CN207017097U - Deep super embankment on soft soil - Google Patents

Deep super embankment on soft soil Download PDF

Info

Publication number
CN207017097U
CN207017097U CN201720936830.4U CN201720936830U CN207017097U CN 207017097 U CN207017097 U CN 207017097U CN 201720936830 U CN201720936830 U CN 201720936830U CN 207017097 U CN207017097 U CN 207017097U
Authority
CN
China
Prior art keywords
soil
prefabricated
cement
rib
diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720936830.4U
Other languages
Chinese (zh)
Inventor
王新泉
李肖
李栋樑
崔允亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou City University
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201720936830.4U priority Critical patent/CN207017097U/en
Application granted granted Critical
Publication of CN207017097U publication Critical patent/CN207017097U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型涉及一种深厚超软土路堤,包括:路堤、水泥土隔离墙、加固区固化水泥土、过渡区固化水泥土、排水垫层、十字预制节点、隔离土工布、钢筋混凝土框格板、一字预制节点、带肋板桩和快速注浆设备;所述带肋板桩穿过加固区固化水泥土到达超软土层,带肋板桩在预制板桩基础上在固定位置把竖向连接筋B弯曲作为肋的受力筋,其中肋上带有圆孔;设有矩形锚固钢板、圆形锚固钢板分别用于将竖向连接筋A、竖向连接筋B锚固为整体。本实用新型的有益效果是:加固区固化水泥土、过渡区固化水泥土、刚性桩、钢筋砼框格板,增强了路基的整体受力,大大减少了地基的不均匀沉降,竖向排水体、排水垫层有效解决了工后地基排水问题。

The utility model relates to a deep ultra-soft soil embankment, comprising: embankment, cement-soil separation wall, solidified cement-soil in the reinforcement area, solidified cement-soil in the transition area, drainage cushion, cross prefabricated nodes, isolation geotextile, reinforced concrete frame grid , one-word prefabricated joints, ribbed sheet piles and rapid grouting equipment; the ribbed sheet piles pass through the reinforcement area to solidify the cement soil to reach the super soft soil layer, and the ribbed sheet piles are placed vertically at a fixed position on the prefabricated sheet pile foundation Bending towards the connecting rib B as a stress rib of the rib, wherein the rib has a round hole; a rectangular anchoring steel plate and a circular anchoring steel plate are respectively used to anchor the vertical connecting rib A and the vertical connecting rib B as a whole. The beneficial effects of the utility model are: solidified cement soil in the reinforcement area, solidified cement soil in the transition area, rigid piles, and reinforced concrete frame panels, which enhance the overall stress of the roadbed, greatly reduce the uneven settlement of the foundation, and vertical drainage , The drainage cushion effectively solves the foundation drainage problem after construction.

Description

深厚超软土路堤Deep and super soft soil embankment

技术领域technical field

本实用新型涉及高速公路工程和地基处理技术领域,具体指深厚超软土路堤。The utility model relates to the technical field of expressway engineering and foundation treatment, in particular to deep and ultra-soft soil embankments.

背景技术Background technique

近40多年来,深厚超软土地基路堤沉降与稳定问题颇受关注。由于问题的复杂性,在建设过程中如何制定合理的地基处理方案是困扰工程顺利实施的一个棘手难题。滨海路堤多为深厚软土地基,地基软弱且几乎没有硬壳层,土的微观结构和成因机理复杂多变,物理模型及其参数具有非均一性、各向异性和不确定性。公路是一种线形带状工程,滨海公路往往穿越不同的地貌单元。面对浙江沿海地区复杂的工程环境,针对无硬壳层、高含水量(ω≥60~ 100%)、高孔隙比(e≥1.8~2.0)、抗剪强度低、灵敏度高、渗透系数很小、厚度大(H0≥40~ 60m)的流塑性淤泥的变形特性,目前在技术资料和工程数据积累方面尚有很多不足。由于工程环境的复杂性和岩土性状的不确定性,深厚超软土地基路堤建设正面临着诸多技术难题,其中最主要的是克服公路的不均匀沉降。In the past 40 years, the settlement and stability of deep and ultra-soft soil foundation embankments have attracted much attention. Due to the complexity of the problem, how to formulate a reasonable foundation treatment plan during the construction process is a thorny problem that plagues the smooth implementation of the project. Most of the coastal embankments are deep and soft soil foundations, which are weak and have almost no hard crust. The microstructure and genetic mechanism of the soil are complex and changeable, and the physical model and its parameters are heterogeneous, anisotropic and uncertain. Highway is a kind of linear belt engineering, and coastal road often passes through different landform units. Facing the complex engineering environment in the coastal areas of Zhejiang, for no hard crust, high water content (ω≥60~100%), high void ratio (e≥1.8~2.0), low shear strength, high sensitivity and low permeability coefficient There are still many deficiencies in the accumulation of technical and engineering data on the deformation characteristics of small and thick (H0≥40~60m) flow plastic silt. Due to the complexity of the engineering environment and the uncertainty of geotechnical properties, the construction of embankments on deep and ultra-soft soil foundations is facing many technical difficulties, the most important of which is to overcome the uneven settlement of roads.

在本实用新型之前,中国发明“板桩组合结构”(专利号:CN101298776A)提供了一种板桩组合结构,其特征在于由钢筋砼预制管桩、钢筋砼预制挡板、钢筋砼纵向梁和横向梁组成,该结构的整体性和稳定性好、刚度大。但是,该技术仍存在路堤侧向位移大,不均匀沉降仍然显著的问题,并且没有考虑工后排水、路堤周边堆土荷载问题。Before the present utility model, China invented "sheet pile composite structure" (patent number: CN101298776A) and provided a kind of sheet pile composite structure, it is characterized in that by reinforced concrete prefabricated pipe pile, reinforced concrete prefabricated baffle, reinforced concrete longitudinal beam and Composed of transverse beams, the structure has good integrity, stability and rigidity. However, this technology still has the problems of large lateral displacement of the embankment and significant uneven settlement, and does not consider the problems of post-construction drainage and soil load around the embankment.

实用新型内容Utility model content

本实用新型的目的就是要解决上述背景技术的不足,提供一种深厚超软土路堤。The purpose of this utility model is to solve the above-mentioned deficiencies in the background technology, to provide a kind of deep super soft soil embankment.

为了实现上述技术目的,本实用新型采用了以下技术方案:In order to achieve the above-mentioned technical purpose, the utility model adopts the following technical solutions:

深厚超软土路堤,包括路堤、水泥土隔离墙、加固区固化水泥土、过渡区固化水泥土、排水垫层、十字预制节点、隔离土工布、钢筋混凝土框格板、一字预制节点、带肋板桩和快速注浆设备;所述带肋板桩穿过加固区固化水泥土到达超软土层,带肋板桩在预制板桩基础上在固定位置把竖向连接筋B弯曲作为肋的受力筋,其中肋上带有圆孔;设有矩形锚固钢板、圆形锚固钢板分别用于将竖向连接筋A、竖向连接筋B锚固为整体,圆形锚固钢板的直径和矩形锚固钢板的边长均小于锚固槽直径;十字预制节点内部设有预应力钢筋形成横向连接筋 A;十字预制节点在纵、横交界处留有底部嵌入槽和顶部锚固槽,上部为顶部锚固槽,下部为底部嵌入槽,槽的直径宽于带孔封底管桩的直径,交界处留有竖向连接筋贯穿孔A,孔的直径大于桩的竖向连接筋A的直径;十字预制节点在端部设有排水管、连接台阶,预制节点的横向连接筋A从台阶处伸出一定长度。Deep and ultra-soft soil embankment, including embankment, cement-soil separation wall, solidified cement-soil in the reinforcement area, solidified cement-soil in the transition area, drainage cushion, cross prefabricated joints, isolated geotextiles, reinforced concrete frame panels, one-line prefabricated joints, strips Ribbed sheet pile and rapid grouting equipment; the ribbed sheet pile passes through the reinforcement area to solidify the cement soil to reach the super soft soil layer, and the ribbed sheet pile bends the vertical connecting rib B at a fixed position on the prefabricated sheet pile foundation as a rib There are round holes in the ribs; there are rectangular anchoring steel plates and circular anchoring steel plates respectively used to anchor the vertical connecting rib A and vertical connecting rib B as a whole, and the diameter of the circular anchoring steel plate and the rectangular The side lengths of the anchoring steel plates are all smaller than the diameter of the anchoring groove; the cross prefabricated joints are equipped with prestressed steel bars to form the transverse connecting bars A; the cross prefabricated joints have bottom embedded grooves and top anchoring grooves at the longitudinal and transverse junctions, and the upper part is the top anchoring groove , the lower part is the bottom embedding groove, the diameter of the groove is wider than the diameter of the pipe pile with a hole in the back cover, and the vertical connecting rib is left at the junction A through the hole, and the diameter of the hole is larger than the diameter of the vertical connecting rib A of the pile; The end is provided with drainage pipes and connecting steps, and the transverse connecting ribs A of the prefabricated nodes protrude from the steps to a certain length.

