CN208010355U - A kind of shield tunnel mortar depositing construction job platform - Google Patents

A kind of shield tunnel mortar depositing construction job platform Download PDF

Info

Publication number
CN208010355U
CN208010355U CN201820172050.1U CN201820172050U CN208010355U CN 208010355 U CN208010355 U CN 208010355U CN 201820172050 U CN201820172050 U CN 201820172050U CN 208010355 U CN208010355 U CN 208010355U
Authority
CN
China
Prior art keywords
bracket
post
mobile
job platform
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820172050.1U
Other languages
Chinese (zh)
Inventor
高文旗
戴振华
赵勇
王敏
雷腾
梁寿
李建磊
候鹰鹏
刘思危
赵晋龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
CCCC SHEC Third Highway Engineering Co Ltd
Original Assignee
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU filed Critical THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Priority to CN201820172050.1U priority Critical patent/CN208010355U/en
Application granted granted Critical
Publication of CN208010355U publication Critical patent/CN208010355U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of shield tunnel mortar depositing construction job platforms, include bottom bracket, column and mobile operation post, the bottom of bottom bracket is equipped with the return pulley group for moving in orbit, several groups column is fixed in bottom bracket, the track runner of at least a pair of of horizontal alignment is equipped on each column, the side of mobile operation post is connected with idler wheel, and the support and slide construction for forming mobile operation post is arranged in track runner in idler wheel;Brake gear is additionally provided in bottom bracket.The construction operation platform of the utility model is mainly used for deep layer slip casting job platform in tunnel, so that easy to operation in the deep layer slip casting drill process of section of jurisdiction.The job platform is longitudinally moved mainly by return pulley group on tunnel battery truck track, it is laterally mobile in track runner mainly by idler wheel that movable operation platform is driven to carry out transverse shifting, make all drillings of shield tunnel lower half section, slip casting etc. that can facilitate carry out operation within the scope of job platform.

