CN207973423U - A kind of architectural engineering hanging device - Google Patents

A kind of architectural engineering hanging device Download PDF

Info

Publication number
CN207973423U
CN207973423U CN201820293175.XU CN201820293175U CN207973423U CN 207973423 U CN207973423 U CN 207973423U CN 201820293175 U CN201820293175 U CN 201820293175U CN 207973423 U CN207973423 U CN 207973423U
Authority
CN
China
Prior art keywords
support bar
pulley
support arm
hanging device
architectural engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820293175.XU
Other languages
Chinese (zh)
Inventor
张娜
赵彦磊
郭森
赵兰
杨运肖
潘清义
鲍献民
任立辉
郭显芳
李利忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XINGTAI MUNICIPAL CONSTRUCTION GROUP CO Ltd
Original Assignee
XINGTAI MUNICIPAL CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XINGTAI MUNICIPAL CONSTRUCTION GROUP CO Ltd filed Critical XINGTAI MUNICIPAL CONSTRUCTION GROUP CO Ltd
Priority to CN201820293175.XU priority Critical patent/CN207973423U/en
Application granted granted Critical
Publication of CN207973423U publication Critical patent/CN207973423U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model is related to construction engineering technical fields, and disclose a kind of architectural engineering hanging device, including pedestal, the upper surface of described pedestal one end is fixedly connected with first support bar, the top of the first support bar is connected by first rotating shaft with support arm, the one end of the support arm far from first support bar is provided with first pulley, upper surface of the support arm far from first support bar one end is installed with second pulley, lower surface of the support arm far from first support bar one end is fixedly connected with steel wire rope, the surface of the steel wire rope is overlapped with third pulley, the outside of the third pulley is provided with hook, the support arm is connected with the second shaft close to one end of first support bar, the support arm is connected by the second shaft with second support bar.The architectural engineering hanging device, have it is simple in structure, it is easy to use, facilitate the torque of adjusting device, be suitble to the lifting of different quality object, the advantages that work efficiency is high.

Description

A kind of architectural engineering hanging device
Technical field
The utility model is related to construction engineering technical field, specially a kind of architectural engineering hanging device.
Background technology
With the development of national basis construction, construction industry development is very rapid, this just needs hanging device to help to build Work.
In architectural engineering there are mainly two types of the methods of vertical transport construction material, first, utilizing tower crane, truck crane or gantry Frame vertical transport, there are certain limitations for this method, and equipment leasing is costly, increase construction cost, do not install tower crane or dragon It can not be used under conditions of door frame;Second is that being pulled up using manpower, it is clear that the weight of lifting heavy is restricted, labour cost is big, Time is long, and there are certain danger in work progress.
Utility model content
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of architectural engineering hanging device, have it is simple in structure, It is easy to use, facilitate the torque of adjusting device, be suitble to the lifting of different quality object, the advantages that work efficiency is high, solves State the problem of being mentioned in background technology.
(2) technical solution
It is easy to use to realize that above structure is simple, facilitate the torque of adjusting device, is suitble to hanging for different quality object Dress, the purpose that work efficiency is high, the utility model provide the following technical solutions:A kind of architectural engineering hanging device, including pedestal, The upper surface of described pedestal one end is fixedly connected with first support bar, and the top of the first support bar passes through first rotating shaft and branch Brace is connected, and the one end of the support arm far from first support bar is provided with first pulley, and the support arm is far from first The upper surface of strut one end is installed with second pulley, and lower surface of the support arm far from first support bar one end, which is fixed, to be connected It is connected to steel wire rope, the surface of the steel wire rope is overlapped with third pulley, and the outside of the third pulley is provided with hook, the branch Brace is connected with the second shaft close to one end of first support bar, and the support arm passes through the second shaft and second support bar It is connected, the 4th pulley, middle part of the pedestal close to first support bar one end is installed at the top of second shaft It is fixedly connected with mounting plate, the mounting plate is installed with the 5th pulley close to the side of second support bar, and the pedestal leans on One end of nearly 5th pulley is fixedly connected with motor, and one end of the steel wire rope is set around the output shaft of motor.
Preferably, the upper surface of the pedestal offers sliding slot, and idler wheel is slidably connected in the sliding slot, and the idler wheel is solid Dingan County is loaded on the one end of second support bar far from support arm.
Preferably, the lower surface of the pedestal is provided with non-slip mat.
Preferably, the idler wheel is connected with anti-skidding limited block close to the side of first support bar.
Preferably, the anti-skidding limited block is right-angle prismatic cylinder, and the upper and lower surface of the anti-skidding limited block is equal It is provided with anti-skid chequer, the side of the anti-skidding limited block is provided with handle.
Preferably, the bottom end of the first support bar is connected by hydraulic telescopic rod with one end of support arm.
Preferably, upper surface of the pedestal far from first support bar one end offers counterweight tank, is set in the counterweight tank It is equipped with clump weight.
(3) advantageous effect
Compared with prior art, the utility model provides a kind of architectural engineering hanging device, has following
Advantageous effect:
1, architectural engineering hanging device, by the way that first support bar, first rotating shaft, support arm, second support bar, cunning is arranged Slot, idler wheel and hydraulic telescopic rod can effectively realize the effect that hanging device freely adjusts torque, to be suitble to different quality object The lifting of product, easy to use, work efficiency is high.
2, the architectural engineering hanging device can effectively limit idler wheel by the way that anti-skidding limited block is arranged, prevent from hanging Second support bar occurs the phenomenon that sliding because of stress during dress, ensure that the normal operation of equipment;By the way that non-slip mat is arranged, It can be effectively prevented the phenomenon that being slided in the equipment course of work, play anti-skidding effect;It is by the way that third pulley is arranged Movable pulley plays the role of labour-saving;By the way that counterweight tank is arranged, convenient for increasing or decreasing counterweight according to the quality of institute's article hoisting The quantity of block is easy to use.
Description of the drawings
Fig. 1 is the utility model structure of the main view;
Fig. 2 is the utility model structure left view schematic diagram;
Fig. 3 is the utility model mounting plates structure schematic diagram;
Fig. 4 is the utility model first pulley structural schematic diagram;
Fig. 5 is the utility model sliding groove structure schematic cross-sectional view;
Fig. 6 is the anti-skidding standoff features stereogram of the utility model.
In figure:1 pedestal, 2 first support bars, 3 first rotating shafts, 4 support arms, 5 first pulleys, 6 second pulleys, 7 steel wire ropes, 8 third pulleys, 9 hooks, 10 second shafts, 11 second support bars, 12 the 4th pulleys, 13 mounting plates, 14 the 5th pulleys, 15 electricity Machine, 16 sliding slots, 17 idler wheels, 18 non-slip mats, 19 anti-skidding limited blocks, 20 handles, 21 hydraulic telescopic rods, 22 clump weights.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
It please refers to Fig.1 to Fig. 6, the utility model provides a kind of technical solution:A kind of architectural engineering hanging device, including bottom Seat 1, the upper surface of pedestal 1 offers sliding slot 16, idler wheel 17 is slidably connected in sliding slot 16, idler wheel 17 is close to first support bar 2 Side be connected with anti-skidding limited block 19, by the way that anti-skidding limited block 19 is arranged, effectively idler wheel 17 can be limited, prevent from hanging Second support bar 11 occurs the phenomenon that sliding because of stress during dress, ensure that the normal operation of equipment, anti-skidding limited block 19 Upper and lower surface for right-angle prismatic cylinder, anti-skidding limited block 19 is both provided with anti-skid chequer, the side of anti-skidding limited block 19 It is provided with handle 20, idler wheel 17 is fixedly installed in the one end of second support bar 11 far from support arm 4, the lower surface setting of pedestal 1 There is non-slip mat 18, by the way that non-slip mat 18 is arranged, the phenomenon that being slided in the equipment course of work can be effectively prevented, played anti- The upper surface of sliding effect, 1 one end of pedestal is fixedly connected with first support bar 2, and pedestal 1 is upper far from 2 one end of first support bar Surface offers counterweight tank, and clump weight 22 is provided in counterweight tank, by the way that counterweight tank is arranged, convenient for according to the matter of institute's article hoisting Amount increases or decreases the quantity of clump weight 22, is easy to use, the top of first support bar 2 passes through first rotating shaft 3 and 4 phase of support arm Connection, the bottom end of first support bar 2 are connected by hydraulic telescopic rod 21 with one end of support arm 4, and the first support of setting is passed through Bar 2, first rotating shaft 3, support arm 4, second support bar 11, sliding slot 16, idler wheel 17 and hydraulic telescopic rod 21, can effectively realize and hang The standby effect for freely adjusting torque of installing, to be suitble to the lifting of different quality article, easy to use, work efficiency is high, support The one end of arm 4 far from first support bar 2 is provided with first pulley 5, and upper surface of the support arm 4 far from 2 one end of first support bar is solid Dingan County is equipped with second pulley 6, and lower surface of the support arm 4 far from 2 one end of first support bar is fixedly connected with steel wire rope 7, steel wire rope 7 It is connected with motor 15, the 5th pulley 14, the 4th pulley 12, second pulley 6, third pulley 8 and support arm in turn from left to right 4, the surface of steel wire rope 7 is overlapped with third pulley 8, and third pulley 8 is movable pulley, and movable pulley cannot change the direction of power, but most Multipotency enough saves the power of half, is movable pulley by the way that third pulley 8 is arranged, plays the role of labour-saving, the outside of third pulley 8 is set It is equipped with hook 9, support arm 4 is connected with the second shaft 10 close to one end of first support bar 2, and support arm 4 passes through second turn Axis 10 is connected with second support bar 11, and the top of the second shaft 10 is installed with the 4th pulley 12, and pedestal 1 is close to first Mounting plate 13 is fixedly connected in the middle part of 2 one end of strut, mounting plate 13 is installed with close to the side of second support bar 11 Five pulleys 14, pedestal 1 are fixedly connected with motor 15 close to one end of the 5th pulley 14, and one end of steel wire rope 7 is set around motor 15 Output shaft.
The electric elements occurred in this article are electrically connected with extraneous main controller and 220V alternating currents, and main controller can be meter Calculation machine etc. plays the conventionally known equipment of control.
In conclusion the architectural engineering hanging device, by the way that first support bar 2, first rotating shaft 3, support arm 4, the is arranged Two supporting rods 11, sliding slot 16, idler wheel 17 and hydraulic telescopic rod 21 can effectively realize the work that hanging device freely adjusts torque With to be suitble to the lifting of different quality article, easy to use, work efficiency is high;It, can be effective by the way that anti-skidding limited block 19 is arranged Ground limits idler wheel 17, prevents second support bar 11 in hoisting process from occurring the phenomenon that sliding because of stress, ensure that and set Standby normal operation;By the way that non-slip mat 18 is arranged, it can be effectively prevented the phenomenon that being slided in the equipment course of work, played Anti-skidding effect;It is movable pulley by the way that third pulley 8 is arranged, plays the role of labour-saving;By the way that counterweight tank is arranged, it is convenient for basis The quality of institute's article hoisting increases or decreases the quantity of clump weight 22, is easy to use.
It should be noted that herein, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also include other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is appreciated that can these embodiments be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (7)

1. a kind of architectural engineering hanging device, including pedestal (1), it is characterised in that:The upper surface of described pedestal (1) one end is fixed It is connected with first support bar (2), the top of the first support bar (2) is connected by first rotating shaft (3) with support arm (4), The one end of the support arm (4) far from first support bar (2) is provided with first pulley (5), and the support arm (4) is far from first The upper surface of strut (2) one end is installed with second pulley (6), separate first support bar (2) one end of the support arm (4) Lower surface is fixedly connected with steel wire rope (7), and the surface of the steel wire rope (7) is overlapped with third pulley (8), the third pulley (8) outside is provided with hook (9), and the support arm (4) is connected with the second shaft close to one end of first support bar (2) (10), the support arm (4) is connected by the second shaft (10) with second support bar (11), the top of second shaft (10) Portion is installed with the 4th pulley (12), and the pedestal (1) is fixedly connected with installation in the middle part of first support bar (2) one end Plate (13), the mounting plate (13) are installed with the 5th pulley (14), the pedestal close to the side of second support bar (11) (1) it is fixedly connected with motor (15) close to one end of the 5th pulley (14), one end of the steel wire rope (7) is set around motor (15) Output shaft.
2. a kind of architectural engineering hanging device according to claim 1, it is characterised in that:The upper surface of the pedestal (1) Sliding slot (16) is offered, slidably connects idler wheel (17) in the sliding slot (16), the idler wheel (17) is fixedly installed in second The one end of strut (11) far from support arm (4).
3. a kind of architectural engineering hanging device according to claim 1, it is characterised in that:The lower surface of the pedestal (1) It is provided with non-slip mat (18).
4. a kind of architectural engineering hanging device according to claim 2, it is characterised in that:The idler wheel (17) is close to first The side of supporting rod (2) is connected with anti-skidding limited block (19).
5. a kind of architectural engineering hanging device according to claim 4, it is characterised in that:The anti-skidding limited block (19) is The upper and lower surface of right-angle prismatic cylinder, the anti-skidding limited block (19) is both provided with anti-skid chequer, the anti-skidding limited block (19) side is provided with handle (20).
6. a kind of architectural engineering hanging device according to claim 1, it is characterised in that:The first support bar (2) Bottom end is connected by hydraulic telescopic rod (21) with one end of support arm (4).
7. a kind of architectural engineering hanging device according to claim 1, it is characterised in that:The pedestal (1) is far from first The upper surface of supporting rod (2) one end offers counterweight tank, and clump weight (22) is provided in the counterweight tank.
CN201820293175.XU 2018-03-02 2018-03-02 A kind of architectural engineering hanging device Expired - Fee Related CN207973423U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820293175.XU CN207973423U (en) 2018-03-02 2018-03-02 A kind of architectural engineering hanging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820293175.XU CN207973423U (en) 2018-03-02 2018-03-02 A kind of architectural engineering hanging device

Publications (1)

Publication Number Publication Date
CN207973423U true CN207973423U (en) 2018-10-16

Family

ID=63764199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820293175.XU Expired - Fee Related CN207973423U (en) 2018-03-02 2018-03-02 A kind of architectural engineering hanging device

Country Status (1)

Country Link
CN (1) CN207973423U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109205482A (en) * 2018-11-07 2019-01-15 江苏广源幕墙装饰工程有限公司 The hanging apparatus of curtain wall lighting roof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109205482A (en) * 2018-11-07 2019-01-15 江苏广源幕墙装饰工程有限公司 The hanging apparatus of curtain wall lighting roof

Similar Documents

Publication Publication Date Title
CN206376515U (en) High-lift operation hanging cradle device
CN201240810Y (en) Novel manual hoister
CN103545751B (en) Overhead transmission line ground wire optical cable fittings replacement bracket
CN208869222U (en) Hanging apparatus
CN205802845U (en) A kind of civil engineering is with hanging a liter machine
CN207973423U (en) A kind of architectural engineering hanging device
CN205687497U (en) A kind of simple and easy hoisting device installing transhipment for power equipment
CN210340141U (en) House building engineering lifting device
CN204324745U (en) A kind of 35KV isolation switch hanging device
CN208327184U (en) A kind of construction of hydro project trash rack lifting mounting device
CN201810014U (en) One-machine multi-plate three-layer lifting traversing parking equipment with one layer of bottom pit
CN202006361U (en) Core extraction machine
CN205653066U (en) Take gantry crane of windrow dolly linkage
CN204752007U (en) Loop wheel machine is used to fitment
CN211895867U (en) Pipeline lifting machine
CN109748194A (en) A kind of hoisting equipment for building
CN206680091U (en) A kind of large-scale transport hoist
CN202704924U (en) Suspending device for mounting screen cover of classifying screen
CN207812982U (en) A kind of inner wall of oil tank construction hanging basket
CN221319208U (en) Liftable bracket platform device for dismounting and mounting electric hoist of bridge crane
CN216336160U (en) Portable multifunctional combined lifting appliance for offshore drilling platform
CN205575417U (en) Building side hoist device
CN205151577U (en) Fix small -size hoisting machine on steel support of groove
CN209259545U (en) A kind of fixed device of elevator
CN203622161U (en) Labor-saving device for honing machine tool face guide rail

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181016

CF01 Termination of patent right due to non-payment of annual fee