CN208366337U - A kind of project cost dosage frame - Google Patents
A kind of project cost dosage frame Download PDFInfo
- Publication number
- CN208366337U CN208366337U CN201820532043.8U CN201820532043U CN208366337U CN 208366337 U CN208366337 U CN 208366337U CN 201820532043 U CN201820532043 U CN 201820532043U CN 208366337 U CN208366337 U CN 208366337U
- Authority
- CN
- China
- Prior art keywords
- fixed
- frame
- bolt
- project cost
- sliding block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Measurement Of The Respiration, Hearing Ability, Form, And Blood Characteristics Of Living Organisms (AREA)
Abstract
The utility model discloses a kind of project cost dosage framves, including pedestal, fixed frame, horizontal support, limited block and coulisse, first sliding groove is offered in the longitudinal carrier, horizontal support outer surface one end is welded with fixed block, first weld holder one end is fixed with the first sliding block, first sliding block is movably fixed in first sliding groove, the second screw thread is offered on second bolt, second bolt is screwed by second the second nut, second sliding slot is offered inside the horizontal support, described limited block one end is welded with the second weld holder, second weld holder one end is fixed with the second sliding block, second sliding block is movably fixed in second sliding slot, second sliding block is fixed with the first bolt away from one end of the second weld holder, the first screw thread is offered on first bolt, the pedestal outer end is fixed with Coulisse.The utility model have quickly open and use, liftable measurement and the high advantage of measuring accuracy.
Description
Technical field
The utility model relates to project cost dosage frame technical field, specially a kind of project cost dosage frame.
Background technique
Project cost dosage frame refers to: project cost is exactly the construction price of engineering, and broadly project cost covers construction
Project cost, installing engineering cost, municipal works cost, Cost for Electric Power Engineering, communication engineering cost etc., project cost are fingering
The full payment that a certain engineering construction of row is spent, investment when core content, correct budgetary estimate, construction budget, work at estimation per design
Journey clearing, budget needed for the completion of projects etc., project cost dosage frame is then the shelf for preventing measuring instrument apparatus, and existing engineering is made
Valence dosage frame is excessively single, does not have quick opening, precise measurement, the measurement of one height of carry out that can only be single, Wu Fajin
Row lifting measurement, and without good fixed frame, causes biggish error when be easy to causeing to staff's measurement, practicability compared with
Difference is unable to satisfy present project cost measurement, and staff can not quickly play open and close using project cost dosage frame
It closes, without preferably fixed supporting point.
Utility model content
The purpose of this utility model is to provide a kind of project cost dosage frame, have quickly open and use, liftable survey
Amount and the high advantage of measuring accuracy are solved the problems, such as to cause error when work measurement and be measured excessively single.
To achieve the above object, the utility model provides the following technical solutions: a kind of project cost dosage frame, including bottom
Seat, fixed frame, horizontal support, limited block and coulisse, the pedestal both ends are fixed with longitudinal carrier, open in the longitudinal carrier
Equipped with first sliding groove, horizontal support outer surface one end is welded with fixed block, and the horizontal support both ends are welded with the first weldering
Frame is connect, first weld holder one end is fixed with the first sliding block, and first sliding block is movably fixed in first sliding groove, and described
One sliding block is fixed with the second bolt away from one end of the first weld holder, offers the second screw thread on second bolt, and described the
Two bolts are screwed by second the second nut, and second sliding slot, the limited block one are offered inside the horizontal support
End is welded with the second weld holder, and second weld holder one end is fixed with the second sliding block, and second sliding block is movably fixed to the
In two sliding slots, second sliding block is fixed with the first bolt away from one end of the second weld holder, offers on first bolt
First screw thread, first bolt are fixed with the first nut by the first thread helix, and the pedestal outer end is fixed with coulisse,
The fixed frame is movably fixed in coulisse, and fixed frame limited block is fixed on the fixed frame.
Preferably, graduated scale is installed on the longitudinal carrier outer surface.
Preferably, level meter is installed on the horizontal support outer surface.
Preferably, there are four the fixed frame is set altogether, and four fixed frame rectangular array distributions.
Preferably, the fixed frame bottom end is fixed with rubber antiskid pad.
Compared with prior art, the beneficial effects of the utility model are as follows:
1, by setting coulisse, having reached project cost dosage frame when in use can quickly open admittedly the utility model
Determine frame, support project cost dosage frame easily and fast, prevent project cost dosage frame using when external force device noumenon is made
At influence, prevent the shaking of project cost dosage frame from impacting to measurement accuracy.
2, the utility model has reached project cost dosage frame when in use, can make work by setting rubber antiskid pad
Journey cost dosage frame has better supporting point, greatly improves accuracy when measurement, makes the practicability of project cost dosage frame
Higher, the simply more convenient staff of structure operates with.
3, the utility model has reached project cost dosage frame when in use by setting graduated scale, can be faster
Fixed position can be needed by reaching, and can be more accurately fixed on and be needed fixed height, prevent excessively high and too low to measurement
As a result error is caused, keeps the practicability of device higher.
4, the utility model has reached project cost dosage frame when in use by setting horizontal support, can be better
The height for needing to measure is selected by mobile horizontal support, avoids that measurement process is excessively single, and the precision to be measured is made
At influence.
Detailed description of the invention
Fig. 1 is the positive structure diagram of the utility model;
Fig. 2 is the enlarged diagram of B in Fig. 1 of the utility model;
Fig. 3 is the enlarged diagram of A in Fig. 1 of the utility model;
Fig. 4 is the overlooking structure diagram of the utility model.
In figure: 1- pedestal;2- rubber antiskid pad;3- fixed frame;4- graduated scale;5- first sliding groove;The first sliding block of 6-;7-
One weld holder;8- fixed block;9- horizontal support;10- second sliding slot;11- level meter;12- limited block;13- longitudinal carrier;14-
Second weld holder;The second sliding block of 15-;The first bolt of 16-;The first nut of 17-;The first screw thread of 18-;The second bolt of 19-;20-
Two nuts;The second screw thread of 21-;22- coulisse;23- fixed frame limited block.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
A kind of embodiment provided by the utility model referring to FIG. 1 to FIG. 4: a kind of project cost dosage frame, including pedestal
1, fixed frame 3, horizontal support 9, limited block 12 and coulisse 22,1 both ends of pedestal are fixed with longitudinal carrier 13, outside longitudinal carrier 13
Graduated scale 4 is installed on surface, by setting graduated scale 4, has reached project cost dosage frame when in use, it can be faster
Fixed position can be needed by reaching, and can be more accurately fixed on and be needed fixed height, prevent excessively high and too low to measurement
As a result error is caused, keeps the practicability of device higher, first sliding groove 5,9 outer surface one of horizontal support are offered in longitudinal carrier 13
End is welded with fixed block 8, by the way that horizontal support 9 is arranged, has reached project cost dosage frame when in use, can preferably pass through
Mobile horizontal support 9 selects the height for needing to measure, and avoids that measurement process is excessively single, causes shadow to the precision to be measured
It rings, 9 both ends of horizontal support are welded with the first weld holder 7, level meter 11, the first weld holder 7 are equipped on 9 outer surface of horizontal support
One end is fixed with the first sliding block 6, and the first sliding block 6 is movably fixed in first sliding groove 5, and the first sliding block 6 is away from the first weld holder 7
One end is fixed with the second bolt 19, and the second screw thread 21 is offered on the second bolt 19, and the second bolt 19 is solid by the second screw thread 21
Surely there is the second nut 20, second sliding slot 10 is offered inside horizontal support 9,12 one end of limited block is welded with the second weld holder 14,
Second weld holder, 14 one end is fixed with the second sliding block 15, and the second sliding block 15 is movably fixed in second sliding slot 10, the second sliding block 15
It is fixed with the first bolt 16 away from one end of the second weld holder 14, the first screw thread 18, the first bolt are offered on the first bolt 16
16 are fixed with the first nut 17 by 18 spiral of the first screw thread, and 1 outer end of pedestal is fixed with coulisse 22, by the way that coulisse is arranged
22, fixed frame 3 can quickly be opened when in use by having reached project cost dosage frame, support project cost use easily and fast
Measure frame, prevent project cost dosage frame using when external force device noumenon is impacted, prevent project cost dosage frame shake pair
Measurement accuracy impacts, and fixed frame 3 is movably fixed in coulisse 22, there are four fixed frame 3 is set altogether, and four fixed frames 3
Rectangular array is distributed, and is fixed with fixed frame limited block 23 on fixed frame 3, and 3 bottom end of fixed frame is fixed with rubber antiskid pad 2, is led to
Setting rubber antiskid pad 2 is crossed, has reached project cost dosage frame when in use, project cost dosage frame can be made to have better branch
Support point greatly improves accuracy when measurement, keeps the practicability of project cost dosage frame higher, the simply more convenient work of structure
Personnel operate with.
Working principle: project cost dosage frame leads in use, by coulisse 22 come sliding opening and closure fixed frame 3
The rubber antiskid pad 2 of 3 bottom end of fixed frame is crossed to increase the stress point of device, selects to need mobile laterally branch by graduated scale 4
The height of frame 9, by mobile limited block 12 come fixation measuring instrument, being adjusted by the level meter 11 being arranged on horizontal support 9 is needed
The levelness to be measured fixes limited block 12 by tightening the first nut 17, by tightening the second nut 20 come fixed lateral
Bracket 9.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and
And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this is practical new in other specific forms
Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this is practical new
The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing for the equivalent requirements of the claims will be fallen in
All changes in justice and range are embraced therein.It should not treat any reference in the claims as limiting
Related claim.
Claims (5)
1. a kind of project cost dosage frame, including pedestal (1), fixed frame (3), horizontal support (9), limited block (12) and coulisse
(22), it is characterised in that: pedestal (1) both ends are fixed with longitudinal carrier (13), and the is offered in the longitudinal carrier (13)
One sliding slot (5), described horizontal support (9) outer surface one end are welded with fixed block (8), and horizontal support (9) both ends are welded with
First weld holder (7), described first weld holder (7) one end are fixed with the first sliding block (6), and the first sliding block (6) activity is fixed
In first sliding groove (5), first sliding block (6) is fixed with the second bolt (19) away from the one end of the first weld holder (7), described
It is offered on second bolt (19) the second screw thread (21), second bolt (19) is fixed with the second spiral shell by the second screw thread (21)
Female (20), the horizontal support (9) is internal to be offered second sliding slot (10), and described limited block (12) one end is welded with the second welding
Frame (14), described second weld holder (14) one end are fixed with the second sliding block (15), and second sliding block (15) is movably fixed to
In two sliding slots (10), second sliding block (15) is fixed with the first bolt (16) away from the one end of the second weld holder (14), described
It is offered on first bolt (16) the first screw thread (18), first bolt (16) is fixed with by the first screw thread (18) spiral
One nut (17), pedestal (1) outer end are fixed with coulisse (22), and the fixed frame (3) is movably fixed to coulisse (22)
It is interior, fixed frame limited block (23) are fixed on the fixed frame (3).
2. a kind of project cost dosage frame according to claim 1, it is characterised in that: longitudinal carrier (13) outer surface
On graduated scale (4) are installed.
3. a kind of project cost dosage frame according to claim 1, it is characterised in that: horizontal support (9) outer surface
On level meter (11) are installed.
4. a kind of project cost dosage frame according to claim 1, it is characterised in that: the fixed frame (3) is equipped with four altogether
It is a, and four fixed frame (3) rectangular array distributions.
5. a kind of project cost dosage frame according to claim 1, it is characterised in that: fixed frame (3) bottom end is fixed
There are rubber antiskid pad (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820532043.8U CN208366337U (en) | 2018-04-16 | 2018-04-16 | A kind of project cost dosage frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820532043.8U CN208366337U (en) | 2018-04-16 | 2018-04-16 | A kind of project cost dosage frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208366337U true CN208366337U (en) | 2019-01-11 |
Family
ID=64922692
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820532043.8U Expired - Fee Related CN208366337U (en) | 2018-04-16 | 2018-04-16 | A kind of project cost dosage frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208366337U (en) |
-
2018
- 2018-04-16 CN CN201820532043.8U patent/CN208366337U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204988276U (en) | Laser is perpendicular / horizontal measuring device | |
CN209247001U (en) | A kind of rail track construction water Pingdu detection device | |
CN209296769U (en) | A kind of bracket improving power frequency electric field measuring instrument accuracy | |
CN206876159U (en) | Pole wire angle quick test device | |
CN208366337U (en) | A kind of project cost dosage frame | |
CN102841366B (en) | Method and system for detecting discrimination threshold of pulse-amplitude discriminator | |
CN105277166B (en) | A kind of measuring device and its measurement method of vertical rail verticality and flatness | |
CN207456407U (en) | A kind of laser lamp plane monitoring-network equipment | |
CN103292661A (en) | Rail weighbridge installation measuring instrument | |
CN204854597U (en) | Multi -functional plane survey appearance | |
CN204944391U (en) | Depth of thread rule depth calibration device | |
CN207423071U (en) | A kind of core diameter measurement jig | |
CN202720028U (en) | Detecting device for high-pressure water meter | |
CN109781217A (en) | A kind of detection device for water meter | |
CN109781585A (en) | A kind of no-Co-alloy steel Repose angle gauge | |
CN109458989A (en) | A kind of device and its detection method for building verticality quality testing | |
CN205301076U (en) | Young modulus measuring apparatu | |
CN209214506U (en) | It is a kind of measure linear slide rail basal plane to four centers Zhu Gou away from cubing | |
CN209446097U (en) | A kind of thyroid gland Pathologic specimen stereometer type instrument | |
CN209446051U (en) | GPS static state altitude meter | |
CN209541719U (en) | A kind of measuring device at elbow curvature angle | |
CN208636358U (en) | A kind of portable power meter | |
CN209327157U (en) | Mortar consistency tester is used in a kind of detection of mortar | |
CN208366348U (en) | A kind of street lamp installation vertical measurement device | |
CN207688885U (en) | Quickly measure the tool of verticality of steel column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190111 Termination date: 20190416 |
|
CF01 | Termination of patent right due to non-payment of annual fee |