CN208120600U - A kind of quick provision for disengagement of large size inside-climbing tower crane - Google Patents
A kind of quick provision for disengagement of large size inside-climbing tower crane Download PDFInfo
- Publication number
- CN208120600U CN208120600U CN201820572254.4U CN201820572254U CN208120600U CN 208120600 U CN208120600 U CN 208120600U CN 201820572254 U CN201820572254 U CN 201820572254U CN 208120600 U CN208120600 U CN 208120600U
- Authority
- CN
- China
- Prior art keywords
- tower crane
- disengagement
- provision
- climbing tower
- elevator boom
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 239000000725 suspension Substances 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 description 16
- 238000010586 diagram Methods 0.000 description 12
- 238000000034 method Methods 0.000 description 5
- 230000009194 climbing Effects 0.000 description 4
- 240000007594 Oryza sativa Species 0.000 description 1
- 235000007164 Oryza sativa Nutrition 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 235000009566 rice Nutrition 0.000 description 1
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model proposes a kind of quick provisions for disengagement of large-scale inside-climbing tower crane, including:Elevator boom rack;A frame is connected to the elevator boom rack;Luffing power mechanism is connected to the elevator boom rack endpoint by hoist rope, and the hoist rope is connected to the luffing power mechanism after supporting by A frame;Stock is connected to the elevator boom rack and A frame, and integral demounting device is installed on inside-climbing tower crane.The utility model proposes large-scale inside-climbing tower crane quick provision for disengagement, can by once mounting, complete large-scale tower crane remove, and after having removed large-scale tower crane, it can voluntarily disintegrate, be transported to ground by artificial etc., this removes the cost and risk of large-scale tower crane by substantially reducing.
Description
Technical field
The utility model belongs to construction machine equipment technical field, relates generally to a kind of the quick of large-scale inside-climbing tower crane
Provision for disengagement.
Background technique
It is big that super high-rise building high-altitude tower crane removes difficulty:Tower crane removes narrow space, and removes disintegration and vertical transport all
In high aerial progress operation, is influenced by external decoration, need remote hoisting transportation.It is hidden that super high-rise building high-altitude tower crane removes safety
Suffer from more:In Super High construction, tower crane crane arm is suspended in the high-altitude of hundred meters or even several hundred meters, and setting safety devices are more difficult, herein
The disassembly that crane arm is carried out under the conditions of kind, has certain risk.It is big that super high-rise building high-altitude tower crane removes cost:Such as
It under the premise of where guaranteeing safety, reduces tower crane and removes cost, be the emphasis for formulating tower crane Demolition Construction scheme.
Super high-rise building generallys use inner climbing crane tower and carries out steel construction skyscraper lifting construction.Climbing tower lifting
Machine takes full advantage of the height of building itself, and covering construction area efficiency is high, and high-building construction use is safer, no
Construction site is occupied, is suitable for the engineering of narrow space, without multiple tracks attachment device and a large amount of tower-body standard section in use
Investment, there is the significant overall economic efficiency of comparison, and especially for the construction of special high-rise, what is do not replaced almost is risen
Heavy-duty machine.
For climbing tower crane after the completion of construction, in high-rise, super high rise building top, disassembly is difficult,
Crane arm especially therein, due to lifting the needs of function, quite a few of crane arm has exceeded the top horizontal of building
Face, is suspended in tens of rice, more than hundred meters, even several hundred meters of high-altitude, even if the part within building vertical plane, because building function
It can be made with reasons, super high rise structure complexity such as shape Art Designs to the high-altitude dismantling of climbing tower crane, transhipment operation
It is a technology complexity, the work that difficulty of construction is big at certain difficulty.
At present in construction, the disassembly of large-scale inside-climbing tower crane needs to be less than by an energy level medium-sized tower of one shelves
It hangs, the dismounting of the medium-sized tower crane needs the small-sized tower crane by a smaller energy level again, and the dismounting of the small-sized tower crane must be by can oneself
The tower crane torn open is completed, and dismounting process efficiency very cumbersome in this way is larger compared with low-risk, and expense cost is also relatively high.
Utility model content
The utility model proposes a kind of quick provisions for disengagement of large-scale inside-climbing tower crane, can be completed by once mounting
Large-scale tower crane is removed, and after having removed large-scale tower crane, can voluntarily be disintegrated, and is transported to ground by artificial etc., this will significantly
Reduce the cost and risk for removing large-scale tower crane.
In order to achieve the above object, the utility model proposes a kind of quick provisions for disengagement of large-scale inside-climbing tower crane, including:
Elevator boom rack;
A frame is connected to the elevator boom rack;
Luffing power mechanism is connected to the elevator boom rack endpoint by hoist rope, and the hoist rope passes through A
The luffing power mechanism is connected to after frame support;
Stock is connected to the elevator boom rack and A frame, and integral demounting device is installed on inside-climbing tower crane.
Further, the stock is connected to the lifting power machine structure on inside-climbing tower crane top by wirerope, passes through steel wire
Rope band is dynamic, and provision for disengagement is made to be increased to certain height.
Further, the provision for disengagement installs in inside-climbing tower crane large arm and is fixed temporarily wirerope, for large arm of disintegrating
When, keep the stable structure of its remainder.
Further, the luffing power mechanism pulls hoist rope, realizes the angle change of elevator boom rack, can
Get at the angle that disassembly large arm can be lifted up to one.
Further, the provision for disengagement, which is decomposed and is segmented, removes large arm and tower body.
Further, the endpoint of the elevator boom rack is provided with suspension hook.
The utility model proposes large-scale inside-climbing tower crane quick provision for disengagement, after the provision for disengagement, large size in climb
The dismounting of tower crane does not need to tear heavy-duty hoisting equipment open certainly by medium-sized tower crane, small-sized tower crane and other smaller ranks, substantially reduces
Equipment application risk and expense, save the duration.
Detailed description of the invention
Fig. 1 show the quick provision for disengagement structural schematic diagram of the large-scale inside-climbing tower crane of the utility model preferred embodiment.
Fig. 2 show the structural schematic diagram of elevator boom rack and A frame.
Fig. 3~Figure 11 show the quick provision for disengagement construction stream of the large-scale inside-climbing tower crane of the utility model preferred embodiment
Journey schematic diagram.
Specific embodiment
Specific embodiment of the present utility model, but the utility model implementation not limited to the following are provided below in conjunction with attached drawing
Mode.According to following explanation and claims, will be become apparent from feature the advantages of the utility model.It should be noted that attached drawing
It is all made of very simplified form and uses non-accurate ratio, be only used for convenience, lucidly aid in illustrating the utility model
The purpose of embodiment.
Fig. 1 and Fig. 2 are please referred to, Fig. 1 show the quick disassembly of the large-scale inside-climbing tower crane of the utility model preferred embodiment
Apparatus structure schematic diagram, Fig. 2 show the structural schematic diagram of elevator boom rack and A frame.The utility model proposes climb in a kind of large size
The quick provision for disengagement of tower crane, including:Elevator boom rack 100;A frame 200 is connected to the elevator boom rack 100;Luffing power mechanism
300, the endpoint of the elevator boom rack 100 is connected to by hoist rope 400, the hoist rope 400 passes through A frame 200
The luffing power mechanism 300 is connected to after support;Stock 500 is connected to the elevator boom rack 100 and A frame 200, and will be whole
Body provision for disengagement is installed on inside-climbing tower crane.
Fig. 3~Figure 11 is please referred to again, and Fig. 3~Figure 11 show the large-scale inside-climbing tower crane of the utility model preferred embodiment
Quick provision for disengagement construction process schematic diagram.
In common buildings construction, inside-climbing tower crane rises to the maximum height set in arrangement and method for construction, completes all correlations
After lifting operation, it will be removed.In the utility model preferred embodiment, inside-climbing tower crane completes all lifting operations
Afterwards, this dismounting device is lifted to building roof face, and be mounted on itself tower body.Referring to FIG. 3, Fig. 3 is shown
Schematic diagram in place is installed in provision for disengagement.
According to the utility model preferred embodiment, the stock 500 is connected on inside-climbing tower crane top by wirerope 600
Lifting power machine structure is driven by wirerope 600, provision for disengagement is made to be increased to certain height, this can highly be such that crane arm has
Enough abilities go disassembly inside-climbing tower crane large arm.Referring to FIG. 4, Fig. 4 show the signal that provision for disengagement is promoted to working depth
Figure.
The provision for disengagement installs in inside-climbing tower crane large arm and is fixed temporarily wirerope, for disintegrate large arm when, keep it
The stable structure of remainder.Further, the luffing power mechanism pulls hoist rope, realizes the angle of elevator boom rack
Variation can reach the angle that can lift disassembly large arm.Referring to FIG. 5, Fig. 5 show the signal for removing large arm
Figure.
The provision for disengagement decomposes and is segmented dismounting large arm;Tower cap and swing mechanism are removed later;Referring to FIG. 6, Fig. 6 institute
It is shown as removing the schematic diagram of final section large arm, swing mechanism etc..
Then the hoist engine or other small lifting equipments installed by roof will remove equipment and drop next tower body standard
The height of section is prepared to remove tower body, removes a section tower-body standard section topmost;Previous step is repeated, tower body standard is completed
The dismounting work of section;Fig. 7~Figure 10 is please referred to, Fig. 7 show inside-climbing tower crane top structure and removes the schematic diagram finished, Fig. 8 institute
It is shown as the schematic diagram that a section standard knot height drops in provision for disengagement, Fig. 9 show the schematic diagram for removing a section standard knot, shown in Figure 10
The schematic diagram of one section standard knot height drops for provision for disengagement.
After having removed building roof face final section tower body, which completes work;By manually disintegrating this section by section
Provision for disengagement is transported to ground by shipping or construction elevator.Figure 11 is please referred to, Figure 11 show tower body and dismantles the signal finished
Figure.Provision for disengagement of the invention can be dismantled by mechanical device or mutual disassembly's method later, completes whole dismantlement works.
Further, the endpoint of the elevator boom rack is provided with suspension hook.
In conclusion the utility model proposes large-scale inside-climbing tower crane quick provision for disengagement, after the provision for disengagement,
The dismounting of large-scale inside-climbing tower crane does not need to tear heavy-duty hoisting equipment open certainly by medium-sized tower crane, small-sized tower crane and other smaller ranks,
Equipment application risk and expense are greatly reduced, the duration is saved.
Although the utility model has been disclosed with preferred embodiment as above, so it is not intended to limit the utility model.This reality
It is without departing from the spirit and scope of the utility model, each when that can make with novel those of ordinary skill in the art
Kind changes and retouches.Therefore, the protection scope of the utility model is subject to view those as defined in claim.
Claims (6)
1. a kind of quick provision for disengagement of large size inside-climbing tower crane, which is characterized in that including:
Elevator boom rack;
A frame is connected to the elevator boom rack;
Luffing power mechanism is connected to the elevator boom rack endpoint by hoist rope, and the hoist rope passes through A frame branch
The luffing power mechanism is connected to after support;
Stock is connected to the elevator boom rack and A frame, and integral demounting device is installed on inside-climbing tower crane.
2. the quick provision for disengagement of large size inside-climbing tower crane according to claim 1, which is characterized in that the stock passes through steel
Cord is connected to the lifting power machine structure on inside-climbing tower crane top, is driven by wirerope, provision for disengagement is made to be increased to certain height.
3. the quick provision for disengagement of large size inside-climbing tower crane according to claim 1, which is characterized in that the provision for disengagement exists
In inside-climbing tower crane large arm installation be fixed temporarily wirerope, for disintegrate large arm when, keep the stable structure of its remainder.
4. the quick provision for disengagement of large size inside-climbing tower crane according to claim 1, which is characterized in that the luffing engine
Structure pulls hoist rope, realizes the angle change of elevator boom rack, can reach the angle that can lift disassembly large arm
Degree.
5. the quick provision for disengagement of large size inside-climbing tower crane according to claim 1, which is characterized in that the provision for disengagement point
It solves and is segmented and remove large arm and tower body.
6. the quick provision for disengagement of large size inside-climbing tower crane according to claim 1, which is characterized in that the elevator boom rack
Endpoint is provided with suspension hook.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820572254.4U CN208120600U (en) | 2018-04-20 | 2018-04-20 | A kind of quick provision for disengagement of large size inside-climbing tower crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820572254.4U CN208120600U (en) | 2018-04-20 | 2018-04-20 | A kind of quick provision for disengagement of large size inside-climbing tower crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208120600U true CN208120600U (en) | 2018-11-20 |
Family
ID=64190994
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820572254.4U Active CN208120600U (en) | 2018-04-20 | 2018-04-20 | A kind of quick provision for disengagement of large size inside-climbing tower crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208120600U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108439228A (en) * | 2018-04-20 | 2018-08-24 | 上海市机械施工集团有限公司 | A kind of provision for disengagement of inside-climbing tower crane |
CN111422759A (en) * | 2020-04-17 | 2020-07-17 | 中国化学工程第三建设有限公司 | Method for dismantling tower crane in narrow space |
-
2018
- 2018-04-20 CN CN201820572254.4U patent/CN208120600U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108439228A (en) * | 2018-04-20 | 2018-08-24 | 上海市机械施工集团有限公司 | A kind of provision for disengagement of inside-climbing tower crane |
CN111422759A (en) * | 2020-04-17 | 2020-07-17 | 中国化学工程第三建设有限公司 | Method for dismantling tower crane in narrow space |
CN111422759B (en) * | 2020-04-17 | 2021-11-09 | 中国化学工程第三建设有限公司 | Method for dismantling tower crane in narrow space |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106115500B (en) | A kind of high-rise building is special, and tearing formula roofing open hangs and tears open certainly method certainly | |
CN206233576U (en) | For the hydraulic pressure lift turnover formwork construction device of bundled-tube structure chimney | |
CN101734560B (en) | High-altitude dismantling method of inside-climbing tower crane for towering structure construction | |
CN200955259Y (en) | Funnel-derrick moving type construction apparatus | |
CN101214908A (en) | Gin pole integrated dismounting method for tower crane | |
CN208120600U (en) | A kind of quick provision for disengagement of large size inside-climbing tower crane | |
CN107697817B (en) | A kind of method of tower crane crane arm elongated degree in the air | |
CN109440985A (en) | Super high-rise building super large curtain wall unit hydraulic synchronizing lifting system and its construction method | |
CN206970045U (en) | A kind of construction hanging device | |
CN204418629U (en) | Integrated form climbs frame | |
CN205973523U (en) | Super high -rise building is special to be hung from tearing formula roofing open | |
CN107587711A (en) | A kind of regularization assembled overhanging protection canopy and its assembly method | |
CN108439228A (en) | A kind of provision for disengagement of inside-climbing tower crane | |
CN202055507U (en) | Desulfurizing tower examination and repair platform | |
CN201223653Y (en) | Bight for safety operation of conical roof | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN102277957B (en) | Overhaul platform of desulfurizing tower | |
CN209098129U (en) | A kind of installing engineering high altitude lift device | |
CN203594215U (en) | High-altitude large-area work platform semi-automatic lifting apparatus | |
CN113023591A (en) | Large-scale circular construction method for small-dismantling of flat-arm type internal-climbing tower crane | |
CN107934744B (en) | Integral hoisting device for ring crane | |
CN207296350U (en) | Detachable operating platform for steel pipe column | |
CN219471646U (en) | Explosion-free chimney dismantling equipment | |
CN215519860U (en) | A kind of high-rise outer frame erecting safety protection device | |
CN211622525U (en) | Can have enough to meet need elevartor shaft construction operation platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |