CN207554030U - A kind of frac-sand jet and fracturing string - Google Patents

A kind of frac-sand jet and fracturing string Download PDF

Info

Publication number
CN207554030U
CN207554030U CN201721458513.2U CN201721458513U CN207554030U CN 207554030 U CN207554030 U CN 207554030U CN 201721458513 U CN201721458513 U CN 201721458513U CN 207554030 U CN207554030 U CN 207554030U
Authority
CN
China
Prior art keywords
hole
sleeve
wear
main body
resistant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721458513.2U
Other languages
Chinese (zh)
Inventor
徐新华
唐海兵
常晓伟
邢希春
李传利
吕进军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DOWNHOLE SPECIAL OPERATION Co OF SINOPEC ZHONGYUAN ENGINEERING Ltd
Sinopec Oilfield Service Corp
Sinopec Zhongyuan Petroleum Engineering Co Ltd
Original Assignee
Down-Hole Job That Requires Special Skills Co Of Central Plains Petroleum Works Co Ltd Of China Petrochemical Industry
Sinopec Oilfield Service Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Down-Hole Job That Requires Special Skills Co Of Central Plains Petroleum Works Co Ltd Of China Petrochemical Industry, Sinopec Oilfield Service Corp filed Critical Down-Hole Job That Requires Special Skills Co Of Central Plains Petroleum Works Co Ltd Of China Petrochemical Industry
Priority to CN201721458513.2U priority Critical patent/CN207554030U/en
Application granted granted Critical
Publication of CN207554030U publication Critical patent/CN207554030U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

本实用新型公开了一种压裂喷砂器及压裂管柱,压裂喷砂器包括:上部连接套,上部连接套的顶端能够连接油管,其内部开设第一通孔;主体,其顶端与上部连接套的底端连接,其底端能够与封隔器连接,且主体的内部开设第二通孔,第一通孔和第二通孔导通,主体的侧壁上开设有喷砂通孔;耐磨套,耐磨套套接在主体的内壁,且耐磨套上开有与喷砂通孔导通的耐磨孔;滑套,滑套连接在上部连接套的内壁上,且在钢球的作用下能够与上部连接套下滑分离露出喷砂通孔和耐磨孔。由于耐磨孔具有耐磨性,即使因地面原因中途停泵,依然能够提供封隔器坐封节流压力,保持封隔器的坐封;且耐磨孔控制了携砂液的喷射流道,使喷砂通孔在一定范围内扩张,防止主体发生断裂。

The utility model discloses a fracturing sandblasting device and a fracturing pipe column. The fracturing sandblasting device comprises: an upper connection sleeve, the top of which can be connected to an oil pipe, and a first through hole is opened inside; a main body, the top end of which is It is connected with the bottom end of the upper connection sleeve, and its bottom end can be connected with the packer, and a second through hole is opened inside the main body, the first through hole and the second through hole are connected, and a sandblasting hole is opened on the side wall of the main body. Through hole; wear-resistant sleeve, the wear-resistant sleeve is sleeved on the inner wall of the main body, and the wear-resistant sleeve is provided with a wear-resistant hole connected with the sandblasting through hole; the sliding sleeve is connected to the inner wall of the upper connecting sleeve, and Under the action of the steel ball, it can slide down and separate from the upper connection sleeve to expose the sandblasting through hole and the wear-resistant hole. Due to the wear resistance of the wear-resistant hole, even if the pump is stopped halfway due to ground reasons, it can still provide the packer setting and throttling pressure to maintain the setting of the packer; and the wear-resistant hole controls the injection flow path of the sand-carrying fluid , so that the sandblasting through hole expands within a certain range to prevent the main body from breaking.

Description

一种压裂喷砂器及压裂管柱A fracturing sand blaster and a fracturing string

技术领域technical field

本实用新型涉及油气勘测装置技术领域,尤其涉及一种压裂喷砂器及压裂管柱。The utility model relates to the technical field of oil and gas surveying devices, in particular to a fracturing sand blaster and a fracturing pipe string.

背景技术Background technique

目前,国内油气田多采用以封隔器为主体的多级压裂管柱。该管柱使用内外压差的方式完成封隔器坐封,并对多个地层进行分隔,从而实现逐级压裂。At present, domestic oil and gas fields mostly use multi-stage fracturing strings with packers as the main body. The string uses the internal and external pressure difference to complete the packer setting and separate multiple formations, thereby achieving stage-by-stage fracturing.

喷砂器安装在封隔器上部,能够通过钢球控制换层并提供各级封隔器坐封所需的压差。现有技术中,在喷砂器本体侧壁周向均布固定孔径的通孔,滑套通过剪钉固定于喷砂器内壁进行油套封隔,钢球后滑套下行打开喷砂通孔进行换层,同时喷砂通孔产生节流压差以保持封隔器的坐封状态。然而,在高速携砂液磨蚀下喷砂通孔时会产生非规则扩径、断裂,造成工程事故;此外,由于喷砂通孔扩径,一旦中途停泵,封隔器无法重复坐封,造成压裂失败。The sand blaster is installed on the upper part of the packer, which can control layer change through steel balls and provide the pressure difference required for the setting of packers at all levels. In the prior art, through-holes with fixed apertures are evenly distributed on the side wall of the blaster body in the circumferential direction, and the sliding sleeve is fixed to the inner wall of the blaster by shear nails to seal off the oil sleeve. At the same time, sand blasting through-holes creates a throttling pressure difference to maintain the setting state of the packer. However, when blasting through-holes under the abrasiveness of high-speed sand-carrying fluid, irregular diameter expansion and fractures will occur, resulting in engineering accidents; in addition, due to the expansion of sandblasting through-holes, once the pump is stopped midway, the packer cannot be re-set. cause fracturing failure.

因此,如何降低喷砂器发生断裂及中途停泵造成封隔器无法坐封的概率是本领域技术人员亟待解决的技术问题。Therefore, how to reduce the probability of breakage of the sand blaster and the failure of the packer to set due to pump stop midway is a technical problem to be solved urgently by those skilled in the art.

实用新型内容Utility model content

本实用新型的第一个目的是提供一种压裂喷砂器,以降低喷砂器发生断裂及中途停泵造成封隔器无法坐封的概率。The first purpose of the present utility model is to provide a fracturing sandblasting device to reduce the probability that the sandblasting device will break and the packer cannot be set due to pump stop midway.

本实用新型的第二个目的是提供一种压裂管柱。The second purpose of the utility model is to provide a fracturing string.

为了实现上述目的,本实用新型提供了如下方案:In order to achieve the above object, the utility model provides the following scheme:

一种压裂喷砂器,包括:A frac blaster comprising:

上部连接套,所述上部连接套的顶端能够连接油管,所述上部连接套的内部开设第一通孔;The upper connecting sleeve, the top end of the upper connecting sleeve can be connected to the oil pipe, and the inside of the upper connecting sleeve is provided with a first through hole;

主体,所述主体的顶端与所述上部连接套的底端连接,所述主体的底端能够与封隔器连接,且所述主体的内部开设第二通孔,所述第一通孔和所述第二通孔导通,所述主体的侧壁上开设有喷砂通孔;The main body, the top end of the main body is connected to the bottom end of the upper connecting sleeve, the bottom end of the main body can be connected with the packer, and a second through hole is opened inside the main body, and the first through hole and the The second through hole is connected, and a sandblasting through hole is opened on the side wall of the main body;

耐磨套,所述耐磨套套接在所述主体的内壁,且所述耐磨套上开有与所述喷砂通孔导通的耐磨孔;A wear-resistant sleeve, the wear-resistant sleeve is sleeved on the inner wall of the main body, and a wear-resistant hole connected to the sandblasting through hole is opened on the wear-resistant sleeve;

滑套,所述滑套连接在所述上部连接套的内壁上,且在钢球的作用下能够与所述上部连接套下滑分离露出所述喷砂通孔和所述耐磨孔。A sliding sleeve, the sliding sleeve is connected to the inner wall of the upper connecting sleeve, and under the action of the steel ball, can slide down and separate from the upper connecting sleeve to expose the sandblasting through hole and the wear-resistant hole.

优选地,在上述压裂喷砂器中,所述耐磨套为硬质合金套。Preferably, in the above-mentioned fracturing sand blaster, the wear-resistant sleeve is a hard alloy sleeve.

优选地,在上述压裂喷砂器中,所述喷砂通孔包括渐扩孔和等直径通孔;Preferably, in the above-mentioned fracturing sand blaster, the sand blasting through holes include expanding holes and through holes with equal diameters;

所述等直径通孔的一端与所述耐磨孔的一端导通,所述等直径通孔的另一端与所述渐扩孔的较小开口端导通。One end of the equal-diameter through hole is connected to one end of the wear-resistant hole, and the other end of the equal-diameter through hole is connected to the smaller opening end of the gradually expanding hole.

优选地,在上述压裂喷砂器中,所述喷砂通孔的轴心线和所述耐磨孔的轴心线重合。Preferably, in the above-mentioned fracturing sand blaster, the axis line of the sandblasting through hole coincides with the axis line of the wear-resistant hole.

优选地,在上述压裂喷砂器中,所述主体与所述上部连接套通过螺纹连接;Preferably, in the above-mentioned fracturing sand blaster, the main body and the upper connecting sleeve are connected by threads;

所述滑套通过剪切销钉连接在所述上部连接套的内壁上。The sliding sleeve is connected to the inner wall of the upper connecting sleeve through shear pins.

优选地,在上述压裂喷砂器中,所述主体的内壁设置有凸台,所述耐磨套的顶端与所述上部连接套的底端抵接;Preferably, in the above-mentioned fracturing sand blaster, the inner wall of the main body is provided with a boss, and the top end of the wear-resistant sleeve abuts against the bottom end of the upper connecting sleeve;

所述耐磨套的底端与所述凸台的顶端抵接。The bottom end of the wear-resistant sleeve abuts against the top end of the boss.

优选地,在上述压裂喷砂器中,所述滑套的外侧壁上开设有第一密封槽和第二密封槽;Preferably, in the above-mentioned fracturing sand blaster, a first sealing groove and a second sealing groove are opened on the outer wall of the sliding sleeve;

所述第一密封槽内安装有第一密封圈,所述第一密封圈与所述上部连接套的内壁间隙配合;A first sealing ring is installed in the first sealing groove, and the first sealing ring is in clearance fit with the inner wall of the upper connecting sleeve;

所述第二密封套内安装有第二密封圈,所述第二密封圈与所述主体的内壁间隙配合。A second sealing ring is installed in the second sealing sleeve, and the second sealing ring is in clearance fit with the inner wall of the main body.

优选地,在上述压裂喷砂器中,所述喷砂通孔的横截面为矩形;Preferably, in the above-mentioned fracturing sand blaster, the cross-section of the sand blasting hole is rectangular;

且所述喷砂通孔的个数为多个,均布在所述主体的内壁上。In addition, there are multiple sandblasting through holes, which are evenly distributed on the inner wall of the main body.

优选地,在上述压裂喷砂器中,所述滑套的顶部开设有与所述钢球密封的锥形口。Preferably, in the above-mentioned fracturing sand blaster, the top of the sliding sleeve is provided with a tapered opening that is sealed with the steel ball.

从上述的技术方案可以看出,本实用新型提供的压裂喷砂器,组装时,将滑套套装在上部连接套的内壁,将耐磨套套接在主体的内壁,然后,将上部连接套和主体连接。使用时,将上部连接套的顶端连接油管,将主体的底端连接封隔器,在进行油气井压裂时,向压裂喷砂器投进钢球后,钢球沿着第一通孔和第二通孔到达滑套位置处,将滑套打落,露出耐磨孔和喷砂通孔,对该喷砂器对应地层进行压裂改造。随着后续施工排量的增加,由于耐磨孔具有耐磨性,在大砂量下孔径仅发生微小变化,即使因地面原因中途停泵,依然能够提供封隔器坐封节流压力,保持封隔器的坐封;另一方面,硬质合金套的耐磨孔控制了携砂液的喷射流道,使喷砂通孔在一定范围内扩张,防止主体发生断裂,提高了工具的安全性。即本实用新型提供的压裂喷砂器,能够降低喷砂器发生断裂及中途停泵造成封隔器无法坐封的概率。It can be seen from the above-mentioned technical scheme that when assembling the fracturing sand blaster provided by the utility model, the sliding sleeve is set on the inner wall of the upper connecting sleeve, the wear-resistant sleeve is sleeved on the inner wall of the main body, and then the upper connecting sleeve Connect with the main body. When in use, connect the top end of the upper connecting sleeve to the oil pipe, and connect the bottom end of the main body to the packer. When fracturing oil and gas wells, after putting steel balls into the fracturing sand blaster, the steel balls will go along the first through hole. and the second through hole reach the position of the sliding sleeve, the sliding sleeve is knocked down to expose the wear-resistant hole and the sandblasting through hole, and the formation corresponding to the sandblasting device is fractured. With the increase of subsequent construction displacement, due to the wear resistance of the wear-resistant hole, the hole diameter will only change slightly under the large sand volume. Even if the pump is stopped midway due to ground reasons, it can still provide the packer setting and throttle pressure The setting of the packer; on the other hand, the wear-resistant hole of the cemented carbide sleeve controls the injection flow channel of the sand-carrying liquid, so that the sand blasting hole can expand within a certain range, preventing the main body from breaking, and improving the safety of the tool sex. That is, the fracturing sand blaster provided by the utility model can reduce the probability that the sand blaster breaks and the probability that the packer cannot be set due to the stop of the pump midway.

为了实现上述第二个目的,本实用新型提供了如下方案:In order to achieve the above-mentioned second purpose, the utility model provides the following scheme:

一种压裂管柱,包括如上述任意一项所述的压裂喷砂器。A fracturing string, comprising the fracturing sand blaster described in any one of the above.

由于本实用新型公开的压裂管柱包括上述任意一项中的压裂喷砂器,因此,压裂喷砂器所具有的有益效果均是本实用新型公开的压裂管柱所包含的。Since the fracturing string disclosed in the utility model includes any one of the fracturing sand blasters mentioned above, the beneficial effects of the fracturing sand blaster are included in the fracturing string disclosed in the utility model.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are only some embodiments of the utility model, and those skilled in the art can also obtain other drawings based on these drawings without creative work.

图1为本实用新型提供的压裂喷砂器的半剖结构示意图;Fig. 1 is the schematic diagram of the half-section structure of the fracturing sand blaster provided by the utility model;

图2为本实用新型提供的压裂管柱的结构示意图。Fig. 2 is a structural schematic diagram of the fracturing string provided by the utility model.

其中,图1-图2中:Among them, in Figure 1-Figure 2:

上部连接套1、第一通孔101、主体2、第二通孔201、喷砂通孔202、耐磨套3、耐磨孔301、滑套4、渐扩孔2021、等直径通孔2022、剪切销钉5、凸台203、第一密封圈6、第二密封圈7、锥形口401、封隔器8、压裂喷砂器9、水力锚10、下直喷11、第一层地层12、第二层地层13、第三层地层14。Upper connecting sleeve 1, first through hole 101, main body 2, second through hole 201, sandblasting through hole 202, wear-resistant sleeve 3, wear-resistant hole 301, sliding sleeve 4, gradually expanding hole 2021, equal diameter through hole 2022 , shear pin 5, boss 203, first sealing ring 6, second sealing ring 7, tapered port 401, packer 8, fracturing sand blaster 9, hydraulic anchor 10, lower direct injection 11, first Layer 12, second layer 13, third layer 14.

具体实施方式Detailed ways

为了使本领域的技术人员更好的理解本实用新型的技术方案,下面结合附图和具体实施方式对本实用新型作进一步的详细说明。In order to enable those skilled in the art to better understand the technical solution of the utility model, the utility model will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

实施例一Embodiment one

请参阅图1,本实用新型公开了一种压裂喷砂器,其中,压裂喷砂器包括上部连接套1、主体2、耐磨套3和滑套4。Please refer to FIG. 1 , the utility model discloses a fracturing sand blaster, wherein the fracturing sand blaster includes an upper connecting sleeve 1 , a main body 2 , a wear-resistant sleeve 3 and a sliding sleeve 4 .

上部连接套1的顶端为连接接头,能够连接油管。上部连接套1的内部开设第一通孔101,即上部连接套1为空心管状体。The top of the upper connecting sleeve 1 is a connecting joint, which can be connected to an oil pipe. A first through hole 101 is opened inside the upper connecting sleeve 1 , that is, the upper connecting sleeve 1 is a hollow tubular body.

主体2的顶端与上部连接套1的底端连接,主体2的底端能够与封隔器连接,且主体2的内部开设第二通孔201,第一通孔101和第二通孔201导通,主体2的侧壁上开设有喷砂通孔202。本实施例中,喷砂通孔202的个数为2个-4个。The top end of the main body 2 is connected to the bottom end of the upper connection sleeve 1, the bottom end of the main body 2 can be connected with the packer, and the inside of the main body 2 is provided with a second through hole 201, and the first through hole 101 and the second through hole 201 guide Through, the side wall of the main body 2 is provided with a sandblasting through hole 202 . In this embodiment, the number of sandblasting through holes 202 is 2-4.

耐磨套3套接在主体2的内壁,且耐磨套3上开有与喷砂通孔202导通的耐磨孔301,具体地,耐磨孔301和喷砂通孔202的位置一致。The wear-resistant sleeve 3 is socketed on the inner wall of the main body 2, and the wear-resistant sleeve 3 is provided with a wear-resistant hole 301 leading to the sandblasting through hole 202. Specifically, the wear-resistant hole 301 is in the same position as the sandblasting through hole 202 .

滑套4连接在上部连接套1的内壁上,且在钢球的作用下能够与上部连接套1下滑分离露出喷砂通孔202和耐磨孔301。The sliding sleeve 4 is connected to the inner wall of the upper connecting sleeve 1 , and can slide down and separate from the upper connecting sleeve 1 under the action of the steel ball to expose the sandblasting through hole 202 and the wear-resistant hole 301 .

本实用新型提供的压裂喷砂器,组装时,将滑套4套装在上部连接套1的内壁,将耐磨套3套接在主体2的内壁,然后,将上部连接套1和主体2连接。使用时,将上部连接套1的顶端连接油管,将主体2的底端连接封隔器,在进行油气井压裂时,向压裂喷砂器投进钢球后,钢球将滑套4打落,露出耐磨孔301和喷砂通孔202,对该喷砂器对应地层进行压裂改造。随着后续施工排量的增加,由于耐磨孔301具有耐磨性,在大砂量下孔径仅发生微小变化,即使因地面原因中途停泵,依然能够提供封隔器坐封节流压力,保持封隔器的坐封;另一方面,硬质合金套的耐磨孔301控制了携砂液的喷射流道,使喷砂通孔202在一定范围内扩张,防止主体2发生断裂,提高了工具的安全性。即本实用新型提供的压裂喷砂器,能够降低喷砂器发生断裂及中途停泵造成封隔器无法坐封的概率。The fracturing sand blaster provided by the utility model, when assembling, the sliding sleeve 4 is set on the inner wall of the upper connecting sleeve 1, the wear-resistant sleeve 3 is sleeved on the inner wall of the main body 2, and then the upper connecting sleeve 1 and the main body 2 connect. When in use, the top end of the upper connection sleeve 1 is connected to the oil pipe, and the bottom end of the main body 2 is connected to the packer. When fracturing oil and gas wells, steel balls are thrown into the fracturing sand blaster, and the steel balls will press the sliding sleeve 4 Knock down to expose the wear-resistant hole 301 and the sandblasting through hole 202, and carry out fracturing reconstruction for the formation corresponding to the sandblasting device. With the increase of subsequent construction displacement, due to the wear resistance of the wear-resistant hole 301, the hole diameter only slightly changes under the large sand volume. Even if the pump is stopped midway due to ground reasons, it can still provide the packer setting and throttle pressure. Keep the set seal of the packer; on the other hand, the wear-resistant hole 301 of the cemented carbide sleeve controls the injection flow channel of the sand-carrying liquid, so that the sandblasting through hole 202 can expand within a certain range, preventing the main body 2 from breaking and improving tool safety. That is, the fracturing sand blaster provided by the utility model can reduce the probability that the sand blaster breaks and the probability that the packer cannot be set due to the stop of the pump midway.

实施例二Embodiment two

在本实用新型提供又一实施例中,本实施例中的压裂喷砂器和实施例一中的压裂喷砂器的结构类似,对相同之处就不再赘述了,仅介绍不同之处。In yet another embodiment of the present invention, the structure of the fracturing sand blaster in this embodiment is similar to that in the first embodiment, and the similarities will not be repeated, only the differences are introduced. place.

在本实施例中,具体公开了耐磨套3为硬质合金套。需要说明的是,耐磨套3也可以是其他耐磨材质制成的耐磨套3。In this embodiment, it is specifically disclosed that the wear-resistant sleeve 3 is a cemented carbide sleeve. It should be noted that the wear-resistant sleeve 3 may also be a wear-resistant sleeve 3 made of other wear-resistant materials.

进一步地,本实用新型公开了喷砂通孔202包括渐扩孔2021和等直径通孔2022,其中,等直径通孔2022的一端与耐磨孔301的一端导通,等直径通孔2022的另一端与渐扩孔2021的较小开口端导通,较小开口端是指渐扩孔2021的开口横截面积较小的那端。具体地,渐扩孔2021为弧形孔,以渐扩孔2021为中心,主体2外壁向内切削为弧形凹状,中心位置最薄,两端逐步加厚。渐扩孔2021也可以是锥形孔。Further, the utility model discloses that the sandblasting through hole 202 includes a gradually expanding hole 2021 and an equal diameter through hole 2022, wherein one end of the equal diameter through hole 2022 is connected to one end of the wear-resistant hole 301, and the equal diameter through hole 2022 The other end communicates with the smaller opening end of the expanding hole 2021 , the smaller opening end refers to the end with a smaller opening cross-sectional area of the expanding hole 2021 . Specifically, the gradually expanding hole 2021 is an arc-shaped hole, with the gradually expanding hole 2021 as the center, the outer wall of the main body 2 is cut inward into an arc-shaped concave shape, the center is the thinnest, and the two ends gradually thicken. The expanding hole 2021 may also be a tapered hole.

为了实现对喷砂通孔202的均匀磨损,本实用新型公开了喷砂通孔202的轴心线和耐磨孔301的轴心线重合,且喷砂通孔202的内径略小于耐磨孔301的内径。In order to achieve uniform wear on the sandblasting through hole 202, the utility model discloses that the axis line of the sandblasting through hole 202 coincides with the axis line of the wear-resistant hole 301, and the inner diameter of the sandblasting through hole 202 is slightly smaller than the wear-resistant hole 301 inner diameter.

更进一步地,本实用新型公开了主体2与上部连接套1通过螺纹连接,上部连接套1的底端为公扣,主体2的顶端为母扣。Furthermore, the utility model discloses that the main body 2 and the upper connecting sleeve 1 are connected by threads, the bottom end of the upper connecting sleeve 1 is a male buckle, and the top end of the main body 2 is a female buckle.

本实施例中,具体公开了上部连接套1的侧壁周向均布安装剪切销钉5的销钉孔,滑套4通过剪切销钉5连接在上部连接套1的内壁上。In this embodiment, it specifically discloses that the side wall of the upper connection sleeve 1 is evenly distributed around the circumference of the pin holes for installing the shear pins 5 , and the sliding sleeve 4 is connected to the inner wall of the upper connection sleeve 1 through the shear pins 5 .

本实施例中,还公开了主体2的内壁设置有凸台203,耐磨套3的顶端与上部连接套1的底端抵接,耐磨套3的底端与凸台203的顶端抵接。进一步增加耐磨套3的安装牢固度。In this embodiment, it is also disclosed that the inner wall of the main body 2 is provided with a boss 203, the top end of the wear-resistant sleeve 3 abuts against the bottom end of the upper connecting sleeve 1, and the bottom end of the wear-resistant sleeve 3 abuts against the top end of the boss 203 . Further increase the installation firmness of the wear-resistant sleeve 3 .

为了增加滑套4与主体2及上部连接套1的密封性,本实用新型公开了滑套4的外侧壁上开设有第一密封槽和第二密封槽。第一密封槽内安装有第一密封圈6,第一密封圈6与上部连接套1的内壁间隙配合,第二密封套内安装有第二密封圈7,第二密封圈7与主体2的内壁间隙配合。In order to increase the sealing performance of the sliding sleeve 4, the main body 2 and the upper connection sleeve 1, the utility model discloses that the outer wall of the sliding sleeve 4 is provided with a first sealing groove and a second sealing groove. The first sealing ring 6 is installed in the first sealing groove, and the first sealing ring 6 is matched with the inner wall of the upper connecting sleeve 1, and the second sealing ring 7 is installed in the second sealing sleeve, and the second sealing ring 7 and the main body 2 Inner wall clearance fit.

本实施例中,还具体公开了喷砂通孔202的横截面为矩形或者槽口状,相对于其它形状,该种形状下携砂液喷射速度降低、喷射范围增大,可有效防止套管被喷射损坏。In this embodiment, it is also specifically disclosed that the cross-section of the blasting through hole 202 is rectangular or notch-shaped. Compared with other shapes, the spraying speed of the sand-carrying liquid in this shape is reduced and the spraying range is increased, which can effectively prevent the casing from Damaged by spraying.

喷砂通孔202的个数为多个,均布在主体2的内壁上,具体为2个-4个,设置过多的喷砂通孔202会造成主体2连接强度不足,加大施工风险。The number of sandblasting through holes 202 is multiple, evenly distributed on the inner wall of the main body 2, specifically 2 to 4. Setting too many sandblasting through holes 202 will cause insufficient connection strength of the main body 2 and increase construction risks .

为了增加滑套4和钢球的密封性,本实用新型公开了滑套4的顶部开设有与钢球密封的锥形口401。In order to increase the sealing performance of the sliding sleeve 4 and the steel ball, the utility model discloses that the top of the sliding sleeve 4 is provided with a tapered mouth 401 which is sealed with the steel ball.

本实用新型提供的压裂喷砂器,组装时,将滑套4用销钉固定在上部连接套1上,再将硬质合金套装入主体2内,底部落在凸台203上,并将喷砂通孔202和耐磨孔301对应,最后将主体2与上部连接套1连接,完成该压裂喷砂器的安装。The fracturing sand blaster provided by the utility model, when assembling, fix the sliding sleeve 4 on the upper connection sleeve 1 with pins, then put the hard alloy sleeve into the main body 2, and the bottom falls on the boss 203, and the spray The sand through hole 202 corresponds to the wear-resistant hole 301, and finally the main body 2 is connected with the upper connecting sleeve 1 to complete the installation of the fracturing sand blaster.

在进行油气井压裂时,向压裂喷砂器投进钢球后,钢球将滑套4打落,露出耐磨孔301和喷砂通孔202,由于主体2上的喷砂通孔202的初始横截面积很小,造成的压力波动小,避免了管柱的蠕动,防止封隔器损坏失效,并且在低排量下也可保证足够的节流压差,使封隔器保持在坐封状态;随着后续施工排量的增加,由于喷砂通孔202处的凹状设计,在携砂液的磨蚀下孔径逐步均匀增大,避免了主体2的断裂;由于硬质合金套的耐磨孔301具有高耐磨,在大砂量下孔径仅发生微小变化,即使因地面原因中途停泵,依然能够提供封隔器坐封节流压力,保持封隔器的坐封;另一方面,硬质合金套的喷砂通孔202控制了携砂液的喷射流道,使喷砂通孔202在一定范围内扩张,防止主体2发生断裂,提高了工具的安全性。When fracturing oil and gas wells, after steel balls are thrown into the fracturing sand blaster, the steel balls will knock down the sliding sleeve 4, exposing the wear-resistant hole 301 and the sand blasting through hole 202, because the sand blasting through hole on the main body 2 The initial cross-sectional area of 202 is very small, resulting in small pressure fluctuations, which avoids the peristalsis of the pipe string, prevents the packer from being damaged and fails, and can also ensure sufficient throttling pressure difference at low displacement to keep the packer In the setting state; with the increase of subsequent construction displacement, due to the concave design of the sand blasting through hole 202, the hole diameter gradually increases uniformly under the abrasion of the sand carrier liquid, avoiding the fracture of the main body 2; due to the cemented carbide sleeve The wear-resistant hole 301 has high wear resistance, and the hole diameter changes only slightly under the large amount of sand. Even if the pump is stopped midway due to ground reasons, it can still provide the packer setting throttling pressure and keep the packer set; On the one hand, the sandblasting through hole 202 of the cemented carbide sleeve controls the injection channel of the sand-carrying liquid, so that the sandblasting through hole 202 expands within a certain range, preventing the main body 2 from breaking and improving the safety of the tool.

实施例三Embodiment three

请参阅图2,本实用新型还公开了一种压裂管柱,包括封隔器8和如上述任意一项实施例中的压裂喷砂器9。水力锚10分别连接在压裂管柱最上端封隔器8之上和最下端封隔器8之下,压裂喷砂器9连接于两级封隔器8之间,与需改造地层在深度上保持一致,压裂管柱末端连接下直喷11,封隔器8和压裂喷砂器9的数量可根据地层需要进行多级调整,但压裂喷砂器9的内通径从上到下逐级减小,以适应不同层级钢球的需要。Please refer to FIG. 2 , the utility model also discloses a fracturing string, including a packer 8 and a fracturing sand blaster 9 as in any one of the above-mentioned embodiments. Hydraulic anchors 10 are respectively connected above the uppermost packer 8 and below the lowermost packer 8 of the fracturing string, and the fracturing sandblasting device 9 is connected between the two-stage packers 8, and the formation to be stimulated is in the The depth is consistent, the end of the fracturing string is connected to the direct injection 11, and the number of packers 8 and fracturing sand blasters 9 can be adjusted in multiple stages according to the needs of the formation, but the inner diameter of the fracturing sand blasters 9 is from It decreases step by step from top to bottom to meet the needs of different levels of steel balls.

在进行油气井压裂时,将压裂喷砂器9及其他工具连接后形成压裂管柱,该压裂管柱在压裂施工过程中钢球后,憋压剪断剪切销钉5,将滑套4打落,对该压裂喷砂器9对应地层进行压裂改造;随着后续施工排量的增加,由于主体2上的喷砂通孔202处的凹状设计,在携砂液的磨蚀下孔径逐步均匀增大,避免了主体2的断裂,同时由于喷砂通孔202的初始孔径小,滑套4打落后造成的压力波动小,避免了管柱的蠕动,防止封隔器8损坏失效,且在低排量下也可保证足够的节流压差,使封隔器8保持在坐封状态。硬质合金套的耐磨孔301具有高耐磨,在大砂量下孔径仅发生微小变化,即使因地面原因中途停泵,依然能够提供封隔器8坐封节流压力,保持封隔器8的坐封;另一方面,硬质合金套的耐磨孔301控制了携砂液的喷射流道,使喷砂通孔202在一定范围内扩张,防止主体2发生断裂,提高了工具的安全性。When fracturing oil and gas wells, the fracturing sand blaster 9 and other tools are connected to form a fracturing string. After the steel ball is in the fracturing construction process, the fracturing string is suppressed and cut off the shear pin 5, and the The sliding sleeve 4 is knocked down, and the formation corresponding to the fracturing sand blaster 9 is subjected to fracturing reconstruction; with the increase in subsequent construction displacement, due to the concave design of the sand blasting through hole 202 on the main body 2, the sand carrying fluid will Under abrasion, the pore diameter increases gradually and uniformly, which avoids the fracture of the main body 2. At the same time, due to the small initial pore diameter of the sandblasting through hole 202, the pressure fluctuation caused by the sliding sleeve 4 is small, which avoids the peristalsis of the pipe string and prevents the packer 8 The damage fails, and sufficient throttling pressure difference can be guaranteed even at low displacement, so that the packer 8 can be kept in the set state. The wear-resistant hole 301 of the tungsten carbide sleeve is highly wear-resistant, and the hole diameter changes only slightly under the large amount of sand. Even if the pump is stopped midway due to ground reasons, it can still provide the packer 8 with the setting and throttling pressure to keep the packer 8; on the other hand, the wear-resistant hole 301 of the cemented carbide sleeve controls the injection channel of the sand-carrying liquid, so that the sandblasting through hole 202 expands within a certain range, prevents the main body 2 from breaking, and improves the durability of the tool. safety.

第一层地层12压裂完成后,投入与下部压裂喷砂器9适配的钢球,地面泵压提高打落滑套4对第二层地层13进行压裂;第二层地层13压裂完成后继续投入钢球打开上部压裂喷砂器9,对第三层地层14进行压裂。在喷砂器9开启瞬间,管柱内压力波动小,管柱稳定性较好,避免了管柱的蠕动,防止封隔器8损坏失效;由于压裂喷砂器9喷砂通孔202处的凹状设计,随着施工排量增加,孔径逐步增大,节流效应减小使地面施工压力随之降低;由于压裂喷砂器9内的硬质合金套耐磨孔301的流道约束,主体2断裂的可能性降低,提高了整个管柱施工的安全性。After the fracturing of the first stratum 12 is completed, the steel balls compatible with the lower fracturing sand blaster 9 are put in, and the ground pump pressure increases and the sliding sleeve 4 is knocked down to perform fracturing on the second stratum 13; After the fracturing is completed, continue to drop steel balls to open the upper fracturing sand blaster 9, and perform fracturing to the third formation 14. At the moment when the sand blaster 9 is opened, the pressure fluctuation in the pipe string is small, and the stability of the pipe string is good, which avoids the peristalsis of the pipe string and prevents the damage and failure of the packer 8; Concave design, as the construction displacement increases, the hole diameter gradually increases, and the throttling effect decreases so that the ground construction pressure decreases; , the possibility of breaking the main body 2 is reduced, and the safety of the entire pipe string construction is improved.

在本实用新型中的“第一”、“第二”等均为描述上进行区别,没有其他的特殊含义。"First" and "second" in the present utility model are for distinction in description, and have no other special meanings.

对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本实用新型。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本实用新型的精神或范围的情况下,在其它实施例中实现。因此,本实用新型将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖性特点相一致的最宽的范围。The above description of the disclosed embodiments enables those skilled in the art to realize or use the utility model. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Therefore, the present invention will not be limited to these embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1.一种压裂喷砂器,其特征在于,包括:1. A fracturing blaster, characterized in that it comprises: 上部连接套(1),所述上部连接套(1)的顶端能够连接油管,所述上部连接套(1)的内部开设第一通孔(101);The upper connection sleeve (1), the top end of the upper connection sleeve (1) can be connected to the oil pipe, and the inside of the upper connection sleeve (1) is provided with a first through hole (101); 主体(2),所述主体(2)的顶端与所述上部连接套(1)的底端连接,所述主体(2)的底端能够与封隔器连接,且所述主体(2)的内部开设第二通孔(201),所述第一通孔(101)和所述第二通孔(201)导通,所述主体(2)的侧壁上开设有喷砂通孔(202);A main body (2), the top end of the main body (2) is connected to the bottom end of the upper connection sleeve (1), the bottom end of the main body (2) can be connected with a packer, and the main body (2) A second through hole (201) is opened inside the body, the first through hole (101) and the second through hole (201) are connected, and the side wall of the main body (2) is provided with a sandblasting through hole ( 202); 耐磨套(3),所述耐磨套(3)套接在所述主体(2)的内壁,且所述耐磨套(3)上开有与所述喷砂通孔(202)导通的耐磨孔(301);A wear-resistant sleeve (3), the wear-resistant sleeve (3) is sleeved on the inner wall of the main body (2), and the wear-resistant sleeve (3) is provided with a guide for the sandblasting through hole (202). Through wear-resistant hole (301); 滑套(4),所述滑套(4)连接在所述上部连接套(1)的内壁上,且在钢球的作用下能够与所述上部连接套(1)下滑分离露出所述喷砂通孔(202)和所述耐磨孔(301)。Sliding sleeve (4), the sliding sleeve (4) is connected to the inner wall of the upper connecting sleeve (1), and under the action of steel balls, it can slide and separate from the upper connecting sleeve (1) to expose the nozzle Sand through holes (202) and the wear-resistant holes (301). 2.根据权利要求1所述的压裂喷砂器,其特征在于,所述耐磨套(3)为硬质合金套。2. The fracturing sand blaster according to claim 1, characterized in that, the wear-resistant sleeve (3) is a cemented carbide sleeve. 3.根据权利要求1所述的压裂喷砂器,其特征在于,所述喷砂通孔(202)包括渐扩孔(2021)和等直径通孔(2022);3. The fracturing sandblasting device according to claim 1, characterized in that, the sandblasting through holes (202) comprise expanding holes (2021) and equal diameter through holes (2022); 所述等直径通孔(2022)的一端与所述耐磨孔(301)的一端导通,所述等直径通孔(2022)的另一端与所述渐扩孔(2021)的较小开口端导通。One end of the equal-diameter through hole (2022) communicates with one end of the wear-resistant hole (301), and the other end of the equal-diameter through hole (2022) communicates with the smaller opening of the gradually expanding hole (2021). terminal conduction. 4.根据权利要求1所述的压裂喷砂器,其特征在于,所述喷砂通孔(202)的轴心线和所述耐磨孔(301)的轴心线重合。4. The fracturing sand blaster according to claim 1, characterized in that, the axis line of the sandblasting through hole (202) coincides with the axis line of the wear-resistant hole (301). 5.根据权利要求1所述的压裂喷砂器,其特征在于,所述主体(2)与所述上部连接套(1)通过螺纹连接;5. The fracturing sand blaster according to claim 1, characterized in that, the main body (2) and the upper connecting sleeve (1) are connected by threads; 所述滑套(4)通过剪切销钉(5)连接在所述上部连接套(1)的内壁上。The sliding sleeve (4) is connected to the inner wall of the upper connecting sleeve (1) through shear pins (5). 6.根据权利要求5所述的压裂喷砂器,其特征在于,所述主体(2)的内壁设置有凸台(203),所述耐磨套(3)的顶端与所述上部连接套(1)的底端抵接;6. The fracturing sand blaster according to claim 5, characterized in that, the inner wall of the main body (2) is provided with a boss (203), and the top end of the wear-resistant sleeve (3) is connected to the upper part The bottom end of the sleeve (1) abuts; 所述耐磨套(3)的底端与所述凸台(203)的顶端抵接。The bottom end of the wear-resistant sleeve (3) abuts against the top end of the boss (203). 7.根据权利要求1所述的压裂喷砂器,其特征在于,所述滑套(4)的外侧壁上开设有第一密封槽和第二密封槽;7. The fracturing sand blaster according to claim 1, characterized in that, the outer wall of the sliding sleeve (4) is provided with a first sealing groove and a second sealing groove; 所述第一密封槽内安装有第一密封圈(6),所述第一密封圈(6)与所述上部连接套(1)的内壁间隙配合;A first sealing ring (6) is installed in the first sealing groove, and the first sealing ring (6) is in clearance fit with the inner wall of the upper connecting sleeve (1); 所述第二密封套内安装有第二密封圈(7),所述第二密封圈(7)与所述主体(2)的内壁间隙配合。A second sealing ring (7) is installed in the second sealing sleeve, and the second sealing ring (7) is in clearance fit with the inner wall of the main body (2). 8.根据权利要求1所述的压裂喷砂器,其特征在于,所述喷砂通孔(202)的横截面为矩形;8. The fracturing sandblasting device according to claim 1, characterized in that, the cross section of the sandblasting through hole (202) is rectangular; 且所述喷砂通孔(202)的个数为多个,均布在所述主体(2)的内壁上。Moreover, there are multiple sandblasting through holes (202), which are evenly distributed on the inner wall of the main body (2). 9.根据权利要求1-8中任意一项所述的压裂喷砂器,其特征在于,所述滑套(4)的顶部开设有与所述钢球密封的锥形口(401)。9. The fracturing sand blaster according to any one of claims 1-8, characterized in that, the top of the sliding sleeve (4) is provided with a tapered opening (401) sealed with the steel ball. 10.一种压裂管柱,其特征在于,包括如权利要求1-9中任意一项所述的压裂喷砂器。10. A fracturing string, characterized by comprising the fracturing sand blaster according to any one of claims 1-9.
CN201721458513.2U 2017-11-03 2017-11-03 A kind of frac-sand jet and fracturing string Active CN207554030U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721458513.2U CN207554030U (en) 2017-11-03 2017-11-03 A kind of frac-sand jet and fracturing string

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721458513.2U CN207554030U (en) 2017-11-03 2017-11-03 A kind of frac-sand jet and fracturing string

Publications (1)

Publication Number Publication Date
CN207554030U true CN207554030U (en) 2018-06-29

Family

ID=62682193

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721458513.2U Active CN207554030U (en) 2017-11-03 2017-11-03 A kind of frac-sand jet and fracturing string

Country Status (1)

Country Link
CN (1) CN207554030U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031725A (en) * 2020-08-06 2020-12-04 北京金科龙石油技术开发有限公司 Eccentric bottom sand blower

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031725A (en) * 2020-08-06 2020-12-04 北京金科龙石油技术开发有限公司 Eccentric bottom sand blower

Similar Documents

Publication Publication Date Title
CN105484695B (en) Mechanical and hydraulic double-acting expansion device suitable for expansion tube drilling well
CN205605160U (en) Ruptured tailpipe plug
CN107859509A (en) Coal seam hydraulic slotting joint fracturing comprehensive anti-permeability device
CN105888638A (en) Timing sliding sleeve fracturing pipe column
CN105840154B (en) A kind of novel clamp tile style underground throttle device
CN202152674U (en) Drillable ball sliding sleeve for staged fracturing and acidizing of horizontal wells
CN105888639A (en) Feeding-controlling full-bore sliding sleeve sectional fracturing tube column
CN202645503U (en) Bowling-type fracture sliding bush for oil and gas well
CN114810021A (en) Gas well full life cycle coiled tubing completion pipe string and process method thereof
CN108625840A (en) The more cluster full-bore fracturing sliding bushs of ball-throwing type
CN104912535B (en) A multi-cluster fracturing sliding sleeve in a stage
CN204532261U (en) A Controllable Dissolvable Ball Seat Multistage Fracturing Sleeve
CN203271694U (en) Built-in integral hydraulic sandblasting perforator
CN206000501U (en) A kind of suspension type self-expanding blocks tubing string
CN111608611A (en) A large-diameter bridge plug and method for realizing single-top seal fracturing
CN204457595U (en) Tubing bridge plug
CN106351602A (en) Expanding type differential pressure opening type fine leakage finding and leakage checking packer
CN205382907U (en) Two effect expansion devices of machinery hydraulic pressure suitable for expansion pipe well drilling
CN206972216U (en) Ball-type multi-cluster full-bore fracturing sleeve
CN116411868A (en) A slim hole plug-free cementing device, rubber plug and its cementing construction method
CN109989723A (en) Multi-cluster perforation combined fracturing sealing device
CN204371233U (en) A casing fracturing ball seat
CN115822530B (en) An integrated tool and method for transmitting, cleaning and perforating wells with a long horizontal section of pressurized drill pipe
CN216811639U (en) Metal sealing bridge plug with starting limiting ring
CN105422075B (en) sandblaster

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20250905

Address after: Room 1202, No. 22, Chaoyangmen North Street, Chaoyang District, Beijing 100020

Patentee after: Sinopec Petroleum Engineering Technology Service Co.,Ltd.

Country or region after: China

Patentee after: SINOPEC ZHONGYUAN PETROLEUM ENGINEERING Co.,Ltd.

Patentee after: DOWNHOLE SPECIAL OPERATION COMPANY OF SINOPEC ZHONGYUAN ENGINEERING LTD.

Address before: 100028 Chaoyang District, Beijing Hui Xin Street 6, Twelfth level.

Patentee before: SINOPEC OILFIELD SERVICE Corp.

Country or region before: China

Patentee before: DOWNHOLE SPECIAL OPERATION COMPANY OF SINOPEC ZHONGYUAN ENGINEERING LTD.