CN208275562U - A kind of civil construction project construction waste material environment-friendly processing unit - Google Patents

A kind of civil construction project construction waste material environment-friendly processing unit Download PDF

Info

Publication number
CN208275562U
CN208275562U CN201820499378.4U CN201820499378U CN208275562U CN 208275562 U CN208275562 U CN 208275562U CN 201820499378 U CN201820499378 U CN 201820499378U CN 208275562 U CN208275562 U CN 208275562U
Authority
CN
China
Prior art keywords
pulverizing chamber
cover board
crushing
pipe
waste material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820499378.4U
Other languages
Chinese (zh)
Inventor
吕建洪
储华锦
韩德宏
吕成
吕燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chuang Heng Construction Co Ltd
Original Assignee
Chuang Heng Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chuang Heng Construction Co Ltd filed Critical Chuang Heng Construction Co Ltd
Priority to CN201820499378.4U priority Critical patent/CN208275562U/en
Application granted granted Critical
Publication of CN208275562U publication Critical patent/CN208275562U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Disintegrating Or Milling (AREA)

Abstract

The utility model discloses a kind of civil construction project construction waste material environment-friendly processing units, it is filled including loading, blower, observation window, cover board, motor, shaft, feed pipe, scum pipe, universal wheel, first discharge nozzle, material storage room, second discharge nozzle, valve, delivery pipe, cache room, connecting tube, pulverizing chamber, crushing cutter, cross bar and sparge pipe, the beneficial effects of the utility model are: by installing shaft inside cover board, so that building castoff to be processed in work enters inside pulverizing chamber from feed pipe, motor drives shaft rotation by belt, and then drive cross bar and crushing cutter rotation, cross bar and crushing cutter are by the building castoff cutting and crushing inside pulverizing chamber, volume becomes smaller, and the biggish building castoff of volume is beaten crushing by cross bar, improve working efficiency, avoid the excessive damage of crushing cutter stress, security performance obtains To raising, building castoff facilitates collection to transport after crushing, and reduces the space occupied, facilitates stacking.

Description

A kind of civil construction project construction waste material environment-friendly processing unit
Technical field
The utility model relates to a kind of environment-friendly processing unit, specially a kind of civil construction project construction waste material environmental protection treatment Device belongs to construction waste processing application field.
Background technique
Construction waste refers to the slag that people generate in the production activity for being engaged in the construction industries such as removal, construction, finishing, repairerment The general designation of soil, waste and old concrete, waste and old masonry and other wastes.Classify by generating source, building waste can be divided into engineering dregs, Decoration garbage, removal rubbish, engineering slurry etc.;Classify by constituent, dregs, concrete block, broken can be divided into building waste Stone, brick and tile fragment, waste mortar, mud, asphalt blocks, waste plastics, old metal, useless bamboo wood etc..In order to pollute construction waste not Environment, common building waste treatment device carry out environmental protection treatment.
But there are still certain deficiencies when in use for existing construction waste processing unit.Existing construction waste processing Apparatus structure is simple, handles the low efficiency of construction waste, cannot classify after construction waste processing, it has not been convenient to collection processing.Place Dust is more during reason, is easily accessible in air, pollutes environment.
Utility model content
Purpose of the utility model is to solve construction wastes in the prior art arbitrarily to abandon, and pollutes environment, processing is not Complete problem, and a kind of civil construction project construction waste material environment-friendly processing unit proposed.
The utility model is achieved through the following technical solutions above-mentioned purpose, a kind of civil construction project construction waste material environmental protection Processing unit, including filling, cover board, shaft and delivery pipe are loaded, the loading fills bottom and is uniformly connected with three groups of universal wheels, and institute It states loading filling bottom middle-end and is connected with the first discharge nozzle, the loading abhiseca portion is connected with cover board, and the cover board top side connects It is connected to feed pipe, one end is connected with sparge pipe at the top of the cover board, and middle-end is equipped with shaft at the top of the cover board, outside the shaft Portion is connected separately with several crushing cutters and cross bar.
The loading fills inner tip and is provided with pulverizing chamber, and the loading fills inner bottom and is provided with caching room, described It loads to fill and is respectively connected with connecting tube with the caching chamber interior side, described connecting tube one end is equipped with blower, the pulverizing chamber Interior side is connected with scum pipe, and the pulverizing chamber bottom is connected with net-shaped delivery pipe, and the loading fills inner bottom setting There is material storage room.
Preferably, the loading fills top side and is provided with observation window, and observation window is perpendicular to pulverizing chamber.
Preferably, the other side is equipped with motor at the top of the cover board, and motor connects shaft by belt.
Preferably, the loading fills bottom side and is connected with the second discharge nozzle, and second discharge nozzle one end is filled through loading Connection Cache room.
Preferably, one end is equipped with valve at the top of the delivery pipe, and valve one end is filled through loading.
Preferably, twist it is arranged outside the delivery pipe, and pulverizing chamber bottom is arc-shaped setting.
Compared with prior art, the utility model has the beneficial effects that
1, by installing shaft inside cover board, so that building castoff to be processed in work enters crushing from feed pipe Chamber interior, motor drive shaft to rotate by belt, and then drive cross bar and crushing cutter rotation, and cross bar and crushing cutter will crush The building castoff cutting and crushing of chamber interior, volume become smaller, and the biggish building castoff of volume is beaten crushing by cross bar, improve Working efficiency, avoids the excessive damage of crushing cutter stress, and security performance is improved.Building castoff facilitates collection to transport after crushing It is defeated, the space occupied is reduced, stacking is facilitated.
2, by loading setting caching room inside filling, so that being turned after the waste in work inside pulverizing chamber crushes Valve will be connected between pulverizing chamber and delivery pipe, and the waste of crushing enters inside delivery pipe, inside spiral delivery pipe The waste of operation repeatedly, crushing is filtered by netted delivery pipe, and volume is biggish to be entered inside material storage room from delivery pipe, Small volume is fallen into inside surge chamber, and last waste is by two discharge nozzle discharges.The pulverized separation of waste, facilitates waste Recycling, collect it is more quick, work efficiency is high.And waste, when crushing conveying, blower passes through connecting tube for pulverizing chamber It is collected with the dirt absorption of caching chamber interior, avoids dust and get into the air, protect the environment from pollution, when dust is more, Sparge pipe removes dust to pulverizing chamber internal spray clean water.
Detailed description of the invention
Fig. 1 is the utility model overall structure diagram.
Fig. 2 is that the utility model loads filling schematic diagram of internal structure.
Fig. 3 is the utility model pipe structure schematic diagram.
In figure: 1, loading and fill;2, blower;3, observation window;4, cover board;5, motor;6, shaft;7, feed pipe;8, deslagging Pipe;9, universal wheel;10, the first discharge nozzle;11, material storage room;12, the second discharge nozzle;13, valve;14, delivery pipe;15, it caches Room;16, connecting tube;17, pulverizing chamber;18, crushing cutter;19, cross bar;20, sparge pipe.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Embodiment 1
It please refers to shown in Fig. 1-3, a kind of civil construction project construction waste material environment-friendly processing unit, including loads and fill 1, cover board 4, shaft 6 and delivery pipe 14 load and fill 1 bottom and be uniformly connected with three groups of universal wheels 9, and load and fill 1 bottom middle-end and be connected with the One discharge nozzle 10 loads 1 top of filling and is connected with cover board 4, and 4 top side of cover board is connected with feed pipe 7, and 4 top one end of cover board connects It is connected to sparge pipe 20,4 top middle-end of cover board is equipped with shaft 6, several crushing cutters 18 and cross bar are connected separately with outside shaft 6 19;It loading 1 inner tip of filling and is provided with pulverizing chamber 17, building castoff to be processed enters inside pulverizing chamber 17 from feed pipe 7, Motor 5 drives shaft 6 to rotate by belt, and then cross bar 19 and crushing cutter 18 is driven to rotate, and cross bar 19 and crushing cutter 18 will Building castoff cutting and crushing inside pulverizing chamber 17, and the biggish building castoff of volume is beaten crushing by cross bar 19, is improved Working efficiency avoids the excessive damage of 18 stress of crushing cutter, and loads 1 inner bottom of filling and be provided with caching room 15, and it is gentle to load filling 1 It deposits 15 interior side of room and is respectively connected with connecting tube 16,16 one end of connecting tube is equipped with blower 2, and 17 interior side of pulverizing chamber is connected with Scum pipe 8,17 bottom of pulverizing chamber are connected with net-shaped delivery pipe 14, load 1 inner bottom of filling and are provided with material storage room 11, pulverizing chamber After waste inside 17 crushes, valve 13 is turned, will be connected between pulverizing chamber 17 and delivery pipe 14, the waste of crushing enters Inside delivery pipe 14, the waste of operation inside spiral delivery pipe 14 repeatedly, crushing passes through netted delivery pipe 14 Filtering, volume is biggish to be entered inside material storage room 11 from delivery pipe 14, and small volume is fallen into inside surge chamber 15, last waste It is discharged by two discharge nozzles.And waste, when crushing conveying, blower 2 by pulverizing chamber 17 and caches room 45 by connecting tube 16 Internal dirt absorption is collected, and is avoided dust and is got into the air, protects the environment from pollution, when dust is more, sparge pipe 20 To 17 internal spray clean water of pulverizing chamber, dust is removed.
Embodiment 2
In addition, the difference with above-described embodiment is please according to Fig. 1-3: loading 1 top side of filling and be provided with sight Window 3 is examined, and observation window 3 can check the crushing feelings inside pulverizing chamber 17 through observation window 3 perpendicular to pulverizing chamber 17 at work Condition, the time for facilitating control valve 13 to open.The 5 top other side of cover board is equipped with motor 5, and motor 5 is connected by belt Switch through axis 6, motor 5 drives shaft 6 to rotate by belt, and then cross bar 19 and crushing cutter 18 is driven to rotate.It loads and fills 1 bottom Side is connected with the second discharge nozzle 12, and 12 one end of the second discharge nozzle caches inside room 15 through 1 Connection Cache room 15 of filling is loaded The waste of small volume is discharged from the second discharge nozzle 12.14 top one end of delivery pipe is equipped with valve 13, and 13 one end of valve 1 is filled through loading, valve 13 can be such that the discarded dirt inside pulverizing chamber 17 does not enter inside delivery pipe 14 in pulverizing chamber 17.Conveying Twist it is arranged outside pipe 14, and 17 bottom of pulverizing chamber is arc-shaped setting, spiral setting makes waste filtering screening More efficient, arc-shaped setting makes waste be not easy to accumulate in 17 bottom of pulverizing chamber.
When the utility model is used, firstly, building castoff to be processed is entered in pulverizing chamber 17 from feed pipe 7 Portion, motor 5 drive shaft 6 to rotate by belt, and then cross bar 19 and crushing cutter 18 is driven to rotate, cross bar 19 and crushing cutter 18 By the building castoff cutting and crushing inside pulverizing chamber 17, and the biggish building castoff of volume is beaten crushing by cross bar 19, is mentioned High working efficiency avoids the excessive damage of 18 stress of crushing cutter.After waste inside pulverizing chamber 17 crushes, valve 13 is turned, it will It is connected between pulverizing chamber 17 and delivery pipe 14, the waste of crushing enters inside delivery pipe 14, in spiral delivery pipe 14 The waste of the operation of portion repeatedly, crushing is filtered by netted delivery pipe 14, and volume is biggish to enter storing from delivery pipe 14 Inside room 11, small volume is fallen into inside surge chamber 15, and last waste is by two discharge nozzle discharges.And waste is crushing When conveying, blower 2 is collected the dirt absorption inside pulverizing chamber 17 and caching room 45 by connecting tube 16, avoids dust entrance It in air, protects the environment from pollution, when dust is more, sparge pipe 20 removes dust to 17 internal spray clean water of pulverizing chamber.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this is practical new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this is practical new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing for the equivalent requirements of the claims will be fallen in All changes in justice and range are embraced therein.It should not treat any reference in the claims as limiting Related claim.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (6)

  1. The waste material environment-friendly processing unit 1. a kind of civil construction project is constructed, including load and fill (1), cover board (4), shaft (6) and defeated Send pipe (14), it is characterised in that: the loading fills (1) bottom and is uniformly connected with three groups of universal wheels (9), and the loading fills (1) Bottom middle-end is connected with the first discharge nozzle (10), and the loading fills to be connected with cover board (4) at the top of (1), one at the top of the cover board (4) Side is connected with feed pipe (7), and one end is connected with sparge pipe (20) at the top of the cover board (4), middle-end installation at the top of the cover board (4) Have shaft (6), is connected separately with several crushing cutters (18) and cross bar (19) outside the shaft (6);
    The loading fills (1) inner tip and is provided with pulverizing chamber (17), and the loading fills (1) inner bottom and is provided with caching room (15), the loading fills (1) and caching room (15) interior side is respectively connected with connecting tube (16), the connecting tube (16) one End is equipped with blower (2), and pulverizing chamber (17) interior side is connected with scum pipe (8), pulverizing chamber (17) the bottom connection Have net-shaped delivery pipe (14), the loading fills (1) inner bottom and is provided with material storage room (11).
  2. The waste material environment-friendly processing unit 2. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: described It loads filling (1) top side to be provided with observation window (3), and observation window (3) is perpendicular to pulverizing chamber (17).
  3. The waste material environment-friendly processing unit 3. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: described The other side is equipped with motor (5) at the top of cover board (4), and motor (5) connects shaft (6) by belt.
  4. The waste material environment-friendly processing unit 4. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: described It loads filling (1) bottom side to be connected with the second discharge nozzle (12), and the second discharge nozzle (12) one end is delayed through filling (1) connection is loaded Deposit room (15).
  5. The waste material environment-friendly processing unit 5. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: described One end is equipped with valve (13) at the top of delivery pipe (14), and valve (13) one end fills (1) through loading.
  6. The waste material environment-friendly processing unit 6. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: described Twist it is arranged outside delivery pipe (14), and pulverizing chamber (17) bottom is arc-shaped setting.
CN201820499378.4U 2018-04-10 2018-04-10 A kind of civil construction project construction waste material environment-friendly processing unit Expired - Fee Related CN208275562U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820499378.4U CN208275562U (en) 2018-04-10 2018-04-10 A kind of civil construction project construction waste material environment-friendly processing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820499378.4U CN208275562U (en) 2018-04-10 2018-04-10 A kind of civil construction project construction waste material environment-friendly processing unit

Publications (1)

Publication Number Publication Date
CN208275562U true CN208275562U (en) 2018-12-25

Family

ID=64749437

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820499378.4U Expired - Fee Related CN208275562U (en) 2018-04-10 2018-04-10 A kind of civil construction project construction waste material environment-friendly processing unit

Country Status (1)

Country Link
CN (1) CN208275562U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112121495A (en) * 2020-09-02 2020-12-25 安徽军松现代农业科技有限公司 Agricultural sewage treatment plant

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112121495A (en) * 2020-09-02 2020-12-25 安徽军松现代农业科技有限公司 Agricultural sewage treatment plant

Similar Documents

Publication Publication Date Title
CN208810238U (en) A kind of aggregate crushed aggregates device
CN208302867U (en) A kind of building construction Slag recovering device
CN110215989A (en) A kind of environment-friendly multi-stage construction waste crushing processing unit
CN108187818A (en) A kind of building waste sorting equipment
CN215277604U (en) Garbage crushing apparatus for building engineering
CN206587821U (en) A kind of building block processing waste material recovery device
CN110882783A (en) Waste timber fragmentation treatment device with dust removal function
CN215140330U (en) Construction waste treatment equipment
CN216173132U (en) Energy-concerving and environment-protective civil engineering construction waste material processing apparatus
CN211612881U (en) Civil engineering construction waste treatment device
CN210279264U (en) Building waste recycling device
CN205056617U (en) Building trash classification recycling device
CN220969395U (en) Stone crushing device for constructional engineering
CN208181867U (en) Mechanical equipment is used in a kind of cleaning of New-type refuse vehicle
CN214390379U (en) Garbage recycling device for house building construction
CN215429515U (en) A crushing device for coal mining
CN117328312A (en) Asphalt pavement recycling, crushing and pretreatment equipment
CN212820060U (en) Stone breaker is used in municipal works construction with dust removal function
CN210495810U (en) Waste gas treatment equipment that recycled aggregate produced for high-strength concrete
CN212000814U (en) Forestry fallen leaves recovery unit
CN210496587U (en) Dustproof equipment in process is smashed with regeneration bone meal to high-strength concrete
CN209565030U (en) Crusher is used in a kind of processing of urban construction solid refuse
CN220547014U (en) Pulverizer with dust removal structure
CN219682684U (en) Gravel bin for producing concrete
CN220803685U (en) Engineering waste material environmental protection processing apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181225

Termination date: 20210410

CF01 Termination of patent right due to non-payment of annual fee