to damage, moreover, hydraulic pressure probe 5 transmits the water pressure data of acquisition through mobile radio network in real time To host computer 1 in control cabinet, wired connection is not needed between hydraulic pressure switch 5 and host computer 1, construction and installation are more convenient.Pass through Data are capable of real-time acquisition after wireless connection, it is subsequent also to carry out pressure law and urbanite water consumption law-analysing using manager, far Journey issues operation control strategy, and energy-saving effect is obvious.The utility model passes through the reality of wireless collection tip water pressure and the end PLC When operating pressure in conjunction with water Annual distribution situation optimize the equipment water pump operation parameter control of high low peak period by tip pressure System, reaches in the case of water the most comfortable, the minimum purpose of low peak period operation energy consumption avoids tip pressure transient to user's hot water The impact of device etc..Based on above-mentioned, so the application prospect that the utility model has had.
Fig. 3, shown in 4, Switching Power Supply U1 be alternating current 220V turn 5V direct-current switch power supply module finished product (brand be bright latitude, Power 500W), tool is there are two ac power input end 1 and 2 feet, two DC power output ends 3 and 4 feet.Hydraulic pressure probe U2 be Pressure drag type pressure Sensitive Apparatus, model are XGZP, when the air pressure input pipe of pressure drag type pressure Sensitive Apparatus U2 inputs different pressures When force signal, after the pressure experience face of pressure drag type pressure Sensitive Apparatus U2 receives different pressures signal, 5 foot of signal output end 1 can be exported to the voltage analog signal changed between 4.5V, two cathode power supply input terminals 2 of pressure drag type pressure Sensitive Apparatus U2 Foot and 4 feet are connected by conducting wire, and two 3 feet of negative power supply input terminal of pressure drag type pressure Sensitive Apparatus U2 and 6 feet pass through conducting wire Ground connection, operating voltage is direct current 5V.One-chip computer module U3 is the one-chip computer module finished product that main control chip is STM32F103C8T6, Tool there are two power input VCC and GND, all the way signal input part X, RS485 signal output port C, operating voltage are all the way Direct current 5V.Data transmitting equipment is GPRS module finished product U4, and model is Air202T, and there are two power supplys for GPRS module finished product U4 tool Input terminal 1 and 2 feet, all the way signal input part X1, SIM card holder has a unique identification telephone number in GPRS module finished product U4 SIM card.PLC(U6 input has different control data in), needs to set according to user, when Water District domain ebb water period Interior, out-put supply does not enter more booster pumps of secondary water supply system parallel connection to first of PLC control power output end, only Second control power output end out-put supply of PLC enters separate unit booster pump;In the water period of Water District domain peak, First of PLC control power output end out-put supply enters more booster pumps of secondary water supply system parallel connection, and the second of PLC Out-put supply does not enter separate unit booster pump to a control power output end;Setting is supplying in the ebb water period of Water District domain When hydraulic pressure is higher than 85% during water use peak in wetting system water outlet, just no longer output is electric for second control power output end of PLC Source enters separate unit booster pump power input, when hydraulic pressure is lower than 85% during water use peak in supply equipment water outlet, PLC's Second control power output end out-put supply enters separate unit booster pump power input, once separate unit pressurization pump operation is certain Time, when pressure is still below peak period 85%, first control power output end out-put supply of PLC enters secondary water-supply system Unite more booster pumps in parallel, more pressurization pump operation Fig. 3 of starting, shown in 4, PLC(U6) first control power supply export End S1 is connected with more booster pump MN power inputs of secondary water supply system parallel connection by conducting wire, and host computer U5 can be received through nothing The digital signal that the mobile network of line is sent, and all can be to PLC(by output order after Digital Signal Processing it is well known in the art at Cooking technique), the second control power output end S2 and small-power separate unit booster pump M power input of PLC (U6) passes through conducting wire Connection, the power input both ends 1 of Switching Power Supply U1 and 2 feet are connected with 220V AC power source the two poles of the earth by conducting wire respectively, switch electricity The power supply output both ends 3 of source U1 and 4 feet and hydraulic pressure probe U2 power input both ends 2 and 3 feet, one-chip computer module U3 power input two VCC and GND, the power input both ends 1 of data transmitting equipment U4 and 2 feet are held to connect respectively by conducting wire, hydraulic pressure probe U2 signal 5 foot of output end is connected with one-chip computer module U3 signal input part X by conducting wire, one-chip computer module U3 signal output end C and data Sending device U4 signal input part X1 is connected by RS485 data line.
Fig. 3, shown in 4, in use, after the power input both ends 1 of 220V AC power source access switch power supply U1 and 2 feet, The power supply output both ends 3 of Switching Power Supply U1 and 4 feet can export stable 5V DC power supply and enter hydraulic pressure probe U2 power input two 2 and 3 feet, one-chip computer module U3 power input both ends VCC and GND, the power input both ends 1 of data transmitting equipment U4 and 2 feet are held, Then, hydraulic pressure probe U2, one-chip computer module U3, data transmitting equipment U4 are in obtain electric standby mode;Hydraulic pressure meeting in user pipe Enter the air pressure input pipe of hydraulic pressure probe U2 through connecting hose in real time, thus in hydraulic pressure probe U2 under the effect of pressure experience face, The voltage signal that 5 foot of signal output end of hydraulic pressure probe U2 exports 1-4.5V variation in real time enters the input of one-chip computer module U3 signal Hold X, one-chip computer module U3 that the analog voltage signal of input is converted to the digital signal of dynamic change, and from its signal output end C is input to data transmitting equipment U4 signal input part X1, and then, data transmitting equipment U4 can send through mobile radio network and set out The digital signal of state variation, when host computer U5 is received in the secondary water supply system equipment box for establishing connection with data transmitting equipment U4 To after wireless data signal, with water slack hours section, the secondary water supply system water supply that U2 is acquired in real time if hydraulic pressure is popped one's head in is set (voltage that 5 foot of signal output end of hydraulic pressure probe U2 exports in real time is low when hydraulic pressure is lower than 85% during water use peak in standby water outlet In 3.8V or so), in host computer U5, PLC(U6) effect under, second control power output end S2 of PLC (U6) will be exported Power supply enters separate unit booster pump M power input, if the secondary water supply system supply equipment that hydraulic pressure probe U2 is acquired in real time goes out (the voltage that 5 foot of signal output end of hydraulic pressure probe U2 exports in real time when 85% during hydraulic pressure being equal to or higher than water use peak in the mouth of a river Greater than or equal to 3.8V or so), in host computer U5, PLC(U6) effect under, PLC(U6) second control power output end S2 No longer out-put supply enters separate unit booster pump M power input, in this way, under associated mechanisms collective effect, when with water ebb Between section, user pipe hydraulic pressure is 85% or so during remaining water use peak.The secondary water supply system water use peak period restores Normal hydraulic pressure, in host computer U5, PLC(U6) under effect, separate unit booster pump M does not work, more booster pump MN work in parallel, Secondary water supply system PLC is mating to be mounted on secondary water supply system under hydraulic pressure switch effect, during guaranteeing water use peak, Yong Huguan Road hydraulic pressure is ebb water period 85%, thus user the water use peak period can just commonly use water (the water use peak period, Hydraulic pressure is lower than a timing in user pipe, and under hydraulic pressure switch, PLC, host computer effect, more booster pump MN in parallel can obtain electric It working, hydraulic pressure is higher than a timing in user pipe, under hydraulic pressure switch, PLC, host computer effect, more booster pump MN in parallel Power loss stops working, and one keeps high water pressure condition in this way in guarantee user pipe.In the utility model, once separate unit booster pump Certain time is run, when pressure is still below peak period 85%, first control power output end out-put supply of PLC enters two More booster pumps of secondary water system parallel connection, start more pressurization pump operation i.e. low peak period enters separate unit booster pump fortune Row can not meet user with water hydraulic pressure PLC and just start more pressurization pump works, meet actual needs, separate unit increases after pressure is constant Press pump and more booster pumps of parallel connection all stop working, then PLC first starts separate unit pressurization pump work when restart.
The basic principles and main features and advantages of the present invention that the utility model has been shown and described above, for ability For field technique personnel, it is clear that the present invention is not limited to the details of the above exemplary embodiments, and practical without departing substantially from this In the case where novel spirit or essential attributes, the utility model can be realized in other specific forms.Therefore, no matter from which From the point of view of a bit, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the utility model is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (5)

