CN206972267U CN201720670843.1U CN201720670843U CN206972267U CN 206972267 U CN206972267 U CN 206972267U CN 201720670843 U CN201720670843 U CN 201720670843U CN 206972267 U CN206972267 U CN 206972267U
Authority
CN
China
Prior art keywords
chamber
upright
side wall
arch
arch chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720670843.1U
Other languages
Chinese (zh)
Inventor
荆晓伟
李旭文
程亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720670843.1U priority Critical patent/CN206972267U/en
Application granted granted Critical
Publication of CN206972267U publication Critical patent/CN206972267U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a kind of deep tunnel supporting new concrete support, including pouring frame, the pouring frame includes arch chamber and two upright chambers, and described two upright chambers are connected respectively at arch chamber both ends, are provided with the arch chamber and pour mouth;The arch chamber is externally connected with some top supporting rods, each upright chamber is externally connected with some side wall support bars, the top supporting rod is fixedly connected with installing plate with side wall support bar tail end, side wall screw is provided with the installing plate, the utility model by pouring frame by being divided into arch chamber and upright chamber, domes have very strong weight capacity, and can be dispersed by bearing capacity, by pouring mouth casting concrete into arch chamber and upright chamber, it is to be solidified air-dry after, it is supported by the palisades for being arranged on arch chamber and the top supporting rod outside upright chamber and side wall support bar and tunnel, installation is fixed by installing plate, it is fixedly connected by side wall screw spiral shell and screw.

Description

A kind of deep tunnel supporting new concrete support
Technical field
Colliery support equipment field is the utility model is related to, specially a kind of deep tunnel supporting new concrete branch Frame.
Background technology
At present, coal enterprises in China situation of production is more severe, and safety problem turns into restricts Dissertation of Development of Coal Industry One of outstanding problem, the t of world's coal production about 5,000,000,000 in 2003, dead total 8000 people of Coal Accidents, coal in China then Yield accounts for the 35% of the whole world, and death tolls then account for more than 80%, considerably beyond other producing coal country coal mining accidents of the world There is ten tens of thousands of accident disable persons in dead sum, the whole nation every year, coal in China production fatality rate per million tons, about India 10 times, 100 times of the U.S., the especially serious accident once more than dead 10 people happen occasionally, and these accidents not only give the people Lives and properties bring huge loss, and at home and abroad cause and have a strong impact on, due to deep tunnel in numerous mine disasters The reason for caving in is in occupation of major part.
Utility model content
For problem above, the utility model provides a kind of deep tunnel supporting new concrete support, integrally sets Meter can effectively be supported to deep tunnel, prevent caving in occurs in tunnel from causing casualties, global design uses coagulation Soil pours, and is supported by support bar, is easily installed and dismantles, and effectively can solve the problems, such as in background technology.
To achieve the above object, the utility model provides following technical scheme:A kind of new coagulation of deep tunnel supporting Native support, including pouring frame, the pouring frame include arch chamber and two upright chambers, and described two upright chambers are respectively at arch Shape chamber both ends are connected, and are provided with the arch chamber and pour mouth;The arch chamber is externally connected with some top supporting rods, institute State each upright chamber and be externally connected with some side wall support bars, the top supporting rod is fixedly connected with side wall support bar tail end Installing plate, side wall screw is provided with the installing plate.
For the utility model by the way that pouring frame is divided into arch chamber and upright chamber, domes have very strong load-bearing energy Power, and can be dispersed by bearing capacity, it is to be solidified to air-dry by pouring mouth casting concrete into arch chamber and upright chamber Afterwards, it is supported by being arranged on the palisades of arch chamber and the top supporting rod outside upright chamber and side wall support bar and tunnel, Installation is fixed by installing plate, is fixedly connected by side wall screw spiral shell and screw.
As a kind of preferable technical scheme of the utility model, the top supporting rod is with side wall support bar using some Root pole forms, and is provided with and bolts on the pole.
As a kind of preferable technical scheme of the utility model, support beam is provided between described two upright chambers, institute State and some support columns are set between support beam and arch chamber, the support column is distributed in three-legged structure.
As a kind of preferable technical scheme of the utility model, each upright bottom of chamber portion is provided with firm banking, institute State and ground connection screw is set on firm banking.
As a kind of preferable technical scheme of the utility model, caching leather packing is provided with the installing plate.
Compared with prior art, the beneficial effects of the utility model are:The utility model global design can be to deep lane Road is effectively supported, and prevents caving in occurs in tunnel from causing casualties, and global design uses concreting, and passes through Support bar is supported, and is easily installed and is dismantled, convenient to promote.
Brief description of the drawings
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is side wall support bar structural representation in Fig. 1;
In figure:1- pouring frames;2- arch chambers;The upright chambers of 3-;4- pours mouth;5- top supporting rods;6- side wall support bars; 7- installing plates;8- side wall screws;9- poles;10- bolts on;11- support beams;12- support columns;13- firm bankings;14- It is grounded screw;15- caches leather packing.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Embodiment:
Fig. 1 and Fig. 2 are referred to, the utility model provides a kind of technical scheme:A kind of new coagulation of deep tunnel supporting Native support, including pouring frame 1, the pouring frame 1 include arch chamber 2 and two upright chambers 3, and described two upright chambers 3 divide It is not connected in the both ends of arch chamber 2, is provided with the arch chamber 2 and pours mouth 4;The arch chamber 2 is externally connected with some tops Portion's support bar 5, each upright chamber 3 are externally connected with some side wall support bars 6, the top supporting rod 5 and side wall support The tail end of bar 6 is fixedly connected with installing plate 7, and side wall screw 8 is provided with the installing plate 7.
The utility model has very strong load-bearing by the way that pouring frame 1 is divided for arch chamber 2 and upright chamber 3, domes Ability, and can be dispersed by bearing capacity, by pouring the casting concrete into arch chamber 2 and upright chamber 3 of mouth 4, wait to coagulate Gu after air-drying, pass through the top supporting rod 5 and side wall support bar 6 and tunnel for being arranged on arch chamber 2 with being set outside upright chamber 3 Palisades are supported, and installation is fixed by installing plate 7, is fixedly connected by the spiral shell of side wall screw 8 and screw.
Specifically, the top supporting rod 5 is formed with side wall support bar 6 using some poles 9, on the pole 9 It is provided with and bolts on 10, can more tunnel palisades and the distance between upright chamber 3 or the outside of arch chamber 2 adjustment length.
Specifically, be provided with support beam 11 between described two upright chambers 3, the support beam 11 and arch chamber 2 it Between some support columns 12 are set, the support column 12 is distributed in three-legged structure, plays stable effect.
Specifically, each upright bottom of chamber 3 is provided with firm banking 13, ground connection spiral shell is set on the firm banking 13 Hole 14, it is easy to be fixedly connected with the ground.
Specifically, being provided with caching leather packing 15 on the installing plate 7, play a part of buffering.
Based on above-mentioned, the utility model has the advantage that:The utility model global design can enter to deep tunnel The effective support of row, prevents caving in occurs in tunnel from causing casualties, global design uses concreting, and passes through support Bar is supported, and is easily installed and is dismantled, convenient to promote.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (5)

  1. A kind of 1. deep tunnel supporting new concrete support, it is characterised in that:Including pouring frame(1), it is described to pour frame Frame(1)Including arch chamber(2)With two upright chambers(3), described two upright chambers(3)Respectively at arch chamber(2)Both ends are connected, The arch chamber(2)On be provided with and pour mouth(4);The arch chamber(2)It is externally connected with some top supporting rods(5), it is described Each upright chamber(3)It is externally connected with some side wall support bars(6), the top supporting rod(5)With side wall support bar(6)Tail end It is fixedly connected with installing plate(7), the installing plate(7)On be provided with side wall screw(8).
  2. A kind of 2. deep tunnel supporting new concrete support according to claim 1, it is characterised in that:The top Support bar(5)With side wall support bar(6)Use some poles(9)Composition, the pole(9)On be provided with and bolt on (10).
  3. A kind of 3. deep tunnel supporting new concrete support according to claim 1, it is characterised in that:It is described two Upright chamber(3)Between be provided with support beam(11), the support beam(11)With arch chamber(2)Between some supports are set Post(12), the support column(12)It is distributed in three-legged structure.
  4. A kind of 4. deep tunnel supporting new concrete support according to claim 1, it is characterised in that:It is described each Upright chamber(3)Bottom is provided with firm banking(13), the firm banking(13)It is upper that ground connection screw is set(14).
  5. A kind of 5. deep tunnel supporting new concrete support according to claim 1, it is characterised in that:The installation Plate(7)On be provided with caching leather packing(15).
CN201720670843.1U 2017-06-11 2017-06-11 A kind of deep tunnel supporting new concrete support Expired - Fee Related CN206972267U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720670843.1U CN206972267U (en) 2017-06-11 2017-06-11 A kind of deep tunnel supporting new concrete support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720670843.1U CN206972267U (en) 2017-06-11 2017-06-11 A kind of deep tunnel supporting new concrete support

Publications (1)

Publication Number Publication Date
CN206972267U true CN206972267U (en) 2018-02-06

Family

ID=61408420

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720670843.1U Expired - Fee Related CN206972267U (en) 2017-06-11 2017-06-11 A kind of deep tunnel supporting new concrete support

Country Status (1)

Country Link
CN (1) CN206972267U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108252727A (en) * 2018-03-21 2018-07-06 安徽理工大学 A kind of mining anti-collapse safety early warning device and its implementation
CN108894806A (en) * 2018-06-27 2018-11-27 王欣 A kind of coal mine roadway safety support device
CN110985085A (en) * 2019-11-25 2020-04-10 中国十九冶集团有限公司 Support arrangement for arch tunnel construction is used
CN113323018A (en) * 2021-06-11 2021-08-31 中国建筑第八工程局有限公司 Support arrangement for underground structure construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108252727A (en) * 2018-03-21 2018-07-06 安徽理工大学 A kind of mining anti-collapse safety early warning device and its implementation
CN108894806A (en) * 2018-06-27 2018-11-27 王欣 A kind of coal mine roadway safety support device
CN108894806B (en) * 2018-06-27 2019-10-08 南理工泰兴智能制造研究院有限公司 A kind of coal mine roadway safety support device
CN110985085A (en) * 2019-11-25 2020-04-10 中国十九冶集团有限公司 Support arrangement for arch tunnel construction is used
CN113323018A (en) * 2021-06-11 2021-08-31 中国建筑第八工程局有限公司 Support arrangement for underground structure construction

Similar Documents

Publication Publication Date Title
CN206972267U (en) A kind of deep tunnel supporting new concrete support
CN207646598U (en) One kind being used for Single column pier antidumping girder falling bracing means
CN105178206B (en) Spliced-type shed tunnel
CN102367653A (en) Support structure for large-span continuous beam construction
CN203113352U (en) Pre-stressed beam for retaining and protection of foundation pit
CN209493860U (en) Antidumping ruggedized construction at a kind of only column bridge pier transformation
CN204919346U (en) Knotted bar iron strutting arrangement that detached pier bent cap is adjustable
CN202851078U (en) High water material filling column bag body
CN206554947U (en) A kind of colliery gob side entry suspension device
CN202482766U (en) Support structure for large span continuous beam constructions
CN202064288U (en) Hoop and A-frame combining construction supporting device for single-column capping beam
CN105422138A (en) Large-clearance tunnel lining trolley framework supporting system
CN206802923U (en) One kind separates packaging traffic lights
CN204826198U (en) High stability suspension type building structure
CN206015700U (en) A kind of raft foundation steelframe support
CN203583874U (en) Prefabricated column mould
CN211523532U (en) Steel structure with reinforcing mechanism for factory building
CN209040291U (en) A kind of assembling type steel structure exempts from casting concrete building structure
CN206157706U (en) Reinforced concrete ground
CN207093108U (en) Gob side entry retaining crosses cutting eye supporting facility
CN208280134U (en) A kind of pile foundation construction operation platform device
CN210368661U (en) A doorway type support for the construction of an urban viaduct over the road
CN205172597U (en) Big headroom tunnel lining platform truck formwork support system
CN207111134U (en) A kind of steel canopy of U-shaped steel supported laneway crossover point
CN105350981A (en) Connection mechanism for four triangular support portal frame pieces of tunnel lining trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180206

Termination date: 20180611

CF01 Termination of patent right due to non-payment of annual fee