CN207553562U - A kind of combination moving type scaffold - Google Patents

A kind of combination moving type scaffold Download PDF

Info

Publication number
CN207553562U
CN207553562U CN201721715278.2U CN201721715278U CN207553562U CN 207553562 U CN207553562 U CN 207553562U CN 201721715278 U CN201721715278 U CN 201721715278U CN 207553562 U CN207553562 U CN 207553562U
Authority
CN
China
Prior art keywords
scaffold
montant
unit
cross bar
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721715278.2U
Other languages
Chinese (zh)
Inventor
董万葵
贺思贤
包继徳
王天鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu 6th Construction Group Ltd Co
Original Assignee
Gansu 6th Construction Group Ltd Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu 6th Construction Group Ltd Co filed Critical Gansu 6th Construction Group Ltd Co
Priority to CN201721715278.2U priority Critical patent/CN207553562U/en
Application granted granted Critical
Publication of CN207553562U publication Critical patent/CN207553562U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型属于建筑器材领域,具体为一种组合移动式脚手架。包括多层脚手架单元,操作台、轨道、斜撑杆,脚手架单元由前后两个横杆a、左右两个横杆b以及四角四个竖杆构成,所述竖杆下端通过封板设置有插管,竖杆上端设有套管,所述横杆a及横杆b位于竖杆中部,竖杆上还设有与横杆b平行的固定杆,上层脚手架单元的插管插于下层脚手架单元的竖杆的上端,上层脚手架单元竖杆的下端位于下层脚手架单元的套管内,所述最下层脚手架单元的竖杆下端未设有插管而设有脚轮,脚轮位于轨道内,每三层脚手架单元前后两侧均设有两个相互交叉的斜撑杆。本实用新型结构简单,安装方便,使用安全,省时省工,便于推广使用。

The utility model belongs to the field of construction equipment, in particular to a combined movable scaffold. It includes a multi-layer scaffolding unit, an operation table, a track, and a diagonal brace. The scaffolding unit is composed of two front and rear horizontal bars a, two left and right horizontal bars b, and four vertical bars at the four corners. The lower ends of the vertical bars are provided with inserts through the sealing plate The upper end of the vertical rod is provided with a casing, the horizontal rod a and the horizontal rod b are located in the middle of the vertical rod, and the vertical rod is also provided with a fixed rod parallel to the horizontal rod b, and the intubation tube of the upper scaffold unit is inserted into the lower scaffold unit The upper end of the vertical bar of the upper scaffolding unit, the lower end of the vertical bar of the upper scaffolding unit is located in the casing of the lower scaffolding unit, the lower end of the vertical bar of the lowermost scaffolding unit is not provided with an intubation tube but is provided with casters, and the casters are located in the track. Every three floors of scaffolding There are two diagonal braces crossing each other on the front and rear sides of the unit. The utility model has the advantages of simple structure, convenient installation, safe use, time saving and labor saving, and is convenient for popularization and use.

Description

一种组合移动式脚手架A combined mobile scaffold

技术领域technical field

本实用新型涉及建筑器材技术领域,特别涉及一种组合移动式脚手架。The utility model relates to the technical field of construction equipment, in particular to a combined movable scaffold.

背景技术Background technique

脚手架指施工现场为工人操作并解决垂直和水平运输而搭设的各种支架。建筑界的通用术语,指建筑工地上用在外墙、内部装修或层高较高无法直接施工的地方。主要为了施工人员上下干活或外围安全网围护及高空安装构件等,说白了就是搭架子,脚手架制作材料通常有:竹、木、钢管或合成材料等。脚手架主要有主框、横框、交叉斜撑、脚手板、可调底座等组成。交叉拉杆又称斜拉杆、是纵向连接两副门架的交叉型拉杆。有些工程也用脚手架当模板使用,此外在广告业、市政、交通路桥、矿山等部门也广泛被使用。目前较多采用的操作平台搭设有两种方式,一种是采用钢管扣件式脚手架搭设操作平台,该方法搭设脚手架,需要按照建筑脚手架搭设规程进行搭设,其搭设流程复杂,搭设速度慢,自重大,移动不方便;另一种是采用由成品井字架组件组装搭设的四轮移动脚手架操作平台,由于四轮移动成品井字架结构尺寸有限,当达到一定施工高度时,该高空操作平台极易倾覆,安全性难以保证,对移动平台搭设和移动场地条件要求高,其施工高度有限。Scaffolding refers to the various supports set up on the construction site for workers to operate and solve vertical and horizontal transportation. The generic term on building circle, refers to building site be used in the higher place that cannot directly construct of exterior wall, interior decoration or floor height. It is mainly for construction workers to work up and down or for peripheral safety net enclosures and high-altitude installation components. Scaffolding mainly consists of main frame, horizontal frame, cross bracing, scaffolding board, adjustable base and so on. Cross tie rods, also known as diagonal tie rods, are cross-type tie rods that connect two mast frames longitudinally. Some projects also use scaffolding as a template, and it is also widely used in advertising, municipal administration, traffic roads and bridges, mines and other departments. At present, there are two ways of erecting the operating platform that are widely used. One is to erect the operating platform by using steel pipe fastener scaffolding. This method needs to be erected in accordance with the construction scaffold erection regulations. The erection process is complicated and the erection speed is slow. It is heavy and inconvenient to move; the other is to use a four-wheel mobile scaffolding operation platform assembled from finished well-shaped frame components. Due to the limited structural size of the four-wheel mobile finished well-shaped frame, when a certain construction height is reached, the high-altitude operation platform It is very easy to overturn, and it is difficult to guarantee safety. It has high requirements for the erection of the mobile platform and the conditions of the mobile site, and its construction height is limited.

实用新型内容Utility model content

本实用新型的目的在于提出一种结构简单,安装方便,使用安全,省时省工的组合移动式脚手架。The purpose of the utility model is to propose a combined mobile scaffold with simple structure, convenient installation, safe use, time-saving and labor-saving.

为了实现上述实用新型目的,本实用新型采用以下技术方案:In order to realize the above utility model purpose, the utility model adopts the following technical solutions:

一种组合移动式脚手架,包括多层脚手架单元,操作台1、轨道2、斜撑杆3,其特征在于:所述脚手架单元包括前后两个横杆a4、左右两个横杆b5以及四角四个竖杆6,所述横杆a4、横杆b5、竖杆6均为钢管结构,所述竖杆6下端通过封板7设置有插管8,竖杆6上端设有套管9,所述横杆a4及横杆b5位于竖杆6中部,竖杆6上还设有与横杆b5平行的固定杆10,上层脚手架单元的插管8插于下层脚手架单元的竖杆6的上端,上层脚手架单元竖杆6的下端位于下层脚手架单元的套管9内,所述最下层脚手架单元的竖杆6下端未设有插管8而设有脚轮11,脚轮11位于轨道2内,所述轨道2一端设有插环12,另一端设有插板13,插板13可插于插环12中并通过螺杆固定,每三层脚手架单元前后两侧均设有两个相互交叉的斜撑杆3,所述斜撑杆3的两端通过其上的通孔活动安装于固定杆10上,所述操作台1左右两端上设有挂钩14,所述挂钩14活动钩于横杆b5上。A combined mobile scaffolding, comprising a multi-layer scaffolding unit, an operation table 1, a rail 2, and a diagonal brace 3, characterized in that: the scaffolding unit includes two front and rear crossbars a4, two left and right crossbars b5 and four corners A vertical bar 6, the horizontal bar a4, the horizontal bar b5, and the vertical bar 6 are all steel pipe structures, the lower end of the vertical bar 6 is provided with an intubation tube 8 through the sealing plate 7, and the upper end of the vertical bar 6 is provided with a casing 9, so The horizontal bar a4 and the horizontal bar b5 are located in the middle of the vertical bar 6, and the vertical bar 6 is also provided with a fixed bar 10 parallel to the horizontal bar b5, and the insertion tube 8 of the upper scaffold unit is inserted into the upper end of the vertical bar 6 of the lower scaffold unit. The lower end of the vertical bar 6 of the upper scaffold unit is located in the casing 9 of the lower scaffold unit, the lower end of the vertical bar 6 of the lowermost scaffold unit is not provided with an intubation tube 8 but is provided with casters 11, and the casters 11 are located in the track 2. One end of the track 2 is provided with an insert ring 12, and the other end is provided with an insert plate 13. The insert plate 13 can be inserted into the insert ring 12 and fixed by a screw. There are two intersecting diagonal braces on the front and back sides of each three-story scaffold unit. Rod 3, the two ends of the diagonal strut 3 are movably installed on the fixed rod 10 through the through holes thereon, and the left and right ends of the operating table 1 are provided with hooks 14, and the hooks 14 are movably hooked on the cross bar b5 superior.

所述轨道2的长度大于横杆a4的长度,所述轨道2至少为四根。The length of the rails 2 is greater than the length of the crossbar a4, and there are at least four rails 2 .

所述脚轮11上设有刹车装置。The caster 11 is provided with a braking device.

本实用新型的有益效果在于:其由多层脚手架单元上下组装形成,操作使用时安装快速方便,不用时收纳起来占地小,容易收放;弃活动安装的斜撑杆,安装拆卸方便,结构稳固安全;其设置的脚轮及轨道可使整个脚手架左右移动,操作稳定安全,移动方便,省时省力。The beneficial effect of the utility model is that: it is formed by the upper and lower assembly of multi-layer scaffolding units, it is fast and convenient to install during operation and use, it takes up a small area when it is not in use, and it is easy to store and put; Stable and safe; the casters and tracks set can make the entire scaffold move left and right, the operation is stable and safe, the movement is convenient, and time and effort are saved.

附图说明Description of drawings

图1为本实用新型的结构示意图。Fig. 1 is the structural representation of the utility model.

图中所示:1.操作台;2.轨道;3.斜撑杆;4.横杆a;5.横杆b;6.竖杆;7.封板;8.插管;9.套管;10.固定杆;11.脚轮;12.插环;13.插板;14.挂钩。As shown in the figure: 1. Console; 2. Track; 3. Diagonal brace; 4. Crossbar a; 5. Crossbar b; Tube; 10. Fixed rod; 11. Caster; 12. Insert ring; 13. Insert plate; 14. Hook.

具体实施方式Detailed ways

以下结合附图对本实用新型的结构及其有益效果进一步说明。The structure of the utility model and its beneficial effects will be further described below in conjunction with the accompanying drawings.

实施例:Example:

一种组合移动式脚手架,如图1,包括多层脚手架单元,操作台1、轨道2、斜撑杆3,所述脚手架单元包括前后两个横杆a4、左右两个横杆b5以及四角四个竖杆6,所述横杆a4、横杆b5、竖杆6均为钢管结构,所述竖杆6下端通过封板7设置有插管8,竖杆6上端设有套管9,所述横杆a4及横杆b5位于竖杆6中部,竖杆6上还设有与横杆b5平行的固定杆10,上层脚手架单元的插管8插于下层脚手架单元的竖杆6的上端,上层脚手架单元竖杆6的下端位于下层脚手架单元的套管9内,所述最下层脚手架单元的竖杆6下端未设有插管8而设有脚轮11,脚轮11位于轨道2内,所述轨道2一端设有插环12,另一端设有插板13,插板13可插于插环12中并通过螺杆固定,每三层脚手架单元前后两侧均设有两个相互交叉的斜撑杆3,所述斜撑杆3的两端通过其上的通孔活动安装于固定杆10上,所述操作台1左右两端上设有挂钩14,所述挂钩14活动钩于横杆b5上。A combined mobile scaffold, as shown in Figure 1, includes a multi-layer scaffold unit, an operating platform 1, a track 2, and a diagonal brace 3, and the scaffold unit includes two front and rear cross bars a4, two left and right cross bars b5, and four corners A vertical bar 6, the horizontal bar a4, the horizontal bar b5, and the vertical bar 6 are all steel pipe structures, the lower end of the vertical bar 6 is provided with an intubation tube 8 through the sealing plate 7, and the upper end of the vertical bar 6 is provided with a casing 9, so The cross bar a4 and the cross bar b5 are located in the middle of the vertical bar 6, and the vertical bar 6 is also provided with a fixed bar 10 parallel to the horizontal bar b5, and the insertion tube 8 of the upper scaffold unit is inserted into the upper end of the vertical bar 6 of the lower scaffold unit, The lower end of the vertical bar 6 of the upper scaffold unit is located in the casing 9 of the lower scaffold unit, the lower end of the vertical bar 6 of the lowermost scaffold unit is not provided with an intubation tube 8 but is provided with casters 11, and the casters 11 are located in the track 2. One end of the track 2 is provided with an insert ring 12, and the other end is provided with an insert plate 13. The insert plate 13 can be inserted into the insert ring 12 and fixed by a screw. There are two intersecting diagonal braces on the front and back sides of each three-story scaffold unit. Rod 3, the two ends of the diagonal strut 3 are movably installed on the fixed rod 10 through the through holes thereon, and the left and right ends of the operation table 1 are provided with hooks 14, and the hooks 14 are movably hooked on the cross bar b5 superior.

所述轨道2的长度大于横杆a4的长度,轨道2至少为四根。在脚手架左右移动的过程中,只需移动轨道的位置便可将脚手架轻松推动。The length of the track 2 is greater than the length of the crossbar a4, and there are at least four tracks 2. During the left and right movement of the scaffold, the scaffold can be easily pushed by simply moving the position of the track.

所述脚轮11上设有刹车装置。The caster 11 is provided with a braking device.

以上所述仅为本实用新型的优选实施方式,本实用新型的保护范围并不仅限于上述实施方式,凡是属于本实用新型原理的技术方案均属于本实用新型的保护范围。对于本领域的技术人员而言,在不脱离本实用新型的原理的前提下进行的若干改进或润饰,这些改进和润饰也应视为本实用新型的保护范围。The above descriptions are only preferred embodiments of the present utility model, and the scope of protection of the present utility model is not limited to the above-mentioned embodiments, and all technical solutions belonging to the principle of the utility model belong to the protection scope of the utility model. For those skilled in the art, some improvements or modifications made on the premise of not departing from the principle of the utility model, these improvements and modifications should also be regarded as the protection scope of the utility model.

Claims (3)

1. a kind of combination moving type scaffold, including multi-layer scaffold unit, operation console (1), track (2), hound (3), It is characterized in that:The scaffold unit includes former and later two cross bars a (4), the two cross bar b (5) in left and right and the montant of quadrangle four (6), the cross bar a (4), cross bar b (5), montant (6) are steel-tube construction, and montant (6) lower end is set by sealing plate (7) There is intubation (8), montant (6) upper end is equipped with casing (9), the cross bar a (4) and cross bar b (5) in the middle part of montant (6), montant (6) fixed link (10) parallel with cross bar b (5) is additionally provided on, the intubation (8) of upper strata scaffold unit inserts in lower floor's scaffold list The upper end of the montant (6) of member, the lower end of the montant (6) of upper strata scaffold unit are located in the casing (9) of lower floor's scaffold unit, Montant (6) lower end of undermost scaffold unit is not provided with intubation (8) equipped with castor (11), and castor (11) is positioned at track (2) in, described track (2) one end is equipped with slotting ring (12), and the other end is equipped with plate (13), and plate (13) can be inserted in slotting ring (12) And pass through screw rod and fix, every three layers of scaffold unit front and rear sides are all provided with there are two cross one another hound (3), the diagonal brace The both ends of bar (3) are movably installed in by through-hole thereon in fixed link (10), and operation console (1) left and right ends are equipped with hook (14), hook (14) movable hook is on cross bar b (5).
2. a kind of combination moving type scaffold according to claim 1, it is characterised in that:The length of the track (2) is big Length in cross bar a (4), the track (2) are at least four.
3. a kind of combination moving type scaffold according to claim 1, it is characterised in that:The castor (11), which is equipped with, stops Vehicle device.
CN201721715278.2U 2017-12-07 2017-12-07 A kind of combination moving type scaffold Expired - Fee Related CN207553562U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721715278.2U CN207553562U (en) 2017-12-07 2017-12-07 A kind of combination moving type scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721715278.2U CN207553562U (en) 2017-12-07 2017-12-07 A kind of combination moving type scaffold

Publications (1)

Publication Number Publication Date
CN207553562U true CN207553562U (en) 2018-06-29

Family

ID=62666723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721715278.2U Expired - Fee Related CN207553562U (en) 2017-12-07 2017-12-07 A kind of combination moving type scaffold

Country Status (1)

Country Link
CN (1) CN207553562U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109707146A (en) * 2018-12-29 2019-05-03 中国二十冶集团有限公司 Simple overhanging type slides scaffold construction method
CN113565312A (en) * 2021-08-23 2021-10-29 江苏广前建设集团有限公司 A suspension type scaffold for demolising tall and erect structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109707146A (en) * 2018-12-29 2019-05-03 中国二十冶集团有限公司 Simple overhanging type slides scaffold construction method
CN113565312A (en) * 2021-08-23 2021-10-29 江苏广前建设集团有限公司 A suspension type scaffold for demolising tall and erect structure
CN113565312B (en) * 2021-08-23 2024-03-26 江苏广前建设集团有限公司 Suspended scaffold for dismantling towering structures

Similar Documents

Publication Publication Date Title
CN203961992U (en) Portable full framing chassis
CN204715722U (en) A kind of all steel attachment type raise scaffold
CN103291066B (en) A kind of construction elevator wall-attached frame servicing unit reinforcement means
CN203669395U (en) Protective operation hanging frame for top die system
CN204715715U (en) Folding movable scaffold
CN206873495U (en) A kind of Portable piping lane side wall formwork jumbo
CN206829570U (en) A kind of modularization scaffold of packaged type
CN206053279U (en) Tool type scaffold unit and tool type scaffold
CN105019657A (en) Building construction system
CN201148726Y (en) Independent climbing frame super large operating platform
CN205296792U (en) A lifting scaffold
CN209760744U (en) Detachable tunnel moving scaffold vehicle
CN209261192U (en) A portable scaffolding
CN104278830A (en) Integral combined scaffold
CN112723094A (en) Integrated wall-attached device based on synchronous climbing of light steel platform
CN207003972U (en) Movable construction operation platform
CN210622261U (en) A mobile scaffold with telescopic pedals
CN205330195U (en) Safety device of outer wall scaffold
CN207063484U (en) Movable operating platform for corridor construction
CN209397897U (en) A kind of Multi-functional indoor scaffold
CN106760458B (en) Movable multipurpose operation guard and method of use
CN205000618U (en) Novel scaffold
CN209874433U (en) A modular integral mobile operating frame
CN205591506U (en) Scaffold
CN204435813U (en) Care-supporting movable Scaffold protected by a kind of band

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180629

Termination date: 20201207

CF01 Termination of patent right due to non-payment of annual fee