CN207362717U CN201721061436.7U CN201721061436U CN207362717U CN 207362717 U CN207362717 U CN 207362717U CN 201721061436 U CN201721061436 U CN 201721061436U CN 207362717 U CN207362717 U CN 207362717U
Authority
CN
China
Prior art keywords
hanger
rope
anchor ear
suspension bridge
cord clip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721061436.7U
Other languages
Chinese (zh)
Inventor
窦勇芝
韦福堂
甘科
李长乐
黎祖金
宁绍锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LIUZHOU OVM ENGINEERING Co Ltd
Liuzhou OVM Machinery Co Ltd
Original Assignee
LIUZHOU OVM ENGINEERING Co Ltd
Liuzhou OVM Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIUZHOU OVM ENGINEERING Co Ltd, Liuzhou OVM Machinery Co Ltd filed Critical LIUZHOU OVM ENGINEERING Co Ltd
Priority to CN201721061436.7U priority Critical patent/CN207362717U/en
Application granted granted Critical
Publication of CN207362717U publication Critical patent/CN207362717U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of device replaced for main rope of suspension bridge cord clip, including interim anchor ear, rubber pad, hanger, steel wire rope and otic placode, hanger is formed by multiple section assemblings, interim anchor ear is separately positioned on main push-towing rope cord clip both sides and is detachably connected with main push-towing rope, temporarily rubber pad is installed between anchor ear and main push-towing rope, interim anchor ear lower part is connected with otic placode, steel wire rope one end connection otic placode, other end connection hanger.The utility model is using the hanger of sectional type assembly as construction platform, effectively it make use of main rope of suspension bridge lower space, using the interim anchor ear being anchored on main push-towing rope as counter-force fulcrum, construct light-duty, operating expenses economy, install convenient, easy to standardized construction, short time limit, influences less advantage to structure stress.

Description

A kind of device replaced for main rope of suspension bridge cord clip
Technical field
A kind of suspension bridge Measuring error technical field is the utility model is related to, is specifically that one kind is used for main rope of suspension bridge cord clip The device of replacement.
Background technology
Job platform below the main push-towing rope of main rope of suspension bridge cord clip replacement is presently used for, takes and is set up from more than bridge floor mostly Full framing mode, such as Chinese patent CN105887701A, there is provided a kind of suspension bridge superstructure is removed with replacing installation side Method, comprises the following steps:A. trestle in parallel, trestle both ends and corresponding suspension bridge both ends are set up on the outside of suspension bridge Access bridge connects;B. check the anchorage at suspension bridge both ends, determine that it is in normal operating conditions;C. suspension bridge top is removed in segmentation Former stiff girder;D. the corresponding former sunpender of former stiff girder, former cord clip are removed;E. main push-towing rope is lifted by crane by crawler crane to realize on suspension bridge The dismounting of portion's original main push-towing rope;F. new main push-towing rope is lifted by crane by crawler crane and realizes installation;G. installed by surveying and locating in relevant position new Cord clip and new sunpender;H. crawler crane merogenesis lifts by crane each section of new girder segment of putting more energy into designated position, treats girder segment peace of all newly putting more energy into After dress, all segments are connected to become entirety, this method can be reduced to remove because of suspension bridge superstructure and brought with replacing Negative effect, but have the disadvantage that:Long construction period, costly, erection construction platform operations face is big, difficult to install, work Make intensity height.
Utility model content
The purpose of this utility model is to provide a kind of device replaced for main rope of suspension bridge cord clip, with reference to Suspension bridge structure Feature, in a manner of hanger sets up full framing for construction platform progress cord clip replacement construction replacement is traditional from more than bridge floor, solution Certainly main push-towing rope cord clip replaces long construction period, and costly, progress is slow, sets up the problem of work surface is big, and working strength is high.
Technical solutions of the utility model are as follows:A kind of device replaced for main rope of suspension bridge cord clip, including interim anchor ear (1), rubber pad (2), hanger (4), steel wire rope (5) and otic placode (8), hanger (4) is assembled by multiple hanger segments (41), can According to practice of construction field condition, adjustment segment quantity increases and decreases and adjusts hanger (4) length;Interim anchor ear (1) is separately positioned on Main push-towing rope cord clip (6) both sides, interim anchor ear (1) to be detachably connected, are pacified with main push-towing rope (7) between interim anchor ear (1) and main push-towing rope (7) Rubber pad (2) is filled, the frictional force of interim anchor ear (1) and main push-towing rope (7) is added, improves fixed reliability, interim anchor ear (1) Lower part is connected with otic placode (8);One end connection otic placode (8) of steel wire rope (5), the other end are connected to opposite below otic placode (8) hang On frame (4).The effective space that make use of main rope of suspension bridge (7) lower part of the invention, to be anchored in interim armful on main push-towing rope (7) It is counter-force fulcrum to bind round (1), is connected interim anchor ear (1) with hanger (4) by steel wire rope (5), with hanger (4) for construction platform, Light-duty, operating expenses economy is constructed, install convenient, easy to standardized construction, short time limit, influences structure stress less excellent Point.
Preferably, interim anchor ear (1) includes the interim anchor ear first half (101) and lower half (102), the interim anchor ear first half (101) connected by bolt (3) with lower half (102) and clamp main push-towing rope (7), it is simple in structure, be conducive to tearing open for interim anchor ear Unload, and clamping force is adjustable.
Preferably, bolt (3) is arranged on the both sides of interim anchor ear (1), and quantity of the bolt (3) in every side is at least two And be axially uniformly distributed along main push-towing rope (7), the interim anchor ear first half (101) and lower half (102) connection uniform force, connection can By property height.
Preferably, the steel wire rope (5) is more than two.
Preferably, steel wire rope (5) and the tie point of hanger (4) are two or more, are fixed using multiple spot, prevent hanger (4) Rollover, ensure that hanger (4) connection stability and reliability.
Preferably, hanger segment (41) include hanger node (412) and hanger rod piece (411), and hanger node (412) is by three Bar steel pipe three-dimensional perpendicular interconnection forms, and three blocks of vertical with steel pipe respectively steel plates are connected with hanger node (412), horizontal It is installed on to, longitudinal and vertical hanger rod piece (411) in the steel pipe of hanger node (412), slanting hanger rod piece (411) The steel plate of hanger node (412) is connected, it is assembled simple, easy to standardized construction, reduce cost.
The beneficial effects of the utility model:
Using the hanger of sectional type assembly as construction platform, main rope of suspension bridge is effectively make use of, to be anchored on main push-towing rope Interim anchor ear is counter-force fulcrum, is connected interim anchor ear with hanger by steel wire rope, so as to provide operation to replace main push-towing rope cord clip Platform.The hood type hanger device, which has, constructs light-duty, operating expenses economy, install convenient, easy to standardized construction, duration It is short, less advantage is influenced on structure stress.
Brief description of the drawings
Fig. 1 is a kind of structure diagram of device replaced for main rope of suspension bridge cord clip described in the utility model.
Fig. 2 is a kind of structural representation of the hanger of device replaced for main rope of suspension bridge cord clip described in the utility model Figure.
Fig. 3 is a kind of structure of the interim anchor ear of device replaced for main rope of suspension bridge cord clip described in the utility model Schematic diagram.
Fig. 4 is the partial enlarged view at B in Fig. 2.
Fig. 5 is a kind of structure of the hanger node of device replaced for main rope of suspension bridge cord clip described in the utility model Schematic diagram.
In figure:1st, interim anchor ear, 101, the interim anchor ear first half, 102, interim anchor ear lower half, 2, rubber pad, 3, spiral shell Bolt, 4, hanger, 41, hanger segment, 411, hanger rod piece, 412, hanger node, 5, steel wire rope, 6, main push-towing rope cord clip, 7, main push-towing rope, 8, Otic placode.
Embodiment:
To describe the technology contents of the utility model, the objects and the effects in detail, below in conjunction with embodiment and match somebody with somebody Attached drawing is closed to be explained.
As depicted in figs. 1 and 2:A kind of device replaced for main rope of suspension bridge cord clip, including interim anchor ear (1), rubber (2), hanger (4), steel wire rope (5) and otic placode (8) are padded, hanger (4) is assembled by multiple hanger segments (41), can be according to reality Border construction site situation, adjustment segment quantity increase and decrease and adjust hanger (4) length;Interim anchor ear (1) is separately positioned on main rope (6) both sides are pressed from both sides, to be detachably connected, rubber is installed between interim anchor ear (1) and main push-towing rope (7) with main push-towing rope (7) for interim anchor ear (1) Pad (2), add the frictional force of interim anchor ear (1) and main push-towing rope (7), improve fixed reliability, interim anchor ear (1) lower part connects It is connected to otic placode (8);One end connection otic placode (8) of steel wire rope (5), the other end are connected to hanger (4) opposite below otic placode (8) On.The effective space that make use of main rope of suspension bridge (7) lower part of the invention, is with the interim anchor ear (1) being anchored on main push-towing rope (7) Interim anchor ear (1), is connected by counter-force fulcrum by steel wire rope (5) with hanger (4), and with hanger (4) for construction platform, construction is light Type, operating expenses economy, install convenient, easy to standardized construction, short time limit, influences less advantage to structure stress.
As shown in figure 3, interim anchor ear (1) includes the interim anchor ear first half (101) and lower half (102), on interim anchor ear Half portion (101) and lower half (102) are connected by bolt (3) and clamp main push-towing rope (7), simple in structure, are conducive to interim anchor ear Dismounting, and clamping force is adjustable.
As shown in figure 3, bolt (3) is arranged on the both sides of interim anchor ear (1), quantity of the bolt (3) in every side is at least Two and along main push-towing rope (7) axially be uniformly distributed, the interim anchor ear first half (101) and lower half (102) connection uniform force, company Connect reliability height.
The steel wire rope (5) is more than two.
As shown in Fig. 2, steel wire rope (5) and the tie point of hanger (4) are two or more, are fixed using multiple spot, prevent hanger (4) turn on one's side, ensure that hanger (4) connection stability and reliability.
As shown in Figure 4:Hanger segment (41) includes hanger node (412) and hanger rod piece (411), hanger node (412) Formed by three steel pipe three-dimensional perpendicular interconnections, three blocks of vertical with steel pipe respectively steel plates be connected with hanger node (412), Horizontal, longitudinal and vertical hanger rod piece (411) is installed in the steel pipe of hanger node (412), slanting hanger rod piece (411) steel plate of hanger node (412) is connected, it is assembled simple, easy to standardized construction, reduce cost.
As shown in Figure 5:Hanger node (412) and hanger rod piece (411) are connected by screw bolts, and connection is removable, and processing is simple, Operating expenses economy.

Claims (7)

  1. A kind of 1. device replaced for main rope of suspension bridge cord clip, it is characterised in that:Including interim anchor ear (1), rubber pad (2), Hanger (4), steel wire rope (5) and otic placode (8), the hanger (4) is assembled by more than one hanger segment (41), described interim Anchor ear (1) be arranged on main push-towing rope cord clip (6) both sides and main push-towing rope (7) it is detachably connected, the interim anchor ear (1) and main push-towing rope (7) Between rubber pad (2) is installed, described interim anchor ear (1) lower part is connected with otic placode (8), one end connection institute of the steel wire rope (5) Otic placode (8) is stated, the other end is connected on the hanger (4) opposite below the otic placode (8).
  2. A kind of 2. device replaced for main rope of suspension bridge cord clip according to claim 1, it is characterised in that:It is described interim Anchor ear (1) includes the interim anchor ear first half (101) and lower half (102), the interim anchor ear first half (101) and the lower half Portion (102) is connected by bolt (3) and clamps the main push-towing rope (7).
  3. A kind of 3. device replaced for main rope of suspension bridge cord clip according to claim 2, it is characterised in that:The bolt (3) both sides of the interim anchor ear (1) are arranged on, quantity of the bolt (3) in every side is at least two and along main push-towing rope (7) Axially it is uniformly distributed.
  4. 4. a kind of device replaced for main rope of suspension bridge cord clip according to any one in claims 1 to 3, its feature It is:The steel wire rope (5) is more than two.
  5. 5. according to a kind of device replaced for main rope of suspension bridge cord clip described in claim 4, it is characterised in that:It is described every One group of steel wire rope (5) and the tie point of the hanger (4) are two or more.
  6. A kind of 6. device replaced for main rope of suspension bridge cord clip according to claim 5, it is characterised in that:The hanger Segment (41) includes hanger node (412) and hanger rod piece (411), and the hanger node (412) is by three steel pipe three-dimensional perpendiculars Interconnection forms, and three blocks of vertical with the steel pipe respectively steel plates, horizontal, longitudinal direction are connected with the hanger node (412) It is installed on the vertical hanger rod piece (411) in the steel pipe of the hanger node (412), the slanting hanger rod piece (411) steel plate of the hanger node (412) is connected.
  7. A kind of 7. device replaced for main rope of suspension bridge cord clip according to claim 6, it is characterised in that:The hanger Node (412) and hanger rod piece (411) are connected by screw bolts.
CN201721061436.7U 2017-08-23 2017-08-23 A kind of device replaced for main rope of suspension bridge cord clip Active CN207362717U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721061436.7U CN207362717U (en) 2017-08-23 2017-08-23 A kind of device replaced for main rope of suspension bridge cord clip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721061436.7U CN207362717U (en) 2017-08-23 2017-08-23 A kind of device replaced for main rope of suspension bridge cord clip

Publications (1)

Publication Number Publication Date
CN207362717U true CN207362717U (en) 2018-05-15

Family

ID=62422489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721061436.7U Active CN207362717U (en) 2017-08-23 2017-08-23 A kind of device replaced for main rope of suspension bridge cord clip

Country Status (1)

Country Link
CN (1) CN207362717U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958064A (en) * 2019-04-15 2019-07-02 中国十七冶集团有限公司 A kind of interim scattered noose device and its application method of erecting suspension bridge main push-towing rope
CN110820522A (en) * 2019-11-22 2020-02-21 柳州欧维姆机械股份有限公司 Sling conversion device for replacing main cable of suspension bridge, sling and construction method
CN111585039A (en) * 2020-05-18 2020-08-25 柳州欧维姆工程有限公司 Replacement method for FAST reflecting surface unit self-adaptive connecting mechanism

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958064A (en) * 2019-04-15 2019-07-02 中国十七冶集团有限公司 A kind of interim scattered noose device and its application method of erecting suspension bridge main push-towing rope
CN110820522A (en) * 2019-11-22 2020-02-21 柳州欧维姆机械股份有限公司 Sling conversion device for replacing main cable of suspension bridge, sling and construction method
CN111585039A (en) * 2020-05-18 2020-08-25 柳州欧维姆工程有限公司 Replacement method for FAST reflecting surface unit self-adaptive connecting mechanism
CN111585039B (en) * 2020-05-18 2021-07-27 柳州欧维姆工程有限公司 Replacement method for FAST reflecting surface unit self-adaptive connecting mechanism

Similar Documents

Publication Publication Date Title
CN207362717U (en) A kind of device replaced for main rope of suspension bridge cord clip
CN104088449B (en) Safe and fast double-track construction platform of super high-rise curtain wall
CN101210418A (en) Non-floor-bracket construction method for suspension bridge tower frame cross beam
CN104594206B (en) A kind of steel truss girder vertical shift suspension type draws anchoring part and method
CN107761570A (en) It is a kind of to be accurately positioned suspension bracket for longspan steel truss girder
CN205558958U (en) Hoist device of tunnel efflux fan
CN106758846A (en) Cast-in-place box beam bracket and construction method
CN107642049A (en) A kind of device and its installation method changed for main rope of suspension bridge cord clip
CN105952133A (en) Suspended large-span reinforced concrete structure construction steel platform and construction method
CN201284551Y (en) Suspension type simple platform for work high above ground
CN203199913U (en) Assembling and disassembling type hoisting truss
CN205741926U (en) Stretch-draw prepressing device in Cast-in-situ Beam steel pipe beret truss platform
CN206418388U (en) The prefabricated middle cross beam of large-span steel bowstring arch bridge, which is installed, uses hanging structure system
CN106245531A (en) Steel structural bridge installation method is hung under bilateral derrick type
CN206874293U (en) Subway tunnel soft oil support device
CN207512597U (en) A kind of expansion joint section bar positioning device
CN206051218U (en) Machine-roomless lift car universal cord head fixing device
CN206426873U (en) A kind of high headroom section contact net cantilever beam of urban track traffic
CN205188837U (en) Cable suspension device suitable for hang basket
CN204212069U (en) A kind of building operations Hanging Basket
CN204826220U (en) Location built -in fitting with U type groove
CN108330833A (en) The method for installing long-span arch bridge tie-rod
CN205347998U (en) Resist pier horizontal force device
CN203794392U (en) Supporting structure for lengthening wall-attached component of construction hoist
CN214743759U (en) Foundation pit pipeline suspension frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant