CN207092971U - Layered production string - Google Patents
Layered production string Download PDFInfo
- Publication number
- CN207092971U CN207092971U CN201720947904.4U CN201720947904U CN207092971U CN 207092971 U CN207092971 U CN 207092971U CN 201720947904 U CN201720947904 U CN 201720947904U CN 207092971 U CN207092971 U CN 207092971U
- Authority
- CN
- China
- Prior art keywords
- electric water
- oil
- tubing
- layered
- packer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本实用新型公开了一种分层采油管柱,属于油气开采技术领域,所述分层采油管柱包括多个封隔器和多个电动堵水装置,相邻的两个所述封隔器之间设置有一个所述电动堵水装置,最下方的所述封隔器的下端连接有一个所述电动堵水装置;所述封隔器与相邻的所述电动堵水装置通过油管短节连接。本实用新型提供的分层采油管柱在进行分层开采的同时,获取不同油层的产能、液性和含水量等数据资料。
The utility model discloses a layered oil recovery string, which belongs to the technical field of oil and gas exploitation. The layered oil recovery string includes a plurality of packers and a plurality of electric water blocking devices, and two adjacent packers An electric water blocking device is arranged between them, and the lower end of the lowermost packer is connected to one of the electric water blocking devices; the packer and the adjacent electric water blocking device are shorted by oil pipe section connection. The layered oil production string provided by the utility model obtains data such as production capacity, fluidity, and water content of different oil layers while performing layered extraction.
Description
技术领域technical field
本实用新型涉及油气开采技术领域,特别涉及一种分层测试采油管柱。The utility model relates to the technical field of oil and gas exploitation, in particular to a layered test oil production string.
背景技术Background technique
油井正常生产过程中,由于油田的不同油层的层间差异大,层间干扰比较严重,各产层对于整体的产液能力贡献不同,需要对油井进行分层试油,以准确获取各小层的产能、液性及含水量等数据资料,进而指导油气开采方案的制定。During the normal production process of oil wells, due to the large interlayer differences of different oil layers in the oilfield and the serious interlayer interference, each production layer contributes differently to the overall fluid production capacity. The production capacity, fluidity and water content and other data can guide the formulation of oil and gas production plans.
一种现有技术提供了一种分层采油管柱,该分层采油管柱包括多个封隔器,多个封隔器之间采用油管短节连接。在进行分层采油时,将待开采的油层上方的封隔器坐封,油层内的油进入到油管短节内,并从油井口流出;之后,将已坐封封隔器上方的封隔器坐封,开采已开采油层上方的油层。A prior art provides a layered oil production string, the layered oil production string includes a plurality of packers, and the plurality of packers are connected by tubing nipples. When carrying out oil production in separate layers, set the packer above the oil layer to be exploited, and the oil in the oil layer enters the short joint of the tubing and flows out from the oil wellhead; after that, the packer above the set packer is set The device is set to exploit the oil layer above the exploited oil layer.
在实现本实用新型的过程中,设计人发现现有技术至少存在以下问题:In the process of realizing the utility model, the designer finds that the prior art has at least the following problems:
采用现有技术提供的分层采油管柱在进行开采时,不能获取各油层的产能、液性及含水量等数据资料。When the layered oil production string provided by the prior art is used for production, the data such as productivity, fluidity and water content of each oil layer cannot be obtained.
实用新型内容Utility model content
有鉴于此,本实用新型提供一种分层采油管柱,在进行分层开采油层的同时,配合其他设备可获取不同油层的产能、液性及含水量等数据资料。In view of this, the utility model provides a layered oil production string, which can obtain data such as production capacity, fluidity and water content of different oil layers by cooperating with other equipment while performing layered oil recovery.
具体而言,本实用新型提供了一种分层采油管柱,包括多个封隔器和多个电动堵水装置,相邻的两个所述封隔器之间设置有一个所述电动堵水装置,最下方的所述封隔器的下端连接有一个所述电动堵水装置;Specifically, the utility model provides a layered oil production string, which includes a plurality of packers and a plurality of electric water blocking devices, and one electric plugging device is arranged between two adjacent packers. A water device, the lower end of the lowermost packer is connected with an electric water blocking device;
所述封隔器与相邻的所述电动堵水装置通过油管短节连接。The packer is connected to the adjacent electric water blocking device through a short joint of oil pipe.
可选择地,最下方的所述电动堵水装置的下端与丝堵连接。Optionally, the lower end of the lowermost electric water blocking device is connected with a plug.
