CN208395818U - A kind of mounting device of high speed highway guardrail upright post - Google Patents

A kind of mounting device of high speed highway guardrail upright post Download PDF

Info

Publication number
CN208395818U
CN208395818U CN201820980140.3U CN201820980140U CN208395818U CN 208395818 U CN208395818 U CN 208395818U CN 201820980140 U CN201820980140 U CN 201820980140U CN 208395818 U CN208395818 U CN 208395818U
Authority
CN
China
Prior art keywords
swing arm
motor
high speed
hole
upright post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820980140.3U
Other languages
Chinese (zh)
Inventor
韦东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Tai Heng Zhi Yuan Technology Co Ltd
Original Assignee
Anhui Tai Heng Zhi Yuan Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Tai Heng Zhi Yuan Technology Co Ltd filed Critical Anhui Tai Heng Zhi Yuan Technology Co Ltd
Priority to CN201820980140.3U priority Critical patent/CN208395818U/en
Application granted granted Critical
Publication of CN208395818U publication Critical patent/CN208395818U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of mounting devices of high speed highway guardrail upright post, including mobile station, support rod, crossbeam, hydraulic pump, telescopic rod, motor, bore cutter, swing arm, swivel ferrule, piling mechanism, cross bar, push rod, extension rod, limit hole, driving wheel, servo motor, wirerope, weight and gag lever post.By the way that support rod is arranged at the top of mobile station, the one end of the beam setting bore cutter installed on support rod, bore cutter is rotated by motor control, motor realizes drilling by the way that hydraulic pump control telescopic rod is flexible up and down, due to there is piling mechanism below crossbeam, piling mechanism is mounted in rotary swing arm, bore cutter is drilled after a hole in this way, column is put into hole, mobile station is pushed to carry out next drilling, and the column in previous hole can be hammered hole by rotation swing arm and complete installation by mechanism of driving piles, and the efficiency of column installation can be improved in this way.The utility model has the characteristics that installation effectiveness is high.

Description

A kind of mounting device of high speed highway guardrail upright post
Technical field
The utility model relates to a kind of mounting device, specially a kind of mounting device of high speed highway guardrail upright post belongs to Freeway guardrail technical field.
Background technique
Freeway guardrail is the principal mode of semi-steel guardrail, it is that one kind is mutually spliced simultaneously with corrugated steel guard rail plate The continuous structure supported by principal post.When vehicle collides it, since waveform steel guard rail plate has good Impact Resisting Capability and absorbs energy The effect of amount is neither easy to be smashed, while can play a very good protection again to vehicle and driver and conductor, and guardrail usually exists In the hole for first column insertion being accomplished fluently when installation, then carry out the installation of guardrail board.
Existing fence upright first passes through drilling machine drilling when installation, then fence upright is embedded to the hole being drilled In, it is tamped finally by pile driving equipment, sometimes column compacting, which finishes, needs to wait drilling machine to be drilled hole, and controls two simultaneously A equipment needs labor intensive, not only reduces working efficiency in this way, and spend human and material resources, uneconomical practical.
Utility model content
The purpose of this utility model be that in order to solve above-mentioned freeway guardrail installation when inefficiency, and And need the problem of expending a large amount of manpower and material resources and a kind of mounting device of high speed highway guardrail upright post is provided, there is installation effectiveness Height, economical and practical advantage.
The utility model is achieved through the following technical solutions above-mentioned purpose, a kind of installation dress of high speed highway guardrail upright post It sets, including mobile station, bore cutter and piling mechanism, support rod, the top weldering of the support rod is arranged in the top of the mobile station Crossbeam is connect, hydraulic pump is arranged in one end of the crossbeam, and telescopic rod is arranged in the bottom of the hydraulic pump, and the bottom end of the telescopic rod is set Motor is set, the bore cutter is installed in the bottom end of the motor, and swing arm is installed in the lower section of the crossbeam, and the inside of the swing arm is by cross The piling mechanism is installed in bar and swivel ferrule composition, one end of the cross bar, and push rod is arranged in the other end of the swing arm, described Two driving wheels are arranged in the inside for mechanism of driving piles, one of them described driving wheel is mounted on the motor shaft of servo motor, another A driving wheel is mounted at the top of one end of the swing arm, and two driving wheels are connected by wirerope, and the wirerope Bottom end be connected with weight.
Preferably, extension rod is arranged in one end of the swing arm installation piling mechanism, and limit is arranged in the inside of the extension rod Hole.
Preferably, gag lever post is arranged in the top side of the weight, and gag lever post passes through limit hole, and gag lever post and limit hole Specification match.
Preferably, the swing arm passes through in rotation connection between swivel ferrule and support rod, and the length of swing arm is greater than cross The length of beam.
Preferably, the bore cutter helically structure, in rotation connection between bore cutter and motor, the motor is by stretching It is movably connected between contracting bar and crossbeam.
Preferably, inside setting table top, movable pulley and the platform handle of the mobile station, and support rod is welded on table top.
Compared with prior art, the utility model has the beneficial effects that
1, by the way that support rod is arranged at the top of mobile station, the one end of the beam setting bore cutter installed on support rod, drilling Knife is rotated by motor control, and motor realizes drilling by the way that hydraulic pump control telescopic rod is flexible up and down, due to having below crossbeam Piling mechanism, piling mechanism are mounted in rotary swing arm, and such bore cutter is drilled after a hole, and column is put into hole In hole, mobile station is pushed to carry out next drilling, and mechanism of driving piles can be by rotating swing arm for the column in previous hole It hammers hole and completes installation, the efficiency of column installation can be improved in this way.
2, the utility model has the advantages of convenient installation, compact-sized, by the way that extension rod is arranged in one end that piling mechanism is installed in swing arm, Extension rod is equipped with limit hole, and since the top of weight is equipped with gag lever post, after gag lever post passes through limit hole, weight is upper Under can be to avoid double swerve, so that weight drop is more accurate, and the cross bar of swing arm composition when beat fence upright Length is greater than the length of crossbeam, accordingly even when driving piles weight within the organization still when mobile station is moved to next hole Also in the surface of column, without waiting for that guardrail can be continuously installed in this way.
Detailed description of the invention
Fig. 1 is the utility model overall structure diagram.
Fig. 2 is the swing arm structure schematic diagram of the utility model.
Fig. 3 is the piling mechanism structural schematic diagram of the utility model.
In figure: 1, mobile station, 2, support rod, 3, crossbeam, 4, hydraulic pump, 5, telescopic rod, 6, motor, 7, bore cutter, 8, pendulum Arm, 9, swivel ferrule, 10, piling mechanism, 11, cross bar, 12, push rod, 13, extension rod, 14, limit hole, 15, driving wheel, 16, watch Take motor, 17, wirerope, 18, weight, 19, gag lever post.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Embodiment 1
It please refers to shown in Fig. 1-3, a kind of mounting device of high speed highway guardrail upright post, including mobile station 1,7 and of bore cutter Support rod 2 is arranged in piling mechanism 10, the top of mobile station 1, and liquid is arranged in one end of the top welding beam 3 of support rod 2, crossbeam 3 Telescopic rod 5 is arranged in press pump 4, the bottom of hydraulic pump 4, and motor 6 is arranged in the bottom end of telescopic rod 5, and bore cutter 7 is installed in the bottom end of motor 6, Swing arm 8 is installed in the lower section of crossbeam 3, and the inside of swing arm 8 is made of cross bar 11 and swivel ferrule 9, and piling is installed in one end of cross bar 11 Push rod 12 is arranged in mechanism 10, the other end of swing arm 8, and two driving wheels 15, one of transmission is arranged in the inside of piling mechanism 10 Wheel 15 is mounted on the motor shaft of servo motor 16, another driving wheel 15 is mounted at the top of one end of swing arm 8, two driving wheels 15 are connected by wirerope 17, and the bottom end of wirerope 17 is connected with weight 18, can control biography by servo motor 16 Driving wheel 15 rotates, and wirerope 17 is wound or unwrapping wire, so that weight 18 can rise and fall, when bore cutter 7 is beaten After what a fence upright hole, mobile station 1 is pushed to go to bore next fence upright hole again, it, can be by column in this period It is put into the hole being drilled, pushes the piling mechanism in swing arm 8 to rotate to the top of column by push rod 12, pass through servo motor 16 Control weight 18 hammers into column in the hole accomplished fluently, and the hole being drilled in this way one more than mounted column, has subtracted vertical forever The waiting time of column installation, improve working efficiency.
Embodiment 2
In addition, referring to Fig.1-3, extension rod is arranged in one end of difference and above-described embodiment 1, the installation piling of swing arm 8 mechanism 10 13, limit hole 14 is arranged in the inside of extension rod 13, and gag lever post 19 is arranged in the top side of weight 18, and gag lever post 19 passes through limit hole 14, and gag lever post 19 and the specification of limit hole 14 match, during weight 18 is controlled rising and fallen by servo motor 16, Since gag lever post 19 is up and down in limit hole 14, shaking when can beating column in this way to avoid weight 18 prevents from standing Stud is askew, and swing arm 8 passes through in rotation connection between swivel ferrule 9 and support rod 2, and the length of swing arm 8 is greater than the length of crossbeam 3 Degree, for such bore cutter 7 when another hole is bored in front, swing arm 8 can allow piling mechanism 10 will by rotation The column at rear hammers into hole, withouts waiting for hole and accomplish fluently to place into column, improves working efficiency, and bore cutter 7 is helically tied Structure, in rotation connection between bore cutter 7 and motor 6, motor 6 between telescopic rod 5 and crossbeam 3 by being movably connected, bore cutter 7 It can not only rotate convenient for punching, but also can be controlled and be moved up and down by hydraulic pump 4, facilitate the progress of boring work, move Inside setting table top, movable pulley and the platform handle of dynamic platform 1, and support rod 2 is welded on table top, pushes platform handle that can push shifting Dynamic platform 1, so that the movement when device punches is more convenient.
When the utility model is used, being pushed away after what a hole bore cutter 7 bores by motor 6 and the control of hydraulic pump 4 first Dynamic mobile station 1 moves forward, and carries out the drilling of second point, is at this time put into column in first hole accomplished fluently, and rotates swing arm 8, piling mechanism 10 hammers into column in hole, and mobile station 1 is pushed to beat third hole again, and column utilization is placed into second hole Piling 10 stickfast of mechanism, only needs a people to push the mobile device of mobile station 1 in this way, and a people is put into column and can be completed at a high speed The installation of highway guard rail upright post, this method is convenient and efficient, time saving and energy saving.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this is practical new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this is practical new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing for the equivalent requirements of the claims will be fallen in All changes in justice and range are embraced therein.It should not treat any reference in the claims as limiting Related claim.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (6)

1. a kind of mounting device of high speed highway guardrail upright post, including mobile station (1), bore cutter (7) and piling mechanism (10), Be characterized in that: top setting support rod (2) of the mobile station (1), the top welding beam (3) of the support rod (2) are described Hydraulic pump (4) are arranged in one end of crossbeam (3), and telescopic rod (5) are arranged in the bottom of the hydraulic pump (4), the bottom of the telescopic rod (5) The bore cutter (7) is installed in end setting motor (6), the bottom end of the motor (6), and swing arm is installed in the lower section of the crossbeam (3) (8), the inside of the swing arm (8) is made of cross bar (11) and swivel ferrule (9), and one end installation of the cross bar (11) is described to beat Push rod (12) are arranged in the other end of stake mechanism (10), the swing arm (8), and two transmissions are arranged in the inside of piling mechanism (10) It takes turns (15), one of them described driving wheel (15) is mounted on the motor shaft of servo motor (16), another described driving wheel (15) it is mounted at the top of one end of the swing arm (8), two driving wheels (15) are connected by wirerope (17), and the steel wire The bottom end of rope (17) is connected with weight (18).
2. a kind of mounting device of high speed highway guardrail upright post according to claim 1, it is characterised in that: the swing arm (8) extension rod (13) are arranged in one end of installation piling mechanism (10), and limit hole (14) are arranged in the inside of the extension rod (13).
3. a kind of mounting device of high speed highway guardrail upright post according to claim 1 or 2, it is characterised in that: described heavy Gag lever post (19) are arranged in the top side for hammering (18) into shape, and gag lever post (19) passes through limit hole (14), and gag lever post (19) and limit hole (14) specification matches.
4. a kind of mounting device of high speed highway guardrail upright post according to claim 1, it is characterised in that: the swing arm (8) by being in rotation connection between swivel ferrule (9) and support rod (2), and the length of swing arm (8) is greater than the length of crossbeam (3).
5. a kind of mounting device of high speed highway guardrail upright post according to claim 1, it is characterised in that: the bore cutter (7) helically structure, in rotation connection between bore cutter (7) and motor (6), the motor (6) passes through telescopic rod (5) and crossbeam (3) it is movably connected between.
6. a kind of mounting device of high speed highway guardrail upright post according to claim 1, it is characterised in that: the mobile station (1) inside setting table top, movable pulley and platform handle, and support rod (2) is welded on table top.
CN201820980140.3U 2018-06-25 2018-06-25 A kind of mounting device of high speed highway guardrail upright post Expired - Fee Related CN208395818U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820980140.3U CN208395818U (en) 2018-06-25 2018-06-25 A kind of mounting device of high speed highway guardrail upright post

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820980140.3U CN208395818U (en) 2018-06-25 2018-06-25 A kind of mounting device of high speed highway guardrail upright post

Publications (1)

Publication Number Publication Date
CN208395818U true CN208395818U (en) 2019-01-18

Family

ID=65133215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820980140.3U Expired - Fee Related CN208395818U (en) 2018-06-25 2018-06-25 A kind of mounting device of high speed highway guardrail upright post

Country Status (1)

Country Link
CN (1) CN208395818U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110076372A (en) * 2019-06-03 2019-08-02 杭州奇伶服饰有限公司 A kind of construction equipment for installing antenna
CN110656883A (en) * 2019-10-23 2020-01-07 徐州市盖力工程机械有限公司 Road construction is with pile drilling all-in-one
CN115506712A (en) * 2022-11-07 2022-12-23 山东省路桥集团有限公司 Stand installation device is used in highway anticollision barrier construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110076372A (en) * 2019-06-03 2019-08-02 杭州奇伶服饰有限公司 A kind of construction equipment for installing antenna
CN110656883A (en) * 2019-10-23 2020-01-07 徐州市盖力工程机械有限公司 Road construction is with pile drilling all-in-one
CN115506712A (en) * 2022-11-07 2022-12-23 山东省路桥集团有限公司 Stand installation device is used in highway anticollision barrier construction
CN115506712B (en) * 2022-11-07 2023-02-03 山东省路桥集团有限公司 Stand installation device is used in highway anticollision barrier construction

Similar Documents

Publication Publication Date Title
CN106522223B (en) A kind of Purely mechanical piling machine for building
CN208395818U (en) A kind of mounting device of high speed highway guardrail upright post
CN203569566U (en) Large-dip-angle multifunctional piling machine
CN104929123B (en) A kind of pile sinking staving press
CN107476303A (en) A kind of construction site ringing engine
CN210288383U (en) Rotary drilling and piling integrated machine
NZ223286A (en) Rolling steel piles on site immediately before placement
CN109537590A (en) A kind of efficient vertical piling machine of civil engineering
CN105780776B (en) A kind of spinning steel-pipe pile construction equipment
CN207331691U (en) A kind of construction site ringing engine
CN115822449B (en) A new type of crawler compound pile driver
CN211395670U (en) Piling device for building construction
CN216948205U (en) Novel board inserting machine structure assembly
CN219908914U (en) Self-propelled multifunctional ramming pile-expanding machine
CN201411693Y (en) Efficient pile driver tower
CN207453885U (en) A kind of multifunctional rotary digging machine
CN214328863U (en) Combined pile machine for stiff composite pile
CN108239965A (en) A kind of automatic construction equipment of town and country reservoir
CN212129112U (en) Foundation tamping device for building
CN220847552U (en) Base construction device
CN222614191U (en) A punching pile driver for water-filled piles
CN217782014U (en) Deep stirring and high-pressure jet grouting composite pile
CN214695589U (en) Construction is with pile driver that prevents shoving
CN213234929U (en) Drilling machine for composite stirring pile
CN207315218U (en) A kind of double pillar constructions of Spiral digging machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190118

Termination date: 20190625