CN208168368U - A kind of construction wall construction template connector - Google Patents
A kind of construction wall construction template connector Download PDFInfo
- Publication number
- CN208168368U CN208168368U CN201820629345.7U CN201820629345U CN208168368U CN 208168368 U CN208168368 U CN 208168368U CN 201820629345 U CN201820629345 U CN 201820629345U CN 208168368 U CN208168368 U CN 208168368U
- Authority
- CN
- China
- Prior art keywords
- stupefied
- construction
- formwork
- screw
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 27
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 47
- 239000010959 steel Substances 0.000 claims abstract description 47
- 239000004567 concrete Substances 0.000 claims abstract description 31
- 229910001208 Crucible steel Inorganic materials 0.000 claims abstract description 9
- 238000007789 sealing Methods 0.000 claims description 7
- 239000011324 bead Substances 0.000 claims 1
- 238000009415 formwork Methods 0.000 abstract description 40
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 15
- 230000000694 effects Effects 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 241000353097 Molva molva Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000003139 buffering effect Effects 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 229920000642 polymer Polymers 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本实用新型公开了一种建筑墙体施工用模板连接件,所述混凝土墙体的两侧均设有模板组件与支撑结构,所述勾头螺栓的一端勾住模板组件的背楞,另一端通过螺母与外钢楞固定连接,所述止水螺杆穿过混凝土墙体、模板组件与支撑结构,且两端通过山形螺母紧固,所述铸钢垫片与外钢楞的接触面设有第一橡胶垫,所述内钢楞与模板组件的接触面设有第二橡胶垫,所述止水螺杆包括两个连接螺杆和一个内撑杆,所述内撑杆的两端焊接有螺纹筒,所述内撑杆的中心点套接有止水环;本实用新型能够牢靠的将模板与支撑结构相连接,并且不会导致模板变形、模板不易脱落,具有防水功能并且便于拆卸,拆卸下来的部分可以重复使用。
The utility model discloses a formwork connector for building wall construction. Both sides of the concrete wall are provided with a formwork assembly and a supporting structure. One end of the hook bolt hooks the back of the formwork assembly, and the other end The nut is fixedly connected to the outer steel corrugation, the water-stop screw passes through the concrete wall, the formwork assembly and the supporting structure, and the two ends are fastened by mountain nuts, and the contact surface between the cast steel gasket and the outer steel corrugation is provided with The first rubber pad, the contact surface between the inner steel flute and the formwork assembly is provided with a second rubber pad, the water-stop screw includes two connecting screws and an inner strut, and the two ends of the inner strut are welded with threads The central point of the inner support rod is sleeved with a water-stop ring; the utility model can firmly connect the formwork with the support structure, and will not cause the formwork to be deformed, the formwork is not easy to fall off, has waterproof function and is easy to disassemble. The part that comes down can be reused.
Description
技术领域technical field
本实用新型涉及建筑模板技术领域,具体为一种建筑墙体施工用模板连接件。The utility model relates to the technical field of building formwork, in particular to a formwork connector for building wall construction.
背景技术Background technique
建筑模板是一种临时性支护结构,按设计要求制作,使混凝土结构、构件按规定的位置、几何尺寸成形,保持其正确位置,并承受建筑模板自重及作用在其上的外部荷载。进行模板工程的目的,是保证混凝土工程质量与施工安全、加快施工进度和降低工程成本。现浇混凝土结构工程施工用的建筑模板结构,主要由面板、支撑结构和连接件三部分组成。面板是直接接触新浇混凝土的承力板;支撑结构则是支承面板、混凝土和施工荷载的临时结构,保证建筑模板结构牢固地组合,做到不变形、不破坏;连接件是将面板与支撑结构连接成整体的配件。The building formwork is a temporary support structure, which is manufactured according to the design requirements, so that the concrete structure and components are formed according to the specified position and geometric size, maintain their correct position, and bear the self-weight of the building formwork and the external load acting on it. The purpose of formwork engineering is to ensure the quality of concrete engineering and construction safety, speed up the construction progress and reduce engineering costs. The building formwork structure used in the construction of cast-in-place concrete structures is mainly composed of three parts: panels, support structures and connectors. The panel is the load-bearing slab that directly contacts the freshly poured concrete; the support structure is a temporary structure that supports the panel, concrete and construction loads, ensuring that the building formwork structure is firmly combined without deformation or damage; the connector is the connection between the panel and the support Fittings that connect structures into a whole.
目前的连接件常采用的是对拉螺栓,通过对拉螺栓将模板与支撑钢楞固定,再浇筑混凝土墙。但是这种连接方式对模板的夹合固定效果并不理想,对拉螺栓上面的螺母如果拧的太紧,会使拉力过大导致模板被支撑钢楞挤压而变形,拧的太松又会导致模板容易脱落;并且对拉螺栓因为螺杆穿过混凝土墙体,水容易沿着螺杆渗透进去,而水对钢筋混凝土的腐蚀是最可怕的,会严重破环混凝土墙体的稳定性和安全性;有的工程使用止水螺栓进行连接,虽然止水螺栓能够起到一定的防水功能,但是在拆除时需要锯掉墙外两头后,中间段留在墙体,以保证墙体的不透水性,拆除十分麻烦,并且锯断的止水螺杆无法重复使用。为此,提出一种建筑墙体施工用模板连接件。What present connector often adopts is pull bolt, formwork and support corrugated are fixed by pull bolt, and then concrete wall is poured. However, this connection method is not ideal for clamping and fixing the formwork. If the nuts on the pull bolts are tightened too tightly, the tension will be too large and the formwork will be squeezed and deformed by the supporting steel corrugation. The formwork is easy to fall off; and because the screw rod passes through the concrete wall, the water is easy to penetrate along the screw rod, and the corrosion of water to the reinforced concrete is the most terrible, which will seriously damage the stability and safety of the concrete wall ; Some projects use water-stop bolts for connection. Although the water-stop bolts can play a certain waterproof function, it is necessary to saw off the two ends of the wall and leave the middle section in the wall to ensure the impermeability of the wall. , It is very troublesome to dismantle, and the sawn off water stop screw cannot be reused. For this reason, a formwork connector for building wall construction is proposed.
发明内容Contents of the invention
本实用新型的目的在于提供一种建筑墙体施工用模板连接件,能够牢靠的将模板与支撑结构相连接,并且不会导致模板变形、模板不易脱落,具有防水功能并且便于拆卸,拆卸下来的部分可以重复使用,以解决上述背景技术中提出的问题。The purpose of this utility model is to provide a formwork connector for building wall construction, which can firmly connect the formwork with the supporting structure, and will not cause the formwork to deform, the formwork is not easy to fall off, has waterproof function and is easy to disassemble. Parts can be reused to solve the problems raised in the background art above.
为实现上述目的,本实用新型提供如下技术方案:一种建筑墙体施工用模板连接件,包括混凝土墙体、勾头螺栓与止水螺杆,所述混凝土墙体的两侧均设有模板组件与支撑结构,所述支撑结构包括内钢楞与外钢楞,所述勾头螺栓的一端勾住模板组件的背楞,另一端通过螺母与外钢楞固定连接,所述止水螺杆穿过混凝土墙体、模板组件与支撑结构,且两端通过山形螺母紧固,所述山形螺母与外钢楞之间设有铸钢垫片,所述铸钢垫片与外钢楞的接触面设有第一橡胶垫,所述内钢楞与模板组件的接触面设有第二橡胶垫,所述止水螺杆包括两个连接螺杆和一个内撑杆,所述内撑杆的两端焊接有螺纹筒,所述连接螺杆的两端均设有螺纹,所述连接螺杆的一端通过螺纹与螺纹筒固定连接,另一端通过螺纹与山形螺母固定连接,所述内撑杆的中心点套接有止水环。In order to achieve the above purpose, the utility model provides the following technical solutions: a formwork connector for building wall construction, including a concrete wall, hook bolts and water-stop screw rods, and formwork components are provided on both sides of the concrete wall and the support structure, the support structure includes an inner steel flute and an outer steel flute, one end of the hook bolt hooks the back flute of the formwork assembly, and the other end is fixedly connected to the outer steel flute through a nut, and the water-stop screw passes through Concrete wall, formwork assembly and support structure, and both ends are fastened by chevron nuts, a cast steel gasket is provided between the chevron nut and the outer steel flute, and the contact surface of the cast steel gasket and the outer steel flute is set There is a first rubber pad, and a second rubber pad is provided on the contact surface between the inner steel flute and the formwork assembly. The water-stop screw includes two connecting screws and an inner strut, and the two ends of the inner strut are welded with threaded cylinder, both ends of the connecting screw are provided with threads, one end of the connecting screw is fixedly connected with the threaded cylinder, and the other end is fixedly connected with the mountain nut through the thread, and the center point of the inner strut is sleeved with Waterstop ring.