可选择地,还包括油管锚,所述油管锚的下端与最上方的所述封隔器的上端连接。Optionally, a tubing anchor is also included, the lower end of the tubing anchor is connected to the upper end of the uppermost packer.
可选择地,还包括油管悬挂器,所述油管悬挂器的下端与所述油管锚的上端连接。Optionally, a tubing hanger is also included, the lower end of the tubing hanger is connected to the upper end of the tubing anchor.
可选择地,所述油管悬挂器的下端与所述油管锚的上端之间设置有丢手接头。Optionally, a hands-off joint is provided between the lower end of the tubing hanger and the upper end of the tubing anchor.
可选择地,所述油管悬挂器的下端与所述丢手接头的上端之间设置有抽油泵。Optionally, an oil well pump is arranged between the lower end of the tubing hanger and the upper end of the hands-off joint.
可选择地,所述油管悬挂器的下端与所述抽油泵的上端、所述抽油泵的下端与所述丢手接头的上端、所述丢手接头的下端与所述油管锚的上端及所述油管锚的下端与最上方的所述封隔器的上端之间通过油管短节和/或加厚油管短节连接。Optionally, the lower end of the tubing hanger and the upper end of the oil well pump, the lower end of the oil well pump and the upper end of the drop joint, the lower end of the drop joint and the upper end of the oil pipe anchor and the The lower end of the tubing anchor is connected to the upper end of the uppermost packer through a tubing nipple and/or a thickened tubing nipple.
可选择地,所述电动堵水装置通过电缆与地面控制器连接。Optionally, the electric water blocking device is connected with the ground controller through cables.
本实用新型实施例提供的技术方案的有益效果是:The beneficial effect of the technical scheme that the utility model embodiment provides is:
本实用新型实施例提供的分层采油管柱,通过设置多个封隔器将不同的油层分割开,通过设置在相邻两个封隔器之间的电动堵水装置和最下方的封隔器下方的电动堵水装置,可配合其他设备获取不同油层的产能、液性、含水量及孔隙度等数据资料。因此,本实用新型提供的分层采油管柱,可在对油层进行分层开采的同时,获取不同油层的产能、液性及含水量等数据资料。In the layered oil production string provided by the embodiment of the utility model, different oil layers are separated by setting a plurality of packers, and the electric water blocking device and the bottommost packer are arranged between two adjacent packers. The electric water shutoff device under the device can cooperate with other equipment to obtain data such as productivity, fluidity, water content and porosity of different oil layers. Therefore, the layered oil production string provided by the utility model can obtain data such as productivity, fluidity, and water content of different oil layers while performing layered extraction of oil layers.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some implementations of the present invention. For example, those of ordinary skill in the art can also obtain other drawings based on these drawings on the premise of not paying creative efforts.
图1为本实用新型一实施例中一种分层采油管柱的结构示意图;Fig. 1 is a schematic structural view of a layered oil production string in an embodiment of the utility model;
图2为本实用新型一实施例中电动堵水装置的结构示意图。Fig. 2 is a schematic structural diagram of an electric water blocking device in an embodiment of the present invention.
图中的附图标记分别表示:The reference signs in the figure represent respectively:
1、油管悬挂短器;1. Tubing suspension shortener;
2、第一油管短节;2. The first tubing pup joint;
3、第一加厚油管短节;3. The first thickened tubing nipple;
4、抽油泵;4. Oil well pump;
5、第二加厚油管短节;5. The second thickened tubing nipple;
6、筛管;6. Screen tube;
7、第三加厚油管短节;7. The third thickened tubing nipple;
8、丢手接头;8. Dropped connectors;
9、第四加厚油管短节;9. The fourth thickened tubing nipple;
10、油管锚;10. Tubing anchor;
11、第五加厚油管短节;11. The fifth thickened tubing nipple;
12、第一封隔器;12. The first packer;
13、第二油管短节;13. The second tubing nipple;
14、第一电动堵水装置;14. The first electric water blocking device;
15、第六加厚油管短节;15. The sixth thickened tubing pup joint;
16、第二封隔器;16. The second packer;
17、第三油管短节;17. The third tubing pup joint;
18、第二电动堵水装置;18. The second electric water blocking device;
19、第七加厚油管短节;19. The seventh thickened tubing nipple;
20、丝堵;20. Silk plugging;
21、套管;21. Casing;
a、偏心上接头;a. Eccentric upper joint;
b、验封定位管;b. Sealing and positioning tube;
c、注水导管;c. Water injection conduit;
d、定位管;d. Positioning tube;
e、开关阀;e. On-off valve;
f、电池筒;f. Battery cartridge;
g、压力传感器;g. Pressure sensor;
h、电动机;h. Motor;
i、控制器;i. Controller;
j、外套筒;j. Outer sleeve;
k、下接头;k, the lower joint;
l、腔体;l. Cavity;
m、压力导入孔。m. Pressure inlet hole.
具体实施方式Detailed ways
为使本实用新型的技术方案和优点更加清楚,下面将结合附图对本实用新型实施方式作进一步地详细描述。In order to make the technical solutions and advantages of the present utility model clearer, the implementation of the present utility model will be further described in detail below in conjunction with the accompanying drawings.
本实用新型一实施例提供了一种分层采油管柱,如图1所示,与油井内的套管21配合进行生产作业。An embodiment of the utility model provides a layered oil production string, as shown in FIG. 1 , which cooperates with the casing 21 in the oil well for production operations.
本实施例提供了一种分层采油管柱,如图1所示,包括封隔器12和封隔器16及电动堵水装置14和电动堵水装置18,封隔器12和封隔器16之间设置有电动堵水装置14,封隔器16的下端与电动堵水装置18连接,封隔器12与电动堵水装置14的上端、电动堵水装置14的下端与封隔器16的上端、封隔器16的下端与电动堵水装置18的上端通过油管短节连接。This embodiment provides a layered oil production string, as shown in Figure 1, including a packer 12, a packer 16, an electric water shutoff device 14, an electric water shutoff device 18, a packer 12 and a packer 16 is provided with an electric water blocking device 14, the lower end of the packer 16 is connected to the electric water blocking device 18, the upper end of the packer 12 and the electric water blocking device 14, the lower end of the electric water blocking device 14 is connected to the packer 16 The upper end of the packer 16, the lower end of the packer 16, and the upper end of the electric water shutoff device 18 are connected through a tubing nipple.
下面对本实施例提供的分层采油管柱的工作原理进行描述:The working principle of the layered oil production string provided in this embodiment is described below:
将本实施例提供的分层采油管柱下入到油井的套管内,使电动堵水装置14和上方的油层相对,电动堵水装置18与下方的油层相对。首先坐封封隔器16,将分层采油管柱与套管之间的在封隔器16下方的环空进行封堵;打开电动堵水装置18,下方的油层内的油通过套管上的射孔进入到电动堵水装置18内,并经分层采油管柱流出油井,电动堵水装置18配合其他设备可获取该油层的产能、液性及含水量等数据资料;关闭电动堵水装置18,坐封封隔器12,打开电动堵水装置14,上方的油层内的油通过套管上的射孔进入到电动堵水装置14内,并经分层采油管柱内部空腔流出油井,电动堵水装置14配合其他设备可获取该油层的产能、液性及含水量等数据资料。The layered oil production string provided in this embodiment is lowered into the casing of the oil well, so that the electric water blocking device 14 is opposite to the upper oil layer, and the electric water blocking device 18 is opposite to the lower oil layer. First, set the packer 16 to seal off the annulus between the layered production string and the casing below the packer 16; turn on the electric water blocking device 18, and the oil in the oil layer below passes through the casing The perforation enters the electric water shutoff device 18, and flows out of the oil well through the layered oil production string. The electric water shutoff device 18 cooperates with other equipment to obtain data such as the production capacity, fluidity and water content of the oil layer; close the electric water shutoff Device 18, set the packer 12, open the electric water shutoff device 14, the oil in the upper oil layer enters the electric water shutoff device 14 through the perforation on the casing, and flows out through the internal cavity of the layered production string For oil wells, the electric water shutoff device 14 cooperates with other equipment to obtain data such as productivity, fluidity and water content of the oil layer.
本实用新型实施例提供的分层采油管柱,通过设置封隔器12和封隔器16,将不同的油层分割开,通过设置在封隔器12和封隔器16之间的电动堵水装置14和封隔器16下方的电动堵水装置18,配合其他设备可获取不同油层的产能、液性、含水量及孔隙度等数据资料。因此,本实用新型实施例提供的分层采油管柱,在对油层进行分层开采的同时,可获取不同油层的产能、液性及含水量等数据资料。The layered oil production string provided by the embodiment of the utility model divides different oil layers by setting the packer 12 and the packer 16, and separates the different oil layers by setting the packer 12 and the packer 16. The electric water shutoff device 18 below the device 14 and the packer 16, in conjunction with other equipment, can obtain data such as productivity, fluidity, water content and porosity of different oil layers. Therefore, the layered oil production string provided by the embodiment of the utility model can obtain data such as productivity, fluidity, and water content of different oil layers while performing layered extraction of oil layers.
需要说明的是,本实施例仅以分层采油管柱包括两个封隔器和两个电动堵水装置为例进行说明,在其他实施例中,分层采油管柱可包括多个封隔器,相邻的两个封隔器之间设置有电动堵水装置,最下方的封隔器的下端连接有电动堵水装置。It should be noted that in this embodiment, the layered oil production string includes two packers and two electric water shutoff devices as an example. In other embodiments, the layered oil production string may include multiple packers An electric water shutoff device is installed between two adjacent packers, and an electric water shutoff device is connected to the lower end of the bottom packer.
本实施例中,如图2所示,采用的电动堵水装置包括偏心上接头a、验封定位管b、定位管d以及外套筒j、下接头k,其中在偏心上接头a上开有一个注水导管c,验封定位管b与定位管d垂直联结后固定于偏心上接头a、外套筒j与下接头k联结后构成的腔体l内,腔体l的内壁与定位管d外壁之间有环空,此环空被绝缘隔板分割为五个独立空间,独立空间内分别固定有电池筒f、压力传感器g、控制器i、电动机h以及开关阀e。其中与压力传感器g所在位置对应的外套筒j上开有压力导入孔m,与开关阀e的进水口所在位置对应的定位管d的管壁上开有带螺纹的通孔,开关阀e的进水口与定位管d通过该通孔作螺纹联结,电动机h的轴与开关阀e的转动轴相联结,开关阀e的出水口与注水导管c相连通,这样,就可以使得定位管d中的液体可以在开关阀e的控制下通过注水导管c流出或流入。电池筒f通过电缆为电动机h供电,压力传感器g测得压力信号后通过信号电缆输送至控制器h的压力信号输入端。In this embodiment, as shown in Figure 2, the electric water blocking device used includes an eccentric upper joint a, a sealing inspection positioning pipe b, a positioning pipe d, an outer sleeve j, and a lower joint k, wherein the eccentric upper joint a is opened There is a water injection conduit c, the sealing inspection positioning pipe b is vertically connected with the positioning pipe d, and then fixed in the cavity l formed by the connection of the eccentric upper joint a, the outer sleeve j and the lower joint k, the inner wall of the cavity l and the positioning tube There is an annulus between the outer walls of d, which is divided into five independent spaces by insulating partitions, and the battery cartridge f, pressure sensor g, controller i, motor h and switch valve e are respectively fixed in the independent spaces. There is a pressure introduction hole m on the outer sleeve j corresponding to the position of the pressure sensor g, and a threaded through hole is opened on the wall of the positioning pipe d corresponding to the position of the water inlet of the switch valve e, and the switch valve e The water inlet and the positioning pipe d are threaded through the through hole, the shaft of the motor h is connected with the rotation shaft of the switch valve e, and the water outlet of the switch valve e is connected with the water injection conduit c, so that the positioning tube d The liquid in the tank can flow out or in through the water injection conduit c under the control of the switch valve e. The battery cartridge f supplies power to the motor h through the cable, and the pressure signal measured by the pressure sensor g is sent to the pressure signal input end of the controller h through the signal cable.
控制器i由放大器、位置编码器、微处理器以及固态继电器构成,其中放大器、位置编码器的输出端依次联结于微处理器的数据输入端,放大器的正输入端作为控制器i的压力信号输入端,微处理器的控制信号输出端连接至固态继电器的启动信号输入端,此固态继电器中启动后导通的控制信号输出端作为接入电动机h供电回路中的控制端,位置编码器上的位置感应开关固定于开关阀e的转动轴承上,由此可以感知开关阀的开关程度。在控制器i中运行微机通讯软件,以USB接口对控制器微处理机芯片进行操作,将层段号、控制压力及控制编码等信息输入微处理芯片内的存贮器中。当控制器i工作时将根据内存信息运行其程序,判断压力传感器g接收到的信息。传感器g感受到的压力信号经放大器放大后送入微处理器进行处理。当判定接收到的信号为真时,向电动机h发出驱动信号,并测量位置编码器输出的位置信号。当与地面发送的控制指令相吻合后停止电机驱动并定位。当判断出压力传感器接收到的信号为假时,作干扰信号处理,等待下一组信号到来。The controller i is composed of an amplifier, a position encoder, a microprocessor and a solid-state relay, wherein the output terminals of the amplifier and the position encoder are connected to the data input terminal of the microprocessor in turn, and the positive input terminal of the amplifier is used as the pressure signal of the controller i The input terminal, the control signal output terminal of the microprocessor is connected to the start signal input terminal of the solid state relay, and the control signal output terminal that is turned on after starting in the solid state relay is used as the control terminal connected to the power supply circuit of the motor h, on the position encoder The position sensing switch is fixed on the rotating bearing of the switching valve e, so that the switching degree of the switching valve can be sensed. Run the microcomputer communication software in the controller i, use the USB interface to operate the microprocessor chip of the controller, and input information such as layer number, control pressure and control code into the memory in the microprocessing chip. When the controller i is working, it will run its program according to the memory information, and judge the information received by the pressure sensor g. The pressure signal sensed by the sensor g is amplified by the amplifier and sent to the microprocessor for processing. When it is determined that the received signal is true, a drive signal is sent to the motor h, and the position signal output by the position encoder is measured. When it matches the control command sent by the ground, stop the motor drive and position. When it is judged that the signal received by the pressure sensor is false, it performs interference signal processing and waits for the arrival of the next group of signals.
地面控制井下任意层段的电动堵水装置的开启、关闭或任意设定嘴径分层配产的工艺方法是:从井口向井内打压,产生一种特殊的压力码,井下的压电控制开关接受到压力码后通过信息处理,控制微电机动作,将工作筒上的开关器调整工作状态即开启、关闭或任意设定嘴径分层配产。在下井前连接PC机与压控开关工具,用专用的通讯软件根据施工要求将层段号、控制压力等参数输入到微处理器中,预先设定好开启或关闭的指令,只有当井口打压产生的压电信号与预先设定的指令一致时,压电控制开关才开始动作完成开启或关闭。由于控制指令是由压力和时间构成的不同间隔的组合波,故可精确地对井下压电开关实现一对一的可靠控制。由于设定的启动压力低,因此对于大多数采油井都能够连续稳定的达到启动压力值。因此通过压电信号可以在地面任意控制每个层位的电动堵水装置的开启和关闭。The ground controls the opening and closing of the electric water blocking device in any section of the downhole, or the process of setting the nozzle diameter layer by layer. After receiving the pressure code, through information processing, the action of the micro-motor is controlled, and the switch on the working cylinder is adjusted to the working state, that is, opening, closing or arbitrarily setting the mouth diameter and layering production. Before going into the well, connect the PC and the pressure control switch tool, use the special communication software to input the layer number, control pressure and other parameters into the microprocessor according to the construction requirements, and pre-set the opening or closing instructions, only when the wellhead is suppressed When the generated piezoelectric signal is consistent with the preset command, the piezoelectric control switch starts to act and completes opening or closing. Since the control command is composed of pressure and time combined waves at different intervals, one-to-one reliable control of the downhole piezoelectric switch can be accurately realized. Since the set start pressure is low, the start pressure value can be reached continuously and stably for most production wells. Therefore, the opening and closing of the electric water blocking device of each layer can be controlled arbitrarily on the ground through the piezoelectric signal.
在本实施例中,如图1所示,下方的电动堵水装置18的下端与丝堵20连接。丝堵20将分层采油管柱的下方封堵,从而通过进入分层采油管柱内部空腔内的油只能通过油井口流出。In this embodiment, as shown in FIG. 1 , the lower end of the lower electric water shutoff device 18 is connected to a plug 20 . The plug 20 blocks the bottom of the layered production string, so that the oil that enters the internal cavity of the layered string can only flow out through the oil wellhead.
在本实施例中,如图1所示,分层采油管柱还包括油管锚10,油管锚10的下端与最上方的封隔器12的上端连接。在将分层采油管柱下入到套管内后,通过油管锚10锚定在套管上,从而分层采油管柱在油井内固定。In this embodiment, as shown in FIG. 1 , the layered production string further includes a tubing anchor 10 , and the lower end of the tubing anchor 10 is connected to the upper end of the uppermost packer 12 . After the layered oil production string is run into the casing, the oil pipe anchor 10 is anchored on the casing, so that the layered oil production string is fixed in the oil well.
在本实施例中,如图1所示,分层采油管柱还包括油管悬挂器1,油管悬挂器1的下端与油管锚10的上端连接。油管悬挂器1起支承油管柱并密封管柱和套管21之间环形空间的作用。In this embodiment, as shown in FIG. 1 , the layered production string further includes a tubing hanger 1 , and the lower end of the tubing hanger 1 is connected to the upper end of a tubing anchor 10 . The tubing hanger 1 plays the role of supporting the tubing string and sealing the annular space between the tubing string and the casing 21 .
在本实施例中,如图1所示,油管悬挂器1的下端与油管锚10的上端之间设置有丢手接头8。当完成分层采油后,向分层采油管柱的空腔内投入重物,使丢手接头8上部的管柱与丢手接头8分开,将丢手接头8上部的管柱从油井内取出。可下入打捞工具,将丢手接头8下部的管柱从油井内打捞出来,也可以将丢手接头8下部的管柱丢弃在油井内。In this embodiment, as shown in FIG. 1 , a hands-off joint 8 is provided between the lower end of the tubing hanger 1 and the upper end of the tubing anchor 10 . After the layered oil recovery is completed, put heavy objects into the cavity of the layered oil production string to separate the string on the upper part of the drop-in joint 8 from the drop-in joint 8, and take out the string on the upper part of the drop-in joint 8 from the oil well . The fishing tool can be lowered to salvage the pipe string at the bottom of the hands-off joint 8 from the oil well, or the pipe string at the bottom of the hands-off joint 8 can be discarded in the oil well.
在本实施例中,如图1所示,油管悬挂器1的下端与丢手接头8的上端之间设置有抽油泵4。抽油泵4的泵筒的上端与油管悬挂器1的下端连接,抽油泵4的泵筒的下端与丢手接头8的上端连接。当进行分层采油时,坐封封隔器16后,打开电动堵水装置18和抽油泵4,抽油泵4将通过电动堵水装置18进入到管柱内的油举升到地面;坐封封隔器12后,打开电动堵水装置14和抽油泵4,抽油泵4将通过电动堵水装置14进入到管柱内的油举升到地面。In this embodiment, as shown in FIG. 1 , an oil well pump 4 is arranged between the lower end of the tubing hanger 1 and the upper end of the hands-off joint 8 . The upper end of the pump barrel of the oil well pump 4 is connected with the lower end of the tubing hanger 1 , and the lower end of the pump barrel of the oil well pump 4 is connected with the upper end of the drop joint 8 . When performing layered oil production, after setting the packer 16, turn on the electric water shutoff device 18 and the oil pump 4, and the oil well pump 4 will lift the oil that has entered the pipe string through the electric water shutoff device 18 to the ground; After the packer 12, turn on the electric water shutoff device 14 and the oil well pump 4, and the oil well pump 4 will lift the oil that has entered the pipe string through the electric water shutoff device 14 to the ground.
在本实施例中,如图1所示,油管悬挂器1与抽油泵4之间可连接有第一油管短节2和第一加厚油管短节3。具体地,油管悬挂器1的下端可通过螺纹与第一油管短节2的上端可拆卸地连接,第一油管短节2的下端可通过螺纹与第一加厚油管短节3的上端可拆卸地连接,第一加厚油管短节3的下端可通过螺纹与抽油泵4的泵筒的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , a first tubing nipple 2 and a first thickening tubing nipple 3 may be connected between the tubing hanger 1 and the oil well pump 4 . Specifically, the lower end of the tubing hanger 1 can be detachably connected with the upper end of the first tubing nipple 2 through threads, and the lower end of the first tubing nipple 2 can be detachably connected with the upper end of the first thickened tubing nipple 3 through threads. Ground connection, the lower end of the first thickened tubing nipple 3 can be detachably connected with the upper end of the pump barrel of the oil well pump 4 through threads.
在本实施例中,如图1所示,抽油泵4的泵筒的下端与丢手接头8之间可连接有第二加厚油管短节5、筛管6和第三加厚油管短节7。具体地,抽油泵4的泵筒的下端可通过螺纹与第二加厚油管短节5的上端可拆卸地连接,第二加厚油管短节5的下端可通过螺纹与筛管6的上端可拆卸地连接,筛管6的下端可通过螺纹与第三加厚油管短节7的上端连接,第三加厚油管短节7的下端可通过螺纹与丢手接头8的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , the second thickened tubing nipple 5 , the screen pipe 6 and the third thickened tubing nipple can be connected between the lower end of the pump barrel of the oil well pump 4 and the hands-off joint 8 7. Specifically, the lower end of the pump cylinder of the oil well pump 4 can be detachably connected with the upper end of the second thickened oil pipe nipple 5 through threads, and the lower end of the second thickened oil pipe nipple 5 can be connected with the upper end of the screen pipe 6 through threads. Connected detachably, the lower end of the screen pipe 6 can be connected with the upper end of the third thickened tubing nipple 7 through threads, and the lower end of the third thickened tubing nipple 7 can be detachably connected with the upper end of the drop joint 8 through threads.
在本实施例中,如图1所示,丢手接头8的下端与油管锚10之间可连接有第四加厚油管短节9。具体地,丢手接头8的下端可通过螺纹与第四加厚油管短节9的上端可拆卸地连接,第四加厚油管短节9的下端可通过螺纹与油管锚10的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , a fourth thickened tubing nipple 9 may be connected between the lower end of the hands-off joint 8 and the tubing anchor 10 . Specifically, the lower end of the hands-off joint 8 can be detachably connected with the upper end of the fourth thickened tubing nipple 9 through threads, and the lower end of the fourth thickened tubing nipple 9 can be detachably connected with the upper end of the tubing anchor 10 through threads. connect.
在本实施例中,如图1所示,油管锚10的下端与封隔器12之间连接有第五加厚油管短节11。具体地,油管锚10的下端可通过螺纹与第五加厚油管短节11的上端可拆卸地连接,第五加厚油管短节11的下端可通过螺纹与封隔器12的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , a fifth thickened tubing nipple 11 is connected between the lower end of the tubing anchor 10 and the packer 12 . Specifically, the lower end of the tubing anchor 10 can be detachably connected with the upper end of the fifth thickened tubing sub-joint 11 through threads, and the lower end of the fifth thickened tubing sub-joint 11 can be detachably connected with the upper end of the packer 12 through threads. connect.
在本实施例中,如图1所示,封隔器12的下端与电动堵水装置14的上端可连接有第二油管短节13。具体地,封隔器12的下端可通过螺纹与第二油管短节13的上端可拆卸地连接,第二油管短节13的下端可通过螺纹与电动堵水装置14的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , the lower end of the packer 12 and the upper end of the electric water shutoff device 14 can be connected with a second tubing nipple 13 . Specifically, the lower end of the packer 12 can be detachably connected with the upper end of the second tubing nipple 13 through threads, and the lower end of the second tubing nipple 13 can be detachably connected with the upper end of the electric water blocking device 14 through threads.
在本实施例中,如图1所示,电动堵水装置14与封隔器16之间可连接有第六加厚油管短节15。具体地,电动堵水装置14的下端可通过螺纹与第六加厚油管短节15的上端可拆卸地连接,第六加厚油管短节15的下端可通过螺纹与封隔器16的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , a sixth thickened tubing nipple 15 may be connected between the electric water shutoff device 14 and the packer 16 . Specifically, the lower end of the electric water blocking device 14 can be detachably connected with the upper end of the sixth thickened tubing nipple 15 through threads, and the lower end of the sixth thickened tubing nipple 15 can be connected with the upper end of the packer 16 through threads. detachable ground connection.
在本实施例中,如图1所示,封隔器16与电动堵水装置18之间可连接有第三油管短节17。具体地,封隔器16的下端可通过螺纹与第三油管短节17的上端可拆卸地连接,第三油管短节17的下端可通过螺纹与电动堵水装置18的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , a third tubing nipple 17 may be connected between the packer 16 and the electric water blocking device 18 . Specifically, the lower end of the packer 16 can be detachably connected with the upper end of the third tubing nipple 17 through threads, and the lower end of the third tubing nipple 17 can be detachably connected with the upper end of the electric water blocking device 18 through threads.
在本实施例中,如图1所示,电动堵水装置18与丝堵20之间可连接有第七加厚油管短节19。具体地,电动堵水装置18的下端可通过螺纹与第七加厚油管短节19可拆卸地连接,第七加厚油管短节19可通过螺纹与丝堵20的上端可拆卸地连接。In this embodiment, as shown in FIG. 1 , a seventh thickened tubing nipple 19 may be connected between the electric water blocking device 18 and the plug 20 . Specifically, the lower end of the electric water blocking device 18 can be detachably connected with the seventh thickened oil pipe short joint 19 through threads, and the seventh thickened oil pipe short joint 19 can be detachably connected with the upper end of the plug 20 through threads.
其中,加厚油管短节相对于油管短节来说,承压能力更好。Among them, thicker tubing nipples have better pressure bearing capacity than tubing nipples.
本实施例中,封隔器12和封隔器16可采用Y341-114型。但不限于此,本实用新型其他实施例中,也可采用其他型号。In this embodiment, the packer 12 and the packer 16 can adopt the Y341-114 type. But not limited thereto, other models can also be used in other embodiments of the present invention.
本实施例中,电动堵水装置14和电动堵水装置18也可通过电缆与地面控制器连接。这样,操作人员可通过地面控制器控制电动堵水装置14和电动堵水装置18的开启或关闭,便于远程控制。地面控制器通过电缆与电动堵水装置14和电动堵水装置18连接,电缆可固定设置在分层采油管柱的管壁内。In this embodiment, the electric water blocking device 14 and the electric water blocking device 18 can also be connected with the ground controller through cables. In this way, the operator can control the opening or closing of the electric water blocking device 14 and the electric water blocking device 18 through the ground controller, which is convenient for remote control. The ground controller is connected with the electric water blocking device 14 and the electric water blocking device 18 through cables, and the cables can be fixedly arranged in the pipe wall of the layered oil production string.
以上所述仅是为了便于本领域的技术人员理解本实用新型的技术方案,并不用以限制本实用新型。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above description is only for those skilled in the art to understand the technical solution of the utility model, and is not intended to limit the utility model. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present utility model shall be included in the protection scope of the present utility model.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720947904.4U CN207092971U (en) | 2017-08-01 | 2017-08-01 | Layered production string |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720947904.4U CN207092971U (en) | 2017-08-01 | 2017-08-01 | Layered production string |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN207092971U true CN207092971U (en) | 2018-03-13 |
Family
ID=61543305
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720947904.4U Active CN207092971U (en) | 2017-08-01 | 2017-08-01 | Layered production string |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN207092971U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111155992A (en) * | 2018-11-07 | 2020-05-15 | 中国石油天然气股份有限公司 | A kind of multi-layer combined oil testing device and method |
-
2017
- 2017-08-01 CN CN201720947904.4U patent/CN207092971U/en active Active
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111155992A (en) * | 2018-11-07 | 2020-05-15 | 中国石油天然气股份有限公司 | A kind of multi-layer combined oil testing device and method |
| CN111155992B (en) * | 2018-11-07 | 2023-05-26 | 中国石油天然气股份有限公司 | Multi-layer combined oil testing device and method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103321628B (en) | Intelligent electric switching sliding sleeve | |
| CN105178947B (en) | An integrated method for finding and plugging water in horizontal wells | |
| CN207568578U (en) | Self-flowing water injection column | |
| US10180064B2 (en) | System for sampling from formation while drilling | |
| CN204663496U (en) | A kind of canned pair of down-hole electric submersible pump producing tubular column | |
| CN109751020B (en) | Intelligent layered water injection and layered oil production pipe column for horizontal well and technological method | |
| CN107725013B (en) | A method for combined stratified testing and stratified oil recovery | |
| CN108894761A (en) | A kind of one-trip string seperated layer water injection sand control back washing device and method | |
| CN201620853U (en) | Multi-layer mining single pump constant pressure gas-proof pipe column | |
| CN106285588A (en) | A pre-set cable direct-controlled electronically controlled layered polymer injection process string and polymer injection method | |
| RU130343U1 (en) | Borehole installation for simultaneous separate development of several operational facilities from one well | |
| CN205936555U (en) | A horizontal well huff and puff intelligent segmented water injection process string | |
| CN215718697U (en) | Cable separate mining test system for tubular pump | |
| CN204457756U (en) | A horizontal well segmented pressure and pressure drop test string | |
| CN202348248U (en) | Multi-hole concentric one-piece continuous quantitative dispenser | |
| CN107387020B (en) | A two-gas co-production device | |
| CN103573214A (en) | Circulation bottom valve which works with pressure | |
| CN209603954U (en) | Horizontal well cable-passing intelligent water distributor and horizontal well underground segmented water injection pipe column | |
| CN209742865U (en) | An intelligent layered water injection and layered production string for horizontal wells | |
| CN202338264U (en) | Microcomputer-controlled packer | |
| CN106089162A (en) | The layering section that a kind of double-direction radio identification controls exploits flow string and regulation device | |
| CN207296957U (en) | A kind of two gas are total to device for picking | |
| CN107420091A (en) | Deep water hydrocarbon well annular pressure monitors and control device | |
| CN108487882A (en) | A kind of production tree device and method for exploitation of gas hydrate | |
| CN204851223U (en) | Tubular column combination of product is asked to oil well multilayer sectionalization test |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |