CN207142683U - Wharf slab installs special gantry crane - Google Patents

Wharf slab installs special gantry crane Download PDF

Info

Publication number
CN207142683U
CN207142683U CN201720695618.3U CN201720695618U CN207142683U CN 207142683 U CN207142683 U CN 207142683U CN 201720695618 U CN201720695618 U CN 201720695618U CN 207142683 U CN207142683 U CN 207142683U
Authority
CN
China
Prior art keywords
crane
cucurbit
group
gantry crane
wheel group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720695618.3U
Other languages
Chinese (zh)
Inventor
郁鸣
范宏明
李兴才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Gray Hoisting Machinery Co Ltd That Rises Abruptly
Original Assignee
Jiangsu Gray Hoisting Machinery Co Ltd That Rises Abruptly
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Gray Hoisting Machinery Co Ltd That Rises Abruptly filed Critical Jiangsu Gray Hoisting Machinery Co Ltd That Rises Abruptly
Priority to CN201720695618.3U priority Critical patent/CN207142683U/en
Application granted granted Critical
Publication of CN207142683U publication Critical patent/CN207142683U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ship Loading And Unloading (AREA)

Abstract

The utility model discloses a kind of wharf slab to install special gantry crane, specially single-motor double suspension centre structure, ensure two suspension centre synchronization liftings, improve it and run balance and stability performance, in addition traveling mechanism of the larger traveller is unilateral three wheel group structures, reduce manufacturing cost, the setting of cucurbit slew gear, effectively increase the working area of crane.The utility model is simple in construction, layout designs are reasonable, security performance is high, improves operation balance and stability performance and has widened working area, not only increase operating efficiency and substantially reduce wharf slab install special gantry crane operation and maintenance cost, practical value it is notable.

Description

Wharf slab installs special gantry crane
Technical field
The hoisting mechanism for trolley of crane is the utility model is related to, especially a kind of wharf slab installs special gate-type lifting Machine.
Background technology
With the fast development of China's economic, process again, logistics, demand of the industry-by-industry such as infrastructure to crane Increasing, the demand of various special purpose cranes is also more and more, such as:Coloring crane, there is crane for being accurately positioned requirement etc..
In order to have a spacing on offshore side in the deepwater wharf of coastal or riverine construction energy berthing large ship, general use From deepwater regions build a seat height stake beam and slab type Wharf Platform, be connected by several access bridges with land.When Wharf Platform is built, Need first by more engineering sunk piles to river bottom or seabed, in engineering pile upper end, prefabricated diameter is more than the concrete in engineering pile stake footpath Pile cover, and on pile cover top between it is prefabricated form grid-shaped crisscross connection multiple row longeron and multirow crossbeam, in harbour Outside large-scale floating crane is pre- by polylith by the prefabricated wharf slab handling being placed on the square barge in its one side to pier The longitudinally adjacent side of wharf slab processed is laid on the adjacent longeron of two row with connecting successively.So repeat to lay precast beam by column Plate, until completing the laying of large pier precast beam.
Conventional harbour width is in 30-40m or so, including fixed width degree harbour and the fixed width degree code of harbour lateral dimension change Head, harbour of the width more than 40m are referred to as ultra-wide harbour.Ultra-wide harbour needs to carry out handling with the longer large-scale floating crane of arm in building Operation, the manufacture of one side large-scale floating crane and construction cost are expensive, on the other hand by tidal level and wind in its running Wave has a great influence, up and down balance system poor-performing.
Therefore, it is necessary to which a kind of new technical scheme is to solve the above problems.
Utility model content
Purpose of utility model:In order to solve the problems of prior art, the utility model provides a kind of structure letter List, layout designs are reasonable, and security performance is high, improves operating efficiency, reduces operating cost, effectively improves the harbour face of working area Plate installs special gantry crane.
Technical scheme:To reach above-mentioned purpose, the utility model can adopt the following technical scheme that:Wharf slab installation is special Gantry crane, specially single-motor double suspension centre structure, by door frame, lifting mechanism, traveling mechanism of the larger traveller, cucurbit slew gear with And electrical equipment composition;The door frame includes lifting machine framework, supporting leg and sill composition;The traveling mechanism of the larger traveller is single The wheel group structure of side three, wherein stress side are provided with the first wheel group and the second wheel group with bogie frame combined support, opposite side Provided with the 3rd wheel group;The bogie frame group is provided with " three-in-one " decelerator;The cucurbit slew gear is located at crane Side, including electric block, slewing equipment and cucurbit that left rotation and right rotation angle is 20 ° run I-steel;The electric block I-steel is run by slewing equipment and cucurbit and is connected to crane side.
Further, the lifting mechanism include variable-frequency motor, shaft coupling, compensator, brake, decelerator, reel, Steel wire rope, fixed pulley group and suspension hook group.
Beneficial effect:Wharf slab disclosed in the utility model installs special gantry crane, specially single-motor double Suspension centre structure, ensure two suspension centre synchronization liftings, improve it and run balance and stability performance, traveling mechanism of the larger traveller is unilateral three cars in addition Wheel group structure, reduces manufacturing cost, the setting of cucurbit slew gear, effectively increases the working area of crane.This practicality New structure is simple, and layout designs are reasonable, and security performance is high, improve operation balance and stability performance and has widened working area, Not only increase operating efficiency and substantially reduce operation and maintenance cost that wharf slab installs special gantry crane, it is practical Value is notable.
Brief description of the drawings
Fig. 1 is that the utility model embodiment wharf slab installs special gate-type crane structure schematic front view;
Fig. 2 is that the utility model embodiment wharf slab installs special gate-type crane structure left view schematic diagram;
Fig. 3 is that the utility model embodiment wharf slab installs special gate-type crane structure schematic top plan view.
Embodiment
With reference to the accompanying drawings and detailed description, the utility model is furtherd elucidate, it should be understood that following specific embodiment parties Formula is merely to illustrate the utility model rather than limitation the scope of the utility model, after the utility model has been read, this Modification of the art personnel to the various equivalent form of values of the present utility model falls within what the application appended claims were limited Scope.
Embodiment 1:
Refer to shown in Fig. 1-Fig. 3, the utility model discloses a kind of wharf slab to install special gantry crane,
Wharf slab installs special gantry crane, is single-motor double suspension centre structure, specifically by door frame 1, lifting mechanism 2, Traveling mechanism of the larger traveller 3, cucurbit slew gear 4 and electrical equipment 5 form;The door frame 1 includes lifting machine framework 11, supporting leg 12 And sill 13 forms;The traveling mechanism of the larger traveller 3 is unilateral three wheel group structures, and wherein stress side is provided with bogie frame group 31 close the first wheel group 32 and the second wheel group 33 of support, and opposite side is provided with the 3rd wheel group 34;In the bogie frame group 31 Provided with " three-in-one " decelerator 35;The cucurbit slew gear 4 is located at the side of crane, including left rotation and right rotation angle is 20 ° Electric block 41, slewing equipment 42 and cucurbit operation I-steel 43;The electric block 41 by slewing equipment 42 and Cucurbit operation I-steel 43 is connected to crane side.
Wherein, the lifting mechanism 2 includes variable-frequency motor, shaft coupling, compensator, brake, decelerator, reel, steel wire Rope, fixed pulley group and suspension hook group, are additionally provided with overload protection and limit protection.
A kind of wharf slab of the utility model installs special gantry crane and uses single-motor double design of lifting points, and two suspension centres are same Step lifting so that wharf slab remains horizontal in operation process, convenient and swift during installation, not only increases operating efficiency, It also assures that the stable equilibrium in operation operation process;In addition unilateral three wheel group structures, the system of crane is effectively reduced This is caused, the cucurbit revolving structure of 20 ° of left rotation and right rotation, plays booster action when carrying out wharf slab lifting, further The working area of crane has been widened, has expanded Work Space Range, has improved operating efficiency, has expanded application space, practical value shows Write.
In addition this device structure is reasonable in design, meets user's special operation condition construction requirement, and the compact maintenance side of structure design Just, profile simple and beautiful, manufacturing cost are low.
User's application report:
It is 25t to hand over two boat offices to look into nation's harbour project to carry out 25t-8.5m i.e. lifting capacity in Thailand and Huang Lan in user, across 8.5m is spent, lifting altitude 2.4m wharf slab motor-driven carrier bridge crane is entered using the structure of the utility model embodiment 1 Row design, effect is fine after customer response dolly raising uses new structure, and from crane installation so far, operation conditions is good and gives On-site maintenance and maintenance offer convenience, and production efficiency greatly improved, and reduce production cost.

Claims (2)

1. wharf slab installs special gantry crane, it is characterised in that is single-motor double suspension centre structure, specifically by door frame(1)、 Lifting mechanism(2), traveling mechanism of the larger traveller(3), cucurbit slew gear(4)And electrical equipment(5)Composition;The door frame(1)Bag Include lifting machine framework, supporting leg and sill;The traveling mechanism of the larger traveller(3)For unilateral three wheel group structures, wherein stress side Provided with bogie frame group(31)Close the first wheel group of support(32)With the second wheel group(33), opposite side is provided with the 3rd wheel group (34);The bogie frame group(31)It is provided with " three-in-one " decelerator(35);The cucurbit slew gear(4)Located at crane Side, including the electric block that left rotation and right rotation angle is 20 °(41), slewing equipment(42)And cucurbit operation I-steel(43); The electric block(41)Pass through slewing equipment(42)And cucurbit operation I-steel(43)It is connected to crane side.
2. wharf slab according to claim 1 installs special gantry crane, it is characterised in that:The lifting mechanism (2)Including variable-frequency motor, shaft coupling, compensator, brake, decelerator, reel, steel wire rope, fixed pulley group and suspension hook group.
CN201720695618.3U 2017-06-15 2017-06-15 Wharf slab installs special gantry crane Active CN207142683U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720695618.3U CN207142683U (en) 2017-06-15 2017-06-15 Wharf slab installs special gantry crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720695618.3U CN207142683U (en) 2017-06-15 2017-06-15 Wharf slab installs special gantry crane

Publications (1)

Publication Number Publication Date
CN207142683U true CN207142683U (en) 2018-03-27

Family

ID=61671197

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720695618.3U Active CN207142683U (en) 2017-06-15 2017-06-15 Wharf slab installs special gantry crane

Country Status (1)

Country Link
CN (1) CN207142683U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114057099A (en) * 2021-12-15 2022-02-18 浙江数智交院科技股份有限公司 Ship lock maintenance door machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114057099A (en) * 2021-12-15 2022-02-18 浙江数智交院科技股份有限公司 Ship lock maintenance door machine

Similar Documents

Publication Publication Date Title
CN101476294B (en) Method for mounting lower beam section of large-span steel box girder cable-stayed bridge tower
CN103061264B (en) Method and device for pre-pressing high-position support single column in water
CN101509229B (en) Method for constructing side span beam section without joist bracket of large-span steel box girder cable-stayed bridge
CN101487233B (en) Method for mounting temporary pier top beam section of large-span steel box girder cable-stayed bridge
CN112695696A (en) Integrated construction equipment for superstructure of high-pile wharf and construction method thereof
CN202557745U (en) Multi-functional double-hull wind power engineering ship for offshore high-altitude heavy-load lifting and installation operations
CN110468743B (en) A mobile hanger and construction method for the renovation of old bridge pier caps
CN100572673C (en) Span continuous beam bridge fabrication machine in a kind of
CN102582786A (en) Building process for deep sea spar platform
CN205820738U (en) A kind of jack up lifting device of bank bridge
CN106638530A (en) Process for lifting offshore booster station jacket in shallow water
CN207142683U (en) Wharf slab installs special gantry crane
CN203238655U (en) Offshore wind power single pile foundation-based tidal current energy power generation foundation structure
CN110644380B (en) A method for installing beams and slabs in narrow space of a widening project of a long-span flyover bridge
CN205917601U (en) Integrally lift up device of bridge arch rib
CN103193152B (en) Hoisting device and method of chain bucket ship unloader
CN205934730U (en) Installation device of wave form steel web
CN105883324A (en) Vertical lifting and horizontal transferring system for fish collecting box
CN105692465A (en) Cableway type fish collection box dam-loading transfer system
CN216336227U (en) Device for high-rise building construction by adopting hydraulic jacking assembly
CN202492298U (en) Simple portal crane used for construction of large quay
CN214456325U (en) Gantry crane beam lifting machine with high legs and low legs
CN204224987U (en) A kind of continuous girder bridge multiple pipeline installation structure
CN202264869U (en) Water transport device for temporary tailrace gates of hydropower stations
CN105804087A (en) Installation method for steel structure below large deep foundation pit supporting beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant