- CN207047897U CN207047897U CN201720768705.7U CN201720768705U CN207047897U CN 207047897 U CN207047897 U CN 207047897U CN 201720768705 U CN201720768705 U CN 201720768705U CN 207047897 U CN207047897 U CN 207047897U
- Authority
- CN
- China
- Prior art keywords
- plate
- groove type
- shear wall
- wall
- pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及管道防沉降技术领域,具体为一种地下室出墙室外管道防沉降的施工装置。The utility model relates to the technical field of pipeline anti-subsidence, in particular to a construction device for anti-subsidence of outdoor pipelines outside the wall of a basement.
背景技术Background technique
检查井是为城市地下基础设施的供电、给水、排水、排污、通讯、有线电视、煤气管、路灯线路等维修,安装方便而设置的,一般设在管道交汇处、转弯处、管径或坡度改变处、以及直线管段上每隔一定距离处,是便于定期检查附属构筑物,目前地下室外墙室外管道在修建检查井时,大多是在回填土区域打垫层,在垫层上砌筑检查井,这种方式由于回填土质量不好控制,存在夯填不实造成管道沉降等质量缺陷,后期管道维修时比较复杂,会产生大量的费用,为此我们提出一种地下室出墙室外管道防沉降的施工装置用以解决上述问题。The inspection well is set up for the maintenance of power supply, water supply, drainage, sewage discharge, communication, cable TV, gas pipe, street lamp line, etc. of urban underground infrastructure, and is convenient for installation. The changed place and the straight pipe section at a certain distance are convenient for regular inspection of the ancillary structures. At present, when the inspection well is built for the outdoor pipeline of the basement wall, the cushion is mostly laid in the backfill area, and the inspection well is built on the cushion. , this method is not easy to control the quality of backfill, and there are quality defects such as pipeline settlement due to improper tamping and filling. Later pipeline maintenance is more complicated and will generate a lot of costs. Therefore, we propose an anti-settlement method for outdoor pipelines outside the basement wall. The construction device is used to solve the above problems.
实用新型内容Utility model content
本实用新型的目的在于提供一种地下室出墙室外管道防沉降的施工装置,以解决上述背景技术中提出的问题。The purpose of this utility model is to provide a construction device for anti-subsidence of outdoor pipes outside the wall of the basement, so as to solve the problems raised in the above-mentioned background technology.
为实现上述目的,本实用新型提供如下技术方案:一种地下室出墙室外管道防沉降的施工装置,包括槽型板,所述槽型板包括剪力墙板、所述剪力墙板的上端连接有顶板,所述剪力墙板的下端连接有底板,且剪力墙板、顶板以及底板为一体成型的混凝土钢筋结构,所述槽型板设在管道仓的下部,所述管道仓内设有管道,且管道仓的底部与槽型板的顶板上表面紧密接触,所述槽型板的剪力墙板与外墙紧密接触,所述槽型板的底板与外墙的承台基础紧密接触。In order to achieve the above object, the utility model provides the following technical solutions: a construction device for anti-subsidence of outdoor pipes outside the wall of the basement, including a grooved plate, the grooved plate includes a shear wall plate, the upper end of the shear wall plate The top plate is connected, the lower end of the shear wall plate is connected with the bottom plate, and the shear wall plate, the top plate and the bottom plate are integrally formed concrete reinforcement structure, the channel plate is arranged at the lower part of the pipeline warehouse, and the pipeline warehouse There are pipelines, and the bottom of the pipeline warehouse is in close contact with the upper surface of the top plate of the channel plate, the shear wall panel of the channel plate is in close contact with the outer wall, and the bottom plate of the channel plate is in close contact with the cap foundation of the outer wall Close contact.
优选的,所述底板、剪力墙板以及顶板的厚度均为250 mm。Preferably, the thickness of the bottom plate, the shear wall plate and the top plate are all 250 mm.
优选的,所述底板、剪力墙板及顶板均为C30混凝土、HRB400级10@150双层双向配置。Preferably, the bottom slab, shear wall slab and top slab are all C30 concrete, HRB400 grade 10@150 double-layer bidirectional configuration.
优选的,所述底板与顶板的宽度为1800mm,所述剪力墙板的高度为2500mm。Preferably, the width of the bottom plate and the top plate is 1800mm, and the height of the shear wall plate is 2500mm.
优选的,所述槽型板和管道仓与外墙之间卡设有防水布,且槽型板槽口侧采用回填土挤压。Preferably, a waterproof cloth is clamped between the channel plate, the pipe warehouse and the outer wall, and the notch side of the channel plate is squeezed with backfill soil.
与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the utility model are:
1、检查井及室外管道主要由预制钢筋混凝土剪力墙板受力,并利用回填土的挤压平衡使槽形板稳定,解决了检查井与管道下沉的难题;1. Inspection wells and outdoor pipelines are mainly supported by prefabricated reinforced concrete shear wall panels, and the extrusion balance of backfill soil is used to stabilize the channel plates, which solves the problem of inspection wells and pipelines sinking;
2、结构简单,施工迅速,投入成本低,实用性强,易于推广使用。2. The structure is simple, the construction is rapid, the input cost is low, the practicability is strong, and it is easy to popularize and use.
附图说明Description of drawings
图1为本实用新型结构示意图;Fig. 1 is a structural representation of the utility model;
图2为本实用新型使用结构示意图。Fig. 2 is a schematic view of the structure of the utility model.
图中:1槽型板、2剪力墙板、3顶板、4底板、5管道仓、6外墙、7承台基础。In the figure: 1 channel plate, 2 shear wall plate, 3 top plate, 4 bottom plate, 5 pipe warehouse, 6 exterior wall, 7 cap foundation.
具体实施方式detailed description
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.
请参阅图1-2,本实用新型提供一种技术方案:一种地下室出墙室外管道防沉降的施工装置,包括槽型板1,槽型板1包括剪力墙板2、底板4、剪力墙板2以及顶板3的厚度均为250 mm,底板4、剪力墙板2及顶板3均为C30混凝土、HRB400级10@150双层双向配置,强度大,起到强有力的支撑作用,剪力墙板2的上端连接有顶板3,剪力墙板2的下端连接有底板4,且剪力墙板2、顶板3以及底板4为一体成型的混凝土钢筋结构,结构简单,易于生产,且成本较低。Please refer to Figure 1-2, the utility model provides a technical solution: a construction device for anti-settlement construction of outdoor pipes outside the basement wall, including a grooved plate 1, which includes a shear wall plate 2, a bottom plate 4, a shear wall plate The thickness of the force wall plate 2 and the top plate 3 are both 250 mm. The bottom plate 4, the shear wall plate 2 and the top plate 3 are all C30 concrete, HRB400 grade 10@150 double-layer bidirectional configuration, which has high strength and plays a strong supporting role , the upper end of the shear wall panel 2 is connected to the top plate 3, and the lower end of the shear wall panel 2 is connected to the bottom plate 4, and the shear wall panel 2, the top plate 3, and the bottom plate 4 are integrally formed concrete reinforcement structures, which have a simple structure and are easy to produce , and the cost is lower.
槽型板1设在管道仓5的下部,安装迅速,降低对人工的投入,管道仓5内设有管道,且管道仓5的底部与槽型板1的顶板3上表面紧密接触,槽型板1的剪力墙板2与外墙6紧密接触,槽型板1的底板4与外墙6的承台基础7紧密接触,槽型板1卡设在承台基础7与管道仓5之间,起支撑作用,可以有效的防止管道仓5发生沉降。The grooved plate 1 is set at the lower part of the pipeline warehouse 5, which can be installed quickly and reduces the labor input. The pipeline warehouse 5 is equipped with pipelines, and the bottom of the pipeline warehouse 5 is in close contact with the upper surface of the top plate 3 of the grooved plate 1. The shear wall panel 2 of the panel 1 is in close contact with the outer wall 6, the bottom plate 4 of the channel plate 1 is in close contact with the cap foundation 7 of the outer wall 6, and the channel plate 1 is clamped between the cap foundation 7 and the pipe warehouse 5 The space acts as a support, which can effectively prevent the pipeline warehouse 5 from settling.
底板4与顶板3的宽度为1800mm,剪力墙板2的高度为2500mm,剪力墙板2的高度以及管道仓5的高度之和与外墙6埋入土中的深度相等。The width of the bottom plate 4 and the top plate 3 is 1800 mm, the height of the shear wall plate 2 is 2500 mm, and the sum of the height of the shear wall plate 2 and the height of the pipe warehouse 5 is equal to the depth of the outer wall 6 buried in the soil.
槽型板1和管道仓5与外墙6之间卡设有防水布,防水布可以使外墙6的底部被保护,不会被水浸泡,且槽型板1槽口侧采用回填土挤压,使槽型板1稳定,解决了检查井下沉、管道沉降的难题。A waterproof cloth is installed between the channel plate 1, the pipeline warehouse 5 and the outer wall 6. The waterproof cloth can protect the bottom of the outer wall 6 from being soaked by water, and the notch side of the channel plate 1 is squeezed with backfill soil. pressure, so that the grooved plate 1 is stable, and solves the problems of inspection well sinking and pipeline settlement.
工作原理:本实用新型管道防沉降装置在使用时,在外墙6的表面固定防水布,将槽型板1的剪力墙板2与外墙6紧密接触,槽型板1的底板4放置在外墙6的承台基础7上,将管道仓5放置在槽型板1的顶板3上表面,最好在槽型板1的槽口侧采用回填土进行挤压即完成了本实用新型管道防沉降装置的安装。Working principle: When the pipeline anti-settling device of the utility model is in use, the waterproof cloth is fixed on the surface of the outer wall 6, the shear wall panel 2 of the channel plate 1 is in close contact with the outer wall 6, and the bottom plate 4 of the channel plate 1 is placed outside On the cap foundation 7 of the wall 6, the pipeline storehouse 5 is placed on the upper surface of the top plate 3 of the grooved plate 1, and it is preferable to use backfill soil on the notch side of the grooved plate 1 to extrude to complete the pipeline protection of the utility model. Installation of settling devices.
尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes and modifications can be made to these embodiments without departing from the principle and spirit of the present invention , replacements and modifications, the scope of the present utility model is defined by the appended claims and their equivalents.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720768705.7U CN207047897U (en) | 2017-06-29 | 2017-06-29 | A kind of basement goes out the constructing device of wall yard piping anti-settling |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720768705.7U CN207047897U (en) | 2017-06-29 | 2017-06-29 | A kind of basement goes out the constructing device of wall yard piping anti-settling |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN207047897U true CN207047897U (en) | 2018-02-27 |
Family
ID=61493419
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720768705.7U Expired - Fee Related CN207047897U (en) | 2017-06-29 | 2017-06-29 | A kind of basement goes out the constructing device of wall yard piping anti-settling |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN207047897U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114687582A (en) * | 2022-05-31 | 2022-07-01 | 中国二十二冶集团有限公司 | Anti-sinking construction method and anti-sinking structure for building out-of-wall pipeline |
-
2017
- 2017-06-29 CN CN201720768705.7U patent/CN207047897U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114687582A (en) * | 2022-05-31 | 2022-07-01 | 中国二十二冶集团有限公司 | Anti-sinking construction method and anti-sinking structure for building out-of-wall pipeline |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN205276316U (en) | Modular prefabricated piping lane | |
| CN202369968U (en) | Assembled water drainage box culvert | |
| CN201232197Y (en) | Combined inspection well | |
| CN203174616U (en) | Clay foundation rain falling and water saving system | |
| CN207597428U (en) | Prefabricated piping lane is connected waterproof construction with cast-in-place piping lane | |
| CN104420480A (en) | Collapsible loess area integrated pipe network layout method and structure | |
| CN204002833U (en) | The embed-type passage of many circular arcs arched corrugated steel plate | |
| CN207268009U (en) | A drainage system of underground comprehensive pipe gallery based on the existing sewage channel | |
| CN204151824U (en) | A kind of glass reinforced plastic underground comprehensive pipe network common trench | |
| CN207047897U (en) | A kind of basement goes out the constructing device of wall yard piping anti-settling | |
| CN204243699U (en) | A Lightweight Concrete Composite Board Assembled Cable Trench | |
| CN206668275U (en) | A kind of subsurface excavation method Pipe rack | |
| CN104455889A (en) | Integrated underground pipe gallery with compensation device | |
| CN204753783U (en) | Prefabricated concrete rain sewage inspection shaft device | |
| CN102593781B (en) | Transformer substation assembled type cable groove body and cable channel system thereof | |
| CN202298873U (en) | Novel GRP (glass-reinforced plastic) drainage inspection well | |
| CN201202121Y (en) | Foundation Pit Drainage Network | |
| CN205205863U (en) | Prefabricated inspection shaft | |
| CN204753639U (en) | Prefabricated well of batch production modular concrete extrusion | |
| CN218633272U (en) | Novel water and electricity is with groove trench | |
| CN204459502U (en) | Prestress steel cylinder concrete electric power piping lane | |
| CN203498866U (en) | Integrated-type plastic common pipe for cities | |
| CN204164577U (en) | With the integrated form underground pipe gallery of compensation device | |
| CN107100198B (en) | A permeable prefabricated underground pipe gallery | |
| CN219100282U (en) | System for collecting and recycling reclaimed water in deep foundation pit construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180227 |