1. based on the energy saver of secondary water supply system pipeline tip hydraulic pressure, host computer, PLC including secondary water supply system, PLC First control power output end connected with more booster pump power inputs of secondary water supply system parallel connection by conducting wire, on Median function receives the digital signal sent through mobile radio network, and can be special by output order after Digital Signal Processing to PLC Sign is also there is Switching Power Supply, hydraulic pressure probe, one-chip computer module, data transmitting equipment, separate unit booster pump, subassembly wrapper, PLC's Second control power output end is connected with small-power separate unit booster pump power input by conducting wire, and separate unit booster pump enters water Pipeline is connected with municipal tap water pipeline by pipeline and pipe joint, and the outlet conduit of separate unit booster pump passes through pipeline, pipeline Connector is connected with more booster pump outlet conduits of secondary water supply system parallel connection, secondary water supply system user pipe tip most There is a tool internal thread aperture in the side of high position, and connecting tube is mounted on the side aperture of user pipe tip extreme higher position Place, on circuit boards, circuit board is mounted on subassembly wrapper for Switching Power Supply, hydraulic pressure probe, one-chip computer module, data transmitting equipment installation Interior, the air pressure input pipe of connection hose one end insertion hydraulic pressure probe, the connection hose other end is inserted into connecting tube, the electricity of Switching Power Supply Source input both ends are connected with 220V AC power source the two poles of the earth by conducting wire respectively, and the power supply output both ends of Switching Power Supply and hydraulic pressure are visited Head, one-chip computer module, data transmitting equipment power input both ends respectively by conducting wire connect, hydraulic pressure probe signal output end and One-chip computer module signal input part is connected by conducting wire, one-chip computer module signal output end and data transmitting equipment signal input part It is connected by RS485 data line.
2. the energy saver according to claim 1 based on secondary water supply system pipeline tip hydraulic pressure, it is characterised in that open Powered-down source is that alternating current 220V turns 5V direct-current switch power supply module.
3. the energy saver according to claim 1 based on secondary water supply system pipeline tip hydraulic pressure, it is characterised in that water Pressure probe is pressure drag type pressure Sensitive Apparatus, and model is XGZP.
4. the energy saver according to claim 1 based on secondary water supply system pipeline tip hydraulic pressure, it is characterised in that single Piece machine module is the one-chip computer module that main control chip is STM32F103C8T6.
5. the energy saver according to claim 1 based on secondary water supply system pipeline tip hydraulic pressure, it is characterised in that number It is GPRS module according to sending device, model is Air202T.
CN201821491383.7U 2018-09-12 2018-09-12 Energy saver based on secondary water supply system pipeline tip hydraulic pressure Active CN209162930U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821491383.7U CN209162930U (en) 2018-09-12 2018-09-12 Energy saver based on secondary water supply system pipeline tip hydraulic pressure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821491383.7U CN209162930U (en) 2018-09-12 2018-09-12 Energy saver based on secondary water supply system pipeline tip hydraulic pressure

