CN208917715U - Prestressed assembly formula Hanging Basket for arch bridge suspender replacement - Google Patents

Prestressed assembly formula Hanging Basket for arch bridge suspender replacement Download PDF

Info

Publication number
CN208917715U
CN208917715U CN201822197737.3U CN201822197737U CN208917715U CN 208917715 U CN208917715 U CN 208917715U CN 201822197737 U CN201822197737 U CN 201822197737U CN 208917715 U CN208917715 U CN 208917715U
Authority
CN
China
Prior art keywords
hanging basket
node
truss structure
basket truss
prestressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822197737.3U
Other languages
Chinese (zh)
Inventor
王晓山
黎祖金
孟盈盈
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LIUZHOU OVM ENGINEERING Co Ltd
Original Assignee
LIUZHOU OVM ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIUZHOU OVM ENGINEERING Co Ltd filed Critical LIUZHOU OVM ENGINEERING Co Ltd
Priority to CN201822197737.3U priority Critical patent/CN208917715U/en
Application granted granted Critical
Publication of CN208917715U publication Critical patent/CN208917715U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to arch bridge suspender replacement apparatus field, is particularly used for the prestressed assembly formula Hanging Basket of arch bridge suspender replacement;The present apparatus is assembled into the Hanging Basket truss structure of random length as suspender replacement operation platform using node I, node II, node III, prestressed draw-bar, brace, cross bar, vertical bar, vertical pole, apply prestressing force by pull rod tensioner stretch-draw prestressing force pull rod, elongated Hanging Basket truss structure is made to generate camber.The walking dolly that counterweight is provided on bridge deck structure is connected by wirerope and each one end of elongated Hanging Basket truss structure, it can be achieved that elongated Hanging Basket truss structure being used in turn between each sunpender setting to be replaced;It has the advantage that: the present apparatus by pin-connected panel cradle structure and the adjustable mode of prestressing force, realizes, construction lightness, peace is torn open and convenient transportation, reduces manufacture processing and construction cost, is used in turn convenient for standardization, while improving using degree of safety.

Description

Prestressed assembly formula Hanging Basket for arch bridge suspender replacement
Technical field
The utility model belongs to arch bridge suspender replacement apparatus field, and the prestressing force for being particularly used for arch bridge suspender replacement is spelled Dress formula Hanging Basket.
Background technique
Since the nineties in last century, China has built a large amount of half through or through arch bridge, such bridge mainly passes through sunpender The dead load of bridge deck and mobile load are transferred to arch rib, therefore sunpender is crucial supporting member.Old sunpender system used at that time Substantially parallel steel wire+bulb-end anchorage mode.Due to by the factors shadow such as technical level at that time, quality of materials and construction quality It rings, after bridge is completed more than 10 years, sunpender just starts disease occur, and the safety for being increasingly becoming bridge structure over time is hidden Suffer from, or even Hangers failure occur to cause the event of bridge collapse.The service life of sunpender is generally 20 years, from the nineties in last century Arch bridge is completed so far, will have a large amount of sunpender to reach its service life, needs replacing.
Currently, taking two ways, a kind of mode mostly for job platform below the bridge deck structure of arch bridge suspender replacement To set up full framing mode from more than ground, disadvantage is long construction period, and costly, progress is slow, and it is big to set up work surface, work Intensity is high.Another way is Hanging Basket mode under beam, and disadvantage is that monoblock type segment sizes are longer or wider, and inconvenience is carried, transported And peace is torn open, need to frequently be cooperated using large-scale lifting appliance, is used in turn at high cost;It is elongated under beam in addition, the increase wide with bridge The span of Hanging Basket increases therewith, middle span deflexion deformation it is larger, for increase construction its steel using amount of rigidity dramatically increase, cause manufacture, Processing cost is high.How Hanging Basket lightness, peace are torn open and convenient transportation, manufacture processing and construction cost are reduced, convenient for standardization week Turn to use, improves and use degree of safety, become letter problem to be solved.
Utility model content
In view of the deficiencies of the prior art and the above problem, one of the purpose of this utility model are used for arch bridge there is provided a kind of The prestressed assembly formula hanging basket device of suspender replacement, the present apparatus are real by pin-connected panel cradle structure and the adjustable mode of prestressing force Showed construction lightness, peace is torn open and convenient transportation, reduce manufacture processing and construction cost, be used in turn convenient for standardization, simultaneously It improves using degree of safety, to solve the deficiency of above-mentioned technology.
The technical solution adopted in the utility model is as follows:
A kind of prestressed assembly formula Hanging Basket for arch bridge suspender replacement, it is characterised in that: the present apparatus consists of two parts, Respectively Hanging Basket truss element and turnover unit, the Hanging Basket truss element are hung to 10 lower part of bridge deck structure, bridge by truck crane For the setting of 10 top of face structure there are two turnover unit, described two turnover units are each by wirerope 12 and Hanging Basket truss element One end connection.
The Hanging Basket truss structure includes several nodes I 1, node II 2, node III 3, prestressed draw-bar 4, brace 5, cross bar 6, vertical bar 7, vertical pole 8 and pull rod tensioner 9;
Node II 2 or node III 3 are inserted into each one end of the cross bar 6 respectively, are connected by bolted-on;7 one end of vertical bar It is inserted into node III 3, the other end is inserted into node I 1, connects by bolted-on;
Node III 3 is inserted into described 8 one end of vertical pole, and the other end is inserted into node II 2, is connected by bolted-on;
Described 5 one end of brace and the bolt of node I 1 connect, and the other end and the bolt of node II 2 connect;Prestressed draw-bar 4 each one End is fixed with node II 2 by nut check respectively.
Each component part of the Hanging Basket truss element can be assembled into the elongated Hanging Basket truss structure of random length, pass through drawing 9 stretch-draw prestressing force pull rod 4 of bar tensioner applies prestressing force, and elongated Hanging Basket truss structure is made to generate camber.
Described two turnover units are made of walking dolly 11 and counterweight 13, and counterweight 13 is placed on walking dolly 11, Walking dolly 11 is connect with elongated each one end of Hanging Basket truss structure by wirerope 12, it can be achieved that elongated Hanging Basket truss structure is each Being used in turn between 14 setting of sunpender to be replaced.
There is provided a kind of prestressed assembly formula Hanging Baskets based on arch bridge suspender replacement for the another object of the utility model Installation method, specific installation steps are as follows:
Step 1: by each node I 1, node II 2, node III 3, prestressed draw-bar 4, brace 5, cross bar 6, vertical bar 7, vertical pole 8 The mode of connecing is fastened by bolt on bridge deck structure 10 and is assembled into elongated Hanging Basket truss structure;
Step 2: prestressing force is applied by 9 stretch-draw prestressing force pull rod 4 of pull rod tensioner, produces elongated Hanging Basket truss structure Raw camber;
Step 3: cooperated by truck crane and elongated Hanging Basket truss structure is hung to bridge deck structure 10 hereinafter, bridge deck structure 10 On be provided with 13 walking dollies 11 of counterweight and connect by wirerope 12 with elongated each one end of Hanging Basket truss structure.
Step 4: above-mentioned steps are completed to complete hanging basket device installation, and it is flat can to meet 14 setting of sunpender construction to be replaced Platform demand is finished to suspender replacement at this, can integrally be moved hanging basket device by the walking dolly 11 on mobile bridge deck structure 10 It moves to next to sunpender operation to be replaced.
The utility model has the following beneficial effects: the present apparatus is with node I, node II, node III, prestressed draw-bar, brace, cross Bar, vertical bar, vertical pole are assembled into the Hanging Basket truss structure of random length as suspender replacement operation platform, pass through pull rod tensioner It draws prestressed draw-bar to apply prestressing force, elongated Hanging Basket truss structure is made to generate camber.The row of counterweight is provided on bridge deck structure Trolley is walked to be connect with elongated each one end of Hanging Basket truss structure by wirerope, it can be achieved that elongated Hanging Basket truss structure is each to be replaced Being used in turn between sunpender setting.Present apparatus standarized component size is smaller easy to carry and transports, in addition, pre- by applying Tension type generates reversed camber in span centre, reduces the excessive lower flexure strain of span centre, significantly reduce and construct rigidity because increasing Required increased steel using amount, realizes construction lightness, peace is torn open and convenient transportation, reduces manufacture processing and construction cost, is convenient for Standardization is used in turn, while being improved using degree of safety.
Detailed description of the invention
Fig. 1 is that the utility model is based on assembly of decking structure structural schematic diagram;
Fig. 2 is the utility model overall structure diagram;
Fig. 3 is the utility model Hanging Basket truss element mounting structure schematic diagram;
Specific embodiment
In conjunction with the embodiments, attached drawing is further described the utility model:
Embodiment 1
As shown in Figures 1 to 3, the utility model provides a kind of prestressed assembly formula Hanging Basket for arch bridge suspender replacement, Including node I 1, node II 2, node III 3, prestressed draw-bar 4, brace 5, cross bar 6, vertical bar 7, vertical pole 8, pull rod tensioner 9, row Walk trolley 11, wirerope 12, counterweight 13.
Node II 2 or node III 3 are inserted into each one end of cross bar 6 respectively, are connected by bolted-on.The insertion of 7 one end of vertical bar Node III 3, the other end are inserted into node I 1, are connected by bolted-on.Node III 3, other end insertion section are inserted into 8 one end of vertical pole Point II 2 is connected by bolted-on.5 one end of brace and the bolt of node I 1 connect.The other end and the bolt of node II 2 connect. Each one end of prestressed draw-bar 4 is fixed with node II 2 by nut check respectively.Pass through 9 stretch-draw prestressing force pull rod 4 of pull rod tensioner Apply prestressing force, elongated Hanging Basket truss structure is made to generate camber.13 walking dollies 11 of counterweight are provided on bridge deck structure 10 It is connect with elongated each one end of Hanging Basket truss structure, it can be achieved that elongated Hanging Basket truss structure is made in each suspender replacement by wirerope 12 Being used in turn between industry point.
Each standarized component of the present apparatus can be assembled into the elongated Hanging Basket truss structure of random length, cross bar 6, vertical bar 7, vertical pole 8 It connects between each rod piece and is connected by way of three kinds of different nodes I 1, node II 2, III 3 plug-in type bolt of node, every kind of section Point is integral by steel pipe and steel plate combination welding.
Each one end of prestressed draw-bar 4 of the present apparatus is fixed with node II 2 by nut check respectively.Pass through pull rod tensioner 9 stretch-draw prestressing force pull rods 4 apply prestressing force, and elongated Hanging Basket truss structure is made to generate camber, and realization effectively reduces middle span deflexion Deformation.
13 walking dollies 11 that counterweight is provided on present apparatus bridge deck structure 10 pass through wirerope 12 and elongated Hanging Basket truss Each one end connection of structure is, it can be achieved that elongated Hanging Basket truss structure being used in turn between each suspender replacement setting.
The installation method of whole device the following is through node I 1, node II 2, node III 3, prestressed draw-bar 4, brace 5, cross bar 6, vertical bar 7, vertical pole 8 can be assembled into the elongated Hanging Basket truss structure of random length, be answered in advance by 9 tensioning of pull rod tensioner Power pull rod 4 applies prestressing force, and elongated Hanging Basket truss structure is made to generate camber.13 walkings of counterweight are provided on bridge deck structure 10 Trolley 11 is connect with elongated each one end of Hanging Basket truss structure by wirerope 12, it can be achieved that elongated Hanging Basket truss structure is respectively to more Change being used in turn between 14 setting of sunpender.Specific installation steps are as follows:
Step 1: by each node I 1, node II 2, node III 3, prestressed draw-bar 4, brace 5, cross bar 6, vertical bar 7, vertical pole 8 The mode of connecing is fastened by bolt on bridge deck structure 10 and is assembled into elongated Hanging Basket truss structure.
Step 2: prestressing force is applied by 9 stretch-draw prestressing force pull rod 4 of pull rod tensioner, produces elongated Hanging Basket truss structure Raw camber.
Step 3: cooperated by truck crane and elongated Hanging Basket truss structure is hung to bridge deck structure 10 hereinafter, bridge deck structure 10 On be provided with 13 walking dollies 11 of counterweight and connect by wirerope 12 with elongated each one end of Hanging Basket truss structure.
Step 4: above-mentioned steps are completed to complete hanging basket device installation, and it is flat can to meet 14 setting of sunpender construction to be replaced Platform demand.It finishes, can integrally be moved hanging basket device by the walking dolly 11 on mobile bridge deck structure 10 to suspender replacement at this It moves to next to sunpender operation to be replaced.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this is practical new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this is practical new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing for the equivalent requirements of the claims will be fallen in All changes in justice and range are embraced therein.It should not treat any reference in the claims as limiting Related claim.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (4)

1. the prestressed assembly formula Hanging Basket for arch bridge suspender replacement, it is characterised in that: the present apparatus consists of two parts, respectively Hanging Basket truss element and turnover unit, the Hanging Basket truss element are hung to bridge deck structure lower part by truck crane, on bridge deck structure There are two turnover unit, described two turnover units to be connect by wirerope with each one end of Hanging Basket truss element for portion's setting.
2. the prestressed assembly formula Hanging Basket according to claim 1 for arch bridge suspender replacement, it is characterised in that: the extension Basket truss element includes several nodes I, node II, node III, prestressed draw-bar, brace, cross bar, vertical bar, vertical pole and pull rod Draw device;
Node II or node III are inserted into described each one end of cross bar respectively, are connected by bolted-on;
Node III is inserted into described vertical bar one end, and the other end is inserted into node I, is connected by bolted-on;
Node III is inserted into described vertical pole one end, and the other end is inserted into node II, is connected by bolted-on;
Described brace one end and the bolt of node I connect, and the other end and the bolt of node II connect;Each one end of prestressed draw-bar respectively with Node II is fixed by nut check.
3. the prestressed assembly formula Hanging Basket according to claim 1 for arch bridge suspender replacement, it is characterised in that: the extension Each component part of basket truss element can be assembled into the elongated Hanging Basket truss structure of random length, pre- by pull rod tensioner tensioning Stress pull rod applies prestressing force, and elongated Hanging Basket truss structure is made to generate camber.
4. the prestressed assembly formula Hanging Basket according to claim 1 for arch bridge suspender replacement, it is characterised in that: described two A turnover unit is made of walking dolly and counterweight, and counterweight is placed on walking dolly, and walking dolly is by wirerope and leads to Long each one end connection of Hanging Basket truss structure is, it can be achieved that turnover of the elongated Hanging Basket truss structure between each sunpender setting to be replaced It uses.
CN201822197737.3U 2018-12-26 2018-12-26 Prestressed assembly formula Hanging Basket for arch bridge suspender replacement Expired - Fee Related CN208917715U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822197737.3U CN208917715U (en) 2018-12-26 2018-12-26 Prestressed assembly formula Hanging Basket for arch bridge suspender replacement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822197737.3U CN208917715U (en) 2018-12-26 2018-12-26 Prestressed assembly formula Hanging Basket for arch bridge suspender replacement

Publications (1)

Publication Number Publication Date
CN208917715U true CN208917715U (en) 2019-05-31

Family

ID=66712974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822197737.3U Expired - Fee Related CN208917715U (en) 2018-12-26 2018-12-26 Prestressed assembly formula Hanging Basket for arch bridge suspender replacement

Country Status (1)

Country Link
CN (1) CN208917715U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111585039A (en) * 2020-05-18 2020-08-25 柳州欧维姆工程有限公司 Replacement method for FAST reflecting surface unit self-adaptive connecting mechanism
CN113774780A (en) * 2021-09-06 2021-12-10 四川省公路规划勘察设计研究院有限公司 Segment unit of super-large span concrete-filled steel tube arch bridge and arch bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111585039A (en) * 2020-05-18 2020-08-25 柳州欧维姆工程有限公司 Replacement method for FAST reflecting surface unit self-adaptive connecting mechanism
CN111585039B (en) * 2020-05-18 2021-07-27 柳州欧维姆工程有限公司 Replacement method for FAST reflecting surface unit self-adaptive connecting mechanism
CN113774780A (en) * 2021-09-06 2021-12-10 四川省公路规划勘察设计研究院有限公司 Segment unit of super-large span concrete-filled steel tube arch bridge and arch bridge

Similar Documents

Publication Publication Date Title
CN201003287Y (en) Template support frame
CN208917715U (en) Prestressed assembly formula Hanging Basket for arch bridge suspender replacement
CN207862749U (en) A kind of novel combination type sunpender
CN101440604A (en) Cable opposite pulling type pier-side bracket
CN104674992A (en) Supporting method and structure of suspended steel bar truss deck
CN211057625U (en) Prefabricated pier stud of assembled installation aligning device
CN207029216U (en) A kind of complicated landform power equipment conveying arrangement
CN207047703U (en) A kind of beam piece prestressed stretch-draw jack easy device in place
CN203385620U (en) Static-load test rack of concrete bridge
CN203583378U (en) Floor plate truss trolley for mounting bridge deck slab of composite structure bridge
CN102926330B (en) Installation method of hanging basket suitable for bridge construction
CN205840316U (en) Large span Zhongting hanging structure form bracing system
CN203475309U (en) Bent cap support used in viaduct construction process
CN211621249U (en) Hoisting device for box-type beam wave web
CN2911003Y (en) Suspension running pulley under railway steel bridge
CN205663175U (en) Adjustable reinforcing pull rod formula scaffold frame of encorbelmenting
CN208152607U (en) Beam-string structure system in the reinforcing of large span rigid frame
CN209522474U (en) A kind of hanging apparatus of tee girder template
CN208563125U (en) A kind of device being lifted using concrete filled steel tube cushion block supporting bridge
CN202299458U (en) Jig frame for high-altitude large-span rod piece
CN102259813A (en) Hearth overhauling platform for multifunctional boiler
CN207513137U (en) Building engineering construction builder's jack
CN207277212U (en) A kind of novel steel beam floorings construction formwork supporting structure
CN206395721U (en) A kind of anode carbon block fixture being installed on stacking overhead travelling crane
CN206955437U (en) A kind of bird assembly jig

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190531

Termination date: 20191226

CF01 Termination of patent right due to non-payment of annual fee