CN207526105U - A kind of support platform poured for floorboard - Google Patents

A kind of support platform poured for floorboard Download PDF

Info

Publication number
CN207526105U
CN207526105U CN201721609466.7U CN201721609466U CN207526105U CN 207526105 U CN207526105 U CN 207526105U CN 201721609466 U CN201721609466 U CN 201721609466U CN 207526105 U CN207526105 U CN 207526105U
Authority
CN
China
Prior art keywords
support body
support
supporting leg
location hole
floorboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721609466.7U
Other languages
Chinese (zh)
Inventor
陈玉达
郭志超
戴艳
郝云艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201721609466.7U priority Critical patent/CN207526105U/en
Application granted granted Critical
Publication of CN207526105U publication Critical patent/CN207526105U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model belongs to construction engineering technical field, more particularly to a kind of support platform poured for floorboard, solving the problems, such as existing floorboard support, in the presence of setting up, dismounting is cumbersome and occupancy floor space is unfavorable for greatly construction personnel and passes through using during scaffold, the first support body and the second support body including relative motion is connected and be capable of by sliding rail, limiting device is provided between first support body and the second support body, first support body and the second support body bottom symmetrical are provided with the supporting leg that can be dismantled, the bottom of supporting leg is connected with hydraulic jack.The utility model avoids a large amount of the problems such as using the dismounting brought during scaffold cumbersome, and without using supporting leg under state and the first support body, supporting leg and the second support body and supporting leg and hydraulic jack can remove separation, facilitate storage, carrying and secondary use.

Description

A kind of support platform poured for floorboard
Technical field
The utility model belongs to construction engineering technical field, and in particular to a kind of support platform poured for floorboard.
Background technology
Floorboard directly influences whole building as the quality of its pouring quality of the important component of building body Quality standard.In construction, the maintenance processes after the pouring or pour of floorboard are required to carry out floorboard Effectively support, to reach the indeformable purpose of floorboard.Traditional support is realized by scaffold, although scaffolding work category In a ripe subdivisional work, but since it is set up there are some potential safety problems and according to national standard, scaffold building Region, height and spacing etc. have strict requirements, it is very big usually to set up the scaffolding pole of completion its density, not only takes If when it is time-consuming and laborious, be unfavorable for passing through for construction personnel, removed after the completion of use also very cumbersome.
Invention content
The utility model is removed cumbersome and occupies building to solve the support of existing floorboard using existing to set up during scaffold Sheaf space be unfavorable for greatly construction personnel by the problem of, provide a kind of support platform poured for floorboard.
The utility model is achieved by the following technical solution:A kind of support platform poured for floorboard, including It is connected by sliding rail and is capable of the first support body and the second support body of relative motion, the first support body and the Limiting device is provided between two support bodies, the first support body and the second support body bottom symmetrical are provided with can The supporting leg of dismounting, the bottom of supporting leg are connected with hydraulic jack.
It is multiple that limiting device, which includes the location hole A of positioning bolt and positioning bolt connection and location hole B, location hole A, And be symmetrical arranged on the second support body surface in two rows, location hole B is set for 2 and on the first support body surface, The spacing of location hole B and the spacing of two row location hole A are adapted, and location hole A is blind hole, and location hole B is the counterbore of perforation.
Supporting leg is fixedly connected with hydraulic jack by ring flange.
First support body is connected through a screw thread with supporting leg.
The length of second support body be the first support body length 1/3~1/2, and the first support body and Effective bearing length that second support body forms support element is 5~8 meters.
First support body or the second support body are both provided with tapped block with supporting leg connecting portion With reinforcement connection sheet, block is inverted T-type structure, strengthens the lower part that connection sheet is arranged on block.
The advantageous effect that the utility model is reached is:
The utility model is simple in structure, reasonable design, connects hydraulic jack by supporting leg, coordinates the first support element sheet Body and the second support body, effectively play preferable supporting role instead of scaffold, simultaneously because the first support element Ontology and the second support body are telescopic structure so that the support plate that the two is formed has support range preferable suitable Ying Xing needs to carry out the selection of hydraulic jack by calculating before floorboard support, and the utility model is suitable for the overwhelming majority Floorboard support occasion, avoid it is a large amount of using scaffold when the dismounting that brings it is cumbersome the problems such as, and under without using state Supporting leg and the first support body, supporting leg and the second support body and supporting leg and hydraulic jack can remove Separation, facilitates storage, carrying and secondary use.
Description of the drawings
Fig. 1 is the structure diagram of the utility model;
Fig. 2 is the cross-sectional view of the utility model.
In figure:The first support bodies of 1-, 2- hydraulic jacks, 3- positioning bolts, the second support bodies of 4-, 5- positioning Hole A, 6- sliding rail, 7- supporting legs, 8- ring flanges, 9- location holes B, 10- block, 11- strengthen connection sheet.
Specific embodiment
The utility model is further elaborated with reference to Fig. 1~Fig. 2, a kind of support platform poured for floorboard, The first support body 1 and the second support body 4 including relative motion is connected and be capable of by sliding rail 6, the first support element Limiting device, 4 bottom pair of the first support body 1 and the second support body are provided between 1 and second support body 4 of ontology Claim to be provided with the supporting leg 7 that can be dismantled, the bottom of supporting leg 7 is connected with hydraulic jack 2.
Supporting leg 7 is fixedly connected with hydraulic jack 2 by ring flange 8.First support body 1 passes through with supporting leg 7 It is threadedly coupled.The length of second support body 4 is the 1/3~1/2 of 1 length of the first support body, and the first support element sheet Effective bearing length that 1 and second support body 4 of body forms support element is 5~8 meters.
The utility model is stored before use for detachable, i.e.,:Supporting leg 7, hydraulic jack 2, the first support body 1 It is respectively stored with the second support body 4.
It is connected between first support body 1 and the second support body 4 by sliding rail 6, sliding rail is separately positioned on first The bottom both ends junction of 1 and second support body 4 of support body, supporting leg 7 respectively with the first support body 1 or the Two support bodies 4 are connected through a screw thread, and the first support body 1 or the second support body 4 and 7 connecting portion of supporting leg are equal Tapped block 10 and tapped reinforcement connection sheet 11 are provided with, block 10 is inverted T-type structure, strengthens connection sheet 11 It is arranged on the lower part of block 10.Be provided with the external screw thread that can be matched with internal thread on supporting leg 7, the bottom end of supporting leg 7 and The top of hydraulic jack 2 is connected separately with the ring flange 8 being arranged in pairs.
In use, respectively by supporting leg 7, hydraulic jack 2, the first support body 1 and the second support body 4 according to Sequence from top to bottom is assembled successively, according to the length of floorboard to be supported, adjusts the first support body 1 and second In the effective length to zone of reasonableness of support body 4, the two is positioned using limiting device.Wherein, limiting device includes The location hole A5 and location hole B9, location hole A5 that positioning bolt 3 and positioning bolt 3 connect are multiple and in the second support element sheet 4 surface of body is symmetrical arranged in two rows, and location hole B9 is set for 2 and on 1 surface of the first support body, the spacing of location hole B9 It is adapted with the spacing of two row location hole A5, location hole A5 is blind hole, and location hole B9 is the counterbore of perforation.
Further, adjust the stroke of hydraulic jack 2, make the first support body 1 and the second support body 4 with Floorboard to be poured is held out against.Since the first support body 1 and the second support body 4 are not at same level, i.e., The height of two support bodies, 4 to the first support body 1 is slightly lower, in Specific construction, can expire in the second support body 4 Spread a steel plate.Wherein, the thickness of steel plate is identical with the difference in height of the first support body 1 and the second support body 4.

Claims (6)

1. a kind of support platform poured for floorboard, including passing through sliding rail(6)Connect and be capable of first of relative motion Support body(1)With the second support body(4), it is characterised in that:First support body(1)With the second support body (4)Between be provided with limiting device, the first support body(1)With the second support body(4)Bottom symmetrical, which is provided with, to be torn open The supporting leg unloaded(7), supporting leg(7)Bottom be connected with hydraulic jack(2).
2. a kind of support platform poured for floorboard according to claim 1, it is characterised in that:Limiting device includes Positioning bolt(3)And positioning bolt(3)The location hole A of connection(5)With location hole B(9), location hole A(5)It is multiple and Two support bodies(4)Surface is symmetrical arranged in two rows, location hole B(9)For 2 and in the first support body(1)Surface is set It puts, location hole B(9)Spacing and two row location hole A(5)Spacing be adapted, location hole A(5)For blind hole, location hole B(9)For The counterbore of perforation.
3. a kind of support platform poured for floorboard according to claim 1, it is characterised in that:Supporting leg(7)With Hydraulic jack(2)Pass through ring flange(8)It is fixedly connected.
4. a kind of support platform poured for floorboard according to claim 1 or 2, it is characterised in that:First support Part ontology(1)With supporting leg(7)It is connected through a screw thread.
5. a kind of support platform poured for floorboard according to claim 1 or 2, it is characterised in that:Second support Part ontology(4)Length be the first support body(1)The 1/3~1/2 of length, and the first support body(1)With second Support body(4)Effective bearing length of formed support element is 5~8 meters.
6. a kind of support platform poured for floorboard according to claim 5, it is characterised in that:First support element sheet Body(1)Or second support body(4)With supporting leg(7)Connecting portion is both provided with tapped block(10)Connect with reinforcement Contact pin(11), block(10)For inverted T-type structure, strengthen connection sheet(11)It is arranged on block(10)Lower part.
CN201721609466.7U 2017-11-28 2017-11-28 A kind of support platform poured for floorboard Expired - Fee Related CN207526105U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721609466.7U CN207526105U (en) 2017-11-28 2017-11-28 A kind of support platform poured for floorboard

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721609466.7U CN207526105U (en) 2017-11-28 2017-11-28 A kind of support platform poured for floorboard

Publications (1)

Publication Number Publication Date
CN207526105U true CN207526105U (en) 2018-06-22

Family

ID=62580485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721609466.7U Expired - Fee Related CN207526105U (en) 2017-11-28 2017-11-28 A kind of support platform poured for floorboard

Country Status (1)

Country Link
CN (1) CN207526105U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110541563A (en) * 2019-08-23 2019-12-06 宜昌楚鑫建设有限责任公司 building template

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110541563A (en) * 2019-08-23 2019-12-06 宜昌楚鑫建设有限责任公司 building template

Similar Documents

Publication Publication Date Title
CN102817484B (en) Heavy multifunctional combined supporting frame
CN204781929U (en) Convenient intelligent hydraulic pressure jacking die carrier system of standard form shellfish thunder frame of assembling
CN206800949U (en) Operating platform for construction work high above the ground
CN203223003U (en) Detachable triangular jig frame for steel truss assembling
CN207526105U (en) A kind of support platform poured for floorboard
CN204645570U (en) One can have enough to meet the need elevator shaft protective platform
CN104179352B (en) Detachable template system
CN206581579U (en) A kind of track-type facilities of elevating scaffold
CN204040450U (en) A kind of for angle connector in tools type section steel builder's jack
CN205116883U (en) Mast hoisting device of superelevation layer steel construction launching tower
CN204662383U (en) A kind of draft tube of hydropower station inspection platform
CN206693642U (en) A kind of positive assembled ground assembling jig frame of triangular truss
CN215946570U (en) Lifting equipment coupling mechanism for civil engineering with adjustable
CN201762664U (en) Bracket for mounting guardrail templates in bridge building
CN205282953U (en) Assembled goods shelves of spatial structure of transformer substation
CN205617772U (en) Gallows structure under lifting foot hand rack special use
CN204552051U (en) The cradle structure of high-altitude crossbeam soffit monitoring point layout
CN203451072U (en) Component for connecting crane beam and network frame
CN204354853U (en) The auxiliary construction device that a kind of electrified railway is built
CN205676914U (en) A kind of device of Fast Installation cement kiln end pylon pre-embedded bolt
CN204357100U (en) A kind of scaffold floor
CN203867167U (en) Attached lifting scaffold bottom truss
CN203462753U (en) Large steel formwork for double-layer reinforced concrete plate wall cavity construction
CN203669362U (en) Connecting device for connecting main truss of bailey frame and jacking stand column
CN204370796U (en) Hoistway formwork platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180622