所述带孔封底管桩采用封底排水式管桩,用砂或碎石灌芯,采用透水混凝土或设透水孔,在桩身设置出浆孔。The bottom-sealed pipe pile with holes adopts a bottom-sealed drainage pipe pile, the core is filled with sand or gravel, permeable concrete is used or water-permeable holes are set, and grout holes are set on the pile body.

所述隔离土工布覆盖在排水垫层上面,用于隔离上部施工的混凝土。The isolation geotextile is covered on the drainage cushion and is used to isolate the concrete of the upper construction.

十字预制节点每个1/4段的长度为2.2~2.4m顶部锚固槽深30~50mm,底部嵌入槽深 30~50mm。The length of each 1/4 section of the cross prefabricated node is 2.2-2.4m, the depth of the anchoring groove at the top is 30-50mm, and the depth of the embedded groove at the bottom is 30-50mm.

所述一字预制节点每个1/2段的长度为2.2~2.4m,内部设有预应力钢筋形成横向连接筋 B、竖向连接筋贯穿孔B,孔的直径大于桩的竖向连接筋B的直径。The length of each 1/2 section of the one-word prefabricated node is 2.2-2.4m, and there are prestressed steel bars inside to form horizontal connecting bars B and vertical connecting bars through holes B, and the diameter of the holes is larger than the vertical connecting bars of the pile B's diameter.

所述快速注浆设备包括:未带孔注浆管段、带孔注浆管段、上隔板、下隔板和泡沫垫层;所述上隔板、下隔板与注浆管焊接在一起。The rapid grouting equipment includes: a grouting pipe section without holes, a grouting pipe section with holes, an upper partition, a lower partition and a foam cushion; the upper partition, the lower partition and the grouting pipe are welded together.

本实用新型的有益效果是:隔离墙解决了工后周边堆土和地下水位变化带来的地基失稳问题,加固区固化水泥土、过渡区固化水泥土、刚性桩、钢筋砼框格板,增强了路基的整体受力,大大减少了地基的不均匀沉降,竖向排水体、排水垫层有效解决了工后地基排水问题。The beneficial effects of the utility model are: the separation wall solves the problem of foundation instability caused by surrounding piled soil and groundwater level changes after construction, solidifies the cement soil in the reinforcement area, solidifies the cement soil in the transition area, rigid piles, and reinforced concrete frame panels, The overall stress of the subgrade is enhanced, the uneven settlement of the foundation is greatly reduced, and the vertical drainage body and drainage cushion effectively solve the drainage problem of the foundation after construction.

附图说明Description of drawings

图1是本实用新型深厚超软土路堤及施工方法的结构断面图;Fig. 1 is the structural sectional view of deep supersoft soil embankment of the present utility model and construction method;

图2是十字预制节点示意图;Figure 2 is a schematic diagram of a cross prefabricated node;

图3是十字预制节点A-A剖面示意图;Fig. 3 is a cross-sectional schematic diagram of prefabricated node A-A;

图4是带肋板桩示意图;Fig. 4 is a schematic diagram of a ribbed sheet pile;

图5是带肋板桩B-B剖面示意图;Fig. 5 is a schematic cross-sectional view of ribbed sheet pile B-B;

图6是一字预制节点示意图;Fig. 6 is a schematic diagram of a word prefabricated node;

图7是矩形锚固钢板示意图;Fig. 7 is a schematic diagram of a rectangular anchoring steel plate;

图8是圆形锚固钢板示意图;Fig. 8 is a schematic diagram of a circular anchoring steel plate;

图9是快速注浆设备示意图;Fig. 9 is a schematic diagram of rapid grouting equipment;

图10是施工工艺流程图。Figure 10 is a flow chart of the construction process.

图中:1—路堤、2—超软土层、3—软土层、4—加固区固化水泥土、5—过渡区固化水泥土、9—带孔封底管桩、10—出浆孔、11—桩侧注浆区、12—排水垫层、13—十字预制节点、 14—竖向连接筋A、15—底部嵌入槽、16—顶部锚固槽、17—竖向连接筋贯穿孔A、18—锚固槽顶部灌芯、19—后灌微膨胀混凝土A、20—矩形锚固钢板、21—圆形锚固钢板、22—锚固钢板贯穿孔、23—连接台阶A、24—横向连接筋A、25—排水管、26—隔离土工布、27—边沟、28—侧向排水孔、29—回填种植土、30—钢筋混凝土框格板、31—一字预制节点、32—护栏、33—带肋板桩、34—竖向连接筋B、35—竖向连接筋贯穿孔B、36—后灌微膨胀混凝土B、37—连接台阶B、38—横向连接筋B、39—快速注浆设备、40—未带孔注浆管段、41 —带孔注浆管段、42—上隔板、43—下隔板、44—泡沫垫层、45—锚固螺栓、46—预制盖梁。In the figure: 1—embankment, 2—super soft soil layer, 3—soft soil layer, 4—solidified cement soil in the reinforcement area, 5—solidified cement soil in the transition area, 9—bottom-sealing pipe pile with holes, 10—grouting hole, 11—pile side grouting area, 12—drainage cushion, 13—cross prefabricated joint, 14—vertical connecting bar A, 15—bottom embedded groove, 16—top anchoring groove, 17—vertical connecting bar through hole A, 18—core filling at the top of the anchoring groove, 19—post-filling micro-expansion concrete A, 20—rectangular anchoring steel plate, 21—circular anchoring steel plate, 22—through hole of anchoring steel plate, 23—connecting step A, 24—transverse connecting rib A, 25—drainage pipe, 26—isolation geotextile, 27—side ditch, 28—lateral drainage hole, 29—backfilling planting soil, 30—reinforced concrete frame panel, 31—one-word prefabricated node, 32—guardrail, 33— Ribbed sheet pile, 34—vertical connecting bar B, 35—vertical connecting bar through hole B, 36—post-filling micro-expansion concrete B, 37—connecting step B, 38—horizontal connecting bar B, 39—rapid grouting Equipment, 40—grouting pipe section without holes, 41—grouting pipe section with holes, 42—upper partition, 43—lower partition, 44—foam cushion, 45—anchor bolts, 46—prefabricated cover beam.

具体实施方式detailed description

下面结合附图对本实用新型的具体实施例做详细说明。Specific embodiments of the present utility model are described in detail below in conjunction with accompanying drawings.

图1是本实用新型深厚超软土路堤及施工方法的结构断面图;图2是十字预制节点示意图;图4是带肋板桩示意图;图6是一字预制节点示意图。所示深厚超软土路堤及施工方法,所述深厚超软土路堤及施工方法主要包括有路堤1、加固区固化水泥土4、过渡区固化水泥土 5、带孔封底管桩9、排水垫层12、十字预制节点13、隔离土工布26、钢筋混凝土框格板30、一字预制节点31、带肋板桩33、快速注浆设备39;所述隔离墙6采用预制板桩,顶部预制盖梁46连为整体。Fig. 1 is a structural sectional view of a deep ultra-soft soil embankment and construction method of the utility model; Fig. 2 is a schematic diagram of a cross prefabricated node; Fig. 4 is a schematic diagram of a ribbed sheet pile; Fig. 6 is a schematic diagram of a one-word prefabricated node. The deep ultra-soft soil embankment and its construction method are shown. The deep ultra-soft soil embankment and its construction method mainly include embankment 1, solidified cement soil in the reinforcement area 4, solidified cement soil in the transition area 5, bottom-sealing pipe piles with holes 9, and drainage pads Layer 12, cross prefabricated nodes 13, isolated geotextiles 26, reinforced concrete frame panels 30, straight prefabricated nodes 31, ribbed sheet piles 33, rapid grouting equipment 39; Cover beam 46 is connected as a whole.

本实施例的深厚超软土路堤,包括路堤1、水泥土隔离墙6、加固区固化水泥土4、过渡区固化水泥土5、排水垫层12、十字预制节点13、隔离土工布26、钢筋混凝土框格板30、一字预制节点31、带肋板桩33和快速注浆设备39;所述带肋板桩33穿过加固区固化水泥土 4到达超软土层2,带肋板桩33在预制板桩基础上在固定位置把竖向连接筋B34弯曲作为肋的受力筋,其中肋上带有圆孔;设有矩形锚固钢板20、圆形锚固钢板21分别用于将竖向连接筋A14、竖向连接筋B34锚固为整体,圆形锚固钢板21的直径和矩形锚固钢板20的边长均小于锚固槽直径;十字预制节点13内部设有预应力钢筋形成横向连接筋A24;十字预制节点13在纵、横交界处留有底部嵌入槽15和顶部锚固槽16,上部为顶部锚固槽,下部为底部嵌入槽,槽的直径宽于带孔封底管桩9的直径,交界处留有竖向连接筋贯穿孔A17,孔的直径大于桩的竖向连接筋A14的直径;十字预制节点在端部设有排水管25、连接台阶23,预制节点的横向连接筋A24从台阶处伸出一定长度。The deep and ultra-soft soil embankment of this embodiment includes embankment 1, cement-soil separation wall 6, solidified cement-soil 4 in the reinforcement zone, solidified cement-soil 5 in the transition zone, drainage cushion 12, cross prefabricated node 13, isolation geotextile 26, steel bars Concrete frame panels 30, prefabricated joints 31, ribbed sheet piles 33 and rapid grouting equipment 39; the ribbed sheet piles 33 pass through the reinforcement area to solidify the cement soil 4 to reach the super soft soil layer 2, and the ribbed sheet piles 33 On the prefabricated sheet pile foundation, bend the vertical connecting rib B34 at a fixed position as the stress rib of the rib, wherein the rib has a round hole; a rectangular anchoring steel plate 20 and a circular anchoring steel plate 21 are respectively used to connect the vertical The connecting bar A14 and the vertical connecting bar B34 are anchored as a whole, and the diameter of the circular anchoring steel plate 21 and the side length of the rectangular anchoring steel plate 20 are both smaller than the diameter of the anchoring groove; the cross prefabricated node 13 is provided with prestressed steel bars to form a horizontal connecting bar A24; The cross prefabricated node 13 has a bottom embedding groove 15 and a top anchoring groove 16 at the longitudinal and transverse intersections, the upper part is the top anchoring groove, and the lower part is the bottom embedding groove. There is a through hole A17 for the vertical connecting rib, and the diameter of the hole is greater than the diameter of the vertical connecting rib A14 of the pile; the cross prefabricated node is provided with a drainage pipe 25 and a connecting step 23 at the end, and the horizontal connecting rib A24 of the prefabricated node is connected from the step. stick out a certain length.

所述带孔封底管桩9采用封底排水式管桩,用砂或碎石灌芯,采用透水混凝土或设透水孔,在桩身设置出浆孔10。The bottom-sealed pipe pile 9 with holes adopts a bottom-sealed drainage pipe pile, the core is filled with sand or gravel, and permeable concrete is used or a water-permeable hole is set, and a grout hole 10 is set on the pile body.

所述隔离土工布26覆盖在排水垫层上面,用于隔离上部施工的混凝土。The isolation geotextile 26 covers the drainage cushion and is used to isolate the concrete of the upper construction.

十字预制节点13每个1/4段的长度为2.2~2.4m顶部锚固槽深30~50mm,底部嵌入槽深30~50mm。The length of each 1/4 section of the cross prefabricated node 13 is 2.2-2.4m, the depth of the anchoring groove at the top is 30-50mm, and the depth of the embedded groove at the bottom is 30-50mm.

所述一字预制节点31每个1/2段的长度为2.2~2.4m,内部设有预应力钢筋形成横向连接筋B38、竖向连接筋贯穿孔B35,孔的直径大于桩的竖向连接筋B34的直径。The length of each 1/2 section of the one-word prefabricated node 31 is 2.2-2.4m, and the interior is equipped with prestressed steel bars to form horizontal connecting bars B38 and vertical connecting bars through holes B35. The diameter of the holes is larger than the vertical connection of piles. The diameter of the rib B34.

所述快速注浆设备39包括:未带孔注浆管段40、带孔注浆管段41、上隔板42、下隔板 43和泡沫垫层44;所述上隔板42、下隔板43与注浆管焊接在一起。The rapid grouting equipment 39 comprises: a grouting pipe section 40 without holes, a grouting pipe section 41 with holes, an upper partition 42, a lower partition 43 and a foam cushion 44; the upper partition 42, the lower partition 43 Welded together with the grouting pipe.

上述深厚超软土路堤及施工方法施工过程主要包括以下步骤:The construction process of the above-mentioned deep ultra-soft soil embankment and construction method mainly includes the following steps:

1、场地清理,应对路幅范围内、地面表层腐殖土、表土、草皮等进行清理;1. For site cleaning, the humus, topsoil, and turf on the ground surface should be cleaned within the road width;

2、隔离墙施工:超软土层2、软土层3中打入带肋板桩33,安装一字预制节点31,采用矩形锚固钢板20将竖向连接筋B34锚固螺栓45锚固连为整体。采用后灌微膨胀混凝土B36封孔。根据预制盖梁46尺寸开挖沟槽把横向连接筋B绑扎链接形成具有一定强度和整体结构的预制盖梁46形成整体,以抵抗周边堆土产生的侧向土压力;2. Construction of the separation wall: Ribbed sheet piles 33 are driven into the ultra-soft soil layer 2 and soft soil layer 3, and the inline prefabricated nodes 31 are installed, and the vertical connecting ribs B34 and anchor bolts 45 are anchored and connected as a whole by using rectangular anchoring steel plates 20 . Use post-filling micro-expansion concrete B36 to seal the hole. Excavate trenches according to the size of the prefabricated cover beam 46 to bind and link the transverse connecting ribs B to form a prefabricated cover beam 46 with a certain strength and overall structure to form a whole to resist the lateral earth pressure generated by the surrounding soil;

3、加固区固化水泥土施工并向前推进,利用固化剂和超软土之间产生的一系列物理化学反应,使软土硬结成具有整体性、水稳定性和一定强度的优质地基;3. Solidify the cement-soil construction in the reinforcement area and move forward, using a series of physical and chemical reactions between the curing agent and the super-soft soil to harden the soft soil into a high-quality foundation with integrity, water stability and certain strength;

4、过渡区固化水泥土5、加固区固化水泥土4施工并向前推进,利用固化剂和超软土之间产生的一系列物理化学反应使软土硬结成具有整体性、水稳定性和一定强度的优质地基;4. Solidify the cement soil in the transition zone 5. Consolidate the cement soil in the reinforcement zone 4. Construction and advance, use a series of physical and chemical reactions between the curing agent and the super soft soil to make the soft soil harden into an integrity and water stability and a high-quality foundation with a certain strength;

5、基础桩施工:在水泥固化前打入带孔封底管桩9,待48小时后,用快速注浆设备注浆。利用机械把快速注浆设备39注浆插入到带孔封底管桩9内,慢慢向里推进带到达指定出浆孔10位置时停止插入,把水泥浆注入未带孔注浆管段40注入,由于上隔板42、下隔板43、泡沫垫层44与带孔封底管桩9内壁贴合,水泥浆从带孔注浆管段41出浆,形成桩侧注浆区。然后依次上提,达到下一个出浆孔10位置时停止上提,注浆,依次操作。5. Construction of the foundation pile: before the cement is solidified, drive the bottom-sealed pipe pile 9 with holes, and after 48 hours, grout with rapid grouting equipment. Utilize the machine to insert the rapid grouting equipment 39 grouting into the bottom-sealed pipe pile 9 with holes, slowly push the belt inward and stop the insertion when it reaches the position of the designated grouting hole 10, inject the grout into the grouting pipe section 40 without holes, Because the upper partition 42, the lower partition 43, the foam cushion 44 are attached to the inner wall of the pipe pile 9 with holes, the cement slurry is discharged from the grouting pipe section 41 with holes to form a pile side grouting area. Then lift up successively, stop when reaching next grout hole 10 positions, lift up, inject grout, operate successively.

6、根据钢筋混凝土框格板30尺寸开挖沟槽;6. Excavate the trench according to the size of the reinforced concrete frame slab 30;

7、铺设排水垫层12并压实;7. Lay drainage cushion 12 and compact it;

8、在排水垫层12顶部铺设隔离土工布26,用于隔离上部土;8. Lay an isolation geotextile 26 on the top of the drainage cushion 12 to isolate the upper soil;

9、装十字预制节点13,采用圆形锚固钢板20将竖向连接筋A14锚固螺栓45锚固连为整体。采用后灌微膨胀混凝土A19封孔。将竖向连接筋A14锚固连为整体;9. Install the cross prefabricated node 13, and use the circular anchor steel plate 20 to anchor the vertical connecting rib A14 anchor bolt 45 into a whole. Use post-filling micro-expansion concrete A19 to seal the hole. Anchor the vertical connecting rib A14 into a whole;

10、用钢筋绑扎或焊接连接横向连接筋A24,浇筑钢筋混凝土框格板30;10. Bind or weld the horizontal connecting bars A24 with steel bars, and pour the reinforced concrete frame panels 30;

11、待钢筋混凝土框格板达到设计强度的70%~80%后,进行路堤1填筑及后续边沟27、侧向排水孔28、回填种植土29、护栏32施工。11. After the reinforced concrete frame slab reaches 70% to 80% of the design strength, carry out embankment 1 filling and follow-up side ditch 27, lateral drainage hole 28, backfill planting soil 29, and guardrail 32 construction.

Claims (6)

1.一种深厚超软土路堤,其特征在于,包括路堤(1)、水泥土隔离墙(6)、加固区固化水泥土(4)、过渡区固化水泥土(5)、排水垫层(12)、十字预制节点(13)、隔离土工布(26)、钢筋混凝土框格板(30)、一字预制节点(31)、带肋板桩(33)和快速注浆设备(39);所述带肋板桩(33)穿过加固区固化水泥土(4)到达超软土层(2),带肋板桩(33)在预制板桩基础上在固定位置把竖向连接筋B(34)弯曲作为肋的受力筋,其中肋上带有圆孔;设有矩形锚固钢板(20)、圆形锚固钢板(21)分别用于将竖向连接筋A(14)、竖向连接筋B(34)锚固为整体,圆形锚固钢板(21)的直径和矩形锚固钢板(20)的边长均小于锚固槽直径;十字预制节点(13)内部设有预应力钢筋形成横向连接筋A(24);十字预制节点(13)在纵、横交界处留有底部嵌入槽(15)和顶部锚固槽(16),上部为顶部锚固槽,下部为底部嵌入槽,槽的直径宽于带孔封底管桩(9)的直径,交界处留有竖向连接筋贯穿孔A(17),孔的直径大于桩的竖向连接筋A(14)的直径;十字预制节点在端部设有排水管(25)、连接台阶(23),预制节点的横向连接筋A(24)从台阶处伸出一定长度。1. a kind of deep supersoft soil embankment is characterized in that, comprises embankment (1), cement-soil separation wall (6), reinforcement zone solidifies cement-soil (4), transition zone solidifies cement-soil (5), drainage cushion ( 12), cross prefabricated joints (13), isolation geotextiles (26), reinforced concrete frame panels (30), straight prefabricated joints (31), ribbed sheet piles (33) and rapid grouting equipment (39); The ribbed sheet pile (33) passes through the reinforcement area to solidify the cement soil (4) to reach the supersoft soil layer (2), and the ribbed sheet pile (33) connects the vertical connecting rib B at a fixed position on the prefabricated sheet pile foundation. (34) Bending the stressed tendons as ribs, wherein the ribs have circular holes; rectangular anchoring steel plates (20) and circular anchoring steel plates (21) are respectively used to connect the vertical connecting ribs A (14), vertical The connecting bar B (34) is anchored as a whole, and the diameter of the circular anchoring steel plate (21) and the side length of the rectangular anchoring steel plate (20) are both smaller than the diameter of the anchoring groove; the cross prefabricated node (13) is provided with prestressed reinforcement inside to form a transverse connection Rib A (24); the cross prefabricated node (13) has a bottom embedded groove (15) and a top anchor groove (16) at the longitudinal and transverse junctions, the upper part is the top anchor groove, the lower part is the bottom embedded groove, and the diameter of the groove is wide According to the diameter of the pipe pile with hole back cover (9), there is a vertical connecting rib through hole A (17) at the junction, and the diameter of the hole is greater than the diameter of the vertical connecting rib A (14) of the pile; the cross prefabricated node is at the end A drainage pipe (25) and a connecting step (23) are provided, and the transverse connecting rib A (24) of the prefabricated node protrudes a certain length from the step. 2.根据权利要求1所述的深厚超软土路堤,其特征在于,所述带孔封底管桩(9)采用封底排水式管桩,用砂或碎石灌芯,采用透水混凝土或设透水孔,在桩身设置出浆孔(10)。2. The deep ultra-soft soil embankment according to claim 1, characterized in that, the bottom-sealing pipe pile with holes (9) adopts a bottom-sealing drainage pipe pile, fills the core with sand or gravel, and adopts permeable concrete or sets a water-permeable Holes are provided with grout holes (10) at the pile body. 3.根据权利要求1所述的深厚超软土路堤,其特征在于,所述隔离土工布(26)覆盖在排水垫层上面,用于隔离上部施工的混凝土。3. The deep ultra-soft soil embankment according to claim 1, characterized in that, the isolation geotextile (26) covers the drainage cushion and is used to isolate the concrete of the upper construction. 4.根据权利要求1所述的深厚超软土路堤,其特征在于,十字预制节点(13)每个1/4段的长度为2.2~2.4m顶部锚固槽深30~50mm,底部嵌入槽深30~50mm。4. The deep ultra-soft soil embankment according to claim 1, characterized in that, the length of each 1/4 section of the cross prefabricated node (13) is 2.2-2.4m, the top anchoring groove is 30-50mm deep, and the bottom embedded groove is deep 30-50mm. 5.根据权利要求1所述的深厚超软土路堤,其特征在于,所述一字预制节点(31)每个1/2段的长度为2.2~2.4m,内部设有预应力钢筋形成横向连接筋B(38)、竖向连接筋贯穿孔B(35),孔的直径大于桩的竖向连接筋B(34)的直径。5. The deep ultra-soft soil embankment according to claim 1, characterized in that, the length of each 1/2 section of the one-shaped prefabricated node (31) is 2.2-2.4m, and prestressed steel bars are arranged inside to form a transverse The connecting rib B (38), the vertical connecting rib runs through the hole B (35), and the diameter of the hole is greater than the diameter of the vertical connecting rib B (34) of the pile. 6.根据权利要求1所述的深厚超软土路堤,其特征在于,所述快速注浆设备(39)包括:未带孔注浆管段(40)、带孔注浆管段(41)、上隔板(42)、下隔板(43)和泡沫垫层(44);所述上隔板(42)、下隔板(43)与注浆管焊接在一起。6. The deep ultra-soft soil embankment according to claim 1, characterized in that, the rapid grouting equipment (39) comprises: a grouting pipe section without holes (40), a grouting pipe section with holes (41), an upper A partition (42), a lower partition (43) and a foam cushion (44); the upper partition (42), the lower partition (43) and the grouting pipe are welded together.
CN201720936830.4U 2017-07-31 2017-07-31 Deep super embankment on soft soil Active CN207017097U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720936830.4U CN207017097U (en) 2017-07-31 2017-07-31 Deep super embankment on soft soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720936830.4U CN207017097U (en) 2017-07-31 2017-07-31 Deep super embankment on soft soil

Publications (1)

Publication Number Publication Date
CN207017097U true CN207017097U (en) 2018-02-16

Family

ID=61481996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720936830.4U Active CN207017097U (en) 2017-07-31 2017-07-31 Deep super embankment on soft soil

Country Status (1)

Country Link
CN (1) CN207017097U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447613A (en) * 2017-07-31 2017-12-08 浙江大学城市学院 A kind of deep super embankment on soft soil and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447613A (en) * 2017-07-31 2017-12-08 浙江大学城市学院 A kind of deep super embankment on soft soil and construction method

Similar Documents

Publication Publication Date Title
CN107447613B (en) A deep ultra-soft soil embankment and its construction method
CN103410167B (en) Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN202227214U (en) Deep soft soil foundation embankment structure of high-speed railway
CN109208545B (en) Construction method of artificial landscape overflow dam with energy dissipation effect
CN113308953B (en) Construction method for widening embankment by utilizing foam concrete of existing retaining wall
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN111778793B (en) A cavity collapse prevention structure and construction method
CN113818300B (en) Sponge city ecological roadbed structure based on original road and construction method thereof
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN101476325A (en) Rigid gridding and pile combined foundation and its use in soft soil foundation reinforcement
CN111305027A (en) Rapid repair construction method and repair structure for pavement collapse in karst area
CN102286955B (en) Reinforced concrete pile type dyke and construction method thereof
CN108677637A (en) A kind of roadbed filling method of precast concrete tube coupling reinforcement light soil
CN109487640B (en) High-speed railway roadbed reinforcing structure in underdrain development area and construction method
CN110965416A (en) A Bamboo Reinforcement System and Construction Method for Reinforcing High Fill Roadbed in Mountainous Areas
CN107288120A (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN215977211U (en) A composite foundation treatment structure of pipe pile combined with cement-soil mixing pile
CN108824412B (en) Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction
CN110485230A (en) A kind for the treatment of structures and construction method of high water level weak soil Bridgehead by Blastig
CN106836034B (en) A flexible load-reducing system and construction method of high-fill cover slab culvert
CN102425179B (en) Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile
CN207017097U (en) Deep super embankment on soft soil
CN209723024U (en) Composite foundation reinforcement counterfort wall structure
CN102535485B (en) Back-shaped reinforced geotechnical retaining structure of soft soil cutting slope and its reverse construction method

Legal Events

Date Code Title Description
GR01 Patent grant