CN208363617U - Water pipe well reserved casing pipe die - Google Patents
Water pipe well reserved casing pipe die Download PDFInfo
- Publication number
- CN208363617U CN208363617U CN201820774271.6U CN201820774271U CN208363617U CN 208363617 U CN208363617 U CN 208363617U CN 201820774271 U CN201820774271 U CN 201820774271U CN 208363617 U CN208363617 U CN 208363617U
- Authority
- CN
- China
- Prior art keywords
- free end
- fixture
- adjusting rod
- top tool
- water pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 24
- 238000003466 welding Methods 0.000 claims abstract description 4
- 229910000831 Steel Inorganic materials 0.000 claims description 23
- 239000010959 steel Substances 0.000 claims description 23
- 230000000903 blocking effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 10
- 230000005611 electricity Effects 0.000 abstract 1
- 238000007493 shaping process Methods 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 6
- 238000000034 method Methods 0.000 description 5
- 230000008901 benefit Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000001360 synchronised effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009408 flooring Methods 0.000 description 1
Landscapes
- Sewage (AREA)
Abstract
The utility model provides a water pipe well reserved casing pipe mould, the main body of which is a # -shaped frame formed by splicing four groups of jacking tool adjusting rods, four corners of which are propped on a structural wall through L-shaped corner jacking tools, and the jacking tool adjusting rods are provided with unit clamps; the L-shaped wall corner tops are four, and the openings are inward, and the corners are respectively attached to the internal corners of the structural wall; the top utensil is adjusted the pole and is formed by two horizontal poles vertical welding, and the top utensil is adjusted the pole and is included a set of stiff end and a set of free end, a set of stiff end respectively with the both sides welded fastening at the opening place of L type corner top utensil, a set of free end outwards extends and be provided with at least three hole that is used for passing the bolt in end position symmetry. The utility model discloses during the use of being under construction, the processing ease, the location is accurate, and the shaping is effectual, and the structure stage is reserved pre-buried work with the water and electricity and is gone on in step. The forming quality and the construction efficiency of the building main body can be improved.
Description
Technical field
The utility model relates to construction ancillary equipment field, especially water pipe manholes to reserve ferrule mold.
Background technique
Building trade technology is maked rapid progress, and when construction, water pipe manhole interior conduit is more and more, and intensive pipeline makes
Need to reserve casing at through-flooring more.
In traditional handicraft work progress, the drifting of rectangle floor is reserved in structure construction stage water pipe manhole, is usually existed
Only reserved steel bar does not pour at pipe well floor when structure pours, secondary after the completion of subsequent casings installation is fixed to pour, and does so
The shortcomings that be: 1, the transport of secondary casting concrete is inconvenient, time-consuming;2, casing subsequent installation is fixed on reserved steel bar,
Easy deviation when pouring, casing installation quality be not high;3, casing installation synchronous with water power set aside pre-embedded when structure construction cannot carry out,
Process lag.
Utility model content
The purpose of the utility model is to overcome the deficiencies in background technique, provide water pipe manhole and reserve ferrule mold, to solve
Building construction process middle sleeve installation quality is high, process lag, secondary pours technical problem at high cost.
To achieve the above objectives, the present invention adopts the following technical solutions:
The utility model provides water pipe manhole and reserves ferrule mold, and the main body of the ferrule mold is that have adjusting rod 2 by four groups of tops
The groined type frame being spliced, through L shape corner top 1 apical grafting of tool on structural wall, top tool adjusting rod 2 is arranged four corners
There is unit fixture 3;
There are four L-type corner top tools 1 and the inside, corner that is open is bonded is arranged at structural wall inner corner trim respectively;
Top tool adjusting rod 2 is formed by two 21 vertical weldings of cross bar, and top tool adjusting rod 2 includes one group of fixing end 23 and one group
Free end 22, one group of fixing end 23 are welded and fixed with the both sides where the opening of L-type corner top tool 1 respectively, one group of free end 22
Extend outwardly and is symmetrically arranged at least three for the hole across bolt 4 in tip position;
The bolt 4 for having 22 end point of free end of adjusting rod 2 by the way that top is arranged between two neighboring L-type corner top tool 1
Adjustable connection;
The unit fixture 3 includes the auxiliary bar 32 of limit of two parallel intervals setting and is used for two auxiliary bars 32 1 of limit
The fixture mobile jib 31 to link together is held, fixture mobile jib 31 and two auxiliary bars 32 of limit are constituted for blocking the recessed of service sleeve 5
Slot;Auxiliary 32 other end of bar is limited to be fixedly connected with a free end 22 of top tool adjusting rod 2;Fixture mobile jib 31, the auxiliary bar 32 of limit
It is parallel with top tool one free end 22 of adjusting rod 2 in same plane, fixture mobile jib 31 with top tool adjusting rod 2.
Further, L-type corner top tool 1 is welded by two channel steels;Channel steel model No. 10 or No. 12.
Further, the intersection point of two cross bars 21 of top tool adjusting rod 2 is positioned close to the side of fixing end 23;Free end 22
Brachium be greater than fixing end 23 brachium.
Further, cross bar 21 uses No. 8 channel steels.
Further, the distance between free end 22 for fixture mobile jib 31 and top tool adjusting rod 2 and reserved casing caliber
It is adapted.
Further, at least one unit fixture 3 is provided on same free end 22;There are multiple pipes in same 22 side of free end
Diameter identical service sleeve 5 shares a fixture mobile jib 31 between adjacent cells fixture 3.
Further, there are multiple service sleeves 5 in same 22 side of free end and caliber is different, between adjacent cells fixture 3 altogether
With a fixture mobile jib 31, maximum caliber is adapted in the distance of fixture mobile jib 31 to free end 22 and multiple reserved casings.
Further, unit fixture 3 further includes for filling between reserved casing and a free end 22 of top tool adjusting rod 2
The backing plate 33 in gap.
Further, backing plate 33 is channel steel or I-steel or steel plate.
Further, fixture mobile jib 31 is No. 8 channel steels;Limit the harness cord bar that auxiliary bar 32 is diameter 8mm.
The beneficial effects of the utility model are embodied in:
1, water pipe manhole provided by the utility model reserves ferrule mold, and structure is simple, and design is reasonable, low cost, Ke Yigen
It is adjusted flexibly according to the diameter of reserved casing;It dismantles and is easy after use, convenient transportation.And it can repeat to have enough to meet the need benefit
With substantially reducing construction cost.Meet requirement of the country to green construction.
2, water pipe manhole provided by the utility model reserves ferrule mold, and when construction usage, worker operation is easy, using just
Victory, accurate positioning, good forming effect, Structure Stage is synchronous with the work of water power set aside pre-embedded to carry out.And it can be with multipoint positioning, really
It is accurate to protect reserved sleeve position.The Forming Quality and construction efficiency of building body can be improved.
3, the utility model practicability with higher, when the reserved casing caliber in same free end side is different
It waits, the same fixture mobile jib still can be used, fixture mobile jib can fill backing plate to the gap between free end, to guarantee to cover
It is put down after pipe installation or preceding flat.
Other features and advantages of the utility model will illustrate in the following description, and partly from specification
It becomes apparent, or is understood and implementing the utility model.The main purpose and further advantage of the utility model can lead to
Specifically noted scheme in specification, claims is crossed to be achieved and obtained.
Detailed description of the invention
The utility model is described in more detail with reference to the accompanying drawing.
Fig. 1 is the top view of the utility model L-type corner top tool.
Fig. 2 is top tool adjusting rod top view.
Fig. 3 is unit fixture structure schematic diagram.
Fig. 4 is 1 use state Fig. 1 of the utility model embodiment.
Fig. 5 is 1 use state Fig. 2 of the utility model embodiment.
Fig. 6 is 2 usage state diagram of the utility model embodiment.
Appended drawing reference: 1-L type corner top tool, the top 2- tool adjusting rod, 21- cross bar, the free end 22-, 23- fixing end, 3- are mono-
First fixture, 31- fixture mobile jib, 32- limit auxiliary bar, 33- backing plate, 4- bolt, 5- service sleeve.
Specific embodiment
The technical solution of the utility model is described in detail by the following examples, embodiment below is only exemplary
, it is only capable of for explanation and illustration the technical solution of the utility model, and cannot be construed to technical solutions of the utility model
Limitation.
Embodiment 1
As shown in figure 4, the main body of the ferrule mold is the groined type frame being spliced by four groups of top tool adjusting rods 2,
For four corners through L shape corner top 1 apical grafting of tool on structural wall, top tool adjusting rod 2 is provided with unit fixture 3.
As shown in Figure 1, the L-type corner is pushed up there are four tools 1 and the inside, corner that is open is bonded setting in structural wall respectively
At inner corner trim;L-type corner top tool 1 can be welded by two channel steels;Channel steel model No. 10 or No. 12.
As shown in Fig. 2, top tool adjusting rod 2 is formed by two 21 vertical weldings of cross bar, cross bar 21 can use No. 8 channel steels.
Top tool adjusting rod 2 includes one group of fixing end 23 and one group of free end 22, and one group of fixing end 23 pushes up opening for tool 1 with L-type corner respectively
Both sides where mouthful are welded and fixed, and one group of free end 22, which extends outwardly and is symmetrically arranged at least three in tip position, to be used for
Across the hole of bolt 4;22 end point of free end for having adjusting rod 2 by the way that top is arranged between two neighboring L-type corner top tool 1
The adjustable connection of bolt 4.The intersection point of two cross bars 21 of top tool adjusting rod 2 is positioned close to the side of fixing end 23;Free end
22 brachium is greater than the brachium of fixing end 23.
As shown in figure 3, the unit fixture 3 includes the auxiliary bar 32 of limit of two parallel intervals setting and is used to limit two
The fixture mobile jib 31 that auxiliary 32 one end of bar in position links together, fixture mobile jib 31 and two auxiliary bars 32 of limit constitute pre-buried for blocking
The groove of casing 5;Auxiliary 32 other end of bar is limited to be fixedly connected with a free end 22 of top tool adjusting rod 2;Fixture mobile jib 31, limit
The auxiliary bar 32 in position and top tool adjusting rod 2 are parallel with top tool one free end 22 of adjusting rod 2 in same plane, fixture mobile jib 31.Card
Tool mobile jib 31 is No. 8 channel steels;Limit the harness cord bar that auxiliary bar 32 is diameter 8mm.
The distance between fixture mobile jib 31 and a free end 22 of top tool adjusting rod 2 are adapted with reserved casing caliber.
A unit fixture 3 can be set in setting on same free end 22.Same 22 side of free end has multiple calibers identical pre-buried
Casing 5 shares a fixture mobile jib 31 between adjacent cells fixture 3, referring to Fig. 5.
Embodiment 2, water pipe manhole reserve ferrule mold, with embodiment 1, the difference is that: as shown in fig. 6, same freedom
It holds 22 sides to have multiple service sleeves 5 and caliber difference, shares a fixture mobile jib 31, fixture master between adjacent cells fixture 3
The maximum caliber into the distance of free end 22 and multiple reserved casings of bar 31 is adapted.The gap occurred at small diameter tube can fill
Channel steel or I-steel or steel plate backing plate 33.
The foregoing is merely the preferable specific embodiment of the utility model, but the protection scope of the utility model not office
Be limited to this, variation that anyone skilled in the art is expected within the technical scope disclosed by the utility model or
Replacement, should be covered within the scope of the utility model.
Claims (10)
1. water pipe manhole reserves ferrule mold, it is characterised in that: the main body of the ferrule mold is by four groups of top tool adjusting rod (2) splicings
Made of groined type frame, four corners by L-type corner top tool (1) apical grafting on structural wall, top tool adjusting rod (2) setting
There are unit fixture (3);
There are four the L-type corner top tools (1) and the inside, corner that is open is bonded is arranged at structural wall inner corner trim respectively;
Top tool adjusting rod (2) formed by two cross bar (21) vertical weldings, top tool adjusting rod (2) include one group of fixing end (23) and
One group of free end (22), the both sides where one group of fixing end (23) pushes up the opening of tool (1) with L-type corner respectively are welded and fixed, and one
Group free end (22) extends outwardly and is symmetrically arranged at least three for the hole across bolt (4) in tip position;
The bolt of free end (22) end point between two neighboring L-type corner top tool (1) by setting in top tool adjusting rod (2)
(4) adjustable connection;
The unit fixture (3) includes the auxiliary bar of limit (32) of two parallel intervals setting and is used for two auxiliary bars (32) of limit
The fixture mobile jib (31) that one end links together, fixture mobile jib (31) and two auxiliary bars (32) of limit are constituted for blocking pre-buried set
Manage the groove of (5);Auxiliary bar (32) other end is limited to be fixedly connected with a free end (22) of top tool adjusting rod (2);Fixture master
Bar (31), the auxiliary bar (32) of limit and top tool adjusting rod (2) are the one of same plane, fixture mobile jib (31) and top tool adjusting rod (2)
A free end (22) is parallel.
2. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that the L-type corner top tool (1) is by two
Channel steel is welded;Channel steel model No. 10 or No. 12.
3. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that two of top tool adjusting rod (2)
The intersection point of cross bar (21) is positioned close to the side of fixing end (23);The brachium of free end (22) is greater than the arm of fixing end (23)
It is long.
4. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that cross bar (21) uses No. 8 channel steels.
5. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that fixture mobile jib (31) and top tool adjusting rod
(2) the distance between free end (22) is adapted with reserved casing caliber.
6. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that be provided on same free end (22) to
A few unit fixture (3);There are the identical service sleeve of multiple calibers (5), adjacent cells fixture in same free end (22) side
(3) a fixture mobile jib (31) is shared between.
7. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that same free end (22) side has multiple
Service sleeve (5) and caliber are different, and a fixture mobile jib (31) is shared between adjacent cells fixture (3), and fixture mobile jib (31) arrives
Maximum caliber is adapted in the distance of free end (22) and multiple reserved casings.
8. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that unit fixture (3) further includes for filling out
Fill the backing plate (33) in gap between reserved casing and a free end (22) of top tool adjusting rod (2).
9. water pipe manhole as claimed in claim 8 reserves ferrule mold, which is characterized in that backing plate (33) is channel steel or I-steel
Or steel plate.
10. water pipe manhole as described in claim 1 reserves ferrule mold, which is characterized in that fixture mobile jib (31) is No. 8 channel steels;
Limit the harness cord bar that auxiliary bar (32) are diameter 8mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820774271.6U CN208363617U (en) | 2018-05-23 | 2018-05-23 | Water pipe well reserved casing pipe die |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820774271.6U CN208363617U (en) | 2018-05-23 | 2018-05-23 | Water pipe well reserved casing pipe die |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208363617U true CN208363617U (en) | 2019-01-11 |
Family
ID=64935640
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820774271.6U Active CN208363617U (en) | 2018-05-23 | 2018-05-23 | Water pipe well reserved casing pipe die |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208363617U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115370141A (en) * | 2022-09-15 | 2022-11-22 | 中国建筑第五工程局有限公司 | Positioning die for reserved sleeve of water pipe well in building |
-
2018
- 2018-05-23 CN CN201820774271.6U patent/CN208363617U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115370141A (en) * | 2022-09-15 | 2022-11-22 | 中国建筑第五工程局有限公司 | Positioning die for reserved sleeve of water pipe well in building |
CN115370141B (en) * | 2022-09-15 | 2024-03-29 | 中国建筑第五工程局有限公司 | Water pipe well reservation sleeve pipe positioning die in building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208363617U (en) | Water pipe well reserved casing pipe die | |
CN204626453U (en) | The supporting device of pipeline in Urban Underground pipe gallery | |
CN110700319A (en) | Comprehensive pipe gallery is with unilateral formwork frock | |
CN211371483U (en) | Pipeline engineering construction clamping device | |
CN212453572U (en) | Embedded bolt wall connecting piece device | |
CN214383884U (en) | Steel box girder for installing and positioning bridge | |
CN215407370U (en) | Construction structures is pour in step to two walls of building movement joint concrete | |
CN213971755U (en) | Lintel integrated prefabricated combined type water and electricity switch control box die | |
CN212269243U (en) | Pipeline fixing frame with lifting function | |
CN212561479U (en) | Lap joint type pipe pile head | |
CN211201997U (en) | Split-type spliced model structure for pouring inverted arch and filling of highway tunnel | |
CN210561747U (en) | Positioning device for bolt preformed hole of bridge support | |
CN210263918U (en) | Anti-bank pouring die | |
CN214834826U (en) | Pre-buried spool bending construction tool convenient to construction | |
CN215452393U (en) | Template pipeline positioning device | |
CN210500788U (en) | Precast concrete pipe culvert convenient to hoist and mount and butt joint | |
CN212773565U (en) | Many spool are fixed and are stereotyped mould in cast-in-place board | |
CN216470140U (en) | Simple and convenient formula hydraulic engineering bank protection prefabricated section handling tool | |
CN212480374U (en) | A water stop pipe | |
CN217272603U (en) | Irrigation equipment is used in forestry afforestation | |
CN213418488U (en) | Anti-deformation supporting device of pre-buried electronic box | |
CN215484634U (en) | Hanging hole device for building | |
CN210685400U (en) | Pipeline hangs mould device suitable for different pipe diameters | |
CN211899656U (en) | Template stabilising arrangement for construction | |
CN215594902U (en) | Pipe pier shaping die for roof outlet pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||