Description

A kind of shield tunnel mortar depositing construction job platform
Technical field
The utility model is related to engineering construction engineering device technique fields, and in particular to carry out slip casting during shield tunnel construction The job platform of construction.
Background technology
During shield tunnel construction, due to geological condition, nearly spacing tunnel etc., need to section of jurisdiction into Row deep layer grouting and reinforcing.Conventionally employed artificial carrying grouting equipment and material can not only be led since slip casting process is mobile operation It causes labor intensity big, and is often difficult the progress for keeping up with operation, harmful effect is caused to work progress.For this purpose, someone Moveable job platform, but current job platform generally existing structure and the unbalanced situation of function are invented, that is, real Now it is increasingly complex to may result in platform structure for more complete function, and want it is simple in structure may result in function reduction, such as at present Simple type job platform the case where can't reach there are some places in more roomy and higher constructing tunnel.
Utility model content
The utility model be directed to disadvantage of the existing technology, provide a kind of structure design it is more reasonable, it is simple in structure, have Levels operation post, transversely movable shield tunnel mortar depositing construction job platform.
In order to solve the above technical problems, the utility model adopts the following technical solution:A kind of shield tunnel mortar depositing construction work Industry platform, it is characterised in that:Include bottom bracket, column and mobile operation post, the bottom of bottom bracket is equipped in track The return pulley group of upper movement, several groups column are fixed in bottom bracket, and the track of at least a pair of of horizontal alignment is equipped on each column The side of sliding slot, mobile operation post is connected with idler wheel, and the support and cunning for forming mobile operation post is arranged in track runner in idler wheel Dynamic structure;Brake gear is additionally provided in bottom bracket.
Further, it is equipped with front and back two groups of columns in bottom bracket, upper and lower two pairs of tracks sliding slot, track are equipped on column Sliding slot and the moving direction of return pulley group are perpendicular;The length of track runner is more than the width of mobile operation post, is slided in two pairs of tracks It is respectively provided with a movement operation post on slot and forms height cross structure.In actual use, can be needed upper layer according to construction or The mobile operation post of lower layer turns left or toward moving right, to reach the position convenient for construction.
Further, it is additionally provided with bar on the top of column, bar is located at the top of track runner, is convenient for constructor Member stands firm on operation post.
Further, it is equipped with object placing cavity in the both sides of bottom bracket, in the recessed bottom bracket of object placing cavity, in the outer side edges of object placing cavity Edge is equipped with several master shields, and master shield connects the lower edges of bottom bracket, not only played reinforcing supporting role, but also can block to be placed on and set Shorter tool in object chamber.
Further, several sub-barriers are additionally provided in the outer ledge of object placing cavity, can block be placed in object placing cavity compared with Big longer tool, such as long tube;The lower edge of bottom bracket is fixed in the bottom end of sub-barrier, and master shield is located at bottom bracket By centre position, and master shield is interposed between centre by sub-barrier respectively close to the front-end and back-end of bottom bracket, is convenient for taking in this way Go out some shorter tools.
Further, the mobile operation post using steelframe and metal net at the dead weight of platform can be reduced.
The construction operation platform of the utility model is mainly used for deep layer slip casting job platform in tunnel, such as shield running tunnel Section is 5.4m, so that easy to operation in the deep layer slip casting drill process of section of jurisdiction.The job platform longitudinally exists mainly by return pulley group It is moved on tunnel battery truck track, it is laterally mobile in track runner mainly by idler wheel that movable operation platform is driven to carry out cross To movement, make all drillings of shield tunnel lower half section, slip casting etc. that can facilitate carry out operation within the scope of job platform.
Description of the drawings
Fig. 1 is the utility model side structure schematic diagram;
Fig. 2 is the utility model positive structure schematic;
Fig. 3 is upper regarding structural schematic diagram after the utility model removal bar.
In figure, 1 is return pulley group, and 2 be bottom bracket, and 3 be column, and 4 be mobile operation post, and 5 be track runner, and 6 be brake dress It sets, 7 be idler wheel, and 8 be bar, and 9 be object placing cavity, and 10 be master shield, and 11 be sub-barrier.
Specific implementation mode
In the present embodiment, referring to FIG. 1, FIG. 2 and FIG. 3, the shield tunnel mortar depositing construction job platform, includes bottom bracket 2, column 3 and mobile operation post 4, the bottom of bottom bracket 2 is equipped with the return pulley group 1 for moving in orbit, several groups column 3 It is fixed in bottom bracket 2, the track runner 5 of at least a pair of of horizontal alignment, the side of mobile operation post 4 is equipped on each column 3 It is connected with idler wheel 7, the support and slide construction that mobile operation post 4 is formed in track runner 5 is arranged in idler wheel 7;In bottom bracket 2 It is additionally provided with brake gear 6, in orbit for job platform is parked.
It is equipped with front and back two groups of columns 3 in bottom bracket 2, upper and lower two pairs of tracks sliding slot 5, track runner 5 are equipped on column 3 It is perpendicular with the moving direction of return pulley group 1;The length of track runner 5 is more than the width of mobile operation post 4, in two pairs of tracks sliding slot It is respectively provided with a movement operation post 4 on 5 and forms height cross structure, if lower layer is on a left side, and upper layer is on the right side.In actual use, may be used To need the mobile operation post 4 by upper layer or lower layer to turn left according to construction or toward moving right, be convenient for the position of construction with arrival.
It is additionally provided with bar 8 on the top of column 3, bar 8 is located at the top of track runner 5, exists convenient for construction personnel It stands firm on operation post.
It is equipped with object placing cavity 9 in the both sides of bottom bracket 2, in 9 recessed bottom bracket 2 of object placing cavity, is set in the outer ledge of object placing cavity 9 There are several master shields 10, master shield 10 to connect the lower edges of bottom bracket 2, not only played reinforcing supporting role, but also can block and be placed on Shorter tool in object placing cavity 9.
Be additionally provided with several sub-barriers 11 in the outer ledge of object placing cavity 9, can block be placed on it is larger longer in object placing cavity 9 Tool, such as long tube;The lower edge of bottom bracket 2 is fixed in the bottom end of sub-barrier 11, and master shield 10 is located at bottom bracket 2 By centre position, and master shield 10 is interposed between centre by sub-barrier 11 respectively close to the front-end and back-end of bottom bracket 2, so just In some shorter tools of taking-up.
The mobile operation post 4 is using steelframe and metal net at can reduce the dead weight of platform.
The utility model is described in detail above, it is described above, only the preferred embodiment of the utility model and , when the utility model practical range cannot be limited, i.e., all according to the made equivalent changes and modifications of the application range, it all should still belong to this In utility model covering scope.

Claims (6)

1. a kind of shield tunnel mortar depositing construction job platform, it is characterised in that:Include bottom bracket, column and mobile operation post, The bottom of bottom bracket is equipped with the return pulley group for moving in orbit, and several groups column is fixed in bottom bracket, in each column It is equipped with the track runner of at least a pair of of horizontal alignment, the side of mobile operation post is connected with idler wheel, and idler wheel setting is slided in track The support and slide construction of mobile operation post are formed in slot;Brake gear is additionally provided in bottom bracket.
2. shield tunnel mortar depositing construction job platform according to claim 1, it is characterised in that:Before being equipped in bottom bracket Two groups of columns afterwards are equipped with upper and lower two pairs of tracks sliding slot on column, and track runner and the moving direction of return pulley group are perpendicular;Track The length of sliding slot is more than the width of mobile operation post, and a movement operation post is respectively provided on two pairs of tracks sliding slot and is formed and is just interlocked Structure.
3. shield tunnel mortar depositing construction job platform according to claim 1, it is characterised in that:It is also set on the top of column There are bar, bar to be located at the top of track runner.
4. shield tunnel mortar depositing construction job platform according to claim 1, it is characterised in that:It is set in the both sides of bottom bracket There is an object placing cavity, in the recessed bottom bracket of object placing cavity, is equipped with several master shields in the outer ledge of object placing cavity, master shield connects bottom bracket Lower edges.
5. shield tunnel mortar depositing construction job platform according to claim 4, it is characterised in that:In the outer side edges of object placing cavity Edge is additionally provided with several sub-barriers, and the lower edge of bottom bracket is fixed in the bottom end of sub-barrier, and master shield is located at bottom bracket By centre position, and master shield is interposed between centre by sub-barrier respectively close to the front-end and back-end of bottom bracket.
6. shield tunnel mortar depositing construction job platform according to claim 1, it is characterised in that:The mobile operation post is adopted With steelframe and metal net at.
CN201820172050.1U 2018-01-31 2018-01-31 A kind of shield tunnel mortar depositing construction job platform Active CN208010355U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820172050.1U CN208010355U (en) 2018-01-31 2018-01-31 A kind of shield tunnel mortar depositing construction job platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820172050.1U CN208010355U (en) 2018-01-31 2018-01-31 A kind of shield tunnel mortar depositing construction job platform

Publications (1)

Publication Number Publication Date
CN208010355U true CN208010355U (en) 2018-10-26

Family

ID=63884849

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820172050.1U Active CN208010355U (en) 2018-01-31 2018-01-31 A kind of shield tunnel mortar depositing construction job platform

Country Status (1)

Country Link
CN (1) CN208010355U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109664928A (en) * 2018-12-21 2019-04-23 上海隧道工程质量检测有限公司 A kind of multi-functional auxiliary vehicle of tunnel quality testing

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109664928A (en) * 2018-12-21 2019-04-23 上海隧道工程质量检测有限公司 A kind of multi-functional auxiliary vehicle of tunnel quality testing

Similar Documents

Publication Publication Date Title
CN103967050B (en) Construction system of subway station
CN109236302B (en) Variable section excavation trolley in tunnel
CN102285616B (en) Walking type shield machine lateral sway system and lateral sway method
CN208010355U (en) A kind of shield tunnel mortar depositing construction job platform
CN203834363U (en) Prefabricated T-beam waterproof coil laying vehicle
CN205977243U (en) A platform truck for tunnel water proofing board is laid and reinforcement
CN205100119U (en) Steel form device in self -propelled
CN106522997A (en) Construction trolley for lagging jack in tunnel and underground construction and construction method
CN207554066U (en) The mobile formwork of a plurality of groove in one-time-concreting tunnel
CN103510436B (en) Bed plate formwork rapid transferring device and technology
CN204851287U (en) Big section moving as a whole formula formwork support
CN105863686A (en) Invert formwork hosting traveling trolley
CN210217757U (en) Overlength lining cutting platform truck
CN207390299U (en) A kind of horizontal rail mounted transport system of heavy steel member
CN203530796U (en) Base plate formwork fast transferring device
CN202707076U (en) Double-line railway tunnel trolley
CN206957228U (en) A kind of quick roughening machine for plate-girder side
CN206972263U (en) The anti-collapse device in the horizontal hole in tunnel
CN206356501U (en) One kind is applied to the self-positioning colligation frock of high speed railway fragments-free track slab steel reinforcement cage
CN203114308U (en) Gantry self-propelled anchoring and supporting machine
CN206088044U (en) Article transporting machine that building site used
CN102431907B (en) Walking type tunnel carriageway plate crane
CN201614550U (en) 3000DWT bridge-erecting machine for full-span erection of steel truss bridge used for both double-layer four-track highway and railway
CN103758542A (en) Trolley for laying tunnel waterproof plate
CN207499886U (en) A kind of large cross-section tunnel moves adjustable waterproof construction trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant