CN208916952U
CN208916952U CN201821005536.2U CN201821005536U CN208916952U CN 208916952 U CN208916952 U CN 208916952U CN 201821005536 U CN201821005536 U CN 201821005536U CN 208916952 U CN208916952 U CN 208916952U
Authority
CN
China
Prior art keywords
pump
tank
water
sludge
high density
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821005536.2U
Other languages
Chinese (zh)
Inventor
张良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Zheng Enterprise Environmental Technology Co Ltd
Original Assignee
Shanxi Zheng Enterprise Environmental Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Zheng Enterprise Environmental Technology Co Ltd filed Critical Shanxi Zheng Enterprise Environmental Technology Co Ltd
Priority to CN201821005536.2U priority Critical patent/CN208916952U/en
Application granted granted Critical
Publication of CN208916952U publication Critical patent/CN208916952U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Suspended Particles By Flocculating Agents (AREA)

Abstract

The utility model discloses a kind of mine water integrated combination settlers, comprising: conditioning tank, flocculation basin, distribution reservoir, high density inclined-tube sedimentation tank, sludge concentration tank, clear water reserviors, intermediate pool, raw water elevator pump, blender plus PAM device plus PAC device, screw rod filter pressing pump, chamber-type press filter, indoor catch pit, sludge relay pump, high efficiency particulate air filter, filtered water pump, dredge pump and ClO2Chlorination equipment.Integration degree is high for the utility model, reduces space occupied, convenient for construction, installation and operation operation, significantly reduces construction investment and operating cost.

Description

Mine water integrated combination settler
Technical field
The utility model relates to Mine Water Transacting Technology fields, and in particular to a kind of mine water integrated combination settler.
Background technique
Shanxi and there is a large amount of coal mine elsewhere, each coal mine has treating mine drainage station, big coal mine and water yield Big mine is according to requirement design, buying, the construction for the treatment of mine drainage;Operational effect is good, the discharge of energy meet the requirement of environmental protection Index.Main technique and structures be conditioning tank sedimentation basin, dosing agglomerate flocculation basin, sedimentation basin, intermediate pool, filter plant, Sludge concentration tank, clear water reserviors, sludge dewatering equipment, sterilizing equipment decontaminating apparatus, water supply pump, high-order conditioning tank, power distribution automation equipment.Water yield It can design and construct according to the above equipment, steel reinforced concrete structures more than the mine of 100m3/h, if but the system that is less than 50m3/h According to the design of above equipment structures, construction, not only cost is high, cover an area of, run that difficulty is big, operator is more, operates Program is more, equipment pipe is more, is unfavorable for the optimizing regulation operation of system, needs to design a novel mine water installations.
Summary of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the utility model provides a kind of mine water integrated combination precipitating dress It sets.
The technical solution adopted in the utility model is: a kind of mine water integrated combination settler, comprising: conditioning tank, wadding Solidifying pond, high density inclined-tube sedimentation tank, sludge concentration tank, clear water reserviors, intermediate pool, raw water elevator pump, blender, adds distribution reservoir PAM device plus PAC device, screw rod filter pressing pump, chamber-type press filter, indoor catch pit, sludge relay pump, high efficiency particulate air filter, filtering Water pump, dredge pump and ClO2Chlorination equipment;
The conditioning tank is connect by raw water elevator pump with flocculation basin, and the conditioning tank and the clear water reserviors share a pond Wall is equipped between the raw water elevator pump and flocculation basin and adds PAM device and add PAC device, is equipped with stirring in the flocculation basin Machine, the flocculation basin are connected with distribution reservoir, and share a pool wall with distribution reservoir, and pool wall is equipped with intake-outlet, the distribution reservoir It is connected with high density inclined-tube sedimentation tank, and shares a pool wall with high density inclined-tube sedimentation tank, pool wall is equipped with intake-outlet, described High density inclined-tube sedimentation tank is connected by pipeline with sludge relay pump, and the sludge relay pump connects sludge condensation by pipeline Pond, the sludge concentration tank and flocculation basin share a pool wall, the sludge concentration tank, the screw rod filter pressing pump and the van-type pressure Filter is sequentially connected, between the sludge concentration tank and the screw rod filter pressing pump be equipped with plus PAM device, the sludge concentration tank and The screw rod filter pressing pump is connect with the indoor catch pit, is equipped with dredge pump in the interior catch pit, the interior is catchmented Hole is connected by dredge pump with conditioning tank, and the high density inclined-tube sedimentation tank is connect with intermediate pool, and is shared with intermediate pool One pool wall, high density inclined-tube sedimentation tank water outlet by the overflow of spilling water triangular-notch weir into intermediate pool, it is the intermediate pool, described High efficiency particulate air filter and the clear water reserviors are sequentially connected, the ClO2Chlorination equipment is connect with intermediate pool.
Further, the pool wall uses 10mm thick steel plate using the steel plate of 8mm thickness, the bottom in the pond.
Further, the inclined tube of the high density inclined-tube sedimentation tank is 60 ° of inclination angle, aperture is 30mm~40mm, thickness For the polypropylene honeycomb inclined tube of 0.5mm~0.8mm.
Further, the inner wall in the pond uses rubber asphalt line with rubber anti-corrosion.
Further, the mud-removing bucket of the high density inclined-tube sedimentation tank uses the cone bottom sludge hopper of steel plate welding.
Further, the distribution reservoir is equipped with water distribution pipe.
The beneficial effects of the utility model are: using the design and construction of integrated apparatus, substantially reduce construction period, Difficulty of construction is reduced, integration degree is high, reduces space occupied, and installation is simple, and operation is easy to operate, reduces engineering throwing Money and operating cost.
Detailed description of the invention
Fig. 1 is the process flow chart of the utility model;
Fig. 2 is the equipment layout viewing of the utility model.
In figure: 1. clear water reserviors, 2.ClO2Catch pit, 4. raw water elevator pumps, 5. conditioning tanks, 6. add in chlorination equipment, Room 3. PAM device, 7. plus PAC device, 8. chamber-type press filters, 9. flocculation basins, 10. blenders, 11. screw rod filter pressing pumps, 12. sludge condensations It is pond, 13. sludge relay pumps, 14. distribution reservoirs, 15. high density inclined-tube sedimentation tanks, 16. intermediate pools, 17. filtered water pumps, 18. high Imitate filter, 19. dredge pumps.
Specific embodiment
It is further to the utility model with reference to the accompanying drawing in order to be more clearly understood that the technical solution of the utility model Explanation.
A kind of mine water integrated combination settler as shown in Figure 1 and Figure 2, comprising: conditioning tank 5, flocculation basin 9, distribution reservoir 14, high density inclined-tube sedimentation tank 15, sludge concentration tank 12, clear water reserviors 1, intermediate pool 16, raw water elevator pump 4, blender 10, plus PAM device 6 plus PAC device 7, screw rod filter pressing pump 11, chamber-type press filter 8, indoor catch pit 3, sludge relay pump 13, efficient mistake Filter 18, filtered water pump 17, dredge pump 19 and ClO2Chlorination equipment 2;
The conditioning tank 5 is connect by raw water elevator pump 4 with flocculation basin 9, and the conditioning tank 5 is shared with the clear water reserviors 1 One pool wall is equipped between the raw water elevator pump 4 and flocculation basin 9 and adds PAM device 6 and add PAC device 7, peace in the flocculation basin 9 Equipped with blender 10, the flocculation basin 9 is connected with distribution reservoir 14, and shares a pool wall with distribution reservoir 14, and pool wall is equipped with disengaging The mouth of a river, the distribution reservoir 14 are connected with high density inclined-tube sedimentation tank 15, and share a pool wall, pond with high density inclined-tube sedimentation tank 15 Wall is equipped with intake-outlet, and the high density inclined-tube sedimentation tank 15 is connected by pipeline with sludge relay pump 13, in the sludge Turn pump 13 and sludge concentration tank 12 is connected by pipeline, the sludge concentration tank 12 shares a pool wall with flocculation basin 9, and the sludge is dense Contracting pond 12, the screw rod filter pressing pump 11 and the chamber-type press filter 8 are sequentially connected, the sludge concentration tank 12 and the screw rod pressure Be equipped between filter pump 11 plus PAM device 6, the sludge concentration tank 12 and the screw rod filter pressing pump 11 with the indoor catch pit 3 connections, the interior catch pit 3 is interior to be equipped with dredge pump 19, and the interior catch pit 3 is connected by dredge pump 19 with conditioning tank 5, And a pool wall is shared with intermediate pool 16, the water outlet of high density inclined-tube sedimentation tank 15 passes through the overflow of spilling water triangular-notch weir into intermediate water Pond 16, the intermediate pool 16, the high efficiency particulate air filter 18 and the clear water reserviors 1 are sequentially connected, the ClO2Chlorination equipment 2 with Intermediate pool 16 connects.
Preferably, the pool wall uses 10mm thick steel plate using the steel plate of 8mm thickness, the bottom in the pond.
Preferably, the inclined tube of the high density inclined-tube sedimentation tank 15 is 60 ° of inclination angle, aperture is 30mm~40mm, thickness For the polypropylene honeycomb inclined tube of 0.5mm~0.8mm.
Preferably, the inner wall in the pond uses rubber asphalt line with rubber anti-corrosion.
Preferably, the mud-removing bucket of the high density inclined-tube sedimentation tank 15 uses the cone bottom sludge hopper of steel plate welding.
Preferably, the distribution reservoir 14 is equipped with water distribution pipe.
Working principle: mine water enters conditioning tank 5, and 5 source water of conditioning tank is promoted to flocculation basin 9, sewage by raw water elevator pump 4 There are also the suspended matter precipitated is largely difficult to after 5 preliminary sedimentation of conditioning tank, by adding PAM/PAC device that flocculating agent and wadding is added Flocculation after the macromolecular that cannot be precipitated cohesion is enhanced the precipitating in heavy pond at biggish particle under the effect of blender 10 by solidifying agent Effect reduces structures volume, accelerates the speed in the precipitating of sedimentation basin, and the water outlet of flocculation basin 9 enters distribution reservoir, and distribution reservoir 14 passes through Water outlet enters high density inclined-tube sedimentation tank 15 after crossing energy dissipating, water distribution, on the one hand high density inclined-tube sedimentation tank 15 is discharged by spilling water Triangular-notch weir overflow enters intermediate pool 16, passes through ClO2Chlorination equipment 2 carries out disinfection to the water of intermediate pool 16, intermediate pool 16 Water outlet finally enters the clear water reserviors 1 of present apparatus integrated design, the water warp of clear water reserviors 1 by filtered water pump 17 to high efficiency particulate air filter 18 High pressure pump enters head-tank with spare;The sludge water that another aspect high density inclined-tube sedimentation tank 15 precipitates is through sludge relay pump 13 enter sludge concentration tank 12, transport outward sludge after screw rod filter pressing pump 11, the processing of chamber-type press filter 8.
Utility model device installation is simple, and integrated apparatus takes up little area;Matched pipeline is greatly reduced, and civil engineering amount subtracts It is few;Strong, easy to maintenance, the disposable installation of globality is simple;Effect is obvious, and saving soil, construction period are short, at low cost.
The above description is only a preferred embodiment of the present invention, therefore all according to described in the utility model patent application range The equivalent change or modification done of structure, feature and principle, be included in the scope of the utility model patent application.

Claims (6)

1. a kind of mine water integrated combination settler, it is characterised in that: including conditioning tank (5), flocculation basin (9), distribution reservoir (14), high density inclined-tube sedimentation tank (15), sludge concentration tank (12), clear water reserviors (1), intermediate pool (16), raw water elevator pump (4), blender (10) plus PAM device (6) plus PAC device (7), screw rod filter pressing pump (11), chamber-type press filter (8), indoor collection Puddle (3), sludge relay pump (13), high efficiency particulate air filter (18), filtered water pump (17), dredge pump (19) and ClO2Chlorination equipment (2);
The conditioning tank (5) is connect by raw water elevator pump (4) with flocculation basin (9), the conditioning tank (5) and the clear water reserviors (1) pool wall is shared, is equipped between the raw water elevator pump (4) and flocculation basin (9) and is added PAM device (6) and add PAC device (7), Is equipped with blender (10) in the flocculation basin (9), the flocculation basin (9) is connected with distribution reservoir (14), and with distribution reservoir (14) Share a pool wall, pool wall is equipped with intake-outlet, and the distribution reservoir (14) is connected with high density inclined-tube sedimentation tank (15), and with height Density inclined-tube sedimentation tank (15) shares a pool wall, and pool wall is equipped with intake-outlet, and the high density inclined-tube sedimentation tank (15) passes through Pipeline is connected with sludge relay pump, and the sludge relay pump (13) connects sludge concentration tank (12) by pipeline, and the sludge is dense Contracting pond (12) and flocculation basin (9) share a pool wall, the sludge concentration tank (12), the screw rod filter pressing pump (11) and the van-type Filter press (8) is sequentially connected, and is equipped between the sludge concentration tank (12) and the screw rod filter pressing pump (11) and is added PAM device (6), The sludge concentration tank (12) and the screw rod filter pressing pump (11) are connect with the indoor catch pit (3), and the interior is catchmented It cheats in (3) and is equipped with dredge pump (19), the interior catch pit (3) is connected by dredge pump (19) with conditioning tank (5), described highly dense Degree inclined-tube sedimentation tank (15) is connect with intermediate pool (16), and shares a pool wall, the high density inclined tube with intermediate pool (16) Sedimentation basin (15) water outlet passes through the overflow of spilling water triangular-notch weir into intermediate pool (16), the intermediate pool (16), the high efficiency filter Device (18) and the clear water reserviors (1) are sequentially connected, the ClO2Chlorination equipment (2) is connect with intermediate pool (16).
2. mine water integrated combination settler according to claim 1, it is characterised in that: the pool wall is thick using 8mm Steel plate, the bottom in the pond uses 10mm thick steel plate.
3. mine water integrated combination settler according to claim 1, it is characterised in that: the inner wall in the pond is coated with rubber Glue pitch line with rubber.
4. mine water integrated combination settler according to claim 1, it is characterised in that: the high density tube settling The inclined tube in pond (15) is 60 ° of inclination angle, aperture is 30mm~40mm, the polypropylene honeycomb inclined tube with a thickness of 0.5mm~0.8mm.
5. mine water integrated combination settler according to claim 1, it is characterised in that: the high density tube settling The mud-removing bucket in pond (15) uses the cone bottom sludge hopper of steel plate welding.
6. mine water integrated combination settler according to claim 1, it is characterised in that: the distribution reservoir (14) is equipped with Water distribution pipe.
CN201821005536.2U 2018-06-28 2018-06-28 Mine water integrated combination settler Expired - Fee Related CN208916952U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821005536.2U CN208916952U (en) 2018-06-28 2018-06-28 Mine water integrated combination settler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821005536.2U CN208916952U (en) 2018-06-28 2018-06-28 Mine water integrated combination settler

Publications (1)

Publication Number Publication Date
CN208916952U true CN208916952U (en) 2019-05-31

Family

ID=66693822

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821005536.2U Expired - Fee Related CN208916952U (en) 2018-06-28 2018-06-28 Mine water integrated combination settler

Country Status (1)

Country Link
CN (1) CN208916952U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139896A (en) * 2020-01-19 2020-05-12 宁波大学 A secondary water supply system and method with side filter function
CN115818901A (en) * 2023-01-06 2023-03-21 中国电建集团北京勘测设计研究院有限公司 Underground cavern production wastewater treatment system and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139896A (en) * 2020-01-19 2020-05-12 宁波大学 A secondary water supply system and method with side filter function
CN115818901A (en) * 2023-01-06 2023-03-21 中国电建集团北京勘测设计研究院有限公司 Underground cavern production wastewater treatment system and method

Similar Documents

Publication Publication Date Title
CN101387119B (en) Large-scale factory roof rainwater collection, treatment and reuse system and method thereof
CN201245484Y (en) Integrated sewage purification processing unit for architectural engineering
CN206069590U (en) Rainwater high efficiency clarification tank
CN103922506B (en) Integrated complete equipment for water quality purification treatment
CN106830252A (en) The unified water treating apparatus of function are precipitated with ballasted flocculation
CN208949033U (en) A kind of recirculated water automatic dosing apparatus with filtering function
CN208916952U (en) Mine water integrated combination settler
CN103239902A (en) Central high-density integrated clarification device and clarification method thereof
CN107298498A (en) Industrial and mineral waste water high-efficiency purifies and recycled equipment
CN205501073U (en) Papermaking wastewater treatment system
CN108002639A (en) Integrated form integration ecological water factory
CN204689696U (en) Integration precipitation process system
CN207091183U (en) A kind of industrial and mineral waste water high-efficiency purifies and recycled equipment
CN206680234U (en) Unified water treating apparatus with ballasted flocculation precipitation function
CN110448940A (en) A kind of water treatment plant's water for drainage slurry system and processing method
CN107500434A (en) A kind of sewage-treatment plant and tunnel Waste Water Treatment and method
CN105585091B (en) A kind of flocculating setting method and device
CN204848509U (en) Mud water processing system
CN212894250U (en) Container type high-efficiency clarified water treatment device
CN216005591U (en) Equipment for preparing fine gypsum from wet desulfurization sludge
CN202107583U (en) Downhole treatment device for sewage of mine
CN1319879C (en) Electrolytic aluminium factory production waste water disposal method
CN204097237U (en) Flat flow dissolved gas floatator
CN116040833A (en) High-concentration fluorine-containing wastewater unit coupling deep purification system and technology
CN107840536A (en) Integrated form integration ecological water factory

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190531

Termination date: 20210628