CN207887912U - A kind of porous bit synchronization Full-automatic drilling line - Google Patents

A kind of porous bit synchronization Full-automatic drilling line Download PDF

Info

Publication number
CN207887912U
CN207887912U CN201721745853.3U CN201721745853U CN207887912U CN 207887912 U CN207887912 U CN 207887912U CN 201721745853 U CN201721745853 U CN 201721745853U CN 207887912 U CN207887912 U CN 207887912U
Authority
CN
China
Prior art keywords
tubing
pedestal
fixture block
borehole drill
bit synchronization
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721745853.3U
Other languages
Chinese (zh)
Inventor
朱亚明
王维林
李立均
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Yi Hua New Energy Technology Co Ltd
Original Assignee
Wuxi Yi Hua New Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Yi Hua New Energy Technology Co Ltd filed Critical Wuxi Yi Hua New Energy Technology Co Ltd
Application granted granted Critical
Publication of CN207887912U publication Critical patent/CN207887912U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a kind of porous bit synchronization Full-automatic drilling lines, including pedestal, the base-plates surface is provided with several borehole drill constructions, several borehole drill constructions are arranged in order setting along tubing conveying direction, mobile fixed part is additionally provided between the pedestal and borehole drill construction, the mobile fixed part is arranged along tubing conveying direction, transmission detent mechanism is additionally provided on the pedestal, the transmission detent mechanism is for colliery carries tubing and the drilling of match-drill mechanism, the borehole drill construction includes multiple tubing rollgangs being arranged along tubing conveying direction and tubing hold-down mechanism.The utility model has the effect of that easily adjusting, steady production, and production efficiency are high, and labor intensity is low, saves processing cost.

Description

A kind of porous bit synchronization Full-automatic drilling line
Technical field
The utility model is related to tubing preparation fields, and in particular to a kind of porous bit synchronization Full-automatic drilling line.
Background technology
It is porous for being bored on the larger big pipe fitting of batch, and hole is not of uniform size, with live all be using laser cutting or Prepared by the mode of punching, cost is larger, and typically single hole operation, and speed is slower, is unable to reach and stablizes quickly Speed of production, and hole on the same axis also can not exact position, drilling quality substantially reduces.
Invention content
The technical problem to be solved by the present invention is to overcome problem above of the existing technology, provide a kind of porous Bit synchronization Full-automatic drilling line has the effect of that easily adjusting, steady production, and production efficiency are high, and labor intensity is low, saves and adds Work cost.
In order to solve the above technical problems, reaching above-mentioned technique effect, the utility model is achieved through the following technical solutions:
A kind of porous bit synchronization Full-automatic drilling line, including pedestal, the base-plates surface are provided with several borehole drill constructions, if It does the borehole drill construction and is arranged in order setting along tubing conveying direction, be additionally provided between the pedestal and borehole drill construction mobile solid Determine portion, the mobile fixed part is arranged along tubing conveying direction, and transmission detent mechanism, the transmission are additionally provided on the pedestal For detent mechanism for colliery carries tubing and the drilling of match-drill mechanism, the borehole drill construction includes multiple along the setting of tubing conveying direction Tubing rollgang and tubing hold-down mechanism.
Further, the mobile fixed part includes the convex conduit being arranged in base-plates surface, the convex conduit Inside it is provided with the bolt assembly for the borehole drill construction that locks.
Further, each borehole drill construction all has one or more drill bit.
Further, further include end blocking mechanism, the conveying in transmission detent mechanism is arranged in the end blocking mechanism Discharge end, the end blocking mechanism includes barrier plate, and lifting cylinder is provided in the blocking version.
Further, the tubing hold-down mechanism includes lower fixture block and upper fixture block, is all provided in the lower fixture block and upper fixture block It is equipped with imitation-shaped groove, the lower fixture block is fixed on fixture block pedestal, and the upper fixture block is also connect with lifting moving component.
Further, the tubing rollgang is arranged on lifting frame, and the lifting frame bottom is provided with evacuation Cylinder, the evacuation cylinder are arranged on roller-way pedestal, and guidance set is additionally provided between the roller-way pedestal and lifting frame, The tubing rollgang is also connect with feeder motor, and the feeder motor is fixed on lifting frame.
Further, the borehole drill construction includes drill rack, and ball linear track, institute are provided on the drill rack It states ball linear track to connect with drilling machine and screw rod transmission component, the screw rod transmission component is connect with lead screw power motor.
The utility model has the beneficial effects that:
Tubing can be carried out to mobile transport by tubing rollgang and tubing hold-down mechanism and gripped, clamping is solid It can be drilled, and position is fixed after clamping, therefore multiple borehole drill constructions can work at the same time, be improved by borehole drill construction after fixed Production efficiency.And it is adjustable to move the fixed position that fixed part enables to borehole drill construction on pedestal, to adapt to different batches pipe Adjustment under material bore position different situations is adjusted and is taken less, convenient and efficient.
The above description is merely an outline of the technical solution of the present invention, in order to better understand the skill of the utility model Art means, and can be implemented in accordance with the contents of the specification, below on the preferred embodiment of the present invention and the accompanying drawings in detail It describes in detail bright as after.Specific embodiment of the present utility model is shown in detail by following embodiment and its attached drawing.
Description of the drawings
Attached drawing described herein is used to provide a further understanding of the present invention, and is constituted part of this application, The exemplary embodiment of the utility model and the description thereof are used to explain the utility model, does not constitute to the improper of the utility model It limits.In the accompanying drawings:
Fig. 1 is the overall structure diagram of one embodiment of the utility model;
Fig. 2 is the utility model convex channel portion structural schematic diagram;
Fig. 3 is the utility model end blocking mechanism structural schematic diagram;
Fig. 4 is the utility model tubing hold-down mechanism structural schematic diagram;
Fig. 5 is the utility model tubing rollgang part-structure schematic diagram;
Fig. 6 is the utility model borehole drill construction structural schematic diagram.
Figure label explanation:1, pedestal, 2, borehole drill construction, 3, mobile fixed part, 4, transmission detent mechanism, 5, tubing conveying Roller-way, 6, tubing hold-down mechanism, 7, convex conduit, 8, bolt assembly, 9, end blocking mechanism, 10, barrier plate, 11, lifting Cylinder, 12, lower fixture block, 13, upper fixture block, 14, imitation-shaped groove, 15, fixture block pedestal, 16, lifting moving component, 17, lifting frame, 18, cylinder is avoided, 19, roller-way pedestal, 20, guidance set, 21, feeder motor, 22, drill rack, 23, ball linear track, 24, lead screw power motor, 25, drilling machine.
Specific implementation mode
Below with reference to the accompanying drawings and in conjunction with the embodiments, the utility model is described in detail.
Shown in referring to Figures 1 and 2, an embodiment of the porous bit synchronization Full-automatic drilling line of the utility model, including base Seat 1, base-plates surface are provided with several borehole drill constructions 2, and several borehole drill constructions are arranged in order setting along tubing conveying direction, pedestal and Mobile fixed part 3 is additionally provided between borehole drill construction, mobile fixed part is arranged along tubing conveying direction, and mobile fixed part is mainly used It, can also be quick in borehole drill construction is fixed on base-plates surface, and when borehole drill construction position is matched with bore position portion Mobile adjustment;Transmission detent mechanism 4 is additionally provided on pedestal, tubing can be carried out conveying movement and closed by transmission detent mechanism Right position, which is set, fixes tubing, is drilled with match-drill mechanism;Wherein, borehole drill construction includes multiple being arranged along tubing conveying direction Tubing rollgang 5 and tubing hold-down mechanism 6, tubing rollgang support set pipeline and rotate, and realize the movement of tubing, tubing pressure The outside of tubing can be then clamped in tight mechanism, with fixed position.
Above-mentioned mobile fixed part includes the convex conduit 7 being arranged in base-plates surface, is provided with and is used in convex conduit The bolt assembly 8 of locking borehole drill construction, is that bolt assembly is unscrewed to the movement that borehole drill construction can be realized when needing movement, is moved It is dynamic that bolt assembly is tightened afterwards in place.
With reference to shown in Fig. 3, in order to find the clip position of tubing accurately, end blocking mechanism 9 can also be set, end stops machine The conveying discharge end in transmission detent mechanism is arranged in structure, and end blocking mechanism includes barrier plate 10, stops and is provided with lifting in version Cylinder 11, when tubing is when conveying mobile, lifting cylinder, which stretches out, extend out to barrier plate in the mobile space of tubing conveying, tubing End can be kept out on barrier plate, realize tubing positioning, and gripping for tubing can ensure bore position after positioning, when After tubing drills, lifting cylinder action declines barrier plate, therefore tubing can smoothly discharge.
With reference to shown in Fig. 4, tubing hold-down mechanism includes lower fixture block 12 and upper fixture block 13, passes through matching for upper fixture block and lower fixture block Tubing is fixedly clamped by conjunction, and imitation-shaped groove 14 is both provided in lower fixture block and upper fixture block, to increase contact surface, improves steady after clamping Qualitative, lower fixture block is fixed on fixture block pedestal 15, and upper fixture block is also connect with lifting moving component 16, lifting moving component energy Upper fixture block is enough driven to carry out clamping downwards or unclamp upwards, direction can also be what horizontal cross was arranged herein certainly, unclamp It is convenient for the conveying of tubing to move afterwards.
Referring to Figure 5, tubing rollgang is arranged on lifting frame 17, and lifting frame bottom is provided with evacuation cylinder 18, evacuation cylinder is arranged on roller-way pedestal 19, guidance set 20 is additionally provided between roller-way pedestal and lifting frame, tubing is defeated Roller-way is sent also to be connect with feeder motor 21, feeder motor is fixed on lifting frame, and lifting frame support tubing conveying roller Road, the action by avoiding cylinder realize that the effect extended and retracted can be connected on tubing when extended, pass through conveying Motor rotation provides conveying power, and tubing can be moved, and when withdrawn, tubing rollgang is detached with tubing, does not influence to manage The clamping and drilling of material.
With reference to shown in Fig. 6, in one embodiment, borehole drill construction includes drill rack 22, and ball is provided on drill rack Linear track 23, ball linear track are connect with drilling machine 25 and screw rod transmission component, screw rod transmission component and lead screw power motor 24 connections.High precision ball linear track is wherein used, sliding is light, stablizes, is not easy to wear, easy-maintaining.Screw rod transmission component Coordinate the reciprocating motion power of supply drilling machine with lead screw power motor, realizes drilling effect.
Wherein each borehole drill construction all has one or more drill bit.When needing to bore a hole, it is only necessary to install one Two drill bits can be arranged when needing drill two holes in a drill bit, and the wherein power resources of drill bit are that the prior art is not done It is described in detail.When needing in the same radial direction of tubing or the multiple holes of the radially brill that is closer to, can be designed as shown in fig. 6 Structure can carry out tubing multi-faceted how dynamic boring work simultaneously.
The preferred embodiment that these are only the utility model, is not intended to limit the utility model, for this field Technical staff for, various modifications and changes may be made to the present invention.Within the spirit and principle of the utility model, Any modification, equivalent replacement, improvement and so on should be included within the scope of protection of this utility model.

Claims (7)

1. a kind of porous bit synchronization Full-automatic drilling line, it is characterised in that:Including pedestal, if the base-plates surface is provided with drilled dry Holes mechanism, several borehole drill constructions are arranged in order setting along tubing conveying direction, are also set between the pedestal and borehole drill construction It is equipped with mobile fixed part, the mobile fixed part is arranged along tubing conveying direction, and transmission localization machine is additionally provided on the pedestal Structure, for the transmission detent mechanism for colliery carries tubing and the drilling of match-drill mechanism, the borehole drill construction includes multiple along tubing The tubing rollgang and tubing hold-down mechanism of conveying direction setting.
2. porous bit synchronization Full-automatic drilling line according to claim 1, it is characterised in that:The mobile fixed part includes Convex conduit in base-plates surface is set, the bolt assembly for the borehole drill construction that locks is provided in the convex conduit.
3. porous bit synchronization Full-automatic drilling line according to claim 1, it is characterised in that:Each borehole drill construction is equal With one or more drill bit.
4. porous bit synchronization Full-automatic drilling line according to claim 1, it is characterised in that:It further include end blocking machine The conveying discharge end in transmission detent mechanism is arranged in structure, the end blocking mechanism, and the end blocking mechanism includes barrier plate, It is provided with lifting cylinder on the barrier plate.
5. porous bit synchronization Full-automatic drilling line according to claim 1, it is characterised in that:The tubing hold-down mechanism packet Lower fixture block and upper fixture block are included, imitation-shaped groove is both provided in the lower fixture block and upper fixture block, the lower fixture block is fixed at fixture block On pedestal, the upper fixture block is also connect with lifting moving component.
6. porous bit synchronization Full-automatic drilling line according to claim 1, it is characterised in that:The tubing rollgang is set It sets on lifting frame, the lifting frame bottom is provided with evacuation cylinder, and the evacuation cylinder is arranged on roller-way pedestal, institute It states and is additionally provided with guidance set between roller-way pedestal and lifting frame, the tubing rollgang is also connect with feeder motor, institute Feeder motor is stated to be fixed on lifting frame.
7. porous bit synchronization Full-automatic drilling line according to claim 1, it is characterised in that:The borehole drill construction includes boring Hole rack is provided with ball linear track, the ball linear track and drilling machine and screw rod transmission component on the drill rack Connection, the screw rod transmission component are connect with lead screw power motor.
CN201721745853.3U 2017-09-06 2017-12-14 A kind of porous bit synchronization Full-automatic drilling line Expired - Fee Related CN207887912U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201721136057 2017-09-06
CN201721136057X 2017-09-06

Publications (1)

Publication Number Publication Date
CN207887912U true CN207887912U (en) 2018-09-21

Family

ID=63548747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721745853.3U Expired - Fee Related CN207887912U (en) 2017-09-06 2017-12-14 A kind of porous bit synchronization Full-automatic drilling line

Country Status (1)

Country Link
CN (1) CN207887912U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109746476A (en) * 2019-02-27 2019-05-14 中建五局安装工程有限公司 A kind of elliptical air manufacturing device
CN112496759A (en) * 2020-11-17 2021-03-16 浙江景宁周氏机械有限公司 Porous drilling device
CN113333809A (en) * 2021-06-10 2021-09-03 重庆市汇畅钢管制造有限公司 Multi-pipe synchronous punching device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109746476A (en) * 2019-02-27 2019-05-14 中建五局安装工程有限公司 A kind of elliptical air manufacturing device
CN112496759A (en) * 2020-11-17 2021-03-16 浙江景宁周氏机械有限公司 Porous drilling device
CN113333809A (en) * 2021-06-10 2021-09-03 重庆市汇畅钢管制造有限公司 Multi-pipe synchronous punching device

Similar Documents

Publication Publication Date Title
CN207887912U (en) A kind of porous bit synchronization Full-automatic drilling line
CN107891273B (en) Multi-station machining forming hole intelligent equipment
CN204018781U (en) A kind of multistation valve flange drilling equipment
CN204018780U (en) A kind of double-ended double-station holes pressure-plate boring device
CN208976890U (en) A kind of crankshaft oil hole facing attachment
CN205237550U (en) Multistation revolving stage and positioner thereof
CN201644856U (en) Special drilling machine for machining 465Q cylinder cover connecting holes
CN108515306A (en) A kind of trigone circular arc drilling rod Intelligent welding equipment
KR20120077918A (en) A drilling machine
CN107971511A (en) A kind of grooved bit component, perforating device and drilling method
CN107150241A (en) A kind of tool for drilling fixture
CN207723538U (en) Dowel hole special fixture is bored on pull-fork assembly
CN110576201B (en) Multi-station feeding type drilling machine
CN212144572U (en) Numerical control machine tool special for machining oblique and straight oil holes of crankshaft
CN213288784U (en) Device for boring deep hole on lathe
CN208628848U (en) A kind of Circular Pipe three-dimensional brill milling workpiece special processing equipment
CN104070200A (en) Drilling machine
CN207086958U (en) A kind of automatic double-head drilling machine
CN207521731U (en) A kind of adjustable bore bit fixture of boring direction
CN208584241U (en) Drilling tool is used in axial support
CN208214700U (en) A kind of trigone circular arc drilling rod Intelligent welding equipment
CN105290455A (en) Drilling device for forming timing hole in balance shaft
CN207857914U (en) A kind of novel drill jig of auto parts and components processing
CN201604014U (en) Large-scale ring piece bolt hole chamfering tooling
CN204094526U (en) A kind of wheel automatic drilling machine automatic positioning equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180921