CN208969494U - A kind of encoder switching device of the double tank elevators of auxiliary shaft - Google Patents

A kind of encoder switching device of the double tank elevators of auxiliary shaft Download PDF

Info

Publication number
CN208969494U
CN208969494U CN201822076380.3U CN201822076380U CN208969494U CN 208969494 U CN208969494 U CN 208969494U CN 201822076380 U CN201822076380 U CN 201822076380U CN 208969494 U CN208969494 U CN 208969494U
Authority
CN
China
Prior art keywords
encoder
monitoring
pulse signal
master control
plc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822076380.3U
Other languages
Chinese (zh)
Inventor
秦磊
陈�峰
程磊
胡建成
赵晓胜
马询
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huainan Mining Group Co Ltd
Original Assignee
Huainan Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huainan Mining Group Co Ltd filed Critical Huainan Mining Group Co Ltd
Priority to CN201822076380.3U priority Critical patent/CN208969494U/en
Application granted granted Critical
Publication of CN208969494U publication Critical patent/CN208969494U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Maintenance And Inspection Apparatuses For Elevators (AREA)

Abstract

The utility model discloses a kind of encoder switching devices of the double tank elevators of auxiliary shaft, master control encoder and main control PLC communication connection, monitor encoder and monitoring PLC communication connection, the left end of the spare terminal of the pulse signal lead and communication cabinet of master control encoder connects, the right end for monitoring the pulse signal lead of encoder and the spare terminal of communication cabinet connects, switch is connected between the left end and right end of spare terminal, when needing to switch over, stop master control encoder and monitor the power switch of encoder, closes the switch of spare terminal;Determine which breaks down for master control encoder and monitoring encoder, closes the power switch of not out of order encoder, into primary control program, modifies a circle coded number of the encoder of failure;The advantages of the utility model has safety failure low, guarantees pit shaft personnel safety.

Description

A kind of encoder switching device of the double tank elevators of auxiliary shaft
Technical field
The utility model relates to electricity fields, are more particularly to a kind of encoder switching device of double tank elevators of auxiliary shaft.
Background technique
Encoder plays very important effect in lifting system, and the data of encoder are in PLC controller as speed Degree control and stroke control use, once master control monitoring encoder or monitoring encoder break down, elevator will appear super Fast failure or progressive error failure, elevator can not drive, and cause pit shaft to hang people for a long time, easily cause safety accident.
Utility model content
It monitors and compiles in master control the technical problem to be solved by the utility model is to the double tank elevators of the auxiliary shaft of the prior art The problem of when code device or monitoring encoder break down, elevator can not drive, and pit shaft is caused to hang people for a long time.
The utility model is to solve above-mentioned technical problem by the following technical programs: a kind of volume of the double tank elevators of auxiliary shaft Code device switching device, including master control encoder, monitoring encoder and communication cabinet, the master control encoder are mounted on the double tanks of auxiliary shaft and mention In the concentric shafts that the main shaft of the machine of liter is drawn, the monitoring encoder is mounted on the gear on the end cap of the double tank elevators of auxiliary shaft On central axis, engaged gears on gear and main shaft on end cap, the master control encoder and main control PLC communication connection are described Monitor encoder and monitoring PLC communication connection, the pulse signal lead of the master control encoder and the spare end of the communication cabinet The pulse signal lead of the left end connection of son, the monitoring encoder is connect with the right end of the spare terminal of the communication cabinet, institute It states and is connected with switch between the left end of spare terminal and right end.
Preferably, the gear diameter ratio on the gear and main shaft on the end cap is 1:1.4.
Preferably, the pulse signal lead of the master control encoder includes A+, A-, B+ and B-, the monitoring encoder Pulse signal lead includes A+, A-, B+ and B-, and there are four connecting terminal, the masters for the left end of the spare terminal and right end Controlling the PLC and monitoring PLC includes output unit, the output unit of the main control PLC including four output pin A2+, The output unit of A2-, B2+ and B2-, the monitoring PLC include four output pins A2+, A2-, B2+ and B2-.
Preferably, the master control encoder pulse signal lead A+, A-, B+ and B- respectively from top to bottom successively with it is spare Four connecting terminals of terminal left end connect, pulse signal lead A+, A-, B+ and B- of the monitoring encoder respectively on to Under successively connect with four connecting terminals of spare terminal right end, four output pin A2 of the output unit of the main control PLC +, A2-, B2+, B2- respectively with pulse signal lead A+, A-, B+, B- communication connection of the master control encoder, the monitoring Four output pins A2+, A2-, B2+, B2- of the output unit of PLC respectively with it is described monitoring encoder pulse signal lead A +, A-, B+ and B- communication connection.
The utility model have the advantage that compared with prior art when master control encoder or monitoring encoder go wrong, Cause elevator to be unable to run, main control PLC can be taken and monitor PLC while using the signal of some encoder, to protect Card promotes function emergency and is promoted, and pit shaft is avoided to hang people for a long time.
Detailed description of the invention
It, below will be to required use in utility model description in order to illustrate more clearly of the technical solution of the utility model Attached drawing be briefly described, it should be apparent that, the drawings in the following description are merely some embodiments of the present invention, right For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings His attached drawing.
Fig. 1 is a kind of circuit of the encoder switching device of the double tank elevators of auxiliary shaft disclosed in the utility model embodiment Structure chart.
Specific embodiment
It elaborates below to the embodiments of the present invention, the present embodiment before being with technical solutions of the utility model It puts and is implemented, the detailed implementation method and specific operation process are given, but the protection scope of the utility model is unlimited In following embodiments.
As shown in Figure 1, a kind of encoder switching device of the double tank elevators of auxiliary shaft, including master control encoder 1, monitoring coding Device 2, the spare terminal 3 of communication cabinet, main control PLC and monitoring PLC.
The master control encoder 1 is mounted on one of the main shaft (not shown) extraction of the double tank elevator (not shown) of auxiliary shaft together In mandrel (not shown), the monitoring encoder 2 is mounted on the gear in the end cap (not shown) of the double tank elevators of auxiliary shaft, and (figure is not Show) on central axis, the engaged gears on gear and main shaft on end cap, the master control encoder 1 and main control PLC communication connection, The monitoring encoder 2 and monitoring PLC communication connection, pulse signal lead and the communication cabinet of the master control encoder 1 The left end of spare terminal 3 connects, the right side of the spare terminal 3 of the pulse signal lead and communication cabinet of the monitoring encoder 2 End connection, is connected with switch 301 between the left end and right end of the spare terminal 3.
Specifically, the gear diameter ratio on gear and main shaft on the end cap is 1:1.4.
Specifically, the pulse signal lead of the master control encoder 1 includes A+, A-, B+ and B-, the monitoring encoder 2 Pulse signal lead include A+, A-, B+ and B-, there are four connecting terminals for the left end of the spare terminal 3 and right end, described Main control PLC and the monitoring PLC include output unit, the output unit of the main control PLC include four output pin A2+, The output unit of A2-, B2+ and B2-, the monitoring PLC include four output pins A2+, A2-, B2+ and B2-.The master control is compiled Pulse signal lead A+, A-, B+ and B- of code device 1 distinguish from top to bottom successively four connecting terminals with 3 left end of spare terminal Connection, it is described monitoring encoder 2 pulse signal lead A+, A-, B+ and B- respectively from top to bottom successively with 3 right end of spare terminal Four connecting terminals connection, four output pins A2+, A2-, B2+, B2- of the output unit of the main control PLC respectively with institute Pulse signal lead A+, A-, B+, B- communication connection of master control encoder 1 is stated, four of the output unit of the monitoring PLC are defeated Out pin A2+, A2-, B2+, B2- respectively with it is described monitoring encoder 2 pulse signal lead A+, A-, B+ and B- communication connection.
The working process of the utility model is as follows:
Step 1: original state, spare terminal 3 are in an off state;
Step 2: when needing to switch over, stop the power switch (not shown) and monitoring coding of master control encoder 1 first Then the power switch (not shown) of device 2 closes the switch 301 of spare terminal 3;
Step 3: determine which breaks down for master control encoder 1 and monitoring encoder 2, if event occurs in master control encoder 1 Barrier closes the power switch of monitoring encoder 2, if monitoring encoder 2 breaks down, closes the power switch of master control encoder 1;
Step 4: entering primary control program, if what is closed is the power switch for monitoring encoder 2, master control encoder 1 one is enclosed Coded number is changed to monitoring encoder 2 one and encloses coded number * 1.4;If what is closed is the power switch of master control encoder 1, monitoring is compiled Code device 2 one encloses coded number and is changed to the circle of master control encoder 1 one coded number/1.4;If the monitoring encoder 2 one encloses coded number and institute It states master control encoder 1 one and encloses the volume that coded number is identical, then the coded number and master control encoder 1 one for monitoring the circle of encoder 2 one enclose Yardage is not modified.
Step 5: carrying out reset driving, promotes speed control within 1m/s;
Step 6: after cage hoisting to well head, replacement processing is carried out to trouble coder.
The working principle of the utility model are as follows: when the motor operation of the double tank elevators of auxiliary shaft, master control encoder 1, monitoring The axis of encoder 2 follows main shaft while rotating, and the positive and negative rotaring signal of the motor of the double tank elevators of auxiliary shaft and pulse signal are divided Supplementary biography is to main control PLC and monitors PLC.PLC software can calculate the speed of service and row of motor according to pulse signal in program Journey is compared the data of master control encoder 1, monitoring encoder 2 in program after data communication.Once master control is compiled The data of code device 1 and the data differences of monitoring encoder 2 are more than specified value, the double tank elevators of auxiliary shaft will report to be formed poor failure and Speed compares failure, and the double tank elevators of auxiliary shaft is caused to be unable to run, once master control encoder 1 or monitoring encoder 2 are asked Topic causes the double tank elevators of auxiliary shaft to be unable to run, closes the switch 301 of spare terminal 3, takes main control PLC and monitoring PLC simultaneously Using the signal of some encoder, to guarantee that the double tanks of auxiliary shaft promote function emergency and promoted, pit shaft is avoided to hang people for a long time.
By above technical scheme, a kind of encoder switching device of the double tank elevators of auxiliary shaft provided by the utility model It is low with safety failure, guarantee pit shaft personnel safety the advantages of.When master control encoder or monitoring encoder go wrong, cause to mention The machine of liter is unable to run, and can be taken main control PLC and be monitored PLC while using the signal of some encoder, to guarantee to be promoted Function emergency is promoted, and pit shaft is avoided to hang people for a long time.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this Made any modifications, equivalent replacements, and improvements etc., should be included in the utility model within the spirit and principle of utility model Protection scope within.

Claims (4)

1. a kind of encoder switching device of the double tank elevators of auxiliary shaft, which is characterized in that including master control encoder, monitoring encoder And communication cabinet, the master control encoder are mounted in a concentric shafts of the main shaft extraction of the double tank elevators of auxiliary shaft, the monitoring Encoder is mounted on the central gear axis on the end cap of the double tank elevators of auxiliary shaft, and the gear on gear and main shaft on end cap is stung It closes, the master control encoder and main control PLC communication connection, the monitoring encoder and monitoring PLC communication connection, the master control are compiled The pulse signal lead of code device is connect with the left end of the spare terminal of the communication cabinet, and the pulse signal of the monitoring encoder draws Line is connect with the right end of the spare terminal of the communication cabinet, is connected with switch between the left end and right end of the spare terminal.
2. a kind of encoder switching device of the double tank elevators of auxiliary shaft according to claim 1, which is characterized in that the end Gear diameter ratio on the gear and main shaft covered is 1:1.4.
3. a kind of encoder switching device of the double tank elevators of auxiliary shaft according to claim 1, which is characterized in that the master The pulse signal lead of control encoder includes A+, A-, B+ and B-, the pulse signal lead of the monitoring encoder include A+, A-, There are four connecting terminals for B+ and B-, the left end of the spare terminal and right end, and the main control PLC and the monitoring PLC are wrapped Include output unit, the output unit of the main control PLC includes four output pin A2+, A2-, B2+ and B2-, the monitoring PLC Output unit include four output pins A2+, A2-, B2+ and B2-.
4. a kind of encoder switching device of the double tank elevators of auxiliary shaft according to claim 3, which is characterized in that the master Pulse signal lead A+, A-, B+ and the B- for controlling encoder distinguish from top to bottom successively four terminals with spare terminal left end Son connection, it is described monitoring encoder pulse signal lead A+, A-, B+ and B- respectively from top to bottom successively with spare terminal right end Four connecting terminals connection, four output pins A2+, A2-, B2+, B2- of the output unit of the main control PLC respectively with institute State pulse signal lead A+, A-, B+, B- communication connection of master control encoder, four outputs of the output unit of the monitoring PLC Pin A2+, A2-, B2+, B2- respectively with it is described monitoring encoder pulse signal lead A+, A-, B+ and B- communication connection.
CN201822076380.3U 2018-12-11 2018-12-11 A kind of encoder switching device of the double tank elevators of auxiliary shaft Active CN208969494U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822076380.3U CN208969494U (en) 2018-12-11 2018-12-11 A kind of encoder switching device of the double tank elevators of auxiliary shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822076380.3U CN208969494U (en) 2018-12-11 2018-12-11 A kind of encoder switching device of the double tank elevators of auxiliary shaft

Publications (1)

Publication Number Publication Date
CN208969494U true CN208969494U (en) 2019-06-11

Family

ID=66766291

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822076380.3U Active CN208969494U (en) 2018-12-11 2018-12-11 A kind of encoder switching device of the double tank elevators of auxiliary shaft

Country Status (1)

Country Link
CN (1) CN208969494U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109343465A (en) * 2018-12-11 2019-02-15 淮南矿业(集团)有限责任公司 A kind of the encoder switching device and its switching method of the double tank elevators of auxiliary shaft

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109343465A (en) * 2018-12-11 2019-02-15 淮南矿业(集团)有限责任公司 A kind of the encoder switching device and its switching method of the double tank elevators of auxiliary shaft
CN109343465B (en) * 2018-12-11 2024-04-30 淮南矿业(集团)有限责任公司 Encoder switching device and method of auxiliary shaft double-tank elevator

Similar Documents

Publication Publication Date Title
CN1021858C (en) Romote monitor and diagnosis apparatus for elevator
CN208969494U (en) A kind of encoder switching device of the double tank elevators of auxiliary shaft
CN103955160A (en) Safety protection module for industrial robot
CN201826672U (en) Controller system for automatic door
CN105242631A (en) Distributed control system of lifting and transferring parking device
CN203173628U (en) Operation safety device of elevator
DE19754141A1 (en) Safety device for escalators and moving walks
CN106843128A (en) Producing line control system and control method based on CC LINK applications
CN204198164U (en) Height limiting device and there is the building hoist of this device
CN109343465A (en) A kind of the encoder switching device and its switching method of the double tank elevators of auxiliary shaft
CN203333107U (en) Lift car cable system
CN205049944U (en) Lifting and horizontal moving parking equipment's distributed control system
CN218088495U (en) Household elevator door motor system
CN201383105Y (en) Centralized staircase control system
CN203806896U (en) Whole-course safe device against slack rope
CN110442077A (en) A kind of bilinear con- trol device
CN201406234Y (en) Elevator based on data acquisition
CN213338411U (en) Locomotive online maintenance system
CN206033001U (en) Mine vertical shaft hoisting machine unmanned on duty control system
CN103663029A (en) Elevator remote monitoring and debugging system
CN208949863U (en) A kind of anti-skidding protection system of self-elevating ocean platform lifting
CN205274905U (en) Elevator cab case controlling means and elevator control system
CN110763938A (en) Intelligent state monitoring type traction control interface module
CN201989736U (en) Handle variable speed controller
CN110018663A (en) Failure to safety Fail-Safe pit vehicle lifting jack control system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant