- CN207633734U CN207633734U CN201721751810.6U CN201721751810U CN207633734U CN 207633734 U CN207633734 U CN 207633734U CN 201721751810 U CN201721751810 U CN 201721751810U CN 207633734 U CN207633734 U CN 207633734U
- Authority
- CN
- China
- Prior art keywords
- truss
- main
- construction
- steel
- main couple
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 40
- 239000010959 steel Substances 0.000 title claims abstract description 40
- 239000000463 material Substances 0.000 claims description 7
- 229910000851 Alloy steel Inorganic materials 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 37
- 238000009415 formwork Methods 0.000 abstract description 21
- 238000000034 method Methods 0.000 abstract description 10
- 238000012423 maintenance Methods 0.000 abstract description 6
- 238000009434 installation Methods 0.000 abstract description 4
- 238000011065 in-situ storage Methods 0.000 description 2
- 238000012938 design process Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 238000009877 rendering Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种高空悬挑主桁架式钢模架施工平台,属于建筑工程技术领域,该平台模架包括主桁架,次桁架,边缘维护杆件,拼接板和高强螺栓。与现有技术相比,本平台安装方式简单,适用范围广,安全储备高,变形量小,用钢量少,综合成本较低。在施工过程中,主桁架将平台上的绝大部分荷载通过相应节点构造措施传递给混凝土柱,次桁架将少部分荷载通过相应节点构造措施传递给混凝土梁。本平台依托下两层混凝土结构对其进行支撑,承担施工平台传递而来的各种荷载,使支撑结构更加牢固,变形量更小。适用于高空悬挑施工平台的搭建。
The utility model relates to a high-altitude cantilevered main truss type steel formwork construction platform, which belongs to the technical field of construction engineering. The platform formwork includes a main truss, a secondary truss, edge maintenance rods, splicing plates and high-strength bolts. Compared with the prior art, the platform has simple installation method, wide application range, high safety reserve, small deformation, less steel consumption and low overall cost. During the construction process, the main truss transfers most of the load on the platform to the concrete columns through the corresponding joint construction measures, and the secondary truss transfers a small part of the load to the concrete beams through the corresponding joint construction measures. The platform relies on the lower two-story concrete structure to support it, and bears various loads transmitted from the construction platform, making the supporting structure stronger and less deformed. It is suitable for the construction of high-altitude cantilevered construction platforms.
Description
技术领域technical field
本发明属于建筑工程技术领域,涉及一种高空悬挑主桁架式钢模架施工平台。The invention belongs to the technical field of construction engineering and relates to a high-altitude suspended main truss type steel formwork construction platform.
背景技术Background technique
近年来随着我国经济的发展,高层、超高层建筑越来越多,建筑造型也日新月异。很多高层、超高层建筑在设计时为了突出建筑立面造型以及拓展上部使用空间,出现了许多高空悬挑现浇混凝土结构,其中不乏存在一些悬挑跨度很大的结构,这对本来就比较危险的施工过程提出了更高的要求。In recent years, with the development of my country's economy, there are more and more high-rise and super high-rise buildings, and the architectural shapes are also changing with each passing day. Many high-rise and ultra-high-rise buildings have been designed with high-altitude overhanging cast-in-place concrete structures in order to highlight the building's facade shape and expand the upper use space. The construction process puts forward higher requirements.
高空悬挑结构所受荷载较大,对施工时模架支撑平台的承载力、刚度以及稳定性要求很高。加之又是高空作业,这就要求在施工过程中,整个模架支撑平台具有绝对的安全可靠性。此类工程传统的施工方法大致分为以下两种:(1)搭设落地高空满堂支架,即将地下室顶板加固后,搭设满堂扣件式钢管模板支撑架至施工所需高度。对于悬挑结构所在高度较高的工程来说,此种方法所需材料用量极大,施工拆卸复杂,并且稳定性难以保证,因此不适用于高空悬挑结构。(2)由悬挑型钢梁和斜撑组成的悬挑支撑体系。此方法虽然较上一种方法有很大改进,但只适合悬挑长度较小的结构,对于悬挑较长,自重较大的结构同样不适用。The high-altitude cantilevered structure is subject to a large load, which requires high bearing capacity, stiffness and stability of the formwork support platform during construction. In addition, it is a high-altitude operation, which requires that the entire formwork support platform has absolute safety and reliability during the construction process. The traditional construction methods of this type of project are roughly divided into the following two types: (1) Set up the floor-to-ceiling high-altitude full hall support, that is, after the basement roof is reinforced, set up the full hall fastener type steel pipe formwork support frame to the height required for construction. For projects with high cantilevered structures, this method requires a large amount of materials, complex construction and disassembly, and difficult to ensure stability, so it is not suitable for high-altitude cantilevered structures. (2) A cantilevered support system consisting of cantilevered steel beams and diagonal braces. Although this method is greatly improved compared with the previous method, it is only suitable for structures with small overhangs, and it is also not suitable for structures with long overhangs and large self-weight.
基于此,本发明提出了一种高空悬挑主桁架式钢模架施工平台,具有承载力高,刚度大,安装拆卸方便,适用范围广,安全储备高,用钢量少,综合成本较低的优点,特别适用于角部存在高空悬挑结构的高层建筑。Based on this, the present invention proposes a high-altitude cantilever main truss type steel formwork construction platform, which has high bearing capacity, high rigidity, convenient installation and disassembly, wide application range, high safety reserve, less steel consumption, and low overall cost It is especially suitable for high-rise buildings with high-altitude overhanging structures at the corners.
发明内容Contents of the invention
本发明提供一种高空悬挑主桁架式钢模架施工平台,以解决在高层、超高层建筑中,搭设长悬挑现浇混凝土结构施工平台的问题。The invention provides a high-altitude cantilever main truss type steel formwork construction platform to solve the problem of erecting a long cantilever cast-in-situ concrete structure construction platform in high-rise and super high-rise buildings.
为实现上述目的,本发明采用如下技术方案:一种高空悬挑主桁架式钢模架施工平台,该平台包括:主桁架(1)、次桁架(2)、边缘维护杆件(3)、拼接板(4)和高强螺栓(5)。In order to achieve the above object, the present invention adopts the following technical scheme: a high-altitude cantilevered main truss type steel formwork construction platform, the platform includes: main truss (1), secondary truss (2), edge maintenance rods (3), splice plate (4) and high-strength bolt (5).
所述的主桁架为两榀交叉的主桁架,材料选用强度为Q345的H型钢,焊接或轧制而成,截面尺寸应由技术人员根据需要计算确定。每一榀桁架包括上弦杆、下弦杆、竖腹杆和斜腹杆,桁架高度为施工中高层混凝土结构的层高,弦杆与斜腹杆、相邻腹杆之间角度保持在大约45度,使桁架受力更加合理。同时在主桁架腹杆设计中,应尽量使较多的腹杆处于受拉状态,避免产生钢结构的稳定问题。The main truss described above is a main truss with two intersecting trusses, and the material is H-shaped steel with a strength of Q345, which is welded or rolled, and the cross-sectional size should be calculated and determined by technical personnel according to needs. Each truss includes upper chords, lower chords, vertical webs and diagonal webs. The height of the truss is the story height of the high-rise concrete structure in construction. The angle between the chords, diagonal webs and adjacent webs is kept at about 45 degrees , so that the truss force is more reasonable. At the same time, in the design of the web members of the main truss, as many web members as possible should be in tension to avoid the stability of the steel structure.
所述主桁架为整个模架体系的主要受力构件,不仅承担自身以及自身上部的荷载,同时承担周围次桁架传递而来的荷载,并将荷载传递给混凝土结构。The main truss is the main force-bearing member of the entire formwork system, which not only bears the load of itself and its upper part, but also bears the load transmitted by the surrounding secondary truss, and transmits the load to the concrete structure.
所述的次桁架材料选用强度为Q345的H型钢,焊接或轧制而成,截面尺寸应由技术人员根据需要计算确定。次桁架同样包括上弦杆、下弦杆、竖腹杆和斜撑。在交叉主桁架内部的次桁架称为井字梁桁架,其弦杆一端和主桁架相连,另一端通过相应节点构造措施与混凝土结构梁相连。井字梁桁架所受荷载一部分传递给混凝土结构梁,另一部分传递给主桁架。在交叉主桁架外部的次桁架,一端与主桁架相连,另一端类似于纯悬挑,将其上荷载传递给主桁架。The material of the secondary truss is made of H-shaped steel with a strength of Q345, which is welded or rolled, and the cross-sectional size should be calculated and determined by technical personnel according to needs. Secondary trusses also include top chords, bottom chords, vertical webs and braces. The secondary truss inside the cross main truss is called the well-shaped beam truss, one end of the chord is connected to the main truss, and the other end is connected to the concrete structural beam through corresponding node construction measures. Part of the load on the well-shaped beam truss is transferred to the concrete structural beam, and the other part is transferred to the main truss. The secondary truss outside the cross main truss is connected to the main truss at one end, and the other end is similar to a pure overhang, which transmits the load on it to the main truss.
所述的边缘维护杆件为H型钢,焊接或轧制而成,截面尺寸应由技术人员根据需要和构造要求确定。边缘维护杆件设置在整个桁架的最外边缘,主要起联系和维护作用,通常受力较小,为了减轻自重以及节约钢材,其截面通常小于主桁架和次桁架的杆件。The edge maintenance bar is made of H-shaped steel, which is welded or rolled, and the cross-sectional size should be determined by technical personnel according to needs and structural requirements. Edge maintenance rods are set on the outermost edge of the entire truss, mainly for connection and maintenance, and usually bear less force. In order to reduce self-weight and save steel, its cross-section is usually smaller than the rods of the main truss and secondary truss.
所述的拼接板和高强螺栓是整个桁架的连接构件,拼接板为矩形钢板,包括上下翼缘的拼接板和腹板拼接板;高强螺栓材料应为45#钢或合金钢,强度级别应为10.9级或更高,其数量、位置、直径和长度应通过计算和构造要求来确定。The splicing plates and high-strength bolts are the connecting members of the entire truss, and the splicing plates are rectangular steel plates, including the splicing plates of the upper and lower flanges and the web splicing plates; the material of the high-strength bolts should be 45# steel or alloy steel, and the strength level should be Class 10.9 or higher, the number, location, diameter and length shall be determined by calculation and construction requirements.
两个交叉杆件连接时,通常是主要受力杆件连续,相对次要杆件断开。次要杆件的一少部分在工厂预制时与主要杆件焊接,剩下的部分在吊装时通过拼接板和高强螺栓与焊接部分连接。When two cross members are connected, the main force member is usually continuous and the relative secondary member is disconnected. A small part of the secondary member is welded with the main member during factory prefabrication, and the remaining part is connected with the welded part through splice plates and high-strength bolts during hoisting.
与现有技术相比,本发明一种高空悬挑主桁架式钢模架施工平台,适用于为高空角部存在悬挑的现浇混凝土结构搭设施工平台,具有以下优势:Compared with the prior art, the present invention provides a high-altitude cantilevered main truss-type steel formwork construction platform, which is suitable for erecting construction platforms for cast-in-situ concrete structures with overhangs at high-altitude corners, and has the following advantages:
(1)承载力大,安全储备高。通过高度为层高的空间钢模架,使整个模架成为一个空间受力体系而非单个杆件受力,大大提高了施工支撑平台的承载力。(1) Large bearing capacity and high safety reserve. Through the space steel formwork with the height of the storey, the entire formwork becomes a space stress system instead of a single rod, which greatly improves the bearing capacity of the construction support platform.
(2)刚度大,变形量小。整个模架体系在受力过程中各杆件相互联系,协调变形,加之又有许多空间竖腹杆和斜腹杆的存在,相比于单独杆件来说,大大提高了整个施工支撑平台的刚度,从而将其变形量降低到最小,从而最大限度的保证了施工的精度要求。(2) High rigidity and small deformation. During the stress process of the entire formwork system, the rods are connected with each other and deformed in coordination. In addition, there are many space vertical webs and oblique webs. Compared with individual rods, the strength of the entire construction support platform is greatly improved. Rigidity, thereby reducing its deformation to a minimum, thereby ensuring the accuracy requirements of construction to the greatest extent.
(3)安装拆卸方便。整个桁架采用工厂预制、现场拼装的方式,各桁架杆之间采用高强螺栓的连接方式,避免高空湿作业,确保连接质量。(3) Easy installation and disassembly. The entire truss is prefabricated in the factory and assembled on site, and the connection method of high-strength bolts is used between the truss rods to avoid high-altitude wet operation and ensure the connection quality.
附图说明Description of drawings
图1是一种高空悬挑主桁架式钢模架施工平台的立体效果图。Fig. 1 is a three-dimensional rendering of a main truss-type steel formwork construction platform cantilevered high above the ground.
图2是一种高空悬挑主桁架式钢模架施工平台中主桁架立面图。Fig. 2 is an elevation view of the main truss in a high-altitude suspended main truss type steel formwork construction platform.
图3是一种高空悬挑主桁架式钢模架施工平台中桁架两杆件拼装节点立体图。Fig. 3 is a three-dimensional view of the assembling joints of the two bars of the truss in a high-altitude cantilevered main truss type steel formwork construction platform.
具体实施方式Detailed ways
下面结合附图和实例,对本发明的具体实施方式作进一步详细描述。以下实例用于说明本发明,但不用来限制本发明的范围。The specific implementation manners of the present invention will be further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
本实例中,所有杆件的截面尺寸、拼接板尺寸、高强螺栓的型号需要技术人员根据实际工程通过计算和构造要求确定。另外在设计与安装过程中,保证平台桁架上弦杆上表面在相同水平高度,有利于后期施工的进行。In this example, the cross-sectional size of all rods, the size of the splice plate, and the type of high-strength bolts need to be determined by technical personnel through calculation and structural requirements based on actual engineering. In addition, during the design and installation process, ensure that the upper surface of the upper chord of the platform truss is at the same level, which is conducive to the later construction.
如图1-3所示,一种高空悬挑主桁架式钢模架施工平台,其施工方法如下:As shown in Figure 1-3, a high-altitude suspension main truss type steel formwork construction platform, the construction method is as follows:
第一步,当混凝土结构施工到相应楼层时,将其中一榀主桁架吊至所需高度,通过相应的节点连接措施与混凝土柱相连。例如,需要浇筑的高空大悬挑混凝土结构在第n层楼板所在高度,那么,整个施工平台需要搭建在第n-1层的整个空间内。即空间钢模架的上弦杆与第n-1层楼板高度处的混凝土柱相锚固连接,下弦杆与第n-2层楼板高度处的混凝土柱相锚固连接,整个模架高度为层高。In the first step, when the concrete structure is constructed to the corresponding floor, one of the main trusses is hoisted to the required height, and connected to the concrete column through corresponding node connection measures. For example, if the high-altitude large overhanging concrete structure to be poured is at the height of the floor slab of the nth floor, then the entire construction platform needs to be built in the entire space of the n-1st floor. That is, the upper chord of the space steel formwork is anchored to the concrete column at the height of the n-1 floor, and the lower chord is anchored to the concrete column at the height of the n-2 floor. The height of the entire formwork is the floor height.
第二步,将另一榀主桁架分段吊至所需高度处,通过拼接板、高强螺栓以及预留的孔,将两榀主桁架螺栓连接,保证有足够的连接强度。The second step is to hoist another main truss to the required height in sections, and connect the two main trusses with bolts through splicing plates, high-strength bolts and reserved holes to ensure sufficient connection strength.
第三步,两榀主桁架吊装完毕后,再分段将次桁架吊装。次桁架与主桁架、次桁架与次桁架之间同样用高强螺栓连接,并确保连接强度。部分次桁架需要通过相应的节点构造措施与混凝土梁锚固连接。In the third step, after the hoisting of the two main trusses is completed, the sub-trusses are hoisted in sections. The secondary truss and the main truss, and the secondary truss and the secondary truss are also connected with high-strength bolts to ensure the connection strength. Some secondary trusses need to be anchored to concrete beams through corresponding joint construction measures.
第四步,主、次桁架吊装完毕后,将边缘维护杆件吊至所需高度,与主桁架或次桁架之间通过高强螺栓拼接。In the fourth step, after the main and secondary trusses are hoisted, the edge maintenance rods are hoisted to the required height, and are spliced with the main truss or secondary truss by high-strength bolts.
第五步,整个空间钢模架吊装完毕后,用仪器检测安装精度是否达到要求,然后在桁架上弦杆上满铺工字钢或钢板等,找出一个完整的平面,作为整个施工平台的底面。Step 5: After the entire space steel formwork is hoisted, use an instrument to check whether the installation accuracy meets the requirements, and then spread I-beams or steel plates on the upper chord of the truss to find a complete plane as the bottom surface of the entire construction platform .
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201721751810.6U CN207633734U (en) | 2017-12-15 | 2017-12-15 | A kind of high-altitude overhanging main truss posture steel mould base operation platform |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201721751810.6U CN207633734U (en) | 2017-12-15 | 2017-12-15 | A kind of high-altitude overhanging main truss posture steel mould base operation platform |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN207633734U true CN207633734U (en) | 2018-07-20 |
Family
ID=62863740
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201721751810.6U Expired - Fee Related CN207633734U (en) | 2017-12-15 | 2017-12-15 | A kind of high-altitude overhanging main truss posture steel mould base operation platform |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN207633734U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108222480A (en) * | 2017-12-15 | 2018-06-29 | 北京工业大学 | A kind of high-altitude overhanging main truss posture steel mould base construction platform |
| CN111677259A (en) * | 2020-06-11 | 2020-09-18 | 北京城建十六建筑工程有限责任公司 | High-rise Bailey truss cantilever construction method |
| CN114809699A (en) * | 2022-05-11 | 2022-07-29 | 北京市第三建筑工程有限公司 | Construction method of assembly type outer facade enclosure system for reconstruction of upper part of super high-rise building |
-
2017
- 2017-12-15 CN CN201721751810.6U patent/CN207633734U/en not_active Expired - Fee Related
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108222480A (en) * | 2017-12-15 | 2018-06-29 | 北京工业大学 | A kind of high-altitude overhanging main truss posture steel mould base construction platform |
| CN108222480B (en) * | 2017-12-15 | 2024-02-02 | 北京工业大学 | High-altitude cantilever main truss type steel formwork construction platform |
| CN111677259A (en) * | 2020-06-11 | 2020-09-18 | 北京城建十六建筑工程有限责任公司 | High-rise Bailey truss cantilever construction method |
| CN111677259B (en) * | 2020-06-11 | 2021-09-28 | 北京城建十六建筑工程有限责任公司 | High-rise Bailey truss cantilever construction method |
| CN114809699A (en) * | 2022-05-11 | 2022-07-29 | 北京市第三建筑工程有限公司 | Construction method of assembly type outer facade enclosure system for reconstruction of upper part of super high-rise building |
| CN114809699B (en) * | 2022-05-11 | 2023-11-17 | 北京市第三建筑工程有限公司 | Construction method of assembled outer elevation enclosure system for transformation of upper part of super high-rise building |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106869316A (en) | The beam column edge of a wing is the group frame system and construction method of concrete filled steel tube | |
| CN108222480B (en) | High-altitude cantilever main truss type steel formwork construction platform | |
| CN106759909A (en) | Bearing structure system and its construction method are hung up under one kind | |
| CN108775084B (en) | Steel-concrete composite prefabricated beam and prefabricated column connection structure and construction method | |
| CN114134995A (en) | Frame core tube rigid-connection floor beam structure system and construction method | |
| CN207633734U (en) | A kind of high-altitude overhanging main truss posture steel mould base operation platform | |
| CN112575948A (en) | Truss string beam and cantilever truss combined roof truss and construction method | |
| CN102140850B (en) | Frame with floors of composite grid structure and construction method thereof | |
| CN106869317A (en) | The beam column edge of a wing is the group frame system and construction method of concrete-filled rectangular steel tube | |
| CN211949511U (en) | A high-altitude large cantilever cast-in-situ structure spanning composite load-bearing steel platform | |
| CN106545115A (en) | Assembled steel Combined concrete superstructure and its construction method | |
| CN109653517B (en) | Multidirectional unloading system and construction method for assembling steel corridor by using same | |
| CN209457263U (en) | An assembled steel structure beam-slab connection structure | |
| CN111979891A (en) | A kind of semi-penetrating rectangular steel tube concrete composite truss bridge and construction method | |
| CN201915631U (en) | High-altitude long-span reinforced concrete corridor construction supporting structure | |
| CN109424072A (en) | The connecting node and construction method of spacer bar concrete column on a kind of girder steel | |
| CN216007260U (en) | Rigid connection joint of steel beam and concrete column | |
| CN213204915U (en) | Overweight overhanging suspended component supporting system of super high-rise residential conversion layer | |
| CN104032855A (en) | Assembly-type cross-shaped mixed coupled wall and construction method thereof | |
| CN218911772U (en) | Combined node of vertical transverse bearing members of assembled building wall, beam and plate | |
| CN105155866A (en) | Separable sheath floor-adding structure of masonry buildings and floor-adding method thereof | |
| CN117071898A (en) | A construction method that combines continuous lifting and scattered assembly of high-altitude multi-story structures | |
| CN112095798B (en) | Super high-rise double-layer super large cantilever steel structure | |
| CN111321880B (en) | A high-altitude large cantilever cast-in-place structure spanning space combined load-bearing steel platform | |
| CN115749258A (en) | High-altitude overhanging roof formwork supporting system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180720 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |