CN208168226U - A kind of assembled stone curtain wall adapting system - Google Patents

A kind of assembled stone curtain wall adapting system Download PDF

Info

Publication number
CN208168226U
CN208168226U CN201820588063.7U CN201820588063U CN208168226U CN 208168226 U CN208168226 U CN 208168226U CN 201820588063 U CN201820588063 U CN 201820588063U CN 208168226 U CN208168226 U CN 208168226U
Authority
CN
China
Prior art keywords
galvanized steel
curtain wall
steel
stone curtain
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820588063.7U
Other languages
Chinese (zh)
Inventor
汪建勇
昝有成
陈家前
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSCEC Curtain Wall Co Ltd
Original Assignee
CSCEC Curtain Wall Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CSCEC Curtain Wall Co Ltd filed Critical CSCEC Curtain Wall Co Ltd
Priority to CN201820588063.7U priority Critical patent/CN208168226U/en
Application granted granted Critical
Publication of CN208168226U publication Critical patent/CN208168226U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

本实用新型公开了一种装配式石材幕墙转接系统,包括镀锌钢支座、镀锌钢挂座以及镀锌钢挂耳;其中镀锌钢支座通过螺栓与建筑混凝土主体结构内的槽式预埋件连接;镀锌钢挂座通过螺栓与镀锌钢支座连接;镀锌钢挂耳一端与石材幕墙板块钢架焊接固定,另一端通过螺栓与镀锌钢挂座连接。由于本实用新型的装配式石材幕墙转接系统中的所有连接点均采用长条孔配合螺栓实现铰接,因此可以在保证石材幕墙板块安装牢靠的同时,具备三维调节功能,并且可以避免施工现场焊接作业,从而有利于施工现场的安全管理。

The utility model discloses an assembled stone curtain wall transfer system, which comprises a galvanized steel support, a galvanized steel hanging seat and a galvanized steel hanging ear; wherein the galvanized steel support is connected to the groove in the main structure of the building concrete through bolts The galvanized steel hanger is connected with the galvanized steel support through bolts; one end of the galvanized steel hanger is welded and fixed with the steel frame of the stone curtain wall plate, and the other end is connected with the galvanized steel hanger through bolts. Since all the connection points in the prefabricated stone curtain wall transfer system of the utility model are hinged by using long holes and bolts, it can ensure that the stone curtain wall panels are installed firmly, and at the same time, it has a three-dimensional adjustment function, and can avoid welding on the construction site operation, which is conducive to the safety management of the construction site.

Description

一种装配式石材幕墙转接系统A prefabricated stone curtain wall transfer system

技术领域technical field

本实用新型涉及建筑幕墙技术领域,尤其涉及一种装配式石材幕墙转接系统。The utility model relates to the technical field of building curtain walls, in particular to an assembly type stone curtain wall transfer system.

背景技术Background technique

装配式石材幕墙是指石材幕墙板块在工厂预制,制作完成后被运输到安装现场安装。现有技术在安装石材幕墙板块时一般是通过机械将石材幕墙板块吊装到建筑外立面的指定位置,并通过焊接的方式将石材幕墙板块钢架和建筑混凝土主体结构中的槽式预埋件焊接在一起,以达到将石材幕墙板块固定在建筑外立面的目的。这种幕墙施工方法的特点是通过加工厂与施工现场的分工协调合作,实现了石材幕墙工业化生产,因此具有工期短,工业化生产加工精度高,现场施工方便等特点。但由于现有安装方式需要现场焊接动火作业,因此不利于现场安全管理。Prefabricated stone curtain wall means that the stone curtain wall panels are prefabricated in the factory and transported to the installation site for installation after completion. In the prior art, when installing stone curtain wall panels, the stone curtain wall panels are generally hoisted to the designated position of the building facade by machinery, and the steel frame of the stone curtain wall panels and the groove-type embedded parts in the main structure of the building concrete are welded together. Welded together to achieve the purpose of fixing the stone curtain wall panels on the facade of the building. The characteristic of this curtain wall construction method is that through the division of labor and coordination between the processing plant and the construction site, the industrial production of stone curtain walls has been realized. Therefore, it has the characteristics of short construction period, high precision of industrial production and processing, and convenient on-site construction. However, because the existing installation method requires on-site welding and hot work, it is not conducive to on-site safety management.

实用新型内容Utility model content

针对上述现有技术中存在的不足之处,本实用新型提供一种装配式石材幕墙转接系统,该转接系统中的所有连接点均采用长条孔配合螺栓的方式实现铰接,因此在保证石材幕墙板块安装牢靠的同时,可以具备三维调节功能,并且避免了施工现场焊接作业,从而更有利于施工现场的安全管理。Aiming at the deficiencies in the above-mentioned prior art, the utility model provides a prefabricated stone curtain wall transfer system. While the stone curtain wall panels are firmly installed, they can have a three-dimensional adjustment function, and avoid welding operations on the construction site, which is more conducive to the safety management of the construction site.

该装配式石材幕墙转接系统包括镀锌钢支座、镀锌钢挂座以及镀锌钢挂耳;所述镀锌钢支座为由钢板焊接而成的角钢结构,其一侧的钢板通过螺栓与建筑混凝土主体结构内的槽式预埋件连接,另一侧的钢板在所述建筑混凝土主体结构的外立面上呈水平分布;The prefabricated stone curtain wall transition system includes galvanized steel support, galvanized steel hanging seat and galvanized steel hanging lug; the galvanized steel support is an angle steel structure welded by steel plates, and the steel plate on one side passes through Bolts are connected to the groove-type embedded parts in the main building concrete structure, and the steel plates on the other side are distributed horizontally on the facade of the main building concrete structure;

所述镀锌钢挂座由一对L型钢件组成,所述L型钢件一侧的钢板通过螺栓与所述镀锌钢支座连接,另一侧的钢板在所述镀锌钢支座上呈竖向分布,且两个所述L型钢件在所述镀锌钢支座上对称分布;The galvanized steel hanger is composed of a pair of L-shaped steel pieces, the steel plate on one side of the L-shaped steel piece is connected to the galvanized steel support by bolts, and the steel plate on the other side is on the galvanized steel support It is vertically distributed, and the two L-shaped steel parts are symmetrically distributed on the galvanized steel support;

所述镀锌钢挂耳包括由挂耳底板连接在一起的两个安装板,两个所述安装板和两个所述L型钢件一一对应;所述安装板一端与石材幕墙板块钢架焊接固定,另一端通过螺栓与相应的所述L型钢件连接。The galvanized steel hanging lugs include two mounting plates connected together by the bottom plate of the hanging lugs, and the two mounting plates correspond to the two L-shaped steel parts one by one; one end of the mounting plate is connected to the steel frame of the stone curtain wall plate It is fixed by welding, and the other end is connected with the corresponding L-shaped steel piece by bolts.

进一步地,所述挂耳底板的底部设置有用于支撑所述镀锌钢挂耳的支撑螺栓。Further, support bolts for supporting the galvanized steel hanging lugs are provided on the bottom of the bottom plate of the hanging lugs.

进一步地,所述镀锌钢支座的前边沿设置有用于当所述支撑螺栓移动到所述镀锌钢支座的前边沿时,限制所述支撑螺栓继续向前移动的限位块。Further, the front edge of the galvanized steel support is provided with a limit block for restricting the support bolts from moving forward when the support bolts move to the front edge of the galvanized steel support.

进一步地,所述镀锌钢支座上开设有用于与所述槽式预埋件连接的竖向的第一长条孔,且所述镀锌钢支座上还开设有用于与所述镀锌钢挂座连接的横向的第二长条孔。Further, the galvanized steel support is provided with a vertical first elongated hole for connecting with the trough-type embedded part, and the galvanized steel support is also provided with a hole for connecting with the galvanized steel support. The second horizontal long hole connected by the zinc-steel hanging seat.

进一步地,所述镀锌钢挂座的每一L型钢件上分别沿垂直于所述建筑混凝土主体结构的方向开设有用于与所述镀锌钢支座连接的第三长条孔;Further, each L-shaped steel piece of the galvanized steel hanger is provided with a third elongated hole for connecting with the galvanized steel support along the direction perpendicular to the main structure of the building concrete;

且所述镀锌钢挂座的每一L型钢件上分别沿竖向开设有用于与所述镀锌钢挂耳连接的长条形的第一安装孔。And each L-shaped steel piece of the galvanized steel hanger is respectively provided with a long strip-shaped first installation hole for connecting with the galvanized steel hanging lug along the vertical direction.

进一步地,所述镀锌钢挂耳的两个安装板上分别开设有用于与所述镀锌钢挂座连接的圆形的第二安装孔。Further, the two mounting plates of the galvanized steel hanging lug are respectively provided with circular second mounting holes for connecting with the galvanized steel hanger.

进一步地,所述镀锌钢支座的内侧设置有多个加强板,每一所述加强板分别与所述镀锌钢支座的两个钢板固定。Further, the inner side of the galvanized steel support is provided with a plurality of reinforcement plates, and each of the reinforcement plates is respectively fixed to two steel plates of the galvanized steel support.

进一步地,所述镀锌钢支座和所述槽式预埋件之间,所述镀锌钢挂座和所述镀锌钢支座之间,以及所述镀锌钢挂耳和所述镀锌钢挂座之间连接用的每一螺栓的螺栓头的两侧分别设置有不锈钢防滑垫片。Further, between the galvanized steel support and the trough-type embedded part, between the galvanized steel hanging seat and the galvanized steel support, and between the galvanized steel hanging lug and the Both sides of the bolt head of each bolt used for connecting between the galvanized steel hangers are respectively provided with stainless steel anti-slip gaskets.

装配式石材幕墙与传统框架式石材幕墙相比可以实现幕墙板块的工业化加工,幕墙板块在工厂预加工完成后被运输到施工现场,通过机械吊装施工,能够缩短工期,减少现场工作量,有利于提高和保证幕墙构件加工质量,减少现场材料组织管理;而进一步采用本实用新型的装配式石材幕墙装接系统后,能够实现石材幕墙板块安装时的三维调节功能,保证安装精度及消化现场结构偏差,在保证幕墙板块安装牢靠的基础上避免了现场焊接动火作业,从而有利于现场施工安全管理。并且其中所设置的限位块,能够在板块调试安装过程中,防止板块意外掉落,保证现场施工安全,而每一连接点处设置的不锈钢防滑垫片则可以进一步增加连接点的牢固性。Compared with the traditional frame-type stone curtain wall, the prefabricated stone curtain wall can realize the industrialized processing of the curtain wall panels. The curtain wall panels are transported to the construction site after pre-processing in the factory. The construction period can be shortened and the on-site workload can be reduced through mechanical hoisting, which is beneficial Improve and ensure the processing quality of curtain wall components, reduce on-site material organization and management; and after further adopting the prefabricated stone curtain wall installation system of the utility model, it can realize the three-dimensional adjustment function during the installation of stone curtain wall panels, ensure installation accuracy and digest on-site structural deviations , On the basis of ensuring the reliable installation of the curtain wall panels, it avoids on-site welding and hot-fire operations, which is conducive to on-site construction safety management. And the limit block set in it can prevent the plate from accidentally falling during the commissioning and installation process of the plate and ensure the safety of on-site construction, and the stainless steel anti-skid gasket set at each connection point can further increase the firmness of the connection point.

附图说明Description of drawings

图1为本实用新型实施例提供的装配式石材幕墙转接系统的立体结构示意图;Fig. 1 is a three-dimensional structural schematic diagram of an assembled stone curtain wall transfer system provided by an embodiment of the present invention;

图2为本实用新型实施例提供的装配式石材幕墙转接系统中的镀锌钢支座的立体结构示意图;Fig. 2 is a three-dimensional structural schematic diagram of the galvanized steel support in the assembled stone curtain wall transfer system provided by the embodiment of the utility model;

图3为本实用新型实施例提供的装配式石材幕墙转接系统中的镀锌钢支座和镀锌钢挂座的安装示意图;Figure 3 is a schematic diagram of the installation of the galvanized steel support and the galvanized steel hanging seat in the assembled stone curtain wall transfer system provided by the embodiment of the present invention;

图4为本实用新型实施例提供的装配式石材幕墙转接系统中的镀锌钢挂耳的立体结构示意图;Fig. 4 is a three-dimensional structural schematic diagram of galvanized steel hanging lugs in the assembled stone curtain wall transfer system provided by the embodiment of the present invention;

图5为本实用新型实施例提供的装配式石材幕墙转接系统的俯视图;Fig. 5 is a top view of the assembled stone curtain wall transfer system provided by the embodiment of the present invention;

图6为本实用新型实施例提供的装配式石材幕墙转接系统的侧视图;Fig. 6 is a side view of the prefabricated stone curtain wall transfer system provided by the embodiment of the present invention;

图7为本实用新型实施例提供的装配式石材幕墙转接系统的平剖示意图;Fig. 7 is a schematic plan view of the assembled stone curtain wall transfer system provided by the embodiment of the present invention;

图8为本实用新型实施例提供的装配式石材幕墙转接系统的竖剖示意图。Fig. 8 is a schematic vertical sectional view of the prefabricated stone curtain wall transition system provided by the embodiment of the present invention.

附图标记说明:Explanation of reference signs:

1:镀锌钢支座,2:镀锌钢挂座,3:镀锌钢挂耳,4:不锈钢防滑垫片,5:支撑螺栓,6:建筑混凝土主体结构,7:槽式预埋件,8:石材幕墙板块钢架,9:石材面板,10:不锈钢石材背栓,11:铝合金石材挂件,12:镀锌钢板;13:保温岩棉,14:第一长条孔,15:第二长条孔,16:限位块,17:加强板,18:第一安装孔,19:第二安装孔。1: Galvanized steel support, 2: Galvanized steel hanging seat, 3: Galvanized steel hanging lug, 4: Stainless steel anti-skid gasket, 5: Support bolt, 6: Main structure of building concrete, 7: Groove embedded parts , 8: steel frame of stone curtain wall plate, 9: stone panel, 10: stainless steel stone back bolt, 11: aluminum alloy stone pendant, 12: galvanized steel plate; 13: thermal insulation rock wool, 14: first long hole, 15: Second elongated hole, 16: limit block, 17: reinforcement plate, 18: first installation hole, 19: second installation hole.

具体实施方式Detailed ways

为使本实用新型实施例的目的、技术方案和优点更加清楚,下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本实用新型的一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本实用新型保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the utility model more clear, the technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the utility model. Obviously, the described The embodiments are some embodiments of the present utility model, but not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

请参阅图1到图8,装配式石材幕墙与传统框架式石材幕墙相比可以实现幕墙板块的工业化加工,幕墙板块在工厂预加工完成后被运输到施工现场,通过机械吊装施工。具体地,加工而成的石材幕墙板块包括石材面板9,在石材面板9的背面固定有不锈钢石材背栓10,该不锈钢石材背栓10通过铝合金石材挂件11与石材幕墙板块钢架8连接:此外,该石材幕墙板块钢架8背面设置有保温岩棉13,该保温岩棉13外包覆有镀锌钢板12,如图7、图8所示。Please refer to Figures 1 to 8. Compared with the traditional framed stone curtain wall, the prefabricated stone curtain wall can realize the industrialized processing of the curtain wall panels. The curtain wall panels are transported to the construction site after pre-processing in the factory, and the construction is carried out by mechanical hoisting. Specifically, the processed stone curtain wall plate includes a stone panel 9, and a stainless steel stone back bolt 10 is fixed on the back of the stone panel 9, and the stainless steel stone back bolt 10 is connected to the steel frame 8 of the stone curtain wall plate through an aluminum alloy stone pendant 11: In addition, thermal insulation rock wool 13 is arranged on the back of the steel frame 8 of the stone curtain wall plate, and the thermal insulation rock wool 13 is covered with a galvanized steel plate 12, as shown in Fig. 7 and Fig. 8 .

本实施例中的装配式石材幕墙转接系统即是用于上述石材幕墙板块的安装,其包括镀锌钢支座1、镀锌钢挂座2以及镀锌钢挂耳3;其中镀锌钢支座1通过螺栓与建筑混凝土主体结构6内的槽式预埋件7连接,镀锌钢挂座2通过螺栓与镀锌钢支座1连接,镀锌钢挂耳3一端与石材幕墙板块钢架8焊接固定,另一端通过螺栓与镀锌钢挂座2连接,从而将石材幕墙板块安装到建筑混凝土主体结构6的外立面上,如图1所示。The prefabricated stone curtain wall transfer system in this embodiment is used for the installation of the above-mentioned stone curtain wall panels, which includes galvanized steel support 1, galvanized steel hanger 2 and galvanized steel hanging ear 3; The support 1 is connected with the trough-type embedded part 7 in the building concrete main structure 6 through bolts, the galvanized steel hanging seat 2 is connected with the galvanized steel support 1 through bolts, and one end of the galvanized steel hanging ear 3 is connected with the stone curtain wall plate steel The frame 8 is welded and fixed, and the other end is connected with the galvanized steel hanging seat 2 by bolts, so that the stone curtain wall plate is installed on the facade of the building concrete main structure 6, as shown in FIG. 1 .

具体地,上述镀锌钢支座1为由16mm厚的镀锌钢板焊接而成的角钢结构,其一侧的钢板上开设有多个竖向的第一长条孔14,另一侧的钢板上开设有多个横向的第二长条孔15,且该镀锌钢支座1的内侧设置有多个加强板17,每一加强板17分别与镀锌钢支座1的两个钢板固定,如图2所示。Specifically, the above-mentioned galvanized steel support 1 is an angle steel structure welded by 16mm thick galvanized steel plates, and a plurality of vertical first elongated holes 14 are opened on the steel plate on one side, and the steel plate on the other side There are a plurality of horizontal second elongated holes 15 on the top, and a plurality of reinforcement plates 17 are arranged on the inner side of the galvanized steel support 1, and each reinforcement plate 17 is respectively fixed to two steel plates of the galvanized steel support 1. ,as shown in picture 2.

通过在第一长条孔14内穿设T型螺栓可以将镀锌钢支座1一侧的钢板固定在建筑混凝土主体结构6内的槽式预埋件7上;完成镀锌钢支座1的固定后,镀锌钢支座1另一侧的钢板在建筑混凝土主体结构6的外立面上呈水平分布。且通过槽式预埋件7的槽口长度及镀锌钢支座1的第一长条孔14可以实现镀锌钢支座1在左右及上下方向上两个维度内±30mm范围内的调节功能。The steel plate on one side of the galvanized steel support 1 can be fixed on the groove type embedded part 7 in the building concrete main structure 6 by passing T-shaped bolts in the first elongated hole 14; the galvanized steel support 1 is completed. After being fixed, the steel plates on the other side of the galvanized steel support 1 are horizontally distributed on the facade of the building concrete main structure 6 . Moreover, the adjustment of the galvanized steel support 1 within the range of ±30mm in two dimensions in the left and right and up and down directions can be realized through the notch length of the groove-type embedded part 7 and the first elongated hole 14 of the galvanized steel support 1 Function.

上述镀锌钢挂座2经过定位放线,定准位置后安装在镀锌钢支座1上,具体地,该镀锌钢挂座2由一对L型钢件组成,该L型钢件由16mm厚的钢板弯折而成,其一侧的钢板上沿垂直于建筑混凝土主体结构6的方向开设有第三长条孔,安装时通过现场定位放线,核准位置后将镀锌钢挂座2上的第三长条孔和镀锌钢支座1上的第二长条孔15对应,并在第三长条孔和第二长条孔15内穿设M16螺栓就可以将L型钢件固定在镀锌钢支座1上。The above-mentioned galvanized steel hanger 2 is installed on the galvanized steel support 1 after being positioned and laid out, and the position is fixed. Specifically, the galvanized steel hanger 2 is composed of a pair of L-shaped steel parts, and the L-shaped steel parts are 16mm thick. The steel plate on one side is formed by bending a steel plate, and a third elongated hole is provided on the steel plate on one side along the direction perpendicular to the building concrete main structure 6. During installation, the on-site positioning is used to lay out the wires. After the position is approved, the galvanized steel hanging seat 2 is placed on the The third elongated hole corresponds to the second elongated hole 15 on the galvanized steel support 1, and M16 bolts are passed through the third elongated hole and the second elongated hole 15 to fix the L-shaped steel piece on the On the galvanized steel support 1.

固定完成后两个L型钢件在镀锌钢支座1上对称分布,每一L型钢件另一侧的钢板在镀锌钢支座1上呈竖向分布且沿竖向开设有用于与镀锌钢挂耳3连接的长条形的第一安装孔18,如图3所示。且通过镀锌钢挂座2上所设置的第三长条孔可以实现镀锌钢挂座2中每一L型钢件在前后方向上±25mm范围内的调节功能。After the fixation is completed, the two L-shaped steel pieces are symmetrically distributed on the galvanized steel support 1, and the steel plate on the other side of each L-shaped steel piece is vertically distributed on the galvanized steel support 1, and there are holes along the vertical for contact with the galvanized steel support 1. The strip-shaped first installation hole 18 connected with the zinc-steel hanging lug 3 is shown in FIG. 3 . And through the third elongated hole provided on the galvanized steel hanger 2, the adjustment function of each L-shaped steel piece in the galvanized steel hanger 2 within the range of ±25mm in the front-rear direction can be realized.

上述镀锌钢挂耳3采用16mm厚的镀锌钢板制成,其包括由挂耳底板连接在一起的两个安装板,两个安装板和上述镀锌钢挂座2中的两个L型钢件一一对应;每一安装板上分别开设有用于与镀锌钢挂座2连接的圆形的第二安装孔19,如图4所示。该安装板一端与石材幕墙板块钢架8焊接固定,另一端的第二安装孔19和镀锌钢挂座2上的第一安装孔18对应,并通过在第二安装孔19和第一安装孔18穿设螺栓将两个安装板和两个L型钢件一一对应连接,通过镀锌钢挂座2上设置的长条形的第一安装孔18,可以实现镀锌钢挂耳3在上下方向上的调节功能。The above-mentioned galvanized steel hanging lug 3 is made of 16mm thick galvanized steel plate, which includes two mounting plates connected together by the bottom plate of the hanging lug, the two mounting plates and the two L-shaped steel plates in the above-mentioned galvanized steel hanging seat 2 There is a one-to-one correspondence between the parts; each mounting plate is respectively provided with a circular second mounting hole 19 for connecting with the galvanized steel hanger 2, as shown in FIG. 4 . One end of the mounting plate is welded and fixed to the steel frame 8 of the stone curtain wall plate, and the second mounting hole 19 at the other end corresponds to the first mounting hole 18 on the galvanized steel hanger 2, and is installed through the second mounting hole 19 and the first mounting hole 18. The holes 18 are pierced with bolts to connect the two mounting plates and the two L-shaped steel parts one by one. Adjustment function in up and down direction.

此外,镀锌钢挂耳3的挂耳底板的底部设置有用于支撑镀锌钢挂耳3的支撑螺栓5。镀锌钢支座1的前边沿设置有用于当支撑螺栓5移动到镀锌钢支座1的前边沿时,限制支撑螺栓5继续向前移动的限位块16,如图5和图6所示。设置该限位块16主要是考虑到当石材幕墙板块尚未固定而是处于安装调试阶段时,石材幕墙板块可能会由于重力的原因而下滑,从而带动与其连接的镀锌钢挂耳3在镀锌钢支座1上滑动,此时,镀锌钢挂耳3底部的支撑螺栓5会同步移动,当支撑螺栓5移动到镀锌钢支座1的前边沿时,会被此处的限位块16挡住而无法继续向前移动,从而有效防止石材幕墙板块滑落,进而有效提高了施工现场的安全性。In addition, a support bolt 5 for supporting the galvanized steel mounting ear 3 is provided at the bottom of the mounting ear bottom plate of the galvanized steel mounting ear 3 . The front edge of the galvanized steel support 1 is provided with a limit block 16 for limiting the support bolt 5 to continue to move forward when the support bolt 5 moves to the front edge of the galvanized steel support 1, as shown in Figures 5 and 6 Show. Setting the limit block 16 is mainly to consider that when the stone curtain wall plate is not fixed but is in the installation and debugging stage, the stone curtain wall plate may slide due to gravity, thereby driving the galvanized steel hanging lug 3 connected to it to be galvanized. Slide on the steel support 1. At this time, the support bolts 5 at the bottom of the galvanized steel lug 3 will move synchronously. When the support bolts 5 move to the front edge of the galvanized steel support 1, they will be blocked by the limit block here 16 blocks and cannot continue to move forward, thereby effectively preventing the stone curtain wall plate from slipping, thereby effectively improving the safety of the construction site.

进一步地,在本实施例中镀锌钢支座1和槽式预埋件7之间,镀锌钢挂座2和镀锌钢支座1之间,以及镀锌钢挂耳3和镀锌钢挂座2之间连接用的每一螺栓的螺栓头的两侧分别设置有不锈钢防滑垫片4,从而使得各部件之间的连接更加紧固,提高了整个系统的稳固性。Further, in this embodiment, between the galvanized steel support 1 and the groove embedded part 7, between the galvanized steel hanging seat 2 and the galvanized steel support 1, and between the galvanized steel hanging lug 3 and the galvanized Both sides of the bolt head of each bolt used for connection between the steel hangers 2 are respectively provided with stainless steel anti-slip gaskets 4, thereby making the connection between the various parts more tightened and improving the stability of the entire system.

使用本实施例中的装配式石材幕墙转接系统安装石材幕墙时,首先需要将镀锌钢支座1定位安装在建筑混凝土主体结构6中的槽式预埋件上7上,完成镀锌钢支座1的安装;然后将镀锌钢挂座2采用螺栓固定在镀锌钢支座1上,固定时需要定位放线,根据石材幕墙板块分格,确定好每个镀锌钢挂座2的位置,并采用螺栓铰接,同时在螺栓头两侧设置不锈钢防滑垫片4,保证镀锌钢挂座4安装的牢靠性;然后在工厂完成镀锌钢挂耳3和石材幕墙板块钢架8的焊接,将镀锌钢挂耳3焊接在石材幕墙板块上;最后进行石材幕墙板块的吊装,通过定位调节将已焊接到石材幕墙板块上的镀锌钢挂耳3与镀锌钢挂座3采用M16螺栓铰接,并在螺栓头两侧设置不锈钢防滑垫片;最终实现石材幕墙板块在建筑混凝土主体结构6上的安装固定。When using the prefabricated stone curtain wall transfer system in this embodiment to install a stone curtain wall, it is first necessary to position and install the galvanized steel support 1 on the groove-type embedded part 7 in the building concrete main structure 6 to complete the galvanized steel support 1. The installation of the support 1; then fix the galvanized steel hanger 2 on the galvanized steel support 1 with bolts. When fixing, it needs to be positioned and set out. According to the division of the stone curtain wall, each galvanized steel hanger 2 is determined. position, and hinged with bolts, and at the same time, set stainless steel anti-slip gaskets 4 on both sides of the bolt head to ensure the reliability of the installation of galvanized steel hanger 4; Welding, welding the galvanized steel hanging lug 3 on the stone curtain wall plate; finally carry out the hoisting of the stone curtain wall plate, and adjust the galvanized steel hanging lug 3 and the galvanized steel hanging seat 3 which have been welded to the stone curtain wall plate through positioning adjustment M16 bolts are used to hinge, and stainless steel anti-slip gaskets are set on both sides of the bolt head; finally, the stone curtain wall plate is installed and fixed on the main concrete structure 6 of the building.

装配式石材幕墙与传统框架式石材幕墙相比可以实现幕墙板块的工业化加工,幕墙板块在工厂预加工完成后被运输到施工现场,通过机械吊装施工,能够缩短工期,减少现场工作量,有利于提高和保证幕墙构件加工质量,减少现场材料组织管理;而进一步采用本实用新型的装配式石材幕墙装接系统后,能够实现石材幕墙板块安装时的三维调节功能,保证安装精度及消化现场结构偏差,在保证幕墙板块安装牢靠的基础上避免了现场焊接动火作业,从而有利于现场施工安全管理。并且其中所设置的限位块,能够在板块调试安装过程中,防止板块意外掉落,保证现场施工安全,而每一连接点处设置的不锈钢防滑垫片则可以进一步增加连接点的牢固性。Compared with the traditional frame-type stone curtain wall, the prefabricated stone curtain wall can realize the industrialized processing of the curtain wall panels. The curtain wall panels are transported to the construction site after pre-processing in the factory. The construction period can be shortened and the on-site workload can be reduced through mechanical hoisting, which is beneficial Improve and ensure the processing quality of curtain wall components, reduce on-site material organization and management; and after further adopting the prefabricated stone curtain wall installation system of the utility model, it can realize the three-dimensional adjustment function during the installation of stone curtain wall panels, ensure installation accuracy and digest on-site structural deviations , On the basis of ensuring the reliable installation of the curtain wall panels, it avoids on-site welding and hot-fire operations, which is conducive to on-site construction safety management. And the limit block set in it can prevent the plate from accidentally falling during the commissioning and installation process of the plate and ensure the safety of on-site construction, and the stainless steel anti-skid gasket set at each connection point can further increase the firmness of the connection point.

需要说明的是,在本文中,“第一”、“第二”的出现,仅仅是为了作区分技术名词和描述方便,不应理解为对本实用新型实施例的限定。术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者终端设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者终端设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者终端设备中还存在另外的相同要素。It should be noted that, in this article, the appearance of "first" and "second" is only for distinguishing technical terms and for convenience of description, and should not be construed as limiting the embodiment of the present utility model. The term "comprises", "comprises" or any other variation thereof is intended to cover a non-exclusive inclusion such that a process, method, article or end-equipment comprising a set of elements includes not only those elements but also items not expressly listed other elements, or also include elements inherent in such a process, method, article, or end-equipment. Without further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article or terminal device comprising said element.

以上仅为本实用新型的优选实施例而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above are only preferred embodiments of the utility model, and are not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present utility model shall be included in the protection scope of the present utility model.

Claims (8)

1.一种装配式石材幕墙转接系统,其特征在于,包括镀锌钢支座、镀锌钢挂座以及镀锌钢挂耳;1. A prefabricated stone curtain wall transfer system, characterized in that it includes a galvanized steel support, a galvanized steel hanger and a galvanized steel hanger; 所述镀锌钢支座为由钢板焊接而成的角钢结构,其一侧的钢板通过螺栓与建筑混凝土主体结构内的槽式预埋件连接,另一侧的钢板在所述建筑混凝土主体结构的外立面上呈水平分布;The galvanized steel support is an angle steel structure welded by steel plates. The steel plate on one side is connected to the groove-type embedded parts in the main structure of the building concrete through bolts, and the steel plate on the other side is connected to the main structure of the building concrete. It is distributed horizontally on the facade; 所述镀锌钢挂座由一对L型钢件组成,所述L型钢件一侧的钢板通过螺栓与所述镀锌钢支座连接,另一侧的钢板在所述镀锌钢支座上呈竖向分布,且两个所述L型钢件在所述镀锌钢支座上对称分布;The galvanized steel hanger is composed of a pair of L-shaped steel pieces, the steel plate on one side of the L-shaped steel piece is connected to the galvanized steel support by bolts, and the steel plate on the other side is on the galvanized steel support It is vertically distributed, and the two L-shaped steel parts are symmetrically distributed on the galvanized steel support; 所述镀锌钢挂耳包括由挂耳底板连接在一起的两个安装板,两个所述安装板和两个所述L型钢件一一对应;所述安装板一端与石材幕墙板块钢架焊接固定,另一端通过螺栓与相应的所述L型钢件连接。The galvanized steel hanging lugs include two mounting plates connected together by the bottom plate of the hanging lugs, and the two mounting plates correspond to the two L-shaped steel parts one by one; one end of the mounting plate is connected to the steel frame of the stone curtain wall plate It is fixed by welding, and the other end is connected with the corresponding L-shaped steel piece by bolts. 2.如权利要求1所述的装配式石材幕墙转接系统,其特征在于,所述挂耳底板的底部设置有用于支撑所述镀锌钢挂耳的支撑螺栓。2. The prefabricated stone curtain wall transition system according to claim 1, characterized in that, the bottom of the bottom plate of the hanging lug is provided with supporting bolts for supporting the galvanized steel hanging lug. 3.如权利要求2所述的装配式石材幕墙转接系统,其特征在于,所述镀锌钢支座的前边沿设置有用于当所述支撑螺栓移动到所述镀锌钢支座的前边沿时,限制所述支撑螺栓继续向前移动的限位块。3. The prefabricated stone curtain wall transfer system according to claim 2, characterized in that, the front edge of the galvanized steel support is provided with a When edge, limit the limit block that described support bolt continues to move forward. 4.如权利要求1所述的装配式石材幕墙转接系统,其特征在于,所述镀锌钢支座上开设有用于与所述槽式预埋件连接的竖向的第一长条孔,且所述镀锌钢支座上还开设有用于与所述镀锌钢挂座连接的横向的第二长条孔。4. The prefabricated stone curtain wall transfer system according to claim 1, characterized in that, the galvanized steel support is provided with a vertical first elongated hole for connecting with the groove-type embedded part , and the galvanized steel support is also provided with a second horizontal elongated hole for connecting with the galvanized steel hanger. 5.如权利要求4所述的装配式石材幕墙转接系统,其特征在于,所述镀锌钢挂座的每一L型钢件上分别沿垂直于所述建筑混凝土主体结构的方向开设有用于与所述镀锌钢支座连接的第三长条孔;5. The prefabricated stone curtain wall transfer system as claimed in claim 4, characterized in that, each L-shaped steel part of the galvanized steel hanger is respectively provided with a set of holes along the direction perpendicular to the main structure of the building concrete. a third elongated hole connected to the galvanized steel support; 且所述镀锌钢挂座的每一L型钢件上分别沿竖向开设有用于与所述镀锌钢挂耳连接的长条形的第一安装孔。And each L-shaped steel piece of the galvanized steel hanger is respectively provided with a long strip-shaped first installation hole for connecting with the galvanized steel hanging lug along the vertical direction. 6.如权利要求5所述的装配式石材幕墙转接系统,其特征在于,所述镀锌钢挂耳的两个安装板上分别开设有用于与所述镀锌钢挂座连接的圆形的第二安装孔。6. The prefabricated stone curtain wall transfer system according to claim 5, characterized in that, the two mounting plates of the galvanized steel hanging lugs are respectively provided with circular holes for connecting with the galvanized steel hanging brackets. the second mounting hole. 7.如权利要求1所述的装配式石材幕墙转接系统,其特征在于,所述镀锌钢支座的内侧设置有多个加强板,每一所述加强板分别与所述镀锌钢支座的两个钢板固定。7. The prefabricated stone curtain wall transfer system according to claim 1, wherein a plurality of reinforcing plates are arranged on the inner side of the galvanized steel support, and each of the reinforcing plates is connected to the galvanized steel support respectively. The two steel plates of the support are fixed. 8.如权利要求1所述的装配式石材幕墙转接系统,其特征在于,所述镀锌钢支座和所述槽式预埋件之间,所述镀锌钢挂座和所述镀锌钢支座之间,以及所述镀锌钢挂耳和所述镀锌钢挂座之间连接用的每一螺栓的螺栓头的两侧分别设置有不锈钢防滑垫片。8. The prefabricated stone curtain wall transfer system according to claim 1, characterized in that, between the galvanized steel support and the trough embedded part, the galvanized steel hanger and the galvanized Stainless steel anti-slip gaskets are respectively provided on both sides of the bolt head between the galvanized steel supports and between the galvanized steel hanger and the galvanized steel hanger.
CN201820588063.7U 2018-04-24 2018-04-24 A kind of assembled stone curtain wall adapting system Active CN208168226U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820588063.7U CN208168226U (en) 2018-04-24 2018-04-24 A kind of assembled stone curtain wall adapting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820588063.7U CN208168226U (en) 2018-04-24 2018-04-24 A kind of assembled stone curtain wall adapting system

Publications (1)

Publication Number Publication Date
CN208168226U true CN208168226U (en) 2018-11-30

Family

ID=64370334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820588063.7U Active CN208168226U (en) 2018-04-24 2018-04-24 A kind of assembled stone curtain wall adapting system

Country Status (1)

Country Link
CN (1) CN208168226U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112127529A (en) * 2020-09-29 2020-12-25 明威科技集团股份有限公司 Semi-unit prefabricated stone curtain wall structure
CN121575870A (en) * 2026-01-20 2026-02-27 中建八局第一建设有限公司 A prefabricated integrated plate upper and lower support connection structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112127529A (en) * 2020-09-29 2020-12-25 明威科技集团股份有限公司 Semi-unit prefabricated stone curtain wall structure
CN121575870A (en) * 2026-01-20 2026-02-27 中建八局第一建设有限公司 A prefabricated integrated plate upper and lower support connection structure

Similar Documents

Publication Publication Date Title
CN108049552B (en) Top-mounted drop-grade ceiling and installation method
CN107503458B (en) Curtain wall hanging piece mounting structure
CN108894372B (en) Modeling plate curtain wall assembly structure
CN208072857U (en) A kind of building wall body insulating board dedicated hanging part structure
CN209204520U (en) A kind of hook-hang type smoke-proof pendant wall mounting structure
CN115182537A (en) Installation structure and construction method of a metal composite wall panel
CN110195477A (en) A kind of modularization wall Multifunctional corner chaining part
CN205077670U (en) Outer containment system of unit assembly type structure
CN109668240A (en) A kind of installation method of smoke control system
CN211114285U (en) Curtain wall unit switching structure and curtain wall unit
CN210947372U (en) Ceiling system adopting H-shaped keel
CN108385895A (en) A kind of fast-assembling walling system
CN209837440U (en) Connecting component for special-shaped GRG suspended ceiling
CN111962791A (en) Wall surface hanging type external corner system
CN210976243U (en) External stone material curtain wall construction of cross keel
RU177131U1 (en) FINAL CLAMMER FOR FASTENING FACADE FACING ELEMENTS
CN110821013A (en) A prefabricated design metal curtain wall structure
CN205077678U (en) Outer containment system's of building panel unit
CN217128708U (en) Lifting point dislocation adjustment structure of keel
CN211499342U (en) A prefabricated design metal curtain wall structure
CN109594731B (en) Unit type face brick system
CN211817324U (en) Indoor corrugated suspended ceiling external corner installation node structure
CN202706224U (en) Connecting structure for single-storey pre-fabricated house
CN108086568B (en) Suspended ceiling hanging assembly and hanging method
CN210421559U (en) Combined mounting structure of curtain wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20250819

Granted publication date: 20181130