优选的,所述内撑杆位于混凝土墙体的内部,且内撑杆的长度与混凝土墙体的厚度相等,内撑杆两端的螺纹筒能够起到限位作用,通过不同长度的内撑杆能够控制墙体的厚度。Preferably, the inner strut is located inside the concrete wall, and the length of the inner strut is equal to the thickness of the concrete wall, and the threaded cylinders at both ends of the inner strut can play a position-limiting role, and the inner struts of different lengths can Ability to control wall thickness.
优选的,所述模板组件由若干个建筑模板固定拼接而成。Preferably, the formwork assembly is formed by fixed splicing of several building formworks.
优选的,所述内钢楞与外钢楞为若干个垂直相交并通过螺栓固定连接,且每个内钢楞与外钢楞的交点处均设有止水螺杆。Preferably, the inner steel flute and the outer steel flute are several vertically intersecting and fixedly connected by bolts, and each intersection of the inner steel flute and the outer steel flute is provided with a water-stop screw.
优选的,所述内钢楞与外钢楞为内卷边槽钢。Preferably, the inner steel flute and the outer steel flute are inner crimped channel steel.
优选的,所述止水环为膨胀止水环。Preferably, the water stop ring is an expandable water stop ring.
与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the utility model are:
1、本实用新型结构简单、可靠、成本低廉、易于实现且使用方便;1. The utility model is simple in structure, reliable, low in cost, easy to realize and convenient to use;
2、通过加装多个勾头螺栓与止水螺杆配合能够使连接结构更牢靠,通过第一橡胶垫与第二橡胶垫能够使连接处的密封性好,并且避免了模板受到的紧固力过大导致挤压变形;2. The connection structure can be made more reliable by adding multiple hook bolts and the water-stop screw, and the sealing of the connection can be made good by the first rubber pad and the second rubber pad, and the fastening force on the formwork can be avoided Excessive size leads to extrusion deformation;
3、止水环能够遇水膨胀,配合第一橡胶垫与第二橡胶垫能够达到很好的止水效果;3. The water-stop ring can expand with water, and the first rubber pad and the second rubber pad can achieve a good water-stop effect;
4、拆卸方便,只需要通过螺纹将止水螺杆两端的连接螺杆拧下即可,不用将止水螺杆锯断,更为省时省力,并且拆卸下来的连接螺杆可以重复使用,节省了施工成本。4. It is easy to disassemble. You only need to unscrew the connecting screws at both ends of the water-stop screw through the thread. You don’t need to saw off the water-stop screw, which saves time and effort, and the disassembled connecting screws can be reused, saving construction costs. .
附图说明Description of drawings
图1为本实用新型的剖面图;Fig. 1 is a sectional view of the utility model;
图2为本实用新型的主视图;Fig. 2 is the front view of the utility model;
图3为本实用新型止水螺杆的剖面图。Fig. 3 is a cross-sectional view of the water-stop screw of the present invention.
图中:1混凝土墙体、2勾头螺栓、3止水螺杆、301连接螺杆、302内撑杆、303螺纹筒、304螺纹、305止水环、4模板组件、5支撑结构、501内钢楞、502外钢楞、6螺母、7山形螺母、8铸钢垫片、9第一橡胶垫、10第二橡胶垫。In the figure: 1 concrete wall, 2 hook bolts, 3 water-stop screw, 301 connecting screw, 302 inner strut, 303 threaded cylinder, 304 thread, 305 water-stop ring, 4 formwork components, 5 support structure, 501 inner steel Leng, 502 outer steel flute, 6 nuts, 7 mountain nuts, 8 cast steel gaskets, 9 first rubber pads, 10 second rubber pads.
具体实施方式Detailed ways
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.
如图1-3所示,一种建筑墙体施工用模板连接件,包括混凝土墙体1、勾头螺栓2与止水螺杆3,所述混凝土墙体1的两侧均设有模板组件4与支撑结构5,所述支撑结构5包括内钢楞501与外钢楞502,所述勾头螺栓2的一端勾住模板组件4的背楞,另一端通过螺母6与外钢楞502固定连接,所述止水螺杆3穿过混凝土墙体1、模板组件4与支撑结构5,且两端通过山形螺母7紧固,所述山形螺母7与外钢楞502之间设有铸钢垫片8,所述铸钢垫片8与外钢楞502的接触面设有第一橡胶垫9,所述内钢楞501与模板组件4的接触面设有第二橡胶垫10,所述止水螺杆3包括两个连接螺杆301和一个内撑杆302,所述内撑杆302的两端焊接有螺纹筒303,所述连接螺杆301的两端均设有螺纹304,所述连接螺杆301的一端通过螺纹304与螺纹筒303固定连接,另一端通过螺纹304与山形螺母7固定连接,所述内撑杆302的中心点套接有止水环305。As shown in Figures 1-3, a formwork connector for building wall construction includes a concrete wall 1, a hook bolt 2 and a water-stop screw 3, and formwork components 4 are provided on both sides of the concrete wall 1 With the support structure 5, the support structure 5 includes an inner steel flute 501 and an outer steel flute 502, one end of the hook bolt 2 hooks the back flute of the formwork assembly 4, and the other end is fixedly connected to the outer steel flute 502 through a nut 6 , the water stop screw 3 passes through the concrete wall 1, the template assembly 4 and the support structure 5, and the two ends are fastened by the chevron nut 7, and a cast steel gasket is arranged between the chevron nut 7 and the outer steel corrugation 502 8. A first rubber pad 9 is provided on the contact surface between the cast steel gasket 8 and the outer steel flute 502, a second rubber pad 10 is provided on the contact surface between the inner steel flute 501 and the formwork assembly 4, and the water-stop Screw rod 3 comprises two connecting screw rods 301 and an inner strut 302, and the two ends of described inner strut 302 are welded with threaded cylinder 303, and the two ends of described connecting screw rod 301 are all provided with screw thread 304, and the two ends of described connecting screw rod 301 One end is fixedly connected to the threaded cylinder 303 through the thread 304 , and the other end is fixedly connected to the mountain nut 7 through the thread 304 , and the center point of the inner support rod 302 is sleeved with a water stop ring 305 .
具体的,所述内撑杆302位于混凝土墙体1的内部,且内撑杆302的长度与混凝土墙体1的厚度相等,内撑杆302两端的螺纹筒303能够起到限位作用,通过不同长度的内撑杆302能够控制墙体的厚度。Specifically, the inner strut 302 is located inside the concrete wall 1, and the length of the inner strut 302 is equal to the thickness of the concrete wall 1, and the threaded cylinder 303 at both ends of the inner strut 302 can play a position-limiting role. Different lengths of inner struts 302 can control the thickness of the wall.
具体的,所述模板组件4由若干个建筑模板固定拼接而成。Specifically, the formwork assembly 4 is formed by fixing and splicing several building formworks.
具体的,所述内钢楞501与外钢楞502垂直相交并通过螺栓固定连接,且每个内钢楞501与外钢楞502的交点处均设有止水螺杆3,通过若干个止水螺栓3将模板组件4与支撑结构5牢靠的连接。Specifically, the inner steel flute 501 and the outer steel flute 502 are vertically intersected and connected by bolts, and each intersection of the inner steel flute 501 and the outer steel flute 502 is provided with a water-stop screw 3, through several water-stop Bolts 3 securely connect the template assembly 4 with the supporting structure 5 .
具体的,所述内钢楞501与外钢楞502为内卷边槽钢。Specifically, the inner steel flute 501 and the outer steel flute 502 are inner crimped channel steel.
具体的,所述止水环305为膨胀止水环,膨胀止水环由高分子无机吸水膨胀材料和橡胶精炼而成,相比传统焊接的止水片安装更加方便,按尺寸选对应产品,套上压紧即可,并且能够遇水膨胀,靠自身的膨胀挤密混凝土墙体1与止水螺杆3的缝隙,可完全起到止水作用。Specifically, the water stop ring 305 is an expansion water stop ring, and the expansion water stop ring is refined from polymer inorganic water-absorbing expansion materials and rubber. Compared with the traditional welded water stop sheet, it is more convenient to install, and the corresponding product is selected according to the size. Just put it on and press it tightly, and it can expand when it encounters water, and the gap between the concrete wall body 1 and the water-stop screw 3 can be tightly squeezed by its own expansion, and the water-stop effect can be fully played.
工作原理:使用时,根据需要浇筑的混凝土墙体1的厚度选择合适的内撑杆302,将内撑杆302的两端通过螺纹筒303与两个连接螺杆301固定连接组成止水螺杆3,通过多个勾头螺栓2和螺母6将模板组件4与外钢楞502固定连接成为一个模板单元,将两组模板单元通过多个止水螺杆3连接并通过山形螺母7紧固,铸钢垫片8能够起到紧固作用,第一橡胶垫9与第二橡胶垫10能够起到缓冲和密封作用,防止螺母6与山形螺母7紧固后内钢楞501对模板组件4压力过大使模板组件4产生变形;在两组模板单元之间浇筑混凝土墙体1,混凝土墙体1的厚度由内撑杆302的长度决定,浇筑完成后内撑杆302上的止水环305能够起到止水作用,防止混凝土墙体1进水;拆除时将山形螺母7与螺母6取下,便可以拆除支撑结构5,将内撑杆302两侧的连接螺杆301通过螺纹304拆除,内撑杆302留在墙体内,以保证墙体的不透水性,整个拆除过程方便快捷;拆除下来的连接螺杆301能够重复使用,适配与不同长度的内撑杆302。Working principle: When in use, select a suitable inner strut 302 according to the thickness of the concrete wall 1 to be poured, and connect the two ends of the inner strut 302 to two connecting screws 301 through a threaded cylinder 303 to form a water-stop screw 3. The template assembly 4 is fixedly connected to the outer steel corrugated 502 by a plurality of hook bolts 2 and nuts 6 to form a template unit, and the two groups of template units are connected by a plurality of water-stop screws 3 and fastened by mountain nuts 7, cast steel pads The sheet 8 can play a fastening role, and the first rubber pad 9 and the second rubber pad 10 can play a buffering and sealing role, preventing the inner steel flute 501 from pressing the template assembly 4 too much to make the template after the nut 6 and the mountain nut 7 are fastened The component 4 is deformed; the concrete wall 1 is poured between the two groups of formwork units. The thickness of the concrete wall 1 is determined by the length of the inner strut 302. After the pouring is completed, the water-stop ring 305 on the inner strut 302 can stop The effect of water prevents the concrete wall 1 from entering water; when removing the chevron nut 7 and the nut 6, the support structure 5 can be removed, and the connecting screw 301 on both sides of the inner strut 302 is removed through the thread 304, and the inner strut 302 Stay in the wall to ensure the impermeability of the wall, and the whole removal process is convenient and quick; the removed connecting screw 301 can be reused and adapted to inner struts 302 of different lengths.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201820629345.7U CN208168368U (en) | 2018-04-28 | 2018-04-28 | A kind of construction wall construction template connector |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201820629345.7U CN208168368U (en) | 2018-04-28 | 2018-04-28 | A kind of construction wall construction template connector |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN208168368U true CN208168368U (en) | 2018-11-30 |
Family
ID=64368466
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201820629345.7U Expired - Fee Related CN208168368U (en) | 2018-04-28 | 2018-04-28 | A kind of construction wall construction template connector |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN208168368U (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109900432A (en) * | 2019-03-20 | 2019-06-18 | 中国建筑第八工程局有限公司 | Sealing up screw seal ring tightness detector and detection method |
| CN110195513A (en) * | 2019-06-25 | 2019-09-03 | 中铁一局集团第四工程有限公司 | Water-stopping pull rod and waterproof construction method in subway work |
| CN111456433A (en) * | 2020-05-11 | 2020-07-28 | 五冶集团上海有限公司 | Drawing rod and its application method |
| CN112942808A (en) * | 2021-01-29 | 2021-06-11 | 广东亿德兴工程建设有限公司 | Combined template construction method combining mechanized construction |
| CN113685018A (en) * | 2021-08-25 | 2021-11-23 | 重庆市渝海建设(集团)有限公司 | Column wall formwork structure and installation process |
| CN114232995A (en) * | 2021-12-31 | 2022-03-25 | 歌山建设集团有限公司 | Water stop screw assembly and construction method thereof |
-
2018
- 2018-04-28 CN CN201820629345.7U patent/CN208168368U/en not_active Expired - Fee Related
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109900432A (en) * | 2019-03-20 | 2019-06-18 | 中国建筑第八工程局有限公司 | Sealing up screw seal ring tightness detector and detection method |
| CN110195513A (en) * | 2019-06-25 | 2019-09-03 | 中铁一局集团第四工程有限公司 | Water-stopping pull rod and waterproof construction method in subway work |
| CN110195513B (en) * | 2019-06-25 | 2024-05-07 | 中铁一局集团第四工程有限公司 | Water stop pull rod in subway construction and waterproof construction method |
| CN111456433A (en) * | 2020-05-11 | 2020-07-28 | 五冶集团上海有限公司 | Drawing rod and its application method |
| CN112942808A (en) * | 2021-01-29 | 2021-06-11 | 广东亿德兴工程建设有限公司 | Combined template construction method combining mechanized construction |
| CN113685018A (en) * | 2021-08-25 | 2021-11-23 | 重庆市渝海建设(集团)有限公司 | Column wall formwork structure and installation process |
| CN113685018B (en) * | 2021-08-25 | 2024-04-30 | 山东千乘建工有限公司 | Column wall mold structure and mounting process |
| CN114232995A (en) * | 2021-12-31 | 2022-03-25 | 歌山建设集团有限公司 | Water stop screw assembly and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN208168368U (en) | A kind of construction wall construction template connector | |
| CN202125073U (en) | Turnover bottom clip bolt for combined beam column template | |
| CN207659980U (en) | A kind of detachable prefabricated assembled concrete-filled steel square tubular column foot node | |
| CN110593485A (en) | A Detachable Steel-Concrete Composite Beam with No Damage to Main Material | |
| CN112412005A (en) | An adjustable formwork system for construction of small-sized deformation joints | |
| CN211114418U (en) | A detachable steel-concrete composite beam with damage-free main material | |
| CN107237437A (en) | Combined type reinforced truss floor support plate and its construction method | |
| CN216475637U (en) | PVC wall-penetrating water-stopping bolt pipe | |
| CN106948599A (en) | A kind of split bolt and its application method | |
| CN215168004U (en) | Wall form for housing construction engineering | |
| CN207749844U (en) | It overlaps wall and overlaps the temporary support system at top plate connecting node | |
| CN201539098U (en) | Detachable and convenient support device for steel structure building formwork | |
| CN108978890B (en) | Prefabricated main beam and secondary beam composite connection node and connection method thereof | |
| CN200961355Y (en) | Wall-piercing counter-pull screw | |
| CN107503513A (en) | Wall body template split bolt constructing device and construction method | |
| CN216892870U (en) | Reinforced concrete structure composite anchoring device | |
| CN217079659U (en) | Aluminum alloy template for narrow building construction joint | |
| CN211058296U (en) | Non-dismantling inorganic composite tongue-and-groove template for building | |
| CN222759384U (en) | Concrete placement mandrel fixing device | |
| CN207122132U (en) | A kind of building template | |
| CN2863981Y (en) | Building formwork for easy assembly and dismantling | |
| CN221502687U (en) | A template subassembly for concrete segment seam is pour | |
| CN222183820U (en) | Horizontal connection node of precast concrete floor slab | |
| CN219034051U (en) | Connecting device for engineering structure template opposite pulling | |
| CN220150900U (en) | Multistage formula stagnant water bolt consolidates multiple wall body construction structures |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181130 Termination date: 20200428 |