CN208633259U - A prefabricated interception well - Google Patents

A prefabricated interception well Download PDF

Info

Publication number
CN208633259U
CN208633259U CN201820877996.8U CN201820877996U CN208633259U CN 208633259 U CN208633259 U CN 208633259U CN 201820877996 U CN201820877996 U CN 201820877996U CN 208633259 U CN208633259 U CN 208633259U
Authority
CN
China
Prior art keywords
pipe
prefabricated
well body
interception
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820877996.8U
Other languages
Chinese (zh)
Inventor
袁健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GAOYOU HENGLI HYDRAULIC WHOLE SET EQUIPMENT Co Ltd
Original Assignee
GAOYOU HENGLI HYDRAULIC WHOLE SET EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GAOYOU HENGLI HYDRAULIC WHOLE SET EQUIPMENT Co Ltd filed Critical GAOYOU HENGLI HYDRAULIC WHOLE SET EQUIPMENT Co Ltd
Priority to CN201820877996.8U priority Critical patent/CN208633259U/en
Application granted granted Critical
Publication of CN208633259U publication Critical patent/CN208633259U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a kind of prefabricated Vatch basin, including well body, and water inlet pipe, outlet pipe are provided in well body and cuts dirty pipe;Liquid level sensor, monitoring device and the sealing lifting gate for being opened and closed outlet pipe are provided in well body;Automatic control device is provided with outside well body, liquid level sensor, monitoring device, sealing lifting gate are connect with automatic control device respectively.Lifting gate is sealed in the utility model to change gatage automatically according to its two sides SEA LEVEL VARIATION, to ensure sewage, initial rainwater, later period rainwater flow direction;The engineering construction duration can be shortened by installing prefabricated Vatch basin, be used manpower and material resources sparingly;First rain and later period rainwater are separately handled in the course of work, greatly improve sewage treatment plant's working efficiency.When such as the Vatch basin is passed into disuse, prefabricated Vatch basin can integrally be dug out and hang away recycling, a large amount of building wastes will not be generated.

Description

A kind of prefabricated Vatch basin
Technical field
The utility model belongs to drainage system technical field, and in particular to a kind of prefabricated Vatch basin.
Background technique
When raining, the rainwater at initial stage can carry a large amount of poisonous and harmful substances and enter storm sewer, if being directly discharged into nature Water body then can seriously pollute water environment.Currently, the Vatch basin system generallyd use is to retain rainwater to sewage conduct, enter Sewage treatment plant's processing.If substantially reducing sewage treatment plant's working efficiency regardless of first rain and later period rainwater, and existing shut off Well is reinforced concrete structure, and for reinforced concrete structure Vatch basin from construction is designed into, entire construction period is long, at high cost, such as It needs to remove, essentially building waste, not recoverable;Therefore, it is necessary to one kind separately to handle first rain, later period rainwater, The prefabricated Vatch basin of duration of a project can be shortened again.
Utility model content
Goal of the invention: in view of the deficienciess of the prior art, the purpose of the utility model is to provide one kind can by first rain, Later period rainwater is separately handled, and can shorten the prefabricated Vatch basin of duration of a project.
Technical solution: in order to achieve the above-mentioned object of the invention, the technical solution adopted in the utility model is as follows:
A kind of prefabricated Vatch basin, including well body are provided with water inlet pipe, outlet pipe in the well body and cut dirty pipe, described Water inlet pipe is connected with municipal wastewater pipeline, and the outlet pipe is connected with natural water, and described section of dirty pipe is connected with sewage treatment plant; Liquid level sensor, monitoring device and the sealing lifting gate for being opened and closed outlet pipe are provided in the well body;Outside the well body Be provided with automatic control device, the liquid level sensor, monitoring device, sealing lifting gate respectively with automatic control device Connection.
Preferably, the water inlet pipe, outlet pipe and section dirty pipe are separately positioned on the lower sidewall of well body, the water inlet pipe It is arranged on the opposite side wall of well body with outlet pipe, described section of dirty pipe is arranged perpendicular to water inlet pipe and outlet pipe.
Preferably, the water inlet pipe and outlet pipe are concentric.
Preferably, being provided with guardrail in the well body internal upper part.
Preferably, being provided with maintenance channel below the guardrail, and the maintenance channel is located at sealing lifting gate Top.
Preferably, the monitoring device is the camera for being mounted on top in well body, there are two the camera installations, It is located in the opposite two side walls of well body.
Preferably, the well body is round or rectangular.
Preferably, the automatic control device is single-chip microcontroller or PLC control cabinet, the automatic control device is adopted Collect and judge the liquid level information of liquid level sensor, the opening and closing of control sealing lifting gate, thus control sewage, initial rainwater and after Phase rainwater flow direction.
The utility model has the advantages that compared with prior art, the utility model has the advantage that
The utility model need to only dig the hole of certain depth at the construction field (site), be not necessarily to a large amount of reinforcing bars and concreting;It is prefabricated Vatch basin is hung in hole to construction site by crane, and connects drainage pipeline, and fixed rear perimeter edge landfill is adjustable, prefabricated to shut off In well seal lifting gate can change automatically gatage according to its two sides SEA LEVEL VARIATION, with ensure sewage, initial rainwater, after Phase rainwater flow direction.The engineering construction duration can be shortened by installing prefabricated Vatch basin, be used manpower and material resources sparingly;In the course of work by first rain and Later period rainwater is separately handled, and greatly improves sewage treatment plant's working efficiency.When such as the Vatch basin is passed into disuse, it can shut off prefabricated Well, which is integrally dug out, hangs away recycling, does not generate a large amount of building wastes.
Detailed description of the invention
Fig. 1 is prefabricated Vatch basin vertical profile figure;
Fig. 2 is prefabricated Vatch basin transverse cross-sectional view.
Specific embodiment
Combined with specific embodiments below, the present invention is furture elucidated, and embodiment is under the premise of the technical scheme of the present invention Implemented, it should be understood that these examples are only for illustrating the present invention and are not intended to limit the scope of the present invention.
As illustrated in fig. 1 and 2, the prefabricated Vatch basin of the application mainly includes well body 1, guardrail 2, maintenance channel 3, water inlet pipe 4, monitoring device 5, liquid level sensor 6, outlet pipe 7, sealing lifting gate 8, section dirty pipe 9 and automatic control device 10.In well It is provided with water inlet pipe 4, outlet pipe 7 on body 1 and cuts dirty pipe 9, water inlet pipe 4 is connected with municipal wastewater pipeline, outlet pipe 7 and Natural Water Body is connected, and cuts dirty pipe 9 and is connected with sewage treatment plant;Liquid level sensor 6, monitoring device 5 and opening and closing water outlet are provided in well body 1 The sealing lifting gate 8 of pipe 7;Automatic control device 10, liquid level sensor 6, monitoring device 5, sealing are provided with outside well body 1 Lifting gate 8 is connect with automatic control device 10 respectively.
Well body 1 is circle or rectangular, and as preferred embodiment, the diagram well body 1 of the present embodiment is circle, circular The production and processing of well body 1 is convenient, and when installation occupies little space.Water inlet pipe 4, outlet pipe 7 and a section dirty pipe 9 are separately positioned on well body 1 Lower sidewall, water inlet pipe 4 and outlet pipe 7 are arranged on the opposite side wall of well body 1, cut dirty pipe 9 perpendicular to water inlet pipe 4 and outlet pipe 7 settings, water inlet pipe 4 and outlet pipe 7 are concentric, and when big convenient for rainfall, rainwater quickly passes through outlet pipe 7 and is discharged into natural water.
1 internal upper part of well body is provided with guardrail 2, maintenance channel 3 is provided with below guardrail 2, and maintenance channel 3 is positioned at close 8 top of lifting gate is sealed, guardrail 2 can bear the total amount for the personnel of applying, prevent from falling into well, be additionally provided on guardrail 2 and lead to well The ladder at bottom can bear the weight of service personnel.Access path 3 carries out sealing lifting gate 8 and water pipe convenient for staff Maintenance and inspection.
Monitoring device 5 is the camera for being mounted on top in well body 1, preferably there are two camera installations, is located at well In the opposite two side walls of body 1.Automatic control device 10 is single-chip microcontroller or PLC control cabinet, automatic control device acquisition And judge the liquid level information of liquid level sensor 6, control sealing lifting gate opening and closing, thus control sewage, initial rainwater and after Phase rainwater flow direction.
The working process and principle of the utility model:
When dry season, sealing lifting gate 8, which is in, rises closed state, after sewage enters well body 1 by water inlet pipe 4, then by cutting Dirty pipe 9 enters sewage treatment plant;
When spotting, sealing lifting gate 8, which is in, rises closed state, and rainwater and sanitary sewage enter well by water inlet pipe 4 After body 1, then by cutting dirty pipe 9 into sewage treatment plant;
In lower when raining heavyly, when liquid level is no more than the warning liquid level that liquid level sensor 6 is arranged, sealing lifting gate 8 is in After rising closed state, initial rainwater and sanitary sewage enter well body 1 by water inlet pipe 4, then by cutting a dirty pipe 9 into sewage treatment Factory;When liquid level is more than the warning liquid level that liquid level sensor 6 is arranged, sealing lifting gate 8 is in decline open state, later period rain Water by water inlet pipe 4 enter well body 1 after, then by outlet pipe 7 enter natural water;
When natural water liquid level is higher than sewage level, sealing lifting gate 8, which is in, rises closed state, prevents Natural Water Body, which flows backward, enters sewage conduct;Everything process and data acquisition are completed by monitoring device 5 and automatic control device 10.
In conclusion the utility model may be implemented the separated processing of sewage, initial rainwater, later period rainwater, i.e., sewage and First rain is discharged into sewage treatment plant and is handled, and later period rainwater enters natural water.
Prefabricated Vatch basin and auxiliary device instrument and automated system all complete in factory, and construction site only needs to dig The hole of certain depth is not necessarily to a large amount of reinforcing bars and concreting;Prefabricated Vatch basin to construction site by crane hang as hole in, and even Run in waterpipe, and fixed rear perimeter edge landfill is adjustable, and sealing lifting gate can become according to its two sides water level in prefabricated Vatch basin Change and change gatage automatically, to ensure sewage, initial rainwater, later period rainwater flow direction.Installing prefabricated Vatch basin can shorten It the engineering construction duration, uses manpower and material resources sparingly;First rain and later period rainwater are separately handled in the course of work, greatly improve sewage treatment Factory's working efficiency.When such as the Vatch basin is passed into disuse, prefabricated Vatch basin can integrally be dug out and hang away recycling, do not generated a large amount of Building waste.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art For art personnel, without departing from the principle of this utility model, several improvements and modifications can also be made, these improve and Retouching also should be regarded as the protection scope of the utility model.

Claims (8)

1.一种预制截流井,其特征在于:包括井体,在所述井体上设置有进水管、出水管和截污管,所述进水管与市政污水管道相连,所述出水管与自然水体相连,所述截污管与污水处理厂相连;在所述井体内设置有液位传感器、监控装置和开闭出水管的密封升降闸门;在所述井体外设置有自动化控制装置,所述液位传感器、监控装置、密封升降闸门分别与自动化控制装置连接。1. A prefabricated interception well, characterized in that: it comprises a well body, and is provided with a water inlet pipe, a water outlet pipe and a sewage interception pipe on the well body, and the water inlet pipe is connected with the municipal sewage pipe, and the water outlet pipe is connected with the natural sewage pipe. The water body is connected, and the sewage interception pipe is connected with the sewage treatment plant; a liquid level sensor, a monitoring device and a sealing lift gate for opening and closing the water outlet pipe are arranged in the well body; an automatic control device is arranged outside the well body, and the The liquid level sensor, the monitoring device and the sealing lift gate are respectively connected with the automatic control device. 2.根据权利要求1所述的预制截流井,其特征在于:所述进水管、出水管和截污管分别设置在井体的侧壁下部,所述进水管和出水管设置在井体相对的侧壁上,所述截污管垂直于进水管与出水管设置。2 . The prefabricated interception well according to claim 1 , wherein the water inlet pipe, the water outlet pipe and the sewage interception pipe are respectively arranged at the lower part of the side wall of the well body, and the water inlet pipe and the water outlet pipe are arranged opposite to the well body. 3 . On the side wall of the pipe, the sewage interception pipe is arranged perpendicular to the water inlet pipe and the water outlet pipe. 3.根据权利要求2所述的预制截流井,其特征在于:所述进水管与出水管同轴心。3 . The prefabricated interception well according to claim 2 , wherein the water inlet pipe and the water outlet pipe are coaxial. 4 . 4.根据权利要求1所述的预制截流井,其特征在于:在所述井体内上部设置有护栏。4 . The prefabricated interception well according to claim 1 , wherein a guardrail is arranged on the upper part of the well body. 5 . 5.根据权利要求4所述的预制截流井,其特征在于:在所述护栏下方设置有维修通道,且所述维修通道位于密封升降闸门上方。5 . The prefabricated interception well according to claim 4 , wherein a maintenance channel is provided below the guardrail, and the maintenance channel is located above the sealing lift gate. 6 . 6.根据权利要求1所述的预制截流井,其特征在于:所述监控装置为安装在井体内上方的摄像头,所述摄像头安装有两个,分别位于井体相对的两个侧壁上。6 . The prefabricated interception well according to claim 1 , wherein the monitoring device is a camera installed above the well body, and two of the cameras are installed on two opposite side walls of the well body. 7 . 7.根据权利要求1所述的预制截流井,其特征在于:所述井体为圆形或者方形。7 . The prefabricated interception well according to claim 1 , wherein the well body is circular or square. 8 . 8.根据权利要求1所述的预制截流井,其特征在于:所述自动化控制装置为单片机或者PLC控制柜,所述自动化控制装置采集并判断液位传感器的液位信息,控制密封升降闸门的开闭,从而控制污水、初期雨水和后期雨水流向。8 . The prefabricated interception well according to claim 1 , wherein the automatic control device is a single-chip microcomputer or a PLC control cabinet, and the automatic control device collects and judges the liquid level information of the liquid level sensor, and controls the level of the sealing lift gate. 9 . Open and close to control the flow of sewage, initial rainwater and later rainwater.
CN201820877996.8U 2018-06-07 2018-06-07 A prefabricated interception well Expired - Fee Related CN208633259U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820877996.8U CN208633259U (en) 2018-06-07 2018-06-07 A prefabricated interception well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820877996.8U CN208633259U (en) 2018-06-07 2018-06-07 A prefabricated interception well

Publications (1)

Publication Number Publication Date
CN208633259U true CN208633259U (en) 2019-03-22

Family

ID=65735136

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820877996.8U Expired - Fee Related CN208633259U (en) 2018-06-07 2018-06-07 A prefabricated interception well

Country Status (1)

Country Link
CN (1) CN208633259U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459206A (en) * 2019-11-11 2021-03-09 扬州蓝翔机电工程有限公司 Telescopic adapting plug, sewage intercepting well with adapting plug and construction method of sewage intercepting well
CN114352760A (en) * 2020-08-26 2022-04-15 武汉圣禹排水系统有限公司 Water treatment facility and drainage system with mechanism dams

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459206A (en) * 2019-11-11 2021-03-09 扬州蓝翔机电工程有限公司 Telescopic adapting plug, sewage intercepting well with adapting plug and construction method of sewage intercepting well
CN112459206B (en) * 2019-11-11 2025-04-18 扬州蓝翔机电工程有限公司 Telescopic receiving plug, sewage interception well with the receiving plug and construction method thereof
CN114352760A (en) * 2020-08-26 2022-04-15 武汉圣禹排水系统有限公司 Water treatment facility and drainage system with mechanism dams

Similar Documents

Publication Publication Date Title
CN207392409U (en) A kind of Mobyneb Vatch basin system
CN105464202B (en) A kind of rainwater discharging well with the adjustable flap valve that dams
CN105507415A (en) Rainwater abandoning well with lifting-type shutoff rubber clack check valve
CN104179248B (en) A kind of vacuum of drainage pipeline networks rinses desilting system
CN208633259U (en) A prefabricated interception well
CN112012306A (en) Sewage intercepting well of residential area and using method thereof
CN113565189B (en) Device capable of automatically controlling rainwater collection and drainage
CN207313403U (en) Intelligent environment protection septic tank system
CN207846619U (en) A kind of turnover panel flow abandoning apparatus
CN110397142A (en) A system and method for flushing and diverting municipal sewage pipes
CN114876046A (en) A kind of multifunctional intelligent management well and control method
CN110578367A (en) Prefabricated vatch basin
CN211597025U (en) An underground rainwater recycling device
CN204401778U (en) Integrated sewage water Boosting pumping station
CN111236391A (en) Intelligent sewage intercepting inspection well
CN208633258U (en) A prefabricated diverter well
CN202730928U (en) Novel rainwater collection system
CN206256528U (en) A kind of early-stage rainwater of confluence of rainwater and sewage pipe separates and collects processing unit
CN213233668U (en) Cut-off equipment, cut-off system for riser
CN204959950U (en) Rainwater automatic collection emptying devices
CN211172290U (en) Gutter inlet filtering and dirt-intercepting hanging basket capable of improving discharged water quality and easy to clean
CN209163262U (en) A kind of rain leader downspout rain sewage diversion device
CN207295964U (en) A kind of horizontal prefabricated pumping plant of integration
CN221941783U (en) A rainwater and sewage diversion well
CN206256529U (en) A kind of early-stage rainwater stream abandoning processing system of confluence of rainwater and sewage pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190322

CF01 Termination of patent right due to non-payment of annual fee