Publications (1)

Publication Number Publication Date
CN209162930U true CN209162930U (en) 2019-07-26

Family

ID=67331062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821491383.7U Active CN209162930U (en) 2018-09-12 2018-09-12 Energy saver based on secondary water supply system pipeline tip hydraulic pressure

Country Status (1)

Country Link
CN (1) CN209162930U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978777A (en) * 2018-09-12 2018-12-11 成都优链加科技有限公司 Energy saver based on secondary water supply system pipeline tip hydraulic pressure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978777A (en) * 2018-09-12 2018-12-11 成都优链加科技有限公司 Energy saver based on secondary water supply system pipeline tip hydraulic pressure

Similar Documents

Publication Publication Date Title
CN205485536U (en) Running water thing networking management system based on internet
CN205805876U (en) Double pump intelligent controlling device
CN105089097A (en) Water supply device and method for automatically matching appropriate water pumps according to real-time flows
CN105806436A (en) Multifunctional hydraulic-electricity-generating-type water meter
CN204919657U (en) According to automatic water supply equipment who matches suitable water pump of real -time flow
CN209162930U (en) Energy saver based on secondary water supply system pipeline tip hydraulic pressure
CN108916013A (en) A kind of water cooling intelligence pump control system
CN209311606U (en) A kind of multifunctional electric meter
CN108978777A (en) Energy saver based on secondary water supply system pipeline tip hydraulic pressure
CN202547004U (en) Air conditioner and RS485 bus system thereof
CN104880984A (en) Remote intelligent irrigation control system
CN203741939U (en) Intelligent box type negative-pressure-free water supply device
CN203373810U (en) Automatic pressure regulating and controlling device for water supply system
CN204112413U (en) Frequency conversion interlock constant pressure water supply system
CN104746584A (en) Intelligent box type non-negative pressure water supply device
CN201421213Y (en) Pipeline evacuating and water saving system of solar water heater
CN209386412U (en) GPRS heat exchange station control system based on FlexRay bus mode
CN210780783U (en) Two-wire system power supply and communication device
CN202969452U (en) Automatic pressurization water supply device
CN209779762U (en) water supply system with flowmeter
CN208294748U (en) A kind of frequency conversion automatic drain system
CN205483126U (en) Multi -functional water gauge of hydroelectric power generation type
CN207453006U (en) A kind of Intelligent constant-voltage water system
CN206249045U (en) A kind of water-proof low-power consumption modularization the Information of Water Supply Pipe Network collecting transmitter