CN208736687U - A kind of thermal performance test system - Google Patents

A kind of thermal performance test system Download PDF

Info

Publication number
CN208736687U
CN208736687U CN201821437680.3U CN201821437680U CN208736687U CN 208736687 U CN208736687 U CN 208736687U CN 201821437680 U CN201821437680 U CN 201821437680U CN 208736687 U CN208736687 U CN 208736687U
Authority
CN
China
Prior art keywords
temperature
storage tank
low
heat
tested
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821437680.3U
Other languages
Chinese (zh)
Inventor
谢宁宁
王亮
陈海生
王艺斐
林曦鹏
林霖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Institute of Engineering Thermophysics
Original Assignee
Institute of Engineering Thermophysics
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute of Engineering Thermophysics filed Critical Institute of Engineering Thermophysics
Priority to CN201821437680.3U priority Critical patent/CN208736687U/en
Application granted granted Critical
Publication of CN208736687U publication Critical patent/CN208736687U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigating Or Analyzing Materials Using Thermal Means (AREA)

Abstract

本实用新型公开了一种热性能测试系统,可以对大功率宽温域的蓄热装置的蓄/释热性能以及大型换热器的换热性能进行测试实验与性能评估。该系统由测控系统、热能产生与存储系统、稳压系统、被测装置组件和泵阀组件等组成,可在较宽温度压力范围下进行测试。该系统也可以模拟可再生能源等非稳态的热能输出,实现大规模中高温蓄热装置阵列性能测试和运行策略研究,并能满足压缩空气储能系统关键部件研发测试等工作。

The utility model discloses a thermal performance testing system, which can perform testing experiments and performance evaluation on the storage/release performance of a heat storage device with high power and a wide temperature range and the heat exchange performance of a large heat exchanger. The system is composed of measurement and control system, heat energy generation and storage system, voltage stabilization system, device under test components and pump valve components, etc. It can be tested under a wide temperature and pressure range. The system can also simulate unsteady heat energy output such as renewable energy, realize the performance test and operation strategy research of large-scale medium and high temperature heat storage device array, and can meet the research and development test of key components of compressed air energy storage system.

Description

A kind of thermal performance test system
Technical field
The utility model belongs to accumulation of heat or heat exchange property testing field, is related to a kind of thermal performance test system, can be to big function Storage/latent heat releasing performance of the regenerative apparatus of the wide temperature range of rate and the heat exchange property of large heat exchanger carry out test experiments and comment with performance Estimate.The system can also simulate the thermal energy output of the unstable state such as renewable energy, realize extensive high temperature regenerative apparatus array Performance test and operation reserve research, and it is able to satisfy the work such as compressed-air energy-storage system critical component research and development test.
Background technique
Solar energy thermal-power-generating is the solar energy generation technology of the potentiality that grow a lot, and solar thermal collector handle is collected into Solar radiant energy be changed into superheated steam through heat exchanger, produced electricl energy with traditional power cycle, have technology maturation, Cost of electricity-generating is low and is easy the advantages of forming hybrid power system with fossil fuel.But due to the discontinuity round the clock of solar energy with And as cloudy overcast and rainy and caused by unstability energy a series of problems, such as, to the steady of solar light-heat power-generation systematic electricity Output produces very big influence.Therefore regenerative apparatus is arranged in solar heat power generation system is one of most efficient method.
Other than solar light-heat power-generation, energy storage field such as compressed-air energy storage also develops very swift and violent at present, it is benefit Air is compressed to certain pressure by compressor with valley power to be stored in air accumulator, and high pressure is empty during peak of power consumption Gas is generated electricity by expanding machine.In order to can be further improved the efficiency of system, can by the heat of compression by heat exchanger replace to Recirculated water simultaneously stores, and heat is replaced to pressure-air by heat exchanger when generating electricity, improves expander inlet temperature, from And it improves efficiency.Therefore heat exchanging device is needed to carry out Performance Evaluation, however there is no the height that power is greater than 10MW in the prior art Intermediate temperature regenerator measuring table, in addition, the performance of some large heat exchangers can only be calculated and be assessed by the method for numerical simulation. Therefore very urgent to the performance measurement demand of regenerative apparatus, heat exchanger in the market.
Utility model content
It, can be with the utility model proposes a kind of thermal performance test system for the disadvantages mentioned above and deficiency of the prior art Test experiments and property are carried out to the storage/latent heat releasing performance of regenerative apparatus and the heat exchange property of large heat exchanger of high-power wide temperature range It can assessment.The system can also simulate the thermal energy output of the unstable state such as renewable energy, realize extensive high temperature regenerative apparatus Array performance test and operation reserve research, and it is able to satisfy the work such as compressed-air energy-storage system critical component research and development test.
The technical solution that the utility model is taken by solution its technical problem is:
A kind of thermal performance test system, to test the heat storage performance of regenerative apparatus or the heat exchange property of heat-exchanger rig, institute The system of stating includes that thermal energy generates and storage unit, voltage regulation unit, part to be tested and measurement and control unit, which is characterized in that
-- the thermal energy generates and storage unit, including high temperature storage tank, low-temperature storage tank, high-temperature pump, cryogenic pump, high temperature flow Measurement and control assembly, flowrate Measurement in Low Temperature and control assembly, electric heater, cooler, wherein
The high temperature storage tank, the inlet of low-temperature storage tank and electric heater are equipped with control valve at liquid outlet;
Inlet at the top of the part to be tested connects a high temperature feed liquor pipeline and a low temperature feed liquor pipeline simultaneously, described The leakage fluid dram of part bottom to be tested connects an at least tapping line, the high temperature feed liquor pipeline, low temperature feed liquor pipeline, drain pipe Valve is equipped on line;
The liquid outlet of the high temperature storage tank is successively added through high-temperature pump, high temperature flow measurement and control assembly, electricity by pipeline Hot device is connected to the high temperature feed liquor pipeline of the part to be tested;
The liquid outlet of the low-temperature storage tank is by pipeline successively through cryogenic pump, flowrate Measurement in Low Temperature and control assembly, cooling Device is connected to the low temperature feed liquor pipeline of the part to be tested;
The tapping line of the part to be tested feed liquor with the inlet of the high temperature storage tank, the low-temperature storage tank respectively Mouth connection;
-- the voltage regulation unit, to carry out degassing processing to the test macro before activation and in test system The stabilization of system pressure is maintained when uniting in operating status, the voltage regulation unit includes an at least high-pressure buffering pot, a condenser With a liquid collecting tank, wherein
The air inlet of the high-pressure buffering pot is connected to high voltage stabilizing gas source,
Ventilation at the top of the blow vent of the gas outlet of the high-pressure buffering pot and the high temperature tank top, low-temperature storage tank Air inlet connection at the top of mouth, liquid collecting tank,
It is equipped with valve at air inlet at the top of the gas outlet of the high-pressure buffering pot, liquid collecting tank,
It is blow vent at the top of the blow vent of the high temperature tank top, low-temperature storage tank, equal at the gas outlet at the top of liquid collecting tank Equipped with relief valve,
The hot side of the condenser is located on the admission line of the liquid collecting tank, and the cold side of the condenser is passed through condensation Water;
-- the measurement and control unit is at least generated with the thermal energy and high-temperature pump, the cryogenic pump, high temperature flow in storage unit Measurement and control assembly, flowrate Measurement in Low Temperature and control assembly, electric heater, cooler and with it is each in the voltage regulation unit Flow control valve communication connection, and each component is controlled according to feedback information;
Temperature sensor and pressure sensor are at least set at the part inlet to be tested, liquid outlet, it is each described Temperature sensor, pressure sensor are communicated to connect with the measurement and control unit, and the measurement and control unit passes through to described to be tested Temperature, pressure and flow parameter at part inlet, liquid outlet carry out real-time measurement and record, and are analyzed and handled, with Realize the test to the part hot property to be tested and Performance Evaluation.
Preferably, the above-mentioned thermal performance test system of the utility model, when the part to be tested be regenerative apparatus, treat When surveying regenerative apparatus progress accumulation of heat and latent heat releasing performance test, process is included at least:
In accumulation of heat testing process, the high-temperature liquid state heat transfer medium in the high temperature storage tank is passed through by high-temperature pump conveying It is flowed into after the electric heater in the regenerative apparatus to be measured and completes heat-accumulating process, the low temperature being discharged from the regenerative apparatus to be measured Liquid heat transfer medium flows back to the low-temperature storage tank;
In heat release testing process, the low temperature liquid heat transfer medium in the low-temperature storage tank is passed through by cryogenic pump conveying Completion heat release process in the regenerative apparatus to be measured is flowed into after the cooler, the high-temperature liquid being discharged from the regenerative apparatus to be measured State heat transfer medium flows back to the high temperature storage tank;
During accumulation of heat and heat release, the measurement and control unit is to the temperature at the regenerative apparatus inlet to be measured, liquid outlet The parameters such as degree, pressure and flow carry out real-time measurement and record, and are analyzed and handled, and are filled with realizing to the accumulation of heat to be measured The accumulation of heat set and heat release experiment test and Performance Evaluation.
Preferably, the above-mentioned thermal performance test system of the utility model, when the part to be tested is heat-exchanger rig, to The leakage fluid dram for surveying heat-exchanger rig connects a high temperature tapping line and a low temperature tapping line, the high temperature tapping line and low temperature row Liquid pipe line is connected to the inlet of the high temperature storage tank and low-temperature storage tank;When the heat exchange property to the heat-exchanger rig to be measured is surveyed When examination, the low temperature heat transfer fluid in the low-temperature storage tank passes through the low temperature through the cooler under the driving of the cryogenic pump Feed liquor pipeline flows into the cold side of the heat-exchanger rig to be measured, and by the high temperature tapping line of the heat-exchanger rig to be measured flow out into Enter the low-temperature storage tank;At the same time, the high temperature heat transfer fluid in the high temperature storage tank is under the driving of the high-temperature pump through institute The hot side of the heat-exchanger rig to be measured is flowed by the high temperature feed liquor pipeline after stating electric heater, and passes through the heat exchange to be measured The low temperature tapping line of device flows into the high temperature storage tank, thus realize the heat exchange property of heat-exchanger rig to be measured is measured and Assessment.
Preferably, the above-mentioned thermal performance test system of the utility model further includes high temperature fluid preparation flow, cryogen Preparation flow, high temperature fluid self-loopa process, cryogen self-loopa process etc..
Further, the cryogenic heat transfer stream when the system is in high temperature fluid preparation flow, in the low-temperature storage tank Body is flowed under the driving of the cryogenic pump in the electric heater, passes through the power regulation and temperature control to the electric heater Low temperature heat transfer fluid, is heated to set temperature and flowed into the high temperature storage tank, which can ensure that the high temperature storage tank by system In heat-transfer fluid volume and temperature.
Further, the high temperature heat transfer stream when the system is in cryogen preparation flow, in the high temperature storage tank Body, which is flowed under the driving of the high-temperature pump in the cooler, to cool down, and is finally flowed into the low-temperature storage tank, the function It can ensure that the volume and temperature of the heat-transfer fluid in the low-temperature storage tank.
Further, the cryogenic heat transfer when the system is in cryogen self-loopa process, in the low-temperature storage tank Fluid, which is flowed under the driving of the cryogenic pump in the cooler, to cool down, last to be flowed into the low-temperature storage tank again, The function can ensure that the temperature of the heat-transfer fluid in the low-temperature storage tank remains at a relatively low temperature.
Further, the heat-transfer fluid when the system is in high temperature fluid self-loopa process, in the high temperature storage tank It flows under the driving of the high-temperature pump in the electric heater, is controlled by the power regulation and temperature of the electric heater, Heat-transfer fluid is heated to set temperature and is flowed into the high temperature storage tank, which can ensure that the heat transfer in the high temperature storage tank The temperature of fluid remains at a relatively high temperature.
Preferably, the high temperature storage tank, be equipped with liquid level emasuring device in low-temperature storage tank, the high-temperature pump, cryogenic pump Entrance is equipped with filter.
Preferably, the high temperature flow measurement and control assembly, flowrate Measurement in Low Temperature and control assembly include a flow Meter and one and the concatenated flow control valve of the flowmeter.
Preferably, the cold side of the cooler and cooling liquid circuit communication, and be equipped on the cooling fluid loop With the flow control valve of measurement and control unit communication connection.
Preferably, the low-temperature storage tank can be consistent or inconsistent with the design parameter of high temperature storage tank;The low-temperature storage tank It can be 2 or more, arrangement mode in parallel or series can be used;The high temperature storage tank can be 2 or more, can be used simultaneously Connection or arranged in series mode;Arrangement mode in parallel or series can be used when can be 1 or more, 1 or more in the cryogenic pump; Arrangement mode in parallel or series can be used when can be 1 or more, 1 or more in the high-temperature pump;The cryogenic pump and high temperature Pump can be the combination of positive displacement pump, dynamical type pump and other types pump or three of the above pump.
Preferably, body of calming the anger is tieed up in storage in the high-pressure buffering pot, and at least at the gas outlet of the high-pressure buffering pot One pneumatic filter is set.Preferably, the dimension calms the anger body as the one of which such as air, nitrogen, helium, argon gas or at least two The mixing of kind.
Preferably, the high temperature storage tank, liquid heat transfer medium is stored in low-temperature storage tank, the liquid heat transfer medium is thermally conductive Oil, high-temperature silicon oil, fused salt, water vapor, class ion fluid, methanol, liquid metal etc. it is one of or at least two it is mixed It closes.
Preferably, the high temperature storage tank and low-temperature storage tank are inside holding formula or external thermal insulation formula;The high temperature storage tank and low temperature Storage tank tank body can be the connection/of non-detachable welding or detachable flanged joint.
Preferably, the high temperature storage tank and low-temperature storage tank include at least one temperature measuring device, at least one pressure Measuring device, at least one safety valve, at least one liquid injection port, at least one sewage draining exit;Preferably, the high temperature storage tank and low The pressure-bearing range of warm storage tank is 0.01MPa-40.0MPa.
Preferably, the liquid collecting tank includes at least one temperature measuring device, at least one device for pressure measurement, at least one A safety valve, at least one sewage draining exit.
Preferably, the cooler be plank frame, plate-fin structure, tube shell type structure or sped structure one kind or Two kinds or more of combination;The cooler side is the mixture of high pressure gas and liquid heat transfer medium, and the other side is accumulation of heat Flow back after the completion of process or heat release process be in a liquid state or gaseous heat transfer medium;Its heat exchange mode can be fair current, adverse current or Both the mixed flow for including.
Preferably, the condenser be plank frame, plate-fin structure, tube shell type structure or sped structure one kind or Two kinds or more of combination;The regenerator side is the mixture of high pressure gas and liquid heat transfer medium, and side is low temperature stream Body or gas;Its heat exchange mode can be the mixed flow that fair current, adverse current or both all include.
Preferably, under interior heat-retaining condition, the material of pressure vessel inner casing is stainless for the low-temperature storage tank and high temperature storage tank The nonmetallic materials of the heat-and corrosion-resistants such as the metal materials such as steel, aluminium, titanium or ceramics, pressure vessel enclosure material are metal material, Such as stainless steel, carbon steel, aluminium alloy or inorganic non-metallic material one of such as ceramics, high temperature concrete or at least two group It closes, thermal insulation material is filled between inner casing and shell;The low-temperature storage tank and high temperature storage tank are under outer heat-retaining condition, outside pressure vessel Shell material is metal material, such as one in stainless steel, carbon steel, aluminium alloy or inorganic non-metallic material such as ceramics, high temperature concrete Kind or at least two combination.
Preferably, the shell of the cooler, condenser and liquid collecting tank is the metal of high pressure resistant corrosion-and high-temp-resistant Material, such as stainless steel, carbon steel, aluminium alloy or inorganic non-metallic material one of such as ceramics, high temperature concrete or at least two Combination.
Preferably, the low-temperature storage tank, high temperature storage tank, surge tank, liquid collecting tank are cylindrical body or the resistance to height of sphere, high temperature resistant Press corrosion resistant sealed pressure vessel.
The thermal performance test system of the utility model, working principle and process for using are as follows:
In advance, degassing processing is carried out to the system using voltage regulation unit, the air of internal system is drained;Liquid is passed Thermal medium is injected into low-temperature storage tank or high temperature storage tank, injection rate be setting value after close exhaust valve, main pipeline in opening system All valves.The gas flow regulating valve door in voltage regulation unit is adjusted, system is carried out to be forced into setting operating pressure.It is being After system pressure reaches the pressure of setting, it is ensured that the valve that system is connected with atmosphere is in close state.To be measured set is connected simultaneously It is standby, and processing is exhausted in device under test, is replaced with inert gas.
In Devices to test stage regenerator, high-temperature pump is first opened, makes liquid heat transfer medium by high temperature flow measurement and control Enter electric heater after component processed, is allowed to heat liquid heat transfer medium, after heat-transfer fluid is heated to set temperature, stream Enter part to be tested.Heat storage medium when part to be tested is regenerative apparatus, inside high temperature heat transfer fluid and part to be tested Progress heat exchange is to be stored in the heat of heat-transfer fluid inside heat storage medium, the Low Temperature Liquid after heat to be transmitted to heat storage medium State heat transfer medium flows back into low-temperature storage tank or high temperature storage tank by the leakage fluid dram of Devices to test bottom to complete a circulation, when When as the inlet of Devices to test upper and lower ends and the temperature measuring device in exit value obtained, it is complete to be considered as heat-accumulating process At, closing electric heater, and the valve being connected with Devices to test upper and lower ends is closed, high-temperature pump is closed, finally to complete to store Thermal process.In the process, due to the liquid heat transfer medium of internal system and pressure stabilizing gas can due to the raising of temperature itself Volume can be expanded, the pressure of system can be stepped up.After pressure rise to setting pressure, low-temperature storage tank or high temperature storage Relief valve between tank and liquid collecting tank on pipeline automatically turns on, by high temperature and high pressure gas by regenerator/or without regenerator, condensation It is stored in liquid collecting tank after device, after the pressure in liquid collecting tank reaches setting pressure, the relief valve for collecting high temperature storage tank upper end is automatic It opens, the extra gas of tank interior is drained into environment.
In the Devices to test heat release stage, cryogenic pump is opened.Make liquid heat transfer medium by flowrate Measurement in Low Temperature and control Enter cooler after component processed, be allowed to cool down liquid heat transfer medium, after heat-transfer fluid is cooled to set temperature, flows into Heat storage medium inside test block, low temperature heat transfer fluid and part to be tested carries out heat exchange to the heat inside heat storage medium Amount is taken out of, and the high-temperature liquid state heat transfer medium after absorbing the stored heat of heat storage medium passes through the leakage fluid dram of Devices to test bottom, stream Low-temperature storage tank or high temperature storage tank are back to complete a circulation, when the inlet of Devices to test upper and lower ends and the temperature in exit When as measuring device value obtained, it is considered as the completion of heat release process, closes the valve being connected with Devices to test upper and lower ends, Cryogenic pump is closed, finally to complete heat release process.
In entire accumulation of heat and heat release stage, measurement and control unit in test macro all in system each main component, flow, Pressure, temperature are measured and are automatically controlled, and temperature parameter inside device under test and pressure parameter measure and remember Record.
Compared with the existing technology, the thermal performance test system of the utility model, the big, power bracket with use temperature range Extensively, the advantages that Applicable media is wide, temperature control precision is high, flow control accuracy is high.The accumulation of heat of high-power wide temperature range can be filled The heat exchange property of the storage/latent heat releasing performance and large heat exchanger set carries out test experiments and Performance Evaluation.It can be filled for high-temperature heat accumulation Offer heat source/cold source is provided, unstable state process and temperature field characteristics measurement are carried out;High-temperature heat storage device and system are carried out in difference Performance test and survey under temperature, pressure, flow are examined;Extensive high temperature regenerative apparatus array performance test can also be carried out simultaneously With operation reserve research etc. work.Due to These characteristics, the above-mentioned test macro of the utility model is suitable for but is not limited to the sun Can heat generating system, industrial exhaust heat high temperature, the high power heat accumulation equipment, heat exchange equipment in thermmal storages secondary use such as utilize Deng.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model embodiment 1;
Fig. 2 is the structural schematic diagram of the utility model embodiment 2;
Fig. 3 is the structural schematic diagram of the utility model embodiment 3.
Specific embodiment
For the purpose of this utility model, technical solution and advantage is more clearly understood, develop simultaneously implementation referring to the drawings The utility model is further described in example.
Embodiment 1
As shown in Figure 1, being the thermal performance test system embodiment 1 of the utility model, which is mainly used for accumulation of heat The heat storage performance of device is tested, this system includes that measurement and control unit 111, thermal energy generate and storage unit, voltage regulation unit, to be measured Regenerative apparatus 106.
Thermal energy generates and storage unit, including high temperature storage tank 101A, low-temperature storage tank 101B, filter 112A, 112B, pump 102A, 102B, electric heater 104, cooler 105, flow control assembly (including flowmeter 103A, 103B, flow control valve 110A,110B).Wherein, the leakage fluid dram punishment of the first inlet at the top of the high temperature storage tank 101A, the second inlet, bottom It She You not valve 2,3,8;The leakage fluid dram of the first inlet, the second inlet, bottom at the top of the low-temperature storage tank 101B is punished It She You not valve 5,4,10;Valve 13,14 is respectively equipped at the inlet of the electric heater 104, liquid outlet;The storage to be measured The inlet at 106 top of thermal connects a high temperature feed liquor pipeline and a low temperature feed liquor pipeline, the regenerative apparatus to be measured simultaneously The leakage fluid drams of 106 bottoms connects one first tapping line and one second tapping line simultaneously, the high temperature feed liquor pipeline, low temperature into Valve 17,18,16,15 is respectively equipped on liquid pipe line, the first tapping line and the second tapping line;The high temperature storage tank 101A's Leakage fluid dram by pipeline successively through filter 112A, high-temperature pump 102A, be made of flowmeter 103A and flow control valve 110A First flow control assembly, electric heater 104 are connected to the high temperature feed liquor pipeline of the regenerative apparatus 106 to be measured;The low temperature The leakage fluid dram of storage tank 101B is by pipeline successively through filter 112B, cryogenic pump 102B, by flowmeter 103B and flow control valve The second flow control assembly of 110B composition, cooler 105 are connected to the low temperature feed liquor pipeline of the regenerative apparatus 106 to be measured; The leakage fluid dram of the regenerative apparatus to be measured 106 passes through the first tapping line the first feed liquor with the high temperature storage tank 101A respectively Mouthful, the connection of the first inlet of the low-temperature storage tank 101B, and by the second tapping line respectively with the high temperature storage tank 101A The second inlet, the low-temperature storage tank 101B the second inlet connection.
Voltage regulation unit, to carry out degassing processing to the test macro before activation and be in the test macro The stabilization of system pressure is maintained when operating status, the voltage regulation unit includes an at least high-pressure buffering pot 109, a condenser 108 With a liquid collecting tank 107, wherein the air inlet of the high-pressure buffering pot 109 is connected to high voltage stabilizing gas source, the high-pressure buffer The gas outlet of tank 109 and blow vent, the blow vent at the top of low-temperature storage tank 101B, liquid collecting tank at the top of the high temperature storage tank 101A The air inlet at 107 tops is connected to, and is equipped with valve at the gas outlet of the high-pressure buffering pot 109, the air inlet at 107 top of liquid collecting tank Door 1,6, the blow vent at the top of the high temperature storage tank 101A, the blow vent at the top of low-temperature storage tank 101B, liquid collecting tank 107 top go out Relief valve is equipped at port, the hot side of the condenser 108 is located on the admission line of the liquid collecting tank 107, the condensation The cold side of device 108 is passed through condensed water, is equipped with flow control valve at the hot side import and cold side import of the condenser 108 110C、110D。
The regenerative apparatus to be measured 106 can be packed bed regenerative apparatus, and the packed bed regenerative apparatus includes shell, institute It states that case top sets inlet, bottom sets leakage fluid dram, part flow arrangement and packed bed, the part flow arrangement setting is set in housing cavity It is the packed bed filled with solid heat storage medium, main operational principle below the top of housing cavity, the part flow arrangement Be: liquid heat transfer medium pass through part flow arrangement after, be atomized into fine drop or several tiny fluid columns, then with consolidating in packed bed Body heat-storing material carries out heat exchange, the heat that the thermal energy storage in liquid heat transfer medium is got up or stored solid-state heat-storing material It releases, to complete the accumulation of heat/of packed bed heat-storing device or the major function of heat release.
In advance, regenerative apparatus 106 to be measured and the other component of high-temperature heat accumulation test macro are connected, utilizes voltage regulation unit Each pipeline and regenerative apparatus to be measured 106 to test macro carry out degassing processing, by the sky inside system and regenerative apparatus to be measured Gas drains.The liquid injection port that liquid heat transfer medium is passed through to low-temperature storage tank 101B again, is injected into low-temperature storage tank 101B, injection rate is Exhaust valve is closed after setting value, opens all valves of main pipeline in test macro.Adjust the gas flow tune in voltage regulation unit Valve is saved, test macro is carried out to be forced into setting operating pressure.After system pressure reaches the pressure of setting, it is ensured that system with The connected valve of atmosphere is in close state, while all valves of main pipeline are all ensured that and are in off state.
When needing the heat storage capacity to regenerative apparatus 106 to be measured to try, first all valves all passes on main pipeline It closes, opens the valves such as 8,110A, 13,14,17,16,5 later, open high-temperature pump 102A, make the height in the high temperature storage tank 101A Warm liquid heat transfer medium enters after the first flow control assembly by being made of flowmeter 103A and flow control valve 110A Electric heater 104 is allowed to heat high-temperature liquid state heat transfer medium, after liquid heat transfer fluid is heated to set temperature, leads to High temperature inlet tube line is crossed to flow into regenerative apparatus 106 to be measured, high temperature heat transfer fluid and solid heat storage medium carry out heat exchange to The heat of heat-transfer fluid is stored in solid heat storage media interior, the low temperature liquid heat transfer after heat to be transmitted to solid heat storage medium Medium flows back into low-temperature storage tank 101B to complete a circulation, when entering for 106 upper and lower ends of regenerative apparatus to be measured by valve 16 When at mouthful and as the temperature measuring device value obtained in exit, it is considered as heat-accumulating process completion, closes electric heater 104, And the valve 17,16 being connected with 106 upper and lower ends of regenerative apparatus to be measured is closed, pump 102A is closed, finally to complete accumulation of heat Journey.In the process, due to the liquid heat transfer medium of internal system and pressure stabilizing gas can due to the raising of temperature itself body Product can be expanded, and the pressure of system can be stepped up.After pressure rise to setting pressure, low-temperature storage tank 101B or high temperature storage Relief valve between tank 101A and liquid collecting tank 107 on pipeline automatically turns on, by high temperature and high pressure gas by regenerator/or without backheat It is stored in liquid collecting tank 107 after device, condenser 108, after the pressure in liquid collecting tank 107 reaches setting pressure, on liquid collecting tank 107 The relief valve at end automatically turns on, and the extra gas of tank interior is drained into environment.
Before the latent heat releasing performance to regenerative apparatus 106 to be measured is tested, first all valves all passes on main pipeline It closes, when beginning preparing to regenerative apparatus 106 to be measured progress latent heat releasing performance test, opens the valves such as valve 10,110B, 18,16,2 Door, then opens cryogenic pump 102B, makes liquid heat transfer medium in the by being made of flowmeter 103B and flow control valve 110B Enter cooler 105 after two flow control assemblies, is allowed to cool down liquid heat transfer medium, be cooled in liquid heat transfer fluid After set temperature, regenerative apparatus 106 to be measured is flowed into, the solid heat storage inside low temperature heat transfer fluid and regenerative apparatus 106 to be measured is situated between Matter carries out height of the heat exchange to which the heat of solid heat storage media interior is taken out of, after absorbing the stored heat of solid heat storage medium Warm liquid heat transfer medium passes through the leakage fluid dram of 106 bottom of regenerative apparatus to be measured, and passes through the first tapping line or the second drain pipe Line flows back into high temperature storage tank 101A or low-temperature storage tank 101B to complete a circulation, when 106 upper and lower ends of regenerative apparatus to be measured When as the temperature measuring device in inlet and exit value obtained, it is considered as the completion of heat release process, closes and accumulation of heat to be measured Two valves 18 and 16 or 15 that 106 upper and lower ends of device are connected close cryogenic pump 102B, finally to complete heat release process.
In entire accumulation of heat and heat release stage, the TT&C system in high-temperature heat accumulation test macro is all to each main portion in system Part, flow, pressure, temperature are measured and are automatically controlled, and temperature parameter and pressure parameter progress inside device under test Measurement and record.
For further promoted the utility model above-mentioned high-temperature heat accumulation Performance Test System test performance, it is shown in FIG. 1 Test macro can also carry out the behaviour such as high temperature fluid preparation, cryogen preparation, high temperature fluid self-loopa, cryogen self-loopa Make.
When carrying out high temperature fluid preparation flow, all valves being first shut off on main pipeline, later open 10,110B, 19, the valves such as 13,14,7,2, flowed under the driving that the liquid heat transfer fluid in low-temperature storage tank 101B passes through cryogenic pump 102B electricity plus In hot device 104, is controlled by the power regulation and temperature of electric heater 104, low temperature heat transfer fluid is heated to set temperature simultaneously It flows into high temperature storage tank 101A, which guarantees to maintain the heat-transfer fluid in high temperature storage tank 101A in certain volume and specific temperature Under degree.
When carrying out cryogen preparation flow, all valves being first shut off on main pipeline, later open 8,110A, 19, the valves such as 20,5, inflow cooler 105 under the driving that the liquid heat transfer fluid in high temperature storage tank 101A passes through high-temperature pump 102A In exchanged heat and cooled down with recirculated water, be finally flowed into low-temperature storage tank 101B, the function guarantee maintain low-temperature storage tank Heat-transfer fluid in 101B is under certain volume and specific temperature.
When carrying out cryogen self-loopa process, all valves being first shut off on main pipeline, later open 10, The valves such as 110B, 105,20,5, inflow cooler under the driving that the heat-transfer fluid in low-temperature storage tank 101B passes through cryogenic pump 102B It is exchanged heat and is cooled down with recirculated water in 105, last to be flowed into low-temperature storage tank 101B again, which can ensure that low-temperature storage tank Temperature in 101B remains at a relatively low temperature.
When carrying out high temperature fluid self-loopa process, all valves being first shut off on main pipeline, later open 8,110A, 13, the valves such as 14,7,2, the heat-transfer fluid in high temperature storage tank 101A flow into electric heater 104 under the driving of high-temperature pump 102A In, it is controlled by the power regulation and temperature of electric heater 104, heat-transfer fluid is heated to set temperature and flows into high temperature storage tank In 101A, which can ensure that the temperature in high temperature storage tank 101A remains at a relatively high temperature.
Embodiment 2
As shown in Fig. 2, unlike the first embodiment, the heat exchange property which is mainly used for exchanging thermal carries out Test.The leakage fluid dram of heat-exchanger rig 106 to be measured connects a high temperature tapping line and a low temperature tapping line, high temperature tapping line and Low temperature tapping line is connected to the inlet of high temperature storage tank 101A and low-temperature storage tank 101B;When to heat-exchanger rig 106 to be measured When heat exchange property is tested, the low temperature heat transfer fluid in low-temperature storage tank 101B is logical through cooler 105 under the driving of cryogenic pump 102B The cold side that low temperature inlet tube line flows into heat-exchanger rig 106 to be measured is crossed, and passes through the high temperature tapping line stream of heat-exchanger rig 106 to be measured Enter low-temperature storage tank 101B out;At the same time, the high temperature heat transfer fluid in high temperature storage tank 101A is under the driving of high-temperature pump 102A The hot side of heat-exchanger rig 106 to be measured is flowed by high temperature feed liquor pipeline after electric heater 104, and passes through heat-exchanger rig to be measured 106 low temperature tapping line flows into high temperature storage tank 101A, thus realize the heat exchange property of heat-exchanger rig to be measured is measured and Assessment.
Embodiment 3
As shown in figure 3, being the high-temperature heat accumulation Performance Test System embodiment 3 of the utility model, this system is mainly by observing and controlling Unit 111, thermal energy are generated to be formed with storage unit, dimension pressure unit, 106 4 major part of tested device test macro heat exchanger.Its Middle thermal energy generates and contains three parallel connection type high temperature storage tank 101A1,101A2,101A3, three low-temperature storage tanks in parallel in storage unit 101B1,101B2,101B3, four 112A1,112A2 of filter, 112B1,112B2, pump four 102A1,102A2,102B1, 102B2, electric heater one 104, one 105, cooler, high temperature resistant flowmeter two 103A, 103B;Dimension pressure unit includes slow Rush tank 109, condenser 108, liquid collecting tank 107;Wherein tested device is liquid liquid heat exchanger 106.The main work of the packed bed 106 It is to complete the energy exchange of two kinds of different liquids as principle, what side fluid temperature (F.T.) reduced is increased to side fluid temperature (F.T.) to reach Purpose.High-temperature heat accumulation test macro further includes pressure-control valve 110A, 110B, 110C, 110D, 110E, while further including several Temperature and device for pressure measurement.
In advance, Devices to test heat exchanger 106 and high-temperature heat accumulation test macro are connected, high temperature is stored using dimension pressure device Thermal test system and packed bed carry out degassing processing, and the air inside system and packed bed is drained.Again by liquid heat transfer medium It by the pouring orifice of pressure-bearing thermal-insulating type low-temperature storage tank, is injected into low-temperature storage tank, injection rate is beaten to close exhaust valve after setting value Open all valves of main pipeline in test macro.The gas flow regulating valve door in dimension pressure system is adjusted, test macro is carried out It is forced into setting operating pressure.After system pressure reaches the pressure of setting, it is ensured that the valve that system is connected with atmosphere, which is in, to close Closed state, while all valves of main pipeline are all ensured that and are in off state.
When due to carrying out performance measurement to liquid liquid heat exchanger, needing cold and hot heat-transfer fluid, inflow heat exchanger is surveyed simultaneously Amount.Therefore between starting to be tested, therefore, to assure that the oil of low-temperature storage tank and high temperature storage tank is all set temperature.Meet this It is required that when all valves are all closed, need to open valve 21,22,23,110A, 32,33,27,2,3,4, open pump 102A1, 102A2 is then turned on electric heater 104, makes the liquid heat transfer fluid inside high temperature storage tank 101A1/2/3 by adding after electric heater Heat to set temperature is flowed into high temperature storage tank, closes electricity after the heat-transfer fluid temperature in high temperature storage tank reaches set temperature Heater turns off pump 102A1/2.
Be then shut off all valves, and open valve 24,25,26,110B, 35,5,6,7 etc., pump 102B1/2 is opened, is made Liquid heat transfer fluid inside low-temperature storage tank 101A1/2/3 flows through after cooler 105 is cooled to set temperature is flowed into low temperature again In storage tank, pump 102A1/2 is closed after the heat-transfer fluid temperature in high temperature storage tank reaches set temperature.
During testing liquid liquid heat exchanger, the high temperature fluid in high temperature storage tank 101A1/2/3 is by pump 102A1/2, stream Heat exchanger side is entered by valve 17 after meter 103A, electric heater 104, inside Devices to test with the low temperature of the other side Heat-transfer fluid carries out indirect heat exchange, and temperature is increased and is flowed into high temperature storage tank 101A1/2/3 by exchanger base valve 36;With This simultaneously, cryogen in low-temperature storage tank 101B1/2/3 is led to after pump 102B1/2, flowmeter 103B and cooler 105 The other side that valve 18 enters heat exchanger 106 is crossed, carries out indirect heat exchange, temperature with the high temperature heat transfer fluid of its internal other side It is flowed into low-temperature storage tank 101B1/2/3 after reduction by exchanger base valve 37.
In entire 106 test process of heat exchanger, the TT&C system in high-temperature heat accumulation test macro is all to each in system Main component, flow, pressure, temperature are measured and are automatically controlled, and temperature parameter and pressure ginseng inside device under test Number is measured and is recorded, and can be analyzed and be assessed with the performance parameter of device under test liquid liquid heat exchanger at any time.
Through the foregoing embodiment, the purpose of this utility model is completely effectively realized.Person skilled in art can be with Understand that the utility model includes but is not limited to content described in attached drawing and the above specific embodiment.Although the utility model is Just it is now recognized that the most practical and preferred embodiment is illustrated, it should be understood that the utility model be not limited to it is disclosed The modification of embodiment, any function and structure principle without departing from the utility model is intended to be included in the range of claims In.

Claims (10)

1.一种热性能测试系统,用以测试蓄热装置的蓄热性能或换热装置的换热性能,所述系统包括热能产生与存储单元、稳压单元、待测试验件及测控单元,其特征在于,1. A thermal performance testing system for testing the thermal storage performance of a thermal storage device or the heat exchange performance of a heat exchange device, the system comprising a thermal energy generation and storage unit, a voltage regulator unit, a test piece to be tested and a measurement and control unit, It is characterized in that, 所述热能产生与存储单元,包括高温储罐、低温储罐、高温泵、低温泵、高温流量测量及控制组件、低温流量测量及控制组件、电加热器、冷却器,其中,The thermal energy generation and storage unit includes a high temperature storage tank, a low temperature storage tank, a high temperature pump, a low temperature pump, a high temperature flow measurement and control assembly, a low temperature flow measurement and control assembly, an electric heater, and a cooler, wherein, 所述高温储罐、低温储罐及电加热器的进液口、出液口处均设有控制阀门;Control valves are provided at the liquid inlet and outlet of the high temperature storage tank, the low temperature storage tank and the electric heater; 所述待测试验件顶部的进液口同时连接一高温进液管线和一低温进液管线,所述待测试验件底部的排液口连接至少一排液管线,所述高温进液管线、低温进液管线、排液管线上均设有阀门;The liquid inlet at the top of the test piece to be tested is simultaneously connected to a high temperature liquid inlet pipeline and a low temperature liquid inlet pipeline, the liquid discharge port at the bottom of the test piece to be tested is connected to at least one liquid discharge pipeline, and the high temperature liquid inlet pipeline, There are valves on the low temperature liquid inlet pipeline and the liquid discharge pipeline; 所述高温储罐的出液口通过管线依次经高温泵、高温流量测量及控制组件、电加热器与所述待测试验件的高温进液管线连通;The liquid outlet of the high-temperature storage tank is connected with the high-temperature liquid inlet pipeline of the test piece to be tested through a pipeline through a high-temperature pump, a high-temperature flow measurement and control assembly, and an electric heater; 所述低温储罐的出液口通过管线依次经低温泵、低温流量测量及控制组件、冷却器与所述待测试验件的低温进液管线连通;The liquid outlet of the low-temperature storage tank is connected to the low-temperature liquid inlet pipeline of the test piece to be tested through the pipeline through the low-temperature pump, the low-temperature flow measurement and control assembly, and the cooler in sequence; 所述待测试验件的排液管线分别与所述高温储罐的进液口、所述低温储罐的进液口连通;The liquid discharge pipeline of the test piece to be tested is respectively connected with the liquid inlet of the high temperature storage tank and the liquid inlet of the low temperature storage tank; 所述稳压单元,用以在启动前对所述测试系统进行除气处理以及在所述测试系统处于运行状态时维持系统压力的稳定,所述稳压单元包括至少一高压缓冲罐、一冷凝器和一集液罐,其中,The pressure-stabilizing unit is used for degassing the test system before starting and maintaining the stability of the system pressure when the test system is in a running state. The pressure-stabilizing unit includes at least a high-pressure buffer tank, a condensation device and a collecting tank, of which, 所述高压缓冲罐的进气口与高压稳压气体源连通,The air inlet of the high pressure buffer tank is communicated with the high pressure stabilized gas source, 所述高压缓冲罐的出气口与所述高温储罐顶部的通气口、低温储罐顶部的通气口、集液罐顶部的进气口连通,The air outlet of the high-pressure buffer tank is communicated with the ventilation port at the top of the high-temperature storage tank, the ventilation port at the top of the low-temperature storage tank, and the air inlet at the top of the liquid collecting tank, 所述高压缓冲罐的出气口、集液罐顶部的进气口处均设有阀门,Valves are provided at the air outlet of the high-pressure buffer tank and the air inlet at the top of the liquid collecting tank. 所述高温储罐顶部的通气口、低温储罐顶部的通气口、集液罐顶部的出气口处均设有泄压阀,A pressure relief valve is provided at the vent on the top of the high-temperature storage tank, the vent on the top of the low-temperature storage tank, and the air outlet on the top of the liquid collecting tank. 所述冷凝器的热侧位于所述集液罐的进气管线上,所述冷凝器的冷侧通入冷凝水;The hot side of the condenser is located on the intake line of the liquid collecting tank, and the cold side of the condenser is fed with condensed water; --所述测控单元,至少与所述热能产生与存储单元中的高温泵、低温泵、高温流量测量及控制组件、低温流量测量及控制组件、电加热器、冷却器以及与所述稳压单元中的各流量控制阀通信连接,并根据反馈信息对各部件进行控制;--The measurement and control unit is at least connected with the high temperature pump, low temperature pump, high temperature flow measurement and control components, low temperature flow measurement and control components, electric heaters, coolers, and the voltage stabilizer in the thermal energy generation and storage unit. Each flow control valve in the unit is connected in communication, and controls each component according to the feedback information; 至少在所述待测试验件进液口、出液口处设置温度传感器和压力传感器,各所述温度传感器、压力传感器均与所述测控单元通信连接,所述测控单元通过对所述待测试验件进液口、出液口处的温度、压力和流量参数进行实时测量和记录,并进行分析和处理,以实现对所述待测试验件热性能的测试和性能评估。At least a temperature sensor and a pressure sensor are arranged at the liquid inlet and outlet of the test piece to be tested, and each of the temperature sensors and pressure sensors is connected in communication with the measurement and control unit. The temperature, pressure and flow parameters at the liquid inlet and outlet of the test piece are measured and recorded in real time, and analyzed and processed, so as to realize the test and performance evaluation of the thermal performance of the test piece to be tested. 2.根据权利要求1所述的热性能测试系统,其特征在于,当所述待测试验件为蓄热装置,对待测蓄热装置进行蓄热及释热性能测试时,其流程至少包括:在蓄热测试流程中,所述高温储罐内的高温液态传热介质被所述高温泵输送通过所述电加热器后流入所述待测蓄热装置中完成蓄热过程,从所述待测蓄热装置排出的低温液态传热介质流回所述低温储罐;2. The thermal performance testing system according to claim 1, characterized in that, when the test piece to be tested is a thermal storage device, and the thermal storage device to be tested is tested for thermal storage and heat release performance, the process at least includes: In the thermal storage test process, the high-temperature liquid heat transfer medium in the high-temperature storage tank is transported by the high-temperature pump through the electric heater and then flows into the thermal storage device to be tested to complete the thermal storage process. The low-temperature liquid heat transfer medium discharged from the thermal storage device flows back to the low-temperature storage tank; 在释热测试流程中,所述低温储罐中的低温液态传热介质被所述低温泵输送通过所述冷却器后流入所述待测蓄热装置中完成释热过程,从所述待测蓄热装置排出的高温液态传热介质流回所述高温储罐;In the heat release test process, the low temperature liquid heat transfer medium in the low temperature storage tank is transported by the cryogenic pump through the cooler and then flows into the heat storage device to be tested to complete the heat release process. The high temperature liquid heat transfer medium discharged from the heat storage device flows back to the high temperature storage tank; 在蓄热和释热过程中,所述测控单元对所述待测蓄热装置进液口、出液口处的温度、压力和流量参数进行实时测量和记录,并进行分析和处理,以实现对所述待测蓄热装置的蓄热和释热实验测试和性能评估。In the process of heat storage and heat release, the measurement and control unit measures and records the temperature, pressure and flow parameters at the liquid inlet and outlet of the heat storage device to be measured in real time, and analyzes and processes them to achieve Heat storage and heat release experimental tests and performance evaluation of the heat storage device to be tested. 3.根据权利要求1所述的热性能测试系统,其特征在于,当所述待测试验件为换热装置时,待测换热装置的排液口连接一高温排液管线和一低温排液管线,所述高温排液管线和低温排液管线均与所述高温储罐和低温储罐的进液口连通;当对所述待测换热装置的换热性能测试时,所述低温储罐中的低温传热流体在所述低温泵的驱动下经所述冷却器通过所述低温进液管线流入所述待测换热装置的冷侧,并通过所述待测换热装置的高温排液管线流出进入所述低温储罐;与此同时,所述高温储罐中的高温传热流体在所述高温泵的驱动下经所述电加热器后通过所述高温进液管线流入所述待测换热装置的热侧,并通过所述待测换热装置的低温排液管线流入所述高温储罐,从而实现对待测换热装置的换热性能进行测量和评估。3 . The thermal performance testing system according to claim 1 , wherein when the test piece to be tested is a heat exchange device, the liquid outlet of the heat exchange device to be tested is connected to a high temperature liquid discharge pipeline and a low temperature discharge pipe. 4 . The high temperature liquid discharge line and the low temperature liquid discharge line are both connected to the liquid inlets of the high temperature storage tank and the low temperature storage tank; when the heat exchange performance of the heat exchange device to be tested is tested, the low temperature The low temperature heat transfer fluid in the storage tank flows into the cold side of the heat exchange device to be tested through the cooler through the low temperature liquid inlet line driven by the cryopump, and passes through the heat exchange device to be tested. The high-temperature liquid discharge line flows out into the low-temperature storage tank; at the same time, the high-temperature heat transfer fluid in the high-temperature storage tank flows in through the high-temperature liquid inlet pipeline after passing through the electric heater under the drive of the high-temperature pump. The hot side of the heat exchange device to be tested flows into the high temperature storage tank through the low temperature drain line of the heat exchange device to be tested, so as to measure and evaluate the heat exchange performance of the heat exchange device to be tested. 4.根据权利要求1至3任一项所述的热性能测试系统,其特征在于,当所述系统处于高温流体制备流程时,所述低温储罐内的低温传热流体在所述低温泵的驱动下流入所述电加热器中,通过对所述电加热器的功率调节和温度控制,把低温传热流体加热至设定温度并流入所述高温储罐中,该功能可确保所述高温储罐中的传热流体的体积和温度。4. The thermal performance testing system according to any one of claims 1 to 3, characterized in that, when the system is in a high-temperature fluid preparation process, the low-temperature heat transfer fluid in the low-temperature storage tank is in the cryogenic pump The low temperature heat transfer fluid is heated to the set temperature and flows into the high temperature storage tank through the power regulation and temperature control of the electrical heater, and this function can ensure that the Volume and temperature of heat transfer fluid in high temperature storage tanks. 5.根据权利要求1至3任一项所述的热性能测试系统,其特征在于,当所述系统处于低温流体制备流程时,所述高温储罐内的高温传热流体在所述高温泵的驱动下流入所述冷却器中进行降温,最后流入到所述低温储罐中,该功能可确保所述低温储罐内的传热流体的体积及温度。5. The thermal performance testing system according to any one of claims 1 to 3, wherein when the system is in a low temperature fluid preparation process, the high temperature heat transfer fluid in the high temperature storage tank is in the high temperature pump It flows into the cooler for cooling under the driving of the radiator, and finally flows into the low-temperature storage tank. This function can ensure the volume and temperature of the heat transfer fluid in the low-temperature storage tank. 6.根据权利要求1至3任一项所述的热性能测试系统,其特征在于,当所述系统处于低温流体自循环流程时,所述低温储罐内的低温传热流体在所述低温泵的驱动下流入所述冷却器中进行降温,最后又流入到所述低温储罐中,该功能可确保所述低温储罐内的传热流体的温度始终保持在一个比较低的温度。6. The thermal performance testing system according to any one of claims 1 to 3, wherein when the system is in a low temperature fluid self-circulation process, the low temperature heat transfer fluid in the low temperature storage tank is at the low temperature Driven by the pump, it flows into the cooler for cooling, and finally flows into the low-temperature storage tank. This function can ensure that the temperature of the heat transfer fluid in the low-temperature storage tank is always kept at a relatively low temperature. 7.根据权利要求1至3任一项所述的热性能测试系统,其特征在于,当所述系统处于高温流体自循环流程时,所述高温储罐内的传热流体在所述高温泵的驱动下流入所述电加热器中,通过所述电加热器的功率调节和温度控制,把传热流体加热至设定温度并流入所述高温储罐中,该功能可确保所述高温储罐内的传热流体的温度始终保持在一个比较高的温度。7. The thermal performance testing system according to any one of claims 1 to 3, wherein when the system is in a high-temperature fluid self-circulation process, the heat transfer fluid in the high-temperature storage tank is in the high-temperature pump. It flows into the electric heater under the driving of the electric heater, and through the power regulation and temperature control of the electric heater, the heat transfer fluid is heated to the set temperature and flows into the high temperature storage tank, this function can ensure the high temperature storage tank. The temperature of the heat transfer fluid in the tank is always maintained at a relatively high temperature. 8.根据权利要求1所述的热性能测试系统,其特征在于,所述低温储罐为2台及以上,采用并联或串联排列方式;所述高温储罐为2台及以上,采用并联或串联排列方式;所述低温泵为1台及以上,1台以上时采用并联或串联排列方式;所述高温泵为1台及以上,1台以上时采用并联或串联排列方式。8. The thermal performance testing system according to claim 1, wherein the number of the low-temperature storage tanks is 2 or more, and a parallel or series arrangement is adopted; the high-temperature storage tanks are 2 or more, and the parallel or Serial arrangement; there are one or more cryogenic pumps, and if there are more than one, a parallel or series arrangement is used; the high temperature pump is one or more, and if there is more than one, a parallel or series arrangement is used. 9.根据权利要求1所述的热性能测试系统,其特征在于,所述高压缓冲罐中存储维压气体,并至少在所述高压缓冲罐的出气口处设置一气体过滤器。9 . The thermal performance testing system according to claim 1 , wherein the pressure-maintaining gas is stored in the high-pressure buffer tank, and a gas filter is provided at least at the gas outlet of the high-pressure buffer tank. 10 . 10.根据权利要求1所述的热性能测试系统,其特征在于,所述高温储罐及低温储罐都包括至少一个温度测量装置、至少一个压力测量装置、至少一个安全阀、至少一个注液口、至少一个排污口;所述集液罐包括至少一个温度测量装置、至少一个压力测量装置、至少一个安全阀、至少一个排污口。10. The thermal performance testing system according to claim 1, wherein the high temperature storage tank and the low temperature storage tank both comprise at least one temperature measurement device, at least one pressure measurement device, at least one safety valve, at least one liquid injection and at least one sewage outlet; the liquid collecting tank includes at least one temperature measuring device, at least one pressure measuring device, at least one safety valve, and at least one sewage outlet.
CN201821437680.3U 2018-09-03 2018-09-03 A kind of thermal performance test system Active CN208736687U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821437680.3U CN208736687U (en) 2018-09-03 2018-09-03 A kind of thermal performance test system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821437680.3U CN208736687U (en) 2018-09-03 2018-09-03 A kind of thermal performance test system

Publications (1)

Publication Number Publication Date
CN208736687U true CN208736687U (en) 2019-04-12

Family

ID=66033520

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821437680.3U Active CN208736687U (en) 2018-09-03 2018-09-03 A kind of thermal performance test system

Country Status (1)

Country Link
CN (1) CN208736687U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110057608A (en) * 2019-04-15 2019-07-26 山东博然电力科技有限公司 A kind of pilot system of air-water heat exchanger
CN111413126A (en) * 2020-04-14 2020-07-14 中国科学院工程热物理研究所 Heat accumulation experimental system and control and detection device thereof
CN119124686A (en) * 2024-08-15 2024-12-13 佛山市芯耀环保科技有限公司 A method and system for detecting heat storage and heat exchange performance

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110057608A (en) * 2019-04-15 2019-07-26 山东博然电力科技有限公司 A kind of pilot system of air-water heat exchanger
CN111413126A (en) * 2020-04-14 2020-07-14 中国科学院工程热物理研究所 Heat accumulation experimental system and control and detection device thereof
CN119124686A (en) * 2024-08-15 2024-12-13 佛山市芯耀环保科技有限公司 A method and system for detecting heat storage and heat exchange performance

Similar Documents

Publication Publication Date Title
CN108918175A (en) A kind of thermal performance test system
CN109059318A (en) A kind of fountain packed bed heat reservoir and its operation method
CN104966536B (en) A kind of high temperature refrigerant heat transfer experiments system and method with conduction oil as hot fluid
CN208983647U (en) A kind of fountain packed bed heat reservoir
CN111307479B (en) A performance testing system for heat storage equipment with steam as working medium
CN201852343U (en) Precise high-temperature cooling compressor refrigerating system
CN104832973B (en) Active solar energy and CO2Air heat source pump combines heating control system and its control method
CN118129067B (en) Energy recovery type supercritical compressed carbon dioxide energy storage system and constant pressure energy release method
CN113686918A (en) Liquid lead bismuth alloy and SCO2Loop coupling heat transfer characteristic research experiment system
CN111238281A (en) An adjustable cascade phase change heat storage device and control method
CN114077271B (en) A high-temperature chloride salt photothermal and energy storage cycle simulation experiment platform and experiment method
CN110657697A (en) A kind of valley electricity energy storage device and using method thereof
Vesely et al. Design of experimental loop with supercritical carbon dioxide
CN113948229B (en) Analysis method for stable operation condition of ocean nuclear power heat pipe type waste heat discharging system
CN118275152A (en) A device and method for testing flow heat transfer characteristics of supercritical carbon dioxide
CN212081701U (en) Step heat accumulation temperature control system based on phase change energy storage technology
CN111735648B (en) System and method for testing thermal performance of pressurized water reactor main evaporator proportional prototype
CN110530182B (en) Special-shaped separate heat pipe waste heat recovery evaporation device for passive ORC system
CN109883234A (en) A kind of normal pressure phase change material device
CN111781239B (en) A high-efficiency closed thermochemical adsorption heat storage test system
CN115750008B (en) Supercritical carbon dioxide experimental device capable of simultaneously measuring the performance of multiple heat exchangers
CN216285014U (en) A Visualized CO2 Mixed Working Fluid Saturation State Point Test System
CN117877778A (en) A liquid metal loop and Stirling coupling experimental system and its use method
CN217465005U (en) Pressurizing cold storage device
CN211576579U (en) A performance testing system for heat storage equipment with steam as working medium

Legal Events

Date Code Title Description
GR01 Patent grant