CN207700194U - Dewatering well protective device - Google Patents
Dewatering well protective device Download PDFInfo
- Publication number
- CN207700194U CN207700194U CN201721519286.XU CN201721519286U CN207700194U CN 207700194 U CN207700194 U CN 207700194U CN 201721519286 U CN201721519286 U CN 201721519286U CN 207700194 U CN207700194 U CN 207700194U
- Authority
- CN
- China
- Prior art keywords
- dewatering well
- anchor ear
- protective device
- anchor
- dewatering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
The utility model is related to a kind of dewatering well protective devices.The dewatering well protective device includes support pile, at least two first anchor ears and multiple second anchor ears, support pile is located at the first side of dewatering well, at least two first anchor ears are sheathed on the top and bottom of dewatering well respectively, second anchor ear is arranged along the short transverse of dewatering well, second anchor ear is arranged between the first anchor ear and along the perimeter of first anchor ear, the both ends of second anchor ear are connect with the first anchor ear respectively, and the distance between the second anchor ear and dewatering well are less than the distance between support pile and dewatering well.Above-mentioned dewatering well protective device close to the side of road in dewatering well by being arranged support pile, expand the excavation face near dewatering well, reduce dynamic load, such as influence of the roadside wagon flow to dewatering well, when in the case where being subject to external force, dewatering well can be limited in protection network by the first anchor ear and the second anchor ear so that stable connection between the pipe of cement of dewatering well, dewatering well is avoided there is a phenomenon where faulting of slab ends and is tilted, the safety of foundation pit construction is improved.
Description
Technical field
The utility model is related to the realm of building construction, more particularly to dewatering well protective device.
Background technology
Dewatering well is the well beaten for lowering of watertable, and water pump groundwater abstraction is put into after having beaten, and reduces the water of underground water
Position.Dewatering well is one of the important measures for ensureing foundation pit smooth construction.Usually, dewatering well is applied using the socket of socket joint pipe of cement
Work connects, and the method is at low cost, easy for construction, but when encountering the construction of deep basal pit slope, at the top slope of part dewatering well
The phenomenon that will appear faulting of slab ends due to the influence of unilateral stress or roadside vehicle flowrate load and tilt so that the earthwork in bank protection,
Sundries and rainwater etc. flow into dewatering well to some extent, be easy to cause well head blocking, there are larger construction safety hidden danger.
Utility model content
Based on this, it is necessary to which the phenomenon that will appear faulting of slab ends and inclination for dewatering well makes foundation pit construction, and there are security risks
The problem of, a kind of dewatering well stable connection is provided, construction safety hidden danger can be reduced dewatering well protective device.
A kind of dewatering well protective device, the dewatering well include the second side close to the first side of road and separate road,
The dewatering well protective device includes:
Support pile is located at first side of the dewatering well;
At least two first anchor ears, are sheathed on the top and bottom of the dewatering well respectively;
Multiple second anchor ears, the short transverse along the dewatering well are arranged, and second anchor ear is located at first anchor ear
Between and along the perimeter of first anchor ear be arranged, the both ends of second anchor ear are connect with first anchor ear respectively, described
The distance between second anchor ear and the dewatering well are less than the distance between the support pile and the dewatering well.
In one embodiment, the dewatering well includes multiple downcomers, and the downcomer is tongue and groove downcomer.
In one embodiment, first anchor ear is steel loop.
In one embodiment, the internal diameter of first anchor ear is equal to the outer diameter of the dewatering well.
In one embodiment, second anchor ear is reinforcing bar.
In one embodiment, further include prestress anchorage cable, the prestress anchorage cable is arranged close to the area of the dewatering well
Domain.
In one embodiment, the support pile includes more supporting reinforcing bars.
Above-mentioned dewatering well protective device is expanded by the way that support pile is arranged close to the side of road in dewatering well near dewatering well
Excavation face, reduce dynamic load, such as influence of the roadside wagon flow to dewatering well, then in the top and bottom of dewatering well setting the
One anchor ear, and multiple second anchor ears are set between the first anchor ear of top and bottom so that dewatering well be located at the first anchor ear and
In the protection network that second anchor ear is formed, when in the case where being subject to external force, the first anchor ear and the second anchor ear can limit dewatering well
It makes in protection network so that stable connection between the pipe of cement of dewatering well avoids dewatering well there is a phenomenon where faulting of slab ends and tilts,
Improve the safety of foundation pit construction.
Description of the drawings
Fig. 1 is the structural schematic diagram of the dewatering well protective device of an embodiment;
Fig. 2 is the structural schematic diagram of the first anchor ear and the second anchor ear of dewatering well protective device shown in FIG. 1;
Fig. 3 is the structural schematic diagram of the support pile of dewatering well protective device shown in FIG. 1;
Fig. 4 is the structural schematic diagram of the support pile of dewatering well protective device shown in FIG. 1.
Specific implementation mode
As shown in Figs. 1-2, dewatering well 1 includes the second side close to the first side of road 2 and separate road, an embodiment
Dewatering well protective device 10 includes support pile 100, at least two first anchor ears 110 and multiple second anchor ears 120, support pile 100
Positioned at the first side of dewatering well 1, at least two first anchor ears 110 are sheathed on the top and bottom of dewatering well 1, the second anchor ear respectively
120 along dewatering well 1 short transverse be arranged, the second anchor ear 120 is between the first anchor ear 110 and along first anchor ear 110
Perimeter setting, the both ends of the second anchor ear 120 are connect with the first anchor ear 110 respectively, between the second anchor ear 120 and dewatering well 1
Distance is less than the distance between support pile 100 and dewatering well 1.
Above-mentioned dewatering well protective device 10 expands precipitation by the way that support pile 100 is arranged close to the side of road in dewatering well 1
Excavation face near well 1, reduces dynamic load, such as influence of the roadside wagon flow to dewatering well 1, then at the top of dewatering well 1 and
The first anchor ear 110 is arranged in bottom, and multiple second anchor ears 120 are arranged between the first anchor ear 110 of top and bottom so that drop
Well 1 is located in the protection network that the first anchor ear 110 and the second anchor ear 120 are formed, when in the case where being subject to external force, the first anchor ear
110 and second anchor ear 120 dewatering well 1 can be limited in protection network so that stable connection between the pipe of cement of dewatering well 1,
Dewatering well 1 is avoided there is a phenomenon where faulting of slab ends and is tilted, the safety of foundation pit construction is improved.
As shown in Fig. 2, dewatering well protective device 10 includes two the first anchor ears 110, a top for being located at dewatering well 1,
That is, close to the place that dewatering well 1 is open.Another is located at the bottom of dewatering well 1.In the present embodiment, the first anchor ear 110 is steel
Ring is sleeved on the outer wall of dewatering well 1.Further, in the present embodiment, the internal diameter of the first anchor ear 110 is equal to the outer of dewatering well 1
Diameter.When the first anchor ear 110 is set in the outer diameter of dewatering well 1, the outer wall of dewatering well 1 can be close to so that when arranging second
After anchor ear 120, the safeguard structure that the first anchor ear 110 and the second anchor ear 120 are formed can be close to the outer wall of dewatering well 1, and then limit
The misalignment or tilting of 1 pipe of cement of dewatering well processed.In other embodiments, the internal diameter of the first anchor ear 110 can also be slightly less than precipitation
The outer diameter of well 1.
Second anchor ear 120 is located between two the first anchor ears 110, one end of the second anchor ear 120 and first armful of top
First anchor ear 110 of 110 connection of hoop, the other end and bottom connects.Multiple second anchor ears 120 are set along the perimeter of the first anchor ear 110
It sets and is evenly distributed between two the first anchor ears 110.In the present embodiment, the second anchor ear 120 is perpendicular to 110 institute of the first anchor ear
Plane.That is, the first anchor ear 110 and the second anchor ear 120 form a frame, it is sheathed on dewatering well 1, due to the first anchor ear
The distance between 110 and dewatering well 1 are smaller so that entire the distance between frame and dewatering well 1 are also smaller, that is, frame is basic
It is the movement or inclination be close to dewatering well 1, and then limit dewatering well 1, thus it is guaranteed that being connected between 1 pipe of cement of dewatering well
Stability, avoid dewatering well 1 dislocation and inclination and cause silt to enter downcomer, improve the safety of construction.At this
In embodiment, the second anchor ear 120 is reinforcing bar.Reinforced steel bar strength is big and is unlikely to deform, and is connected between raising 1 pipe of cement of dewatering well steady
It is qualitative.In other embodiments, the second anchor ear 120 or bamboo cane.
Please refer to Fig. 1, Fig. 3 and Fig. 4, dewatering well 1 includes the second side close to the first side of road and separate road,
Support pile 100 is located at the first side of dewatering well 1.That is, support pile 100 is located at dewatering well 1 close to the side of road, support pile 100
Excavation face can be expanded, reduce influence of the roadside wagon flow to downcomer.In the present embodiment, support pile 100 includes more supportings
Reinforcing bar.More reinforcing bars form a supporting mesh, reduce influence of the dynamic load on road to dewatering well 1.Wherein, support pile 100
Shape matched with the shape of excavation face.For example, when excavation face is arc, the shape of support pile 100 is also arc.In addition,
The distance between second anchor ear 120 and dewatering well 1 are less than the distance between support pile 100 and dewatering well 1.That is, in dewatering well 1
Around two layers of protection of setting, one layer is support pile 100, another layer be the first anchor ear 110 and 120 property of the second anchor ear at frame,
Ensure the stability of dewatering well 1.
In the present embodiment, dewatering well 1 includes multiple downcomers, and downcomer is tongue and groove downcomer.Dewatering well 1 is by multiple
Downcomer is arranged to be formed successively, can facilitate the splicing of downcomer using tongue and groove downcomer, improves the efficiency that dewatering well 1 makes.
Please continue to refer to Fig. 1, in the present embodiment, dewatering well protective device 10 further includes prestress anchorage cable 130, prestressing force
Anchor cable 130 is arranged close to the region of dewatering well 1.Prestress anchorage cable 130 is by drilling through soft stratum or sliding surface, one end
It is anchored in hard rock stratum, then in another free end tensioning, to apply pressure in turn to unstable rock mass to rock stratum
It is anchored.In the present embodiment, 130 one end of prestress anchorage cable is anchored on the outer wall of foundation pit, wherein prestress anchorage cable 130
Ontology be proximate to the region of setting dewatering well 1 and eliminate the shakiness of rock stratum to being anchored to the region near dewatering well 1
It is fixed that dewatering well 1 is impacted.
In addition, in order to ensure the stability of dewatering well 1, it, can be in dewatering well 1 close to road side during slope excavating
Expand excavation face, and expand the branch mask of support pile 100, further decreases influence of the roadside wagon flow to dewatering well 1.In addition,
The bell and spigot depth of 1 pipe of cement of socket joint dewatering well can also be increased, improve the stability of 1 pipe of cement of dewatering well connection.
Above-mentioned dewatering well protective device 10 reduces influence of the dynamic load to dewatering well 1 using support pile 100, using first armful
Hoop 110 and the second anchor ear 120 solve the problems, such as easy fracture at 1 side slope of dewatering well, while being eliminated using prestress anchorage cable 130
Influence of the unstable formation to dewatering well 1.Therefore, using 1 stable connection of dewatering well of above-mentioned dewatering well protective device 10, it is ensured that
Foundation pit structure safety, ensure that effective progress of precipitation process.
Each technical characteristic of embodiment described above can be combined arbitrarily, to keep description succinct, not to above-mentioned reality
It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited
In contradiction, it is all considered to be the range of this specification record.
Above-described embodiments merely represent several embodiments of the utility model, the description thereof is more specific and detailed,
But therefore it can not be interpreted as the limitation to utility model patent range.It should be pointed out that for the common skill of this field
For art personnel, without departing from the concept of the premise utility, various modifications and improvements can be made, these are belonged to
The scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.
Claims (7)
1. a kind of dewatering well protective device, the dewatering well includes the second side close to the first side of road and separate road,
It is characterized in that, the dewatering well protective device includes:
Support pile is located at first side of the dewatering well;
At least two first anchor ears, are sheathed on the top and bottom of the dewatering well respectively;
Multiple second anchor ears, the short transverse along the dewatering well are arranged, and second anchor ear is between first anchor ear
And be arranged along the perimeter of first anchor ear, the both ends of second anchor ear are connect with first anchor ear respectively, and described second
The distance between anchor ear and the dewatering well are less than the distance between the support pile and the dewatering well.
2. dewatering well protective device according to claim 1, which is characterized in that the dewatering well includes multiple downcomers,
The downcomer is tongue and groove downcomer.
3. dewatering well protective device according to claim 1, which is characterized in that first anchor ear is steel loop.
4. dewatering well protective device according to claim 3, which is characterized in that the internal diameter of first anchor ear is equal to described
The outer diameter of dewatering well.
5. dewatering well protective device according to claim 1, which is characterized in that second anchor ear is reinforcing bar.
6. dewatering well protective device according to claim 1, which is characterized in that further include prestress anchorage cable, it is described pre- to answer
Power anchor cable is arranged close to the region of the dewatering well.
7. dewatering well protective device according to claim 1, which is characterized in that the support pile includes more Support Steels
Muscle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721519286.XU CN207700194U (en) | 2017-11-15 | 2017-11-15 | Dewatering well protective device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721519286.XU CN207700194U (en) | 2017-11-15 | 2017-11-15 | Dewatering well protective device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207700194U true CN207700194U (en) | 2018-08-07 |
Family
ID=63022525
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721519286.XU Active CN207700194U (en) | 2017-11-15 | 2017-11-15 | Dewatering well protective device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207700194U (en) |
-
2017
- 2017-11-15 CN CN201721519286.XU patent/CN207700194U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104532868B (en) | High abrupt change shape sloped region bridge anchor pull-type high cap pile group basis construction method | |
CN105155548B (en) | A kind of drag-line double-row pile (wall) supporting construction | |
CN107663865A (en) | A kind of cable-stayed type immersed tube tunnel structure and method | |
CN210529712U (en) | Construction structure for foundation pit crossing underground pipeline area | |
CN107059882A (en) | Arch anchor net and Anchor-Pile Retaining Structure structure | |
CN105002914B (en) | Deformation-controllable prestressed concrete cantilever supporting structure and design and construction method thereof | |
CN109322241A (en) | Trestle work structure and construction method | |
CN208309593U (en) | A kind of steel pipe structure with oblique member | |
CN106368219A (en) | Supporting reinforcing structure of deep foundation pit and construction method | |
CN103866766A (en) | Steel anchor pier for landslide emergency treatment and construction method thereof | |
CN108316328A (en) | A kind of pressurization sinking device and its construction method for open caisson construction | |
CN101691760B (en) | Composite foundation combining anchor rods with excavation and construction method thereof | |
CN107165173A (en) | A kind of foundation pit supporting system and its construction method | |
CN206693242U (en) | A kind of vertical bearing structure of suspension support beam in base pit engineering | |
CN207700194U (en) | Dewatering well protective device | |
CN209923952U (en) | Miniature anti-slide pile of soil slope makes up reinforced structure | |
CN209412681U (en) | Trestle work structure | |
CN206376274U (en) | A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure | |
CN2878518Y (en) | Stress releasing cage | |
CN211472527U (en) | Highway reconstruction and extension engineering high slope construction safety protection structure | |
CN108589738A (en) | Half gravity dam formula foundation pit enclosure structure and its construction method | |
CN210459232U (en) | Soil nailing wall supporting structure for pure sand area | |
CN204401462U (en) | For the support of pier prestressed cap beam with extra length Construction Supporting System in water | |
CN210459233U (en) | Pile anchor foundation pit supporting structure for soft soil area | |
CN211948471U (en) | Steel pipe inclined pile support for foundation pit support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |