CN207392221U CN201721175096.0U CN201721175096U CN207392221U CN 207392221 U CN207392221 U CN 207392221U CN 201721175096 U CN201721175096 U CN 201721175096U CN 207392221 U CN207392221 U CN 207392221U
Authority
CN
China
Prior art keywords
foundation
concrete
brick
bed course
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721175096.0U
Other languages
Chinese (zh)
Inventor
周国坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Haisheng Asphalt Co Ltd
Original Assignee
Shenzhen Haisheng Asphalt Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Haisheng Asphalt Co Ltd filed Critical Shenzhen Haisheng Asphalt Co Ltd
Priority to CN201721175096.0U priority Critical patent/CN207392221U/en
Application granted granted Critical
Publication of CN207392221U publication Critical patent/CN207392221U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model is related to a kind of foundation structure of steel plate house, including:Concrete bed course;Several foundation concrete bodies being carried on the concrete bed course, be carried on the concrete bed course, constructional column;And it is arranged on the foundation beam between the foundation concrete body and the constructional column;The foundation beam includes:The first brick foundation being connected with the concrete bed course, being embedded in underground, vertically protrude from second brick foundation on ground and be arranged between first brick foundation and the second brick foundation and the ground collar tie beam that is embedded in underground;When building, foundation concrete body and constructional column are cast in by template on concrete bed course, grade beam is poured between foundation concrete body and constructional column, meanwhile, it is configured collar tie beam between the first brick foundation and the second brick foundation in foundation beam, so set, the shearing resistance of ground is added, improves tensile strength, so that ground is more stablized, reduce the occurrence probability of building collapse accident to a certain extent, ensure that building safety.

Description

A kind of foundation structure of steel plate house
Technical field
The utility model is related to ground technical field of buildings more particularly to a kind of foundation structures of steel plate house.
Background technology
Basis of the ground as building, to the more demanding of stability, ground of the prior art, due to structure design letter It is single, ruggedized construction is not provided in corresponding position, therefore, after the completion of construction, if running into earthquake, it is this simple and Ground without ruggedized construction, easily causes that shearing resistance, tensile strength are inadequate, so that building lot so holds very much built on the sand Stiffness cracks are easily caused, so as to cause collapsing for whole building, anti-seismic performance is poor.
Utility model content
The utility model provides a kind of foundation structure of steel plate house, to find and solve ground shearing resistance, tensile strength not It is enough, the technical issues of causing ground built on the sand, even whole building caused to collapse.
A kind of foundation structure for steel plate house that the utility model first aspect provides, including:Concrete bed course;It is carried on the concrete On bed course, for bolster stake beam regular distribution several foundation concrete bodies;It is carried on the concrete bed course, for carrying side wall The constructional column of body;And it is arranged on the foundation beam for load side wall between the foundation concrete body and the constructional column;Institute Stating foundation beam includes:The first brick foundation being connected with the concrete bed course, being embedded in underground, vertically protrudes from ground , for load side wall the second brick foundation and be arranged between first brick foundation and the second brick foundation and bury Ground collar tie beam in underground.
Realize the foundation structure of the steel plate house of said program, when building, foundation concrete body and constructional column are poured by template On concrete bed course, grade beam is poured between foundation concrete body and constructional column, meanwhile, the first brick foundation and second in foundation beam Collar tie beam is configured between brick foundation, ground is so set, added the shearing resistance of ground, improve tensile strength, so that ground More stablize, reduce the occurrence probability of building collapse accident to a certain extent, ensure that building safety.
With reference to first aspect, in the first possible realization method of first aspect, described ground collar tie beam includes:Concrete It beam and is placed in the beams of concrete to reinforce the first steel reinforcement cage of the beams of concrete.
Realize the foundation structure of the steel plate house of said program, ground collar tie beam uses concrete construction, meanwhile, in ground collar tie beam Core is provided with the first steel reinforcement cage, so as to improve the shearing resistance of ground and tensile strength, meanwhile, the waterproof for improving ground is prevented Damp effect.
With reference to first aspect, in second of possible realization method of first aspect, the foundation concrete body includes:With institute The opposite another side end face in side where stating concrete bed course is equipped with the reinforced concrete pile of shearing resistance keyhole, be placed in the shearing resistance keyhole, For resisting the shear key of shearing, pour in grout blanket that is on the reinforced concrete pile and wrapping up the shear key and, pour It builds in the concrete layer for being used to wrap up the reinforced concrete pile on the grout blanket.
Realize the foundation structure of the steel plate house of said program, shear key is assemblied in reinforced concrete body and offers among shearing resistance keyhole It is sheared with resisting, then shear key is wrapped up by grout blanket and is poured on reinforced concrete body, one is finally poured on reinforced concrete pile Layer concrete layer, the foundation concrete body stability so set is high, improves the shearing resistance of ground.
Second of possible realization method with reference to first aspect, in the third possible realization method of first aspect In, the reinforced concrete pile includes:The foundation base being connected with the concrete bed course, be connected with foundation base for support main beam Concrete column and, be arranged in the foundation base and the concrete column to reinforce the reinforcing bar of the foundation base and the concrete column.
It realizes the foundation structure of the steel plate house of said program, reinforcing bar is set in the foundation base of steel bar column, makes steel by pouring Muscle is fixed in foundation base, meanwhile, the reinforcing bar mutually overlapped with the reinforcing bar in foundation base is provided in concrete column, then makes concrete by pouring Column is connected with foundation base, and the steel bar column so set is secured, while improves tensile strength.
With reference to first aspect, in the 4th kind of possible realization method of first aspect, set in the constructional column useful In the second steel reinforcement cage for reinforcing the constructional column.
It realizes the foundation structure of the steel plate house of said program, the second steel reinforcement cage is provided in constructional column, so as to promote structure The tensile strength of column is made, increases the stability of ground.
The possible realization method of with reference to first aspect the first, in the 5th kind of possible realization method of first aspect In, first brick foundation and second brick foundation are mainly built by laying bricks or stones by autoclaved fly ash brick and mortar.
Realize said program steel plate house foundation structure, the first brick foundation formed using autoclaved fly ash brick masonry and Second brick foundation, compression strength height and good frost resistance.
Second of possible realization method with reference to first aspect, in the 6th kind of possible realization method of first aspect In, the grout blanket material therefor is expansion fine-stone concrete grouting material, and the concrete layer material therefor is plain concrete.
It realizes the foundation structure of the steel plate house of said program, is poured using expansion fine-stone concrete grouting material and build up grout blanket, used Plain concrete, which pours, builds up concrete layer, economical and practical, on the premise of ground stability is not influenced, reduces construction cost.
With reference to first aspect, in the 7th kind of possible realization method of first aspect, the foundation bearing capacity is in 101- Between 150 kPas and embedded depth of foundation is between 1.45-1.55 meters.
It realizes the foundation structure of the steel plate house of said program, by embedded depth of foundation and underground, enhances the stability of ground.
Advantageous effect:By providing a kind of foundation structure of steel plate house, including:Concrete bed course;Be carried on the concrete bed course, For several foundation concrete bodies of the regular distribution of bolster stake beam;It is carried on the concrete bed course, for the construction of load side wall Column;And it is arranged on the foundation beam for load side wall between the foundation concrete body and the constructional column;The foundation beam Including:The first brick foundation being connected with the concrete bed course, being embedded in underground, vertically protrude from ground, be used for Second brick foundation of load side wall and be arranged between first brick foundation and the second brick foundation and be embedded in underground Ground collar tie beam;When building, foundation concrete body and constructional column are cast in by template on concrete bed course, while in foundation concrete body and construction Grade beam is poured between column, meanwhile, it is configured collar tie beam between the first brick foundation and the second brick foundation in foundation beam and so sets Ground is put, after the reinforcing by ground collar tie beam, the shearing resistance of ground is added, improves tensile strength, so that ground is more Stablize, reduce the occurrence probability of building collapse accident to a certain extent, ensure that building safety.
Description of the drawings
Fig. 1 is the top view of the foundation structure of the steel plate house of the utility model embodiment one.
Fig. 2 is along the sectional view of line A-A cutting in Fig. 1.
Fig. 3 is along the sectional view of line B-B cutting in Fig. 1.
Fig. 4 is along the sectional view of line C-C cutting in Fig. 1.
Reference numeral:1st, concrete bed course;2nd, foundation concrete body;3rd, constructional column;4th, foundation beam;5th, the first brick foundation;6th, the second brick Basis;7th, collar tie beam;8th, beams of concrete;9th, the first steel reinforcement cage;10th, reinforced concrete pile;11st, shear key;12nd, grout blanket;13rd, coagulation Soil layer;14th, foundation base;15th, concrete column;16th, reinforcing bar;17th, the second steel reinforcement cage;18th, indoor terrace;19th, grade.
Specific embodiment
Below in conjunction with attached drawing, the technical solution of the utility model embodiment is described.Obviously, described implementation Example is only the utility model part of the embodiment, instead of all the embodiments.Based on these embodiments, the common skill in this field Art personnel all other embodiments obtained without creative efforts, belong to the utility model to be protected The scope of shield.
Embodiment one:
As shown in Fig. 1,3,4, the present embodiment is related to a kind of foundation structure of steel plate house, including:Concrete bed course 1;It is carried on concrete Concrete bed course 1 is carried on bed course 1, for several foundation concrete bodies 2 of the regular distribution of bolster stake beam, for load side wall Constructional column 3, be provided in constructional column 3 for reinforcing constructional column 3 the second steel reinforcement cage 17 and, be arranged on foundation concrete body 2 and structure The foundation beam 4 for load side wall between column 3 is made, foundation beam 4 includes:It is being connected with concrete bed course 1, be embedded in underground First brick foundation 5, vertically protrude from ground, for load side wall the second brick foundation 6 and be arranged on first Ground collar tie beam 7 that is between 5 and second brick foundation 6 of brick foundation and being embedded in underground, ground collar tie beam 7 include:It beams of concrete 8 and is placed in The first steel reinforcement cage 9 of reinforced concrete beam is used in beams of concrete 8.
As shown in Fig. 2, foundation concrete body 2 includes:Another side end face opposite with 1 place side of concrete bed course is equipped with shearing resistance keyhole Reinforced concrete pile 10, be placed in 11 preformed hole of shear key, for resist shearing shear key 11, pour on reinforced concrete pile 10 And the grout blanket 12 that wraps up shear key 11 and, pour in the coagulation for being used to wrap up reinforced concrete pile 10 on grout blanket 12 Soil layer 13, reinforced concrete pile 10 include:The foundation base 14 being connected with concrete bed course 1, be connected with foundation base 14 for carrying master The concrete column 15 of beam and, be arranged in foundation base 14 and concrete column 15 for the reinforcing bar 16 of underpinning seat 14 and concrete column 15.
First brick foundation 5 is mainly built by laying bricks or stones by autoclaved fly ash brick and mortar;Second brick foundation 6 is mainly by steam pressure powder Coal-dust brick and mortar are built by laying bricks or stones, and 12 material therefor of grout blanket is to expand fine-stone concrete grouting material, 13 material therefor of concrete layer For plain concrete, foundation bearing capacity is between 101-150 kPas and embedded depth of foundation is between 1.45-1.55 meters.
The use principle of the foundation structure of the kind steel plate house of the present embodiment is approximately as stating:
During construction, worker is first laid with concrete bed course 1 in foundation pit, and the reinforcing bar 16 in foundation base 14 and concrete column 15 is placed To corresponding position, corresponding template is installed, by the cavity of concreting to template, by 10 formed by integrally casting of reinforced concrete pile into Type, meanwhile, it completes the first brick foundation 5 using autoclaved fly ash brick and mortar and builds by laying bricks or stones, the first steel reinforcement cage 9 places the first brick foundation Corresponding position on 5, the second steel reinforcement cage 17 are positioned between foundation concrete body 2 and vertical with the first steel reinforcement cage 9 and put straight up It puts, is fixed using corresponding template, among concreting to the template fixed, ground collar tie beam 7 and constructional column 3 one It is body formed, after pouring molding, built by laying bricks or stones on ground collar tie beam 7 using autoclaved fly ash brick and mortar the second brick foundation 6 of completion, It reserves shearing resistance keyhole during 16 concrete body of pouring reinforcement, after pouring molding, shear key 11 is placed in reserved shear key 11, simultaneously Using expansion fine-stone concrete grouting material, reuse plain concrete and wrap 10 entirety of reinforced concrete pile, the building column for completing ground is applied Work.
Autoclaved fly ash brick selection is MU20 in first brick foundation 5(The compression strength for representing this building block is 30 megapascal) Autoclaved fly ash brick, i.e. compression strength and flexural strength grade are the autoclaved fly ash brick of MU20, and mortar selection is Ms10(Table The compression strength for showing this Site mortar is 10 megapascal)Dedicated mortar;Autoclaved fly ash brick is selected in second brick foundation 6 For MU15(The compression strength for representing this building block is 15 megapascal)Flyash brick, i.e. compression strength and flexural strength grade are MU15 Pressing fly ash brick, mortar selection is Ms5(The compression strength for representing this Site mortar is 5 megapascal)Dedicated mortar.
Above example is only to illustrate the technical solution of the utility model rather than the protection domain of utility model is carried out Limitation.Although the utility model is described in detail with reference to above-described embodiment, those of ordinary skill in the art still may be used It is modified with not making creative work to the technical solution recorded in above-described embodiment, so as to obtain different, essence not Depart from the other technologies scheme of the design of the utility model, it is claimed that these technical solutions similarly belong to the utility model Scope.

Claims (8)

1. a kind of foundation structure of steel plate house, which is characterized in that including:
Concrete bed course (1);
Be carried on the concrete bed course (1), for bolster stake beam regular distribution several foundation concrete bodies (2);
It is carried on the concrete bed course (1), the constructional column (3) for load side wall;And
The foundation beam (4) for load side wall being arranged between the foundation concrete body (2) and the constructional column (3);
The foundation beam (4) includes:The first brick foundation (5) being connected with the concrete bed course (1), being embedded in underground, along perpendicular Nogata to protrude from ground, for load side wall the second brick foundation (6) and be arranged on first brick foundation (5) with Ground collar tie beam (7) that is between second brick foundation (6) and being embedded in underground.
2. the foundation structure of steel plate house according to claim 1, which is characterized in that described ground collar tie beam (7) includes:Concrete It beam (8) and is placed in the beams of concrete (8) to reinforce the first steel reinforcement cage (9) of the beams of concrete.
3. the foundation structure of steel plate house according to claim 1, which is characterized in that the foundation concrete body (2) includes:With institute The opposite another side end face in side where stating concrete bed course (1) is equipped with the reinforced concrete pile (10) of shear key (11) preformed hole, is placed in In the shearing resistance keyhole, for resist shearing shear key (11), pour in it is on the reinforced concrete pile (10) and will it is described resist Cut key (11) package grout blanket (12) and, pour on the grout blanket (12) for by the reinforced concrete pile (10) wrap The concrete layer (13) wrapped up in.
4. the foundation structure of steel plate house according to claim 3, which is characterized in that the reinforced concrete pile (10) includes:With The foundation base (14) that the concrete bed course (1) is connected, the concrete column (15) for support main beam being connected with foundation base (14), with And it is arranged in the foundation base (14) and the concrete column (15) to reinforce the foundation base (14) and the concrete column (15) Reinforcing bar (16).
5. the foundation structure of steel plate house according to claim 1, which is characterized in that set in the constructional column (3) useful In the second steel reinforcement cage (17) for reinforcing the constructional column (3).
6. the foundation structure of steel plate house according to claim 2, which is characterized in that first brick foundation (5) mainly by Autoclaved fly ash brick and mortar are built by laying bricks or stones;Second brick foundation (6) is mainly built by laying bricks or stones by autoclaved fly ash brick and mortar It forms.
7. the foundation structure of steel plate house according to claim 3, which is characterized in that grout blanket (12) material therefor is Fine-stone concrete grouting material is expanded, concrete layer (13) material therefor is plain concrete.
8. the foundation structure of steel plate house according to claim 1, which is characterized in that the foundation bearing capacity is in 101-150 Between kPa and embedded depth of foundation is between 1.45-1.55 meters.
CN201721175096.0U 2017-09-12 2017-09-12 A kind of foundation structure of steel plate house Expired - Fee Related CN207392221U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721175096.0U CN207392221U (en) 2017-09-12 2017-09-12 A kind of foundation structure of steel plate house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721175096.0U CN207392221U (en) 2017-09-12 2017-09-12 A kind of foundation structure of steel plate house

Publications (1)

Publication Number Publication Date
CN207392221U true CN207392221U (en) 2018-05-22

Family

ID=62417385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721175096.0U Expired - Fee Related CN207392221U (en) 2017-09-12 2017-09-12 A kind of foundation structure of steel plate house

Country Status (1)

Country Link
CN (1) CN207392221U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114197640A (en) * 2022-01-19 2022-03-18 中建科工集团有限公司 Arch steel structure supporting structure
CN115522645A (en) * 2022-01-29 2022-12-27 同济大学建筑设计研究院(集团)有限公司 Anchor bolt connecting structure of low-rise plate type house and foundation and installation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114197640A (en) * 2022-01-19 2022-03-18 中建科工集团有限公司 Arch steel structure supporting structure
CN115522645A (en) * 2022-01-29 2022-12-27 同济大学建筑设计研究院(集团)有限公司 Anchor bolt connecting structure of low-rise plate type house and foundation and installation method thereof

Similar Documents

Publication Publication Date Title
CN102383443B (en) Connection structures between foundation pit support piles and outer walls of basement and construction method
CN100543239C (en) One pile three-purpose method in underground engineering
CN101418569B (en) Optimized composite arch wall with combination of prefabricated arch, support and main structure
CN103195085B (en) Downward story-adding basement and construction method thereof
CN103046665B (en) Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof
CN206667459U (en) A kind of pre-splicing Standard formula building of prefabrication type reinforced concrete shear wall
CN101285330A (en) Environment protection type structure thermal insulation concrete block, masonry and method for anti-knock domestic architecture
CN108005399A (en) Add the construction method for building multi-layer underground space under a kind of existing building group
CN103953114B (en) Steel frame-reinforced masonry shear wall combinative structure and construction method thereof
CN101736832B (en) Confined masonry structure and making method thereof
CN104532957A (en) Inversed construction method for adding basement in existing building
CN103161176B (en) Tower crane foundation construction method in main building disjunctor garage
CN105421477A (en) Construction method for tower crane foundation
CN104295003A (en) Structural column construction method
CN103526781A (en) Integrated-tray, shock-insulation and reinforcing structure for historic building foundation and construction method thereof
CN207392221U (en) A kind of foundation structure of steel plate house
CN103821263A (en) Precast assembly self-heat preservation concrete shear wall system and construction method thereof
CN201722813U (en) Confined masonry structure
CN204001278U (en) A kind of prefabricated assembled self-insulating concrete shear wall system
CN106193120B (en) Basement is encorbelmented, and bottom plate is inverse to make structure and construction method
CN111980050A (en) Small foundation bearing platform formwork and construction method thereof
CN105888282B (en) A kind of seismic reinforcing structure and method that big hole is opened for transformer station's masonry wall
CN202347534U (en) Force transferring structure between foundation ditch support pile and basement outer wall
CN101469559A (en) Composite heat insulating walling and mounting method thereof
CN203603176U (en) Historic building foundation overall tray shock insulating and reinforcing structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180522

Termination date: 20180912

CF01 Termination of patent right due to non-payment of annual fee