CN208440942U - A kind of municipal works road pavement structure - Google Patents

A kind of municipal works road pavement structure Download PDF

Info

Publication number
CN208440942U
CN208440942U CN201821140446.4U CN201821140446U CN208440942U CN 208440942 U CN208440942 U CN 208440942U CN 201821140446 U CN201821140446 U CN 201821140446U CN 208440942 U CN208440942 U CN 208440942U
Authority
CN
China
Prior art keywords
road
water
pavement
municipal works
abs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821140446.4U
Other languages
Chinese (zh)
Inventor
黄�隆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821140446.4U priority Critical patent/CN208440942U/en
Application granted granted Critical
Publication of CN208440942U publication Critical patent/CN208440942U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of municipal works road pavement structures, it is related to road pavement technical field of structures, it is particularly suitable for the road Municipal project Zhong Lv, pavement, it goes slowly channel, the low influence development & construction in the projects combination sponge city such as garden road use, specially a kind of municipal works road pavement structure, including pavement of road, the lower surface of the pavement of road is equipped with water-permeable brick, the lower surface of the water-permeable brick is provided with ABS net form skeleton, the inside of the ABS net form skeleton is filled with haydite, sand metalling is equipped with below the ABS net form skeleton, the sand metalling is internally provided with draining blind pipe.The municipal works road pavement structure, pass through the design of the colorful water-permeable concrete and lower section pervious bed of pavement of road, not only make the water permeability of road good, and keep entire road surface also relatively beautiful, establish good city image, the design of sand metalling plays the role of filtration, purification to rainwater etc., and infiltration effect is also very good.

Description

A kind of municipal works road pavement structure
Technical field
The utility model relates to road pavement technical field of structures, are particularly suitable for the road Municipal project Zhong Lv, people The low influence development & construction in the projects combination sponge city such as trade, channel of going slowly, garden road use, specially a kind of municipal works road Laying structure.
Background technique
Sponge city is new generation of city storm water man- agement concept, refers to that city is adapting to environmental change and reply rainwater band Natural calamity come etc. has good " elasticity ", and also referred to as " water elasticity city ", international term is " low shadow Ring the building of exploitation storm-water system ", water suction, water storage, infiltration and water purification when raining by the water stored " release " and are subject to benefit when needing With.
Traditional cities construction mode is hard surface everywhere, whenever heavy rain, relies primarily on pipe duct, pumping plant etc. " grey " and sets It applies to drain, with " quickly excluding " and " end concentration " control for main planning and design concept, often results in and meet rain flooded, drought and waterlogging Racing, according to " sponge urban construction technical manual ", urban construction will emphasize preferentially to utilize grass planting ditch, seepage brick, Rain Garden, Sunk type greenery patches etc. " green " measure carrys out tissue draining, is that main planning and designing are managed with " slow row's sustained release " and " source dispersion " control It reads, not only avoids flood, but also effectively have collected rainwater.So needing a kind of infiltration now, the road of water purification and water storage is alleviated Municipal drainage pressure and effectively utilize water resource.
Utility model content
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of municipal works road pavement structure, solves State the problem of proposing in background technique.
(2) technical solution
In order to achieve the above object, the utility model is achieved by the following technical programs: a kind of municipal works road paving If structure, including pavement of road, the lower surface of the pavement of road is equipped with water-permeable brick, and the lower surface of the water-permeable brick is provided with ABS net form skeleton, the inside of the ABS net form skeleton are filled with haydite, are equipped with sand rubble below the ABS net form skeleton Layer, the sand metalling are internally provided with draining blind pipe, and the outer surface of the draining blind pipe is provided with the double-deck permeable geotextiles, The exit of the draining blind pipe is provided with reflux flap valve, and the two sides of the draining blind pipe offer seugh and several rows The top at the mouth of a river, the seugh is equipped with concealed cover board, and the seugh is internally provided with water and sundries space, The two sides of the cover board, which are fixedly connected to, increases angle bar, and the two sides of the ABS net form skeleton are positioned by kerbstone, institute It states and is provided with compacted subgrade below sand metalling.
Optionally, the pavement of road is formed by colorful water-permeable concreting.
Optionally, the lower surface of the pavement of road is equipped with water-permeable brick, is formed with gap between the adjacent water-permeable brick, And gap is internally provided with haydite.
Optionally, the quantity for increasing angle bar is two, and increases angle bar described in two and be set in parallel.
Optionally, the size of the seugh is adapted with the size of concealed cover board.
(3) beneficial effect
The utility model provides a kind of municipal works road pavement structure, have it is following the utility model has the advantages that
1, the municipal works road pavement structure passes through the colorful water-permeable concrete of pavement of road and lower section pervious bed Design, not only makes the water permeability of road good, but also keep entire road surface also relatively beautiful, establishes good city image, Meanwhile the design of sand metalling, play the role of filtration, purification to rainwater etc., and the effect that seeps water is also very good.
2, municipal works road pavement structure, by the way that ABS net form skeleton is arranged below water-permeable brick, on the one hand to upper layer Structure plays good supporting role, and filler haydite on the other hand can be allowed integrally to play resistance to compression effect, guarantee road bed It is firm, it is finally the presence because of ABS net form skeleton grid, the path of rainwater infiltration has been standardized, so that rainwater permeates downwards more It is efficient.
3, the municipal works road pavement structure realizes rule by the design of the draining blind pipe of setting package geotextiles The function of model infiltration main path, but also the water permeated is discharged in the seugh of two sides, to realize draining or storage The function of water is conducive to the utilization again of water resource, avoids the waste of water resource.
4, municipal works road pavement structure, by the reflux flap valve of draining blind pipe setting, when can prevent high water level Water flow, which is reversely flowed backward to road foundation, damages road structure, extends roadbed service life.
5, the municipal works road pavement structure dramatically reduces pavement of road draining by the design of seugh Pressure, it is therefore prevented that the generation of pavement of road ponding serious conditions when precipitation is excessive, in addition, the water of seugh can pass through Other discharge outlet concentration is emitted into the ground such as Rain Garden, reservoir, to realize the utilization again to water resource.
Detailed description of the invention
Fig. 1 is the utility model cross-section parts structural schematic diagram;
Fig. 2 is the utility model pavement of road overlooking structure diagram.
In figure: 1- pavement of road, 2- water-permeable brick, 3-ABS net form skeleton, 4- haydite, 5- sand metalling, 6- draining blind pipe, The permeable geotextiles of 7-, 8- seugh, 9- kerbstone, the concealed cover board of 10-, 11- compacted subgrade, 12- water and sundries space, 13- reflux flap valve, 14- increase angle bar, 15- discharge outlet.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.
Fig. 1 to Fig. 2 is please referred to, the utility model provides a kind of technical solution: a kind of municipal works road pavement structure, packet Include pavement of road 1, pavement of road 1 is formed by colorful water-permeable concreting, by the colorful water-permeable concrete of pavement of road 1 with And the design of lower section pervious bed, not only make the water permeability of road good, but also keep entire road surface also relatively beautiful, establishes good Good city image, meanwhile, the design of sand metalling 5 plays the role of filtration, purification to rainwater etc., and the effect that seeps water Very good, the lower surface of pavement of road 1 is equipped with water-permeable brick 2, and the lower surface of pavement of road 1 is equipped with water-permeable brick 2, adjacent permeable It is formed with gap between brick 2, and gap is internally provided with haydite 4, the lower surface of water-permeable brick 2 is provided with ABS net form skeleton 3, By the way that ABS net form skeleton 3 is arranged below water-permeable brick 2, good supporting role, another party on the one hand are played to superstructure Face can allow filler haydite 4 integrally to play resistance to compression effect, guarantee that road bed is firm, be finally because of 3 grid of ABS net form skeleton Presence, standardized the path of rainwater infiltration so that rainwater permeate downwards it is highly efficient.The inside of ABS net form skeleton 3 is filled with Haydite 4, the lower section of ABS net form skeleton 3 are equipped with sand metalling 5, and sand metalling 5 is internally provided with draining blind pipe 6, drains blind The outer surface of pipe 6 is provided with the double-deck permeable geotextiles 7, and the exit of draining blind pipe 6 is provided with reflux flap valve 13, blind by draining The reflux flap valve 13 that pipe 6 is arranged can prevent water flow when high water level from reversely flowing backward to road foundation damage road structure, extend road The two sides of base service life, draining blind pipe 6 offer seugh 8 and several discharge outlet 15, pass through setting for seugh 8 Meter dramatically reduces the pressure of the draining of pavement of road 1, it is therefore prevented that 1 ponding serious conditions of pavement of road when precipitation is excessive Occur, in addition, the water of seugh 8 can be concentrated by other discharge outlet is emitted into the ground such as Rain Garden, reservoir, thus real Show the utilization again to water resource, by the design of the draining blind pipe 6 of setting package geotextiles, realizes specification infiltration main road The function of diameter, but also the water permeated is discharged in the seugh 8 of two sides, so that the function of draining or water storage is realized, The utilization again for being conducive to water resource, avoids the waste of water resource, and the top of seugh 8 is equipped with concealed cover board 10, row The size of water underdrain 8 is adapted with the size of concealed cover board 10, and seugh 8 is internally provided with water and sundries space 12, the two sides of cover board 10, which are fixedly connected to, increases angle bar 14, and the quantity for increasing angle bar 14 is two, and two are increased angle bar 14 It is set in parallel, the two sides of ABS net form skeleton 3 are positioned by kerbstone 9, and the lower section of sand metalling 5 is provided with compacting road Base 11.
In conclusion the municipal works road pavement structure, passes through the colorful water-permeable concrete of pavement of road 1 and lower section The design of pervious bed not only makes the water permeability of road good, but also keeps entire road surface also relatively beautiful, establishes good city City's image, meanwhile, the design of sand metalling 5 plays the role of filtration, purification to rainwater etc., and seeps water effect also very It is good, by the way that ABS net form skeleton 3 is arranged below water-permeable brick 2, good supporting role on the one hand is played to superstructure, separately On the one hand filler haydite 4 can be allowed integrally to play resistance to compression effect, guarantee that road bed is firm, be finally because of ABS net form skeleton 3 The presence of grid has standardized the path of rainwater infiltration, so that rainwater permeates downwards highly efficient, passes through setting and wraps up permeable geotechnique The draining blind pipe 6 of cloth 7, and in the design of draining blind pipe 6 outlet setting reflux flap valve 13, realize the function of specification infiltration main path Can, and can prevent water flow when high water level from reversely flowing backward to road foundation damage road structure, extend roadbed service life.Connection row Other discharge outlet 15 are arranged in the seugh 8 of water french drain 6, not only act as the effect for the water that discharge is permeated, also have certain Water storage function is conducive to the utilization again of water resource, avoids the waste of water resource, to realize to the sharp again of water resource With.
In the description of the present invention, it should be understood that term " center ", " longitudinal direction ", " transverse direction ", " length ", " width Degree ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside", " suitable The orientation or positional relationship of the instructions such as hour hands ", " counterclockwise ", " axial direction ", " radial direction ", " circumferential direction " is orientation based on the figure Or positional relationship, be merely for convenience of describing the present invention and simplifying the description, rather than the device of indication or suggestion meaning or Element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as the limit to the utility model System.
In the present invention unless specifically defined or limited otherwise, term " setting ", " connected ", " connects " installation " Connect ", the terms such as " fixation " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral; It can be mechanical connection, can be directly connected, can also can be inside two elements indirectly connected through an intermediary The interaction relationship of connection or two elements.For the ordinary skill in the art, it can manage as the case may be Solve the concrete meaning of above-mentioned term in the present invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Implicitly include one or more of the features.The meaning of " plurality " is two or two in the description of the present invention, More than, unless otherwise specifically defined.
It should be noted that in the present invention unless specifically defined or limited otherwise, fisrt feature is in the second spy It can be that the first and second features directly contact or the first and second features are connect indirectly by intermediary "above" or "below" sign Touching.Moreover, fisrt feature can be above the second feature " above ", " above " and " above " fisrt feature right above second feature or Oblique upper, or first feature horizontal height is merely representative of higher than second feature.Fisrt feature second feature " under ", " lower section " " following " can be fisrt feature and be directly under or diagonally below the second feature, or is merely representative of first feature horizontal height and is less than Second feature.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model Within enclosing.

Claims (5)

1. a kind of municipal works road pavement structure, including pavement of road (1), it is characterised in that: under the pavement of road (1) Surface is equipped with water-permeable brick (2), and the lower surface of the water-permeable brick (2) is provided with ABS net form skeleton (3), the ABS net form skeleton (3) inside is filled with haydite (4), is equipped with sand metalling (5) below the ABS net form skeleton (3), the sand metalling (5) be internally provided with drains blind pipe (6), and the outer surface of draining blind pipe (6) is provided with the double-deck permeable geotextiles (7), institute The exit for stating draining blind pipe (6) is provided with reflux flap valve (13), and the two sides of draining blind pipe (6) offer seugh (8) and several discharge outlet (15), the top of the seugh (8) are equipped with concealed cover board (10), the seugh (8) Water and sundries space (12) are internally provided with, the two sides of the cover board (10), which are fixedly connected to, increases angle bar (14), described The two sides of ABS net form skeleton (3) are positioned by kerbstone (9), are provided with compacted subgrade below the sand metalling (5) (11)。
2. a kind of municipal works road pavement structure according to claim 1, it is characterised in that: the pavement of road (1) It is formed by colorful water-permeable concreting.
3. a kind of municipal works road pavement structure according to claim 1, it is characterised in that: the pavement of road (1) Lower surface be equipped with water-permeable brick (2), be formed with gap between the adjacent water-permeable brick (2), and gap is internally provided with pottery Grain (4).
4. a kind of municipal works road pavement structure according to claim 1, it is characterised in that: described to increase angle bar (14) Quantity be two, and increase angle bar (14) described in two and be set in parallel.
5. a kind of municipal works road pavement structure according to claim 1, it is characterised in that: the seugh (8) Size be adapted with the size of concealed cover board (10).
CN201821140446.4U 2018-07-18 2018-07-18 A kind of municipal works road pavement structure Expired - Fee Related CN208440942U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821140446.4U CN208440942U (en) 2018-07-18 2018-07-18 A kind of municipal works road pavement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821140446.4U CN208440942U (en) 2018-07-18 2018-07-18 A kind of municipal works road pavement structure

Publications (1)

Publication Number Publication Date
CN208440942U true CN208440942U (en) 2019-01-29

Family

ID=65085619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821140446.4U Expired - Fee Related CN208440942U (en) 2018-07-18 2018-07-18 A kind of municipal works road pavement structure

Country Status (1)

Country Link
CN (1) CN208440942U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719369A (en) * 2020-05-15 2020-09-29 龙德建设有限公司 City landscape garden pavement construction structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719369A (en) * 2020-05-15 2020-09-29 龙德建设有限公司 City landscape garden pavement construction structure

Similar Documents

Publication Publication Date Title
CN104692588B (en) For processing the ecological multidimensional gaseous-waste holdup system of bank, river course rain-water drainage
CN205100360U (en) Urban road rainwater holds stagnant structure
CN207567889U (en) Residential quarters Rainwater collection system
CN110042724A (en) Collapsible Loess District road sponge facility rainwater catchment system and exhaust system
CN209293141U (en) Water permeable sidewalk drainage system in sponge city
CN101467511A (en) Dispersion type rainwater-collecting infiltrating irrigation device for urban road green area
CN206666962U (en) Square permeable pavement structure
CN106917522A (en) A kind of Outdoor Parking position system based on sponge the idea of the city
CN206571217U (en) Outdoor Parking position system based on sponge the idea of the city
CN209636585U (en) A kind of pavement grass planting ditch
CN218621638U (en) Municipal administration road that permeates water
CN208440941U (en) A kind of sponge urban water-through road surface automatic water collects extraordinary pavement structure
CN208440942U (en) A kind of municipal works road pavement structure
CN205224230U (en) LID type urban rainwater oozes and holds clean drainage closed conduit
CN207582619U (en) A kind of Rain Garden based on sponge city
CN208748463U (en) A kind of town road rainwater infiltration storage row's integral system
CN106049348A (en) Retaining wall structure for sponge city construction
CN107354988B (en) Create a concave green space structure that supplements rainwater infiltration under the landscape background
CN214362640U (en) Sidewalk drainage pavement
CN202440922U (en) Infiltration system capable of reducing discharge intensity of house surface rainwater
CN206233301U (en) Green grassland rainwater cyclic utilization system
CN210002537U (en) A lateral slope grass planting ditch for sponge city
CN204780521U (en) Composite water storage and drainage environment-friendly ground
CN116752518B (en) A sponge city rainwater harvesting, infiltration, and recharge system
CN217150554U (en) High-water-storage-property green belt structure based on utilization of construction waste resources

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190129

Termination date